Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Suman Mitra vs The Executive Engineer
2023 Latest Caselaw 3773 Cal

Citation : 2023 Latest Caselaw 3773 Cal
Judgement Date : 9 June, 2023

Calcutta High Court (Appellete Side)
Suman Mitra vs The Executive Engineer on 9 June, 2023
Form No. J.(2)
Item No.2
           IN THE HIGH COURT OF JUDICATURE AT CALCUTTA
                    CIVIL APPELLATE JURISDICTION
                           APPELLATE SIDE

                           HEARD ON :09.06.2023

                         DELIVERED ON: 09.06.2023

                                   CORAM:

            THE HON'BLE CHIEF JUSTICE T.S. SIVAGNANAM
                               AND
        THE HON'BLE MR. JUSTICE HIRANMAY BHATTACHARYYA

                           M.A.T. No.2022 of 2022
                                    With
                             IA No.CAN 1 of 2022

                              Suman Mitra
                                  Vs.
      The Executive Engineer, HPIU, WBSRDA, Malda Division & Ors.
Appearance:-

Mr. Utpal Das
Mr. Sanjay Saha                     ...........For the Appellant

Mr. Srikanta Dutta                  ..........For the Respondent No.4

Mr. Nilotpal Chatterjee
Ms. Amrita Panja Moulick
                                   ..........For the State

                                 JUDGMENT

(Judgment of the Court was delivered by T.S. SIVAGNANAM, C.J.)

1. This intra-Court appeal by the writ petitioner is directed against the order

dated 24th November, 2022 passed in W.P.A. No.19572 of 2022. The

appellant had impugned the order passed by the respondent authorities

terminating the contract awarded to the appellant by proceedings dated 6 th

July, 2022.

2. It appears that the appellant is not aggrieved by the award of the contract

to another contractor for completing the remaining work, but would

challenge the correctness of the termination stating that the suspension of

work for construction work was ordered by proceedings of the Executive

Engineer dated 22nd June, 2022 and within less than 28 days, the

impugned termination order was passed on 6 th July, 2022, which is in clear

violation of Clause 52.2(a) of the terms and conditions of tender.

3. Apart from that, various other grounds have also been raised stating that

factually there is no ground to terminate the contract. The learned Single

Bench after taking note of the relevant terms and conditions of contract,

thought it fit to direct a joint inspection to be conducted to assess the

quantum of work done by the appellant before the contract was terminated

on 6th July, 2022 so that the compensation to be paid to the appellant can

be worked out.

4. That apart, the learned Single Bench has also noted that in clause 24 of the

terms and conditions, there is a dispute redressal system and liberty was

granted to the appellant to work out his grievances in terms of the said

clause. We also note that in clause 25 it has been stated that in view of the

provisions of clause 24 on dispute redressal system, it is the condition of

the contract and there will be no arbitration clause for settlement of any

dispute between the parties.

5. We find that the dispute redressal system mentioned in clause 24 is an

elaborate procedure, where the aggrieved contractor will have due

opportunity to put forth all his contentions.

6. Therefore, we are of the view that the learned Single Bench was right in

disposing of the writ petition by issuing the necessary directions for joint

inspection to assess the quantum of work done by the appellant before the

termination of the contract and also simultaneously granting liberty to avail

the dispute redressal system under clause 25 of the terms and conditions

of the contract.

7. Thus, we find no ground to interfere with the order passed by the learned

Single Bench. In the event, the appellant invokes the clause 24 of the

terms and conditions of contract by availing the dispute redressal system,

the competent authority in terms of the said clause shall expeditiously

consider the prayer made by the appellant and conclude the proceedings as

expeditiously as possible, preferably within a period of three months from

the date on which such an application is filed in terms of clause 24 of the

terms and conditions of contract.

8. With the above observations, the appeal along with the connected

application stand disposed of.

9. There shall be no order as to costs.

10. Urgent photostat certified copy of this order, if applied for, be furnished to

the parties expeditiously upon compliance of all legal formalities .





                                                       (T.S. SIVAGNANAM)
                                                         CHIEF JUSTICE



I agree,                                      (HIRANMAY BHATTACHARYYA, J.)
 Pallab/KS AR(Ct.)
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter