Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

And Another vs Union Of India And Others
2023 Latest Caselaw 4162 Cal

Citation : 2023 Latest Caselaw 4162 Cal
Judgement Date : 7 July, 2023

Calcutta High Court (Appellete Side)
And Another vs Union Of India And Others on 7 July, 2023
                    In the High Court at Calcutta
                   Constitutional Writ Jurisdiction
                            Appellate Side

The Hon'ble Justice Sabyasachi Bhattacharyya

                          WPA No. 15369 of 2023

                Texmaco Rail and Engineering Limited
                            and another
                                Vs.
                     Union of India and others

                                  With

                          WPA No. 15370 of 2023

                Texmaco Rail and Engineering Limited
                            and another
                                Vs.
                     Union of India and others


    For the petitioners           :      Mr. Jishnu Saha,
                                         Mr. Rajarshi Dutta,
                                         Mr. Soorjya Ganguli,
                                         Mr. Somdutta Bhattacharyya,
                                         Mr. Shaunak Mukhopadhyay,
                                         Ms. Devanshi Prasad

    For the
    respondent nos.1, 2 & 4       :      Mr. Atarup Banerjee,

Ms. Sarada Sha

For the respondent no.3 : Ms. Rajshree Kajaria, Mr. Sarvapriya Mukherjee, Mr. Uttam Sharma

Hearing concluded on : 30.05.2023

Judgment on : 07.07.2023

Sabyasachi Bhattacharyya, J:-

1. The petitioners have filed the present writ petitions in respect of a

tender floated by the respondent no.2 in respect of design, supply,

installation, testing and commissioning of Automatic Block Signalling

System in a particular section of the Chakradharpur Division of the

South-Eastern Railway. The petitioner no.1, with which one Kalindee

Rail Nirman (Engineers) Limited has been amalgamated, participated

as Kalindee in the said tender. However, the Techno Commercial Bid

of the petitioner was rejected on the ground of technical and financial

ineligibility, bid capacity and improper information. Immediately

thereafter, the financial bids were opened and only the bids of two of

the private respondents were accepted.

2. As per the tender agreement, unless there were at least three

successful participants at this techno commercial stage, there would

not be any reverse auction. It is argued on behalf of the petitioners

that, in order to avoid reverse auction and restrict the tender only to

chosen competitors,it was tailor-made to suit the purpose of the said

competitors. It is argued that the technical rejection was arbitrary

and mala fide.

3. It is argued that in terms of the Tender Document, one of the

technical eligibility criteria was, inter alia, that the tenderer must have

substantially completed any of the three categories of works stipulated

therein. Under sub-clause (1)(iii) of Clause 2 of the Eligibility Criteria,

such work included one similar work costing not less than the amount

equal to 60 per cent of the advertised value of tender. The advertised

value of the tender was Rs.106,70,01,466.30p.

4. Learned senior counsel for the petitioner argues that the petitioner

duly produced previous work experience in a similar work undertaken

by Kalindee in respect of a job awarded by the RVNL (Rail Vikas Nigam

Limited) on behalf of the North Central Railways in the State of Uttar

Pradesh, India. Kalindee was one of the members of a joint venture,

by the name of M/s. GMR-Kalindee-TPL (JV). The other member was

one M/s. GMR Infrastructure Limited.

5. By placing reliance on the relevant Annexures to the writ petitions, it

is submitted that a Final Works Certificate was issued by the RVNL to

the Joint Venture, where it was clearly indicated that the value of

Signalling and Telecommunication (S&T) Works executed, and

payment made till that date, was Rs.102.084cr. By a subsequent

Corrigendum dated March 10, 2022, it was modified to the extent that

the value of the S&T Works executed, and payment made till that

date, was Rs.68.460cr., which is above the minimum stipulation of 60

per cent of the present advertised value.

6. By placing reliance on the relevant Corrigendum dated March 10,

2022, learned senior counsel for the petitioner argues that in a note

given in Item No.10 thereof, it was clarified that as per the joint

venture agreement, the entire Indoor S&T in the concerned section

and Outdoor Signalling for a different section were within the scope of

work of M/s. Kalindee and the Indoor and Outdoor Works physically

completed and commissioned by GMR-Kalindee-TPL (JV) were

enumerated therein. It is argued that since the entire Indoor S&T

work was done by Kalindee, for which the value of the works executed

was more than 60 per cent of the advertised value of the present

disputed tender, the petitioner could not be said to be ineligible to

participate in the present contract, on a technical score.

7. It is argued that in the present case, the tender was floated on

February 16, 2023 and the petitioner submitted its bid on March 24,

2023. On June 16, 2023, there was a request to the bidders to extend

the bid validity till July 31, 2023.

8. It is contended that on June 22, 2023, the person in charge of

conducting the tender process was transferred to some other office.

Immediately thereafter, the technical bid of the petitioner was rejected

on June 24, 2023. It is submitted that a nexus between the two

events, on some extraneous count, cannot be ruled out.

9. It is submitted that elimination of the petitioner and another

participant was merely to avoid the reverse auction and to award the

contract to the successful participant among the two remaining

participants.

10. It is argued by the petitioner that there is a Clarification Clause in the

tender document, being Clause 7E, which clearly stipulates that, to

assist in the examination, evaluation and comparison and pre-

qualification of the tender, the Railway may, at its discretion, ask any

bidder for clarification of its bid. Such clarification had to be in

writing.

11. In the present case, however, the said provision was not invoked at all

by the respondent-Authorities, despite a similar clarification having

been sought in the tender floated by the RVNL, which has been cited

by the petitioner as its past experience.

12. It is, thus, submitted that the sudden rejection, after three months

from the submission of the bid of the petitioner, was patently arbitrary

and tainted by mala fides.

13. Learned counsel appearing for the respondent/successful tenderer

controverts such contentions and submits that the relevant Notice

Inviting Tender (NIT) Clause, pertaining to the eligibility conditions,

contemplated 60 per cent of the advertised value to be satisfied

individually by the petitioner. However, the document relied on by the

petitioner to show past experience clearly indicates that the petitioner

was only a minor shareholder of 29 per cent in the profits of a joint

venture, which had done the work. Hence, it is not established by the

said document that the petitioner, individually, had undertaken the

said work to the extent of 60 per cent of the present advertised value.

14. Since there was no scope of doubt, it is argued, there was no question

of any clarification being sought by the Railway-Authorities.

Moreover, the Railway-Authorities cannot be compelled to seek such

clarification, since it is the discretion of the said Authority as per the

tender document.

15. It is argued by the private respondents that other Railways' action in

seeking clarification in different tenders with different terms from the

present one are not a comparable yardstick for the adjudication of the

present case. Since the conditions of the said 'other tenders' were

different and the contexts were different, the actions of the

respondent-Authorities in the present tender cannot be equated with

those.

16. Hence, it is argued that the writ court may not interfere with the

lawful exercise of discretion by the Tender Issuing Authority. It is

submitted that the well-settled legal proposition is that the discretion

vests exclusively with the Tender Issuing Authority to decide as to the

nature of eligibility criteria and the participants sought by the said

Authority for a particular work. Such terms cannot be dictated by the

participants, that too after participating in the tender process.

17. Upon hearing learned counsel for the parties, the argument of the

petitioner regarding the clarification clause not being resorted to by

the respondent-Authorities has to be ruled out, since the same, ex

facie, is a discretionary provision. The provision of seeking a

clarification to assist in the examination, evaluation and comparison

and pre-qualification of the tender leaves the discretion entirely with

the Railway authority and it is not a mandate on the said authority as

such.

18. However, insofar as the rejection of the technical bid of the petitioners

is concerned, the same is an arguable question, to be decided on the

basis of the materials-on-record. In the present case, since no facts

have been argued which require adjudication upon taking detailed

evidence, the writ court is competent enough to decide whether there

was any patent arbitrariness in such rejection. The relevant

document in this context is the document produced by the petitioners

with regard to their previous work experience. The Corrigendum

dated March 10, 2022 is the document which is to be looked into in

this regard, as per both sides.

19. A salient feature of the same is Serial No. 10 thereof, which contains a

'Note' indicating that, as per the Joint Venture Agreement, the entire

Indoor S&T regarding the section involved therein was in the scope of

M/s. Kalindee. Serial No.6 of the Corrigendum shows that the value

of S&T Works (which is similar to the work envisaged in the present

contract-in-dispute) executed and payment made was to the tune of

Rs.68.460cr.,which was clearly above 60 per cent of the advertised

value of the present tender.

20. A cloud has been sought to be cast by the private respondents to the

effect that, as per the Joint Venture Agreement between the petitioner

and the other members of the said Joint Venture, the petitioner's

share was only to the tune of 29 per cent.

21. However, what is relevant is not the share of profits of the petitioner in

the said Joint Venture but whether the work done by the petitioner as

a member of the said Joint Venture measures up to the eligibility

criteria of the present contract. As per the eligibility condition in

Clause 2, sub-clause (1)(iii) of the present contract, the bidder had to

do one similar work costing not less than the amount equal to 60 per

cent of advertised value of the tender.

22. There is no doubt that the present work is similar in nature to the

work done by the Joint Venture for RVNL. The petitioner was one of

the members of the joint venture. The scope of the present work is

design, supply, installation, testing and commissioning of Automatic

Block Signalling System, which is exactly similar to the S&T

(Signalling and Telecommunication) Work done for the RVNL.

23. The relevant consideration is reflected in Serial No.6 of the Final Work

Certificate issued by the RVNL in that regard, which clearly shows

that the value of the S&T Works executed and the payments therefor,

made till that date, was Rs.68.460cr. Read in conjunction with Serial

No.10 thereof, it is ex facie clear that the entire Indoor S&T Work for

the whole section was done exclusively by M/s. Kalindee Rail Nirman,

which has amalgamated with the petitioner no.1. Hence, there can be

no manner of doubt regarding the petitioner individually, albeit as one

of the members of a joint venture, having completed the previous work

of a value more than 60 per cent of the total advertised value for the

present contract. The work was also of a similar nature. Hence, there

cannot be any shade of doubt regarding the petitioner having complied

with the eligibility condition. The rejection, it is relevant to mention,

was on the ground that the technical and financial eligibility criteria

and bid capacity were not met and the information furnished by the

petitioner was improper.

24. There was no basis for such rejection, as apparent ex facie from the

materials furnished by the petitioner. The same was arbitrary and de

hors the tender terms.

25. More importantly, the impugned rejection would imply that the

reverse auction contemplated under the tender would be avoided

altogether, which bodes ill for the tender process, by curtailing wider

participation, fair competition and transparency.

26. In order to ensure that the best competitor is chosen, the process of

selection adopted by a public undertaking is required to be

transparent. As such, the impugned rejection cannot be sustained.

27. Insofar as the Clarification Clause not being invoked by the

respondent no.2 is concerned, it was the option of the Railway

Authorities either to invoke or not to invoke the same. Exercising

such discretion, the Railway Authorities did not invoke the said

provision and, as such, there is no further scope of invoking the same

at this juncture. In any event, in view of the above findings, the said

issue becomes otiose.

28. The impugned rejections, being arbitrary and mala fide, ought to be

set aside.

29. Accordingly, WPA No.15369 of 2023 and WPA No.15370 of 2023 are

allowed, thereby setting aside the impugned rejections of the

petitioner's technical bids.

30. The respondent no.2 shall conduct the tender processes afresh from

the stage of holding reverse auction, treating the petitioner to have

succeeded at the techno-commercial stage by acceptance of its bids.

In view of the quashing of the rejection order by the present order, the

respondent no.2 shall now hold reverse auction and proceed to select

the successful bidder accordingly. For such purpose, a fresh schedule

of dates shall be published by the respondent no.2, starting from the

stage of reverse auction as per the tender terms. In view of the public

nature of the project, it is expected that the respondent-Authorities

shall take immediate steps to comply with this order.

31. There will be no order as to costs.

32. Urgent certified server copies, if applied for, be issued to the parties

upon compliance of due formalities.

( Sabyasachi Bhattacharyya, J. )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter