Citation : 2023 Latest Caselaw 401 Cal
Judgement Date : 16 January, 2023
IN THE HIGH COURT AT CALCUTTA
Civil Appellate Jurisdiction
APPELLATE SIDE
Present:
The Hon'ble Justice Tapabrata Chakraborty
&
The Hon'ble Justice Raja Basu Chowdhury
F.M.A. 663 of 2022
with
IA No. CAN 1 of 2019 (Old No. CAN 11814 of 2019)
with
IA No. CAN 2 of 2019 (Old No. CAN 12462 of 2019)
Sukumar Samanta & Others.
Versus
The State of West Bengal & Others.
For the Appellants : Mr. Saibal Acharya,
Mr. Sujit Bhunia.
For the State : Mr. Tapas Kumar Adhikari,
Mr. Bipin Ghosh.
For the WBSETCL : Mr. Sumit Kumar Panja,
Mr. Sumit Ray.
Hearing is concluded on : 3rd November, 2022.
Judgment On : 16th January, 2023.
Raja Basu Chowdhury, J.:
1. By way of the present intra court mandamus appeal, the appellants'
challenge the authority and jurisdiction of the District Magistrate to
determine compensation payable to the appellants under Section 16 of
2
the Indian Telegraph Act 1885, (hereinafter referred to as the 1885 Act),
concerning works executed by a transmission licensee for transmission
of electricity, being empowered under section 164 of the Electricity Act
2003 (hereinafter referred to as the 2003 Act).
2. Briefly the facts are, that the appellants, who are also the writ
petitioners claim to be lawful owners of diverse plots of land as detailed
in the writ petition. Records would reveal that the writ application was
filed by 18 several writ petitioners, three of them being joint holders. It is
the appellants' contention that their lands are adjacent to Debra-Digha
Highway. The appellants' further claim that the respondent nos. 1 and 2
on the basis of a policy decision taken by them had taken steps to install
High Tension electricity line from Kharagpur to Debra Electricity station.
It is also the appellants' case that men and agent of the respondent nos.
2, 3 and 4 without taking prior consent of the appellants, started the
construction work of installing metal towers as well as laying High
Tension Electricity Wires, upon the lands belonging to the appellant nos.
1 to 18.
3. This prompted the appellants to make representations so as to object
to the works carried out by the respondents. Several such
representations were made. By such representation the appellants had
also sought the intervention of Block Development Officer and Project
Manager of the respondent no. 2.
4. Mr. Acharya, learned advocate representing the appellants submits
that since the aforesaid representations did not yield any result, a writ
application being W.P. No. 13260 (W) of 2019 was filed before the Hon'ble
High Court at Calcutta, inter alia, praying for issuance of a writ in the
nature of Mandamus commanding the respondent nos. 2 to 4 not to
install High Tension Electric Tower and High Tension Electric Wire upon
the lands in question.
5. Mr. Acharya further submits that when the writ application was taken
up for hearing, the learned senior advocate representing the respondent
no. 2 had submitted that they had been authorised by the State of West
Bengal under Section 164 of the Electricity Act, 2003 (hereinafter
referred to as the 2003 Act), to carry out works, concerning transmission
of electricity, as such the provisions of the 1885 Act, inter alia, including
provisions relating to payment of compensation payable to the appellants
on account of damage caused by the Transmission Company while
setting up its transmission lines, applies. It is on the basis of
submissions made on behalf of the respondent no. 2, that the learned
Single Judge had directed the District Magistrate being the respondent
no. 5 to consider all documents and pass a reasoned order, under
Section 16 of the 1885 Act, within a period of 8 weeks from the date of
communication of such order.
6. The appellants impugn the aforesaid judgment on several grounds.
7. Mr. Acharya, submits that provisions of Section 16 of the 1885 Act,
cannot be made applicable for determination of compensation payable to
the appellants. He says that the State Government has since published a
notification in the extra ordinary Gazette on 18th October, 2006 notifying
the West Bengal Works of Licensees Rules 2006 (hereinafter referred to
as the 2006 Rules). As per the 2006 Rules although it was incumbent on
the part of the respondent no. 2 to obtain prior approval from the
appellants, over whose lands the High Tension Electricity Towers have
been installed and the High Tension Electric wires have been drawn, no
such permission has been obtained. To emphasis on the above, he relies
on Rule 3 of the 2006 Rules. He further submits that the 2003 Act,
defines licensee, to mean and include both distribution as well as
transmission licensee and as such the respondent no. 2 is obliged to
ensure compliance of 2006 Rules.
8. Mr. Acharya further submits that the authority to determine
compensation under sub rule 1 of rule 3 of 2006 Rules, vests with the
District Magistrate or the Commissioner of Police or such other officers
authorised by the State Government, as the case may be. Although the
learned Single Judge had been pleased to direct the District Magistrate
to decide, the compensation payable to the appellants, however, such
decision had been directed to be taken in terms of section 16 of the 1885
Act. According to him it has never been the intention of the legislature to
permit any licensee to carry out the works, without the consent of the
owners. If 1885 Act is applied, no such consent would be required. He
further submits that once 2006 Rules have been framed under Section
67 of the 2003 Act, by the State Government, the same should get
primacy and the 1885 Act cannot be made applicable for payment of
compensation. He further submits that if determination of compensation
is made by an authority under the 1885 Act, then no opportunity would
be available to his clients to avail the remedy of referring the disputes if
any, which may arise out of the determination of compensation, to the
State Commission. He says that his clients would lose a forum which
right has statutorily been conferred on his clients.
9. Mr. Acharya by drawing our attention to the supplementary affidavit
affirmed by the appellant no.1 on 24th January, 2020, submits that the
District Magistrate by an order dated 17th December, 2019 has already
determined the compensation payable by the respondent no. 2 being the
transmission licensee, to the land owners purportedly under Section
10(c) and (d) of the 1885 Act. Mr. Acharya submits that the aforesaid
order had been passed by an authority who had no competence to pass
the same. The above order, if sustained, would prejudice the appellants,
as they would lose their right to refer the dispute as regards
determination of compensation, to the State Commission. Mr. Acharya
submits that the order passed by the learned Single Judge is not
sustainable in law and the same should be set aside. The consequential
order passed by the respondent no. 5 is also without jurisdiction, bad for
reasons stated above and the same should also be set aside. He further
submits that since work of setting up transmission towers and
energising the power lines have already been completed long ago, the
District Magistrate should now be directed determine compensation
payable to the appellants in terms of 2006 Rules framed under the 2003
Act.
10. Per contra, the Mr. Sumit Kumar Panja, learned senior advocate
appearing for the respondent no. 2 submits that his client has been
authorised under Section 164 of the 2003 Act, to carry out the works by
the State Government. According to Mr. Panja, once such an order under
section 164 of the 2003 Act is issued, the licensee become vested with
the powers of the Telegraph authority and all the provisions of 1885 Act
apply. According to Mr. Panja, the 2003 Act itself carves out an
exception, of conferring a right on the transmission licensee to carry out
its works by exercising powers under the 1885 Act. Mr. Panja submits
that once the provisions of 1885 Act are made applicable, question of
falling back on the 2006 Rules which has been framed under Section 67
of the 2003 Act cannot and does not arise. According to Mr. Panja the
1885 Act provides for manner of exercise of power by the District
Magistrate as regards determination of compensation. Drawing our
attention to sub-rule 4 of rule 3 of the 2006 Rules, Mr. Panja submits
that the aforesaid rule 3 has no application in cases where a permission
is accorded under Section 164 of the 2003 Act. As such there is no
irregularity on the part of the learned Judge in directing the respondent
no. 5 to decide the issue under Section 16 of the 1885 Act.
11. We have heard the advocates for the respective parties at length, we
find that the primary question that falls for consideration in the instant
appeal is whether the provisions relating to determination of
compensation under the 1885 Act, can be made applicable in respect of
works to be carried out by the transmission licensee, when empowered
under Section 164 of the 2003 Act.
12. Before proceeding further we must indicate that perusal of Section
164 of the 2003 Act would demonstrate that in order to invoke the
aforesaid section an order in writing from the appropriate Government,
in this case being the State Government, needs to be issued. While
responding to our query, Mr. Panja, has disclosed a notification dated
16th August, 2005 issued by the Principal Secretary, Government of West
Bengal, wherefrom it would appear that the State Government in
exercise of powers conferred by Section 164 of the said Act, has
authorized the respondent no.2 to exercise all power vested in the
telegraph authority under part III of the Act, 1885, in respect of electric
lines and electric plant established or maintained, ought to be so
established or maintained for transmission and/or supply of electricity
or for the purpose of telephonic or telegraphic communication necessary
for the proper coordination of the works within the licence area of the
respondent no.2.
13. Sub rule 4 of rule 3 of 2006 Rules, provides that nothing in rule 3
shall affect the powers conferred upon any licensee under Section 164 of
the said Act. Undoubtedly, 2006 Rules has been framed under Section
67(2) of the 2003 Act. From the aforesaid rules, it seen that the rule 3 of
the 2006 Rules framed under Section 67(2) of the 2003 Act has not been
made applicable in cases where the licensee has been empowered under
164 of the 2003 Act. As such there is no conflict in exercising powers
under 1885 Act.
14. We must, however, note that the primary question, which fell for
consideration as to whether the respondent no. 2,by reasons being
vested with powers under 1885 Act, assumes the mantle of a Telegraph
Authority within the meaning of the 1885 Act, insofar as payment
determination of compensation is concerned, is no longer res integra.
The Hon'ble Supreme Court in the case of Power Grid Corporation of
India Limited Vs. Century Textiles and Industries Limited & Ors.1 has,
inter alia, held :
"19. Another submission made was that permission of the writ petitioner was not obtained which was needed as per Rule 3 of the 2006 Rules. Rule 3(a) reads as under:
"3. Licensee to carry out works.--(1) A licensee may--
(a) carry out works, lay down or place any electric supply line or other works in, through, or against, any building, or on, over or under any land whereon, whereover or whereunder any electric supply line or works has not already been lawfully laid down or placed by such licensee, with the prior consent of the owner or occupier of any building or land;"
20. In the instant case, the aforesaid Rule is not applicable in view of Section 164 of the Electricity Act, 2003, which reads as under:
Power Grid Corporation of India Limited Vs. Century Textiles and Industries Limited & Ors., (2017)5 SCC 143
"164. Exercise of powers of telegraph authority in certain cases.--The appropriate Government may, by order in writing, for the placing of electric lines or electrical plant for the transmission of electricity or for the purpose of telephonic or telegraphic communications necessary for the proper coordination of works, confer upon any public officer, licensee or any other person engaged in the business of supplying electricity under this Act, subject to such conditions and restrictions, if any, as the appropriate Government may think fit to impose and to the provisions of the Indian Telegraph Act, 1885 (13 of 1885), any of the powers which the telegraph authority possesses under that Act with respect to the placing of telegraph lines and posts for the purposes of a telegraph established or maintained, by the Government or to be so established or maintained."
21. It is not in dispute that in exercise of powers under the aforesaid provision, the appropriate Government has conferred the powers of telegraph authority vide Notification dated 24-12-2003 exercisable under the Telegraph Act, 1885 upon the Power Grid. It may also be mentioned that a Central transmission utility (CTU) is a deemed licensee under the second proviso to Section 14 of the Electricity Act, 2003. Power Grid is a Central transmission utility and is, therefore, a deemed licensee under the Electricity Act, 2003. This coupled with the fact that Power Grid is treated as authority under the Telegraph Act, 1885, it acquires all such powers which are vested in a telegraph authority under the provisions of the Telegraph Act, 1885 including power to eliminate any obstruction in the laying down of power transmission lines. As per the provisions of the Telegraph Act, 1885, unobstructed access to lay down telegraph and/or electricity transmission lines is an imperative in the larger public interest. Electrification of villages all over the country and availability of telegraph lines are the most essential requirements for growth and development of any country,
economy and the well-being/progress of the citizens. The legislature has not permitted any kind of impediment/obstruction in achieving this objective and through the scheme of the Telegraph Act, 1885 empowering the licensee to lay telegraph lines, applied the same, as it is, for laying down the electricity transmission lines."
15. In the aforesaid judgment in paragraphs 23 and 24 the Hon'ble
Supreme Court has also inter alia considered the applicability of the
2006 Rules and has, inter alia, held as follows:
"23. Section 10 of the Telegraph Act, 1885 empowers the telegraph authority to place and maintain a telegraph line under, over, along or across and posts in or upon any immovable property. The provision of Section 10(b) of the Telegraph Act, 1885 makes it abundantly clear that while acquiring the power to lay down telegraph lines, the Central Government does not acquire any right other than that of user in the property. Further, Section 10(d) of the Telegraph Act, 1885 obliges the telegraph authority to ensure that it causes as little damage as possible and that the telegraph authority shall also be obliged to pay full compensation to all persons interested for any damage sustained by them by reason of the exercise of those powers.
24. As Power Grid is given the powers of telegraph authority, Rule 3(1) of the 2006 Rules ceases to apply in the case of Power Grid by virtue of execution clause contained in sub-rule (4) of Rule 3 which reads as under:
"3. (4) Nothing contained in this rule shall effect the powers conferred upon any licensee under Section 164 of the Act.""
16. Proceeding further the Hon'ble Supreme Court has concluded that
the determination of compensation is required to be made in terms of the
provisions of the Telegraph Act, and that the final authority to determine
sufficiency of compensation vests in the District Judge in terms of
Section 16(3) of 1885 said Act.
17. In light of the above, we are of the opinion, it is the primary
obligation of the respondent no.2 in terms of Section 10 (d) of the
Telegraph Act, 1885 to determine compensation and disburse the same
to all persons interested for any damage sustained by them, by reasons
of exercise of authority conferred upon the respondent no.2, under
Section 164 of the 2003 Act. If, however, any dispute arise as regards
entitlement to receive compensation, or as to the proportion in which the
persons interested are entitled to share in it, or as regards sufficiency of
the compensation so determined or entitlement to receive compensation
under the 1885Act, the same shall be decided by the District Judge in
accordance with section 16(4) of the 1885 Act.
18. In the present case the respondent nos. 2 to 4 have not disclosed any
document or records so as to demonstrate that compensation has
already been determined by them.
19. We, however, find that the appellants have made out a specific case
that they have suffered damages, such fact would corroborate from the
representation dated 17th of April, 2019. Records would, however, reveal
that meetings had been convened to discuss issues relating to execution
of 132kV transmission line project. Similar meetings were also convened
by the District Magistrate, to discuss the issues raised by the persons
affected by the project, which, inter alia, includes the appellants and
upon such discussion the said officer arrived at a finding that the
compensation rate for agricultural land would be Rs. 20/- per square
metre and value for non-agricultural land/bastu would be Rs. 173/- per
square metre.
20. It has, however, been brought to our notice that pursuant to
directions passed by the learned Single Judge, the respondent no. 5 has
already determined compensation. We are of the view that the
respondent no. 5 does not enjoy the authority or jurisdiction to make
any determination in terms of the 1885 Act. We are also of the view that
the respondent no.5 cannot be conferred with any power as are available
to the Telegraph authority under Section 10(d) of the 1885 Act. In any
event, no such decision can also be taken by the District Judge at the
first instance without there being a determination by the respondent
no.2 or its agents.
21. For reasons discussed above, the order impugned dated 30th July,
2019 passed by the learned Single Judge cannot be sustained and is,
accordingly, set aside. The consequential order dated 17th December,
2019 passed by the respondent no.5 which is dehors the provisions of
the 1885 Act, is also quashed.
22. We find that the matter has been pending for several years. We thus
direct the respondent no.2 to consider the representation dated 17th of
April, 2019, annexed at page 152 of the stay application and to take a
decision in the matter as regards the quantum of compensation payable
to the affected persons including the individual appellants upon giving
an opportunity of hearing to all interested parties and to communicate
such decision to the appellants within a period of eight weeks from date
of communication of this order along with a copy of the representation
dated 17th of April, 2019. At the time of hearing the appellants would be
at liberty to file additional documents in support of their claim. Upon
determination of such compensation, the West Bengal State Electricity
Transmission Company shall disburse same within a period of two
months.
23. We, however, make it clear that the if the appellants are aggrieved
by the decision to be taken by the respondent no.2, it shall be open to
them to challenge such decision before the learned District Judge having
jurisdiction in terms of sub-section 3 of Section 16 of the 1885 Act.
24. We find that an application being CAN No.12462 of 2019 has been
filed by 12 several applicants who are seeking addition as parties in the
present appeal. We find that the applicants herein have not moved any
application under Article 226 of the Constitution of India. They simply
seek addition in the instant appeal. Since we have already directed the
respondent no.2 to take a decision in respect of persons affected, we
grant liberty to the applicants to approach the respondent no.2 within a
period of 3 months from date. If such application is filed, within the time
specified hereinabove the same shall be decided by the respondent no.2
upon giving an opportunity of hearing of all interested parties within a
period of 8 weeks thereafter. Nothing therefore, survives in the
application being CAN No. 12462 of 2019 and the same is, accordingly,
disposed of.
25. With the aforesaid direction, the appeal being FMA No. 663 of 2022
and the application being CAN No. 11814 of 2019 are disposed of.
26. There shall, however, be no order as to costs.
27. Urgent certified copy of the aforesaid order if applied for be made
available to the parties on urgent basis.
(Raja Basu Chowdhury, J.) (Tapabrata Chakraborty, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!