Citation : 2023 Latest Caselaw 3016 Cal
Judgement Date : 28 April, 2023
Form No.J(2)
IN THE HIGH COURT AT CALCUTTA
CONSTITUTIONAL WRIT JURISDICTION
APPELLATE SIDE
Present :
The Hon'ble Justice Raja Basu Chowdhury
WPA 2868 of 2023
Gora Chand Adhikary & Anr.
Versus
The State of West Bengal & Ors.
For the petitioners : Mr. Subhas Chandra Sarkar.
For the respondent no.4 : Mr. Debashis Kundu
Mr. A. Bose
Heard on : 27.02.2023
Judgment on : 28.04.2023
Raja Basu Chowdhury, J:
1. The petitioners claim to have been appointed by the company
namely M/s Eastern Paper Mills Ltd. The petitioners claim that
they were refused employment. Challenging refusal of
employment, a conciliation proceeding was initiated.
Subsequently, the appropriate Government by powers conferred
under Section 10 read with Section 2A of the Industrial Disputes
Act, 1947 (hereinafter referred to as the "said Act") was, inter
alia, pleased to frame the following issues and had referred the
same to the Fifth Industrial Tribunal:
"1. Whether refusal of employment of Sarbashri Ashis Kumar Bose, Dipak Kumar Sen, Gora Chand Adhikari, Sankar Das, Joydeb Bhattacharjee, Haridas Malo and Debasish Banerjee by the management of M/s. Eastern Paper Mill Limited w.e.f. 27.12.2006 is justified?
2. What relief, if any, are the workmen entitled to?"
2. Subsequently by order of the Labour Department the case was
transferred to the Second Industrial Tribunal.
3. In connection with the above reference case the petitioners had
filed an application under Section 15(2)(b) of the said Act. The
same was, however, rejected on the ground that the same was
filed belatedly.
4. Being aggrieved a writ application was filed before this Hon'ble
Court which was registered as WP No. 15561 of 2012. By an
order dated 7th May, 2014, this Hon'ble Court was, inter alia,
pleased to set aside the order of rejection and directed the
Tribunal to decide the matter on the basis of evidence on record
after giving an opportunity to the parties to argue the matter and
also directed the Tribunal to revisit the application under Section
15(2)(b) of the said Act, and pass a reasoned order. By the
aforesaid order this Hon'ble Court also directed the Tribunal to
decide the main matter on merits as expeditiously as possible,
preferably within a period of 6 (Six) months from the date of
conclusion of evidence.
5. Since then by an order dated 20th March, 2019, the Tribunal
was, inter alia, pleased to allow the application under Section
15(2)(b) of the said Act, on contest thereby holding that the
petitioners shall be entitled to get interim relief equivalent to
subsistence allowance admissible under the West Bengal
Payment of Subsistence Allowance Act, 1969, with effect from the
date of the order of reference under Section 10(2A) of the said
Act. By the aforesaid order the Tribunal also fixed a date for
further cross-examination of the opposite party's witness no. 3.
Since then, the matter had been kept pending.
6. In the interregnum, the learned Second Industrial Tribunal, West
Bengal, by an order dated 26th May, 2022 was, inter alia, pleased
to record that since both parties are not willing to proceed, the
case should be dismissed and following such observation, he
held since the proceedings under Section 10(2A) of the said Act is
dismissed, as the industrial dispute between the parties is no
longer in existence. The aforesaid order was directed to be
treated as an award.
7. The petitioners were unaware of the aforesaid order and had no
notice of such order until the time mentioned hereinafter.
Immediately upon ascertaining the factum of passing of the
aforesaid award, the petitioners had filed an application before
the Tribunal, inter alia, praying for review of the aforesaid order
on the ground that the petitioners were unaware of the order of
dismissal. During the Covid period the petitioners could not
contact their advocates and could not take steps in the matter.
In the aforesaid facts the petitioners prayed for review of the
order dated 26th May, 2022. The said application was, however,
rejected by the Tribunal by order dated 6th September, 2022,
inter alia, on the ground that the review petition had not been
filed within 15 days from the date of the award, the same was
barred by limitation and cannot be considered legally.
8. Mr. Sarkar, learned advocate appearing on behalf of the
petitioners, submits that the petitioners were completely in the
dark and unaware with regard to the factum of passing of the
aforesaid order dated 26th May, 2022. In fact, subsequent to the
passing of the order for interim relief, a writ application was filed
before this Hon'ble Court challenging the same. Such application
was registered as WPA 15561 of 2021. The respondent/ employer
did not comply with the order of interim relief and due to paucity
of funds/ financial hardship, the petitioners also could not keep
regular contact with their lawyer. In the interregnum, pandemic
intervened. On repeated occasions the respondent no.4 took
adjournments. On one hand the petitioners were denied the
benefit of the order for interim relief passed by the learned
Tribunal by reasons of pendency of the writ application and on
the other hand the present proceedings were dismissed. It is
submitted that since the matter was pending before this Hon'ble
Court, no further steps were taken in connection with the main
application pending before the Tribunal. It is submitted that it
was expected that final hearing before the Tribunal would take
place after disposal of the application pending before this Hon'ble
Court. He says that is only on 5th July, 2022 that the respondent
no. 4 made a disclosure before the Hon'ble Court that the
Industrial dispute is no longer in existence. According to the
petitioners they were unaware of the order of dismissal till 5 th
July, 2022. Only thereafter the review was filed.
9. The Tribunal also did not take into consideration that the
petitioners were interested in the matter. He says that the
Tribunal had overlooked the fact that the respondent no.4 had
denied the petitioners, the benefits of the interim relief which
coupled with the pandemic, prevented the petitioners from taking
effective steps in the matter. Financial stress also prevented the
petitioners from effectively perusing the matter before the
Tribunal.
10. Mr. Sarkar, learned advocate representing the petitioners,
submits that the application for review was dismissed on a
technical ground. He says that technicality should not stand in
any way of the petitioners getting relief. In support of his
contention, he has placed reliance on a judgment delivered by
this Hon'ble Court in the case of Ganesh Chandra Guha v.
State of West Bengal & Ors., reported in 2023 SCC OnLine
Cal 241.
11. Mr. Kundu, learned advocate enters appearance on behalf
of the respondent no.4. He submits that the Tribunal has rightly
dismissed the application for review. He says that no review is
permissible beyond 15 days in terms of Rule 27 of the West
Bengal Industrial Disputes Rules, 1958. He prays for dismissal of
this application.
12. Heard the learned advocates appearing for the respective
parties and considered the materials on record.
13. It also appears from the record that the application for
interim relief was allowed by order dated 29th March, 2019. The
employer/ respondent no. 4 did not comply with the direction for
interim relief. Challenging the order for interim relief, a writ
application was filed on 27th September, 2021, which was
registered as WPA 15561 of 2021. The petitioners claim that the
aforesaid writ application was called on 11 occasions and on
each and every occasion the respondent no.4 took adjournments.
It is only on 5th July, 2022 the respondent no. 4 made a
disclosure before the Hon'ble Court that the Industrial dispute is
no longer in existence. As such according to the petitioners they
were unaware of the order of dismissal till 5th July, 2022. Only
thereafter the review was filed. This apparently was not
considered.
14. Even otherwise the petitioners are without any service for a
more than a decade. Although the petitioners had been able to
secure bare minimum relief to sustain themselves in the form of
subsistence allowance, the employer chose not to make payment
of the same. Being unable to sustain themselves the petitioners
could not get the assistance of a lawyer. It is at this stage when
the main application was pending for hearing of arguments on
merits that the same was dismissed. It is, therefore, apparent
that when the reference case was dismissed, witness action was
already completed. Simply because the parties did not submit
their arguments, the same could not be a ground for the
Tribunal not to adjudicate upon the issue, especially when the
witness action was otherwise complete. In the instant case,
records would reveal that challenging the order for interim relief,
a writ application was filed, and the respondents did not make
payment of such interim relief. In my view, in the facts of the
case the Tribunal ought not to have rejected the petitioners'
application solely on the ground of non-filing of arguments. I find
that the petitioners have also relied on a judgment delivered by
this Hon'ble Court in the case of Ganesh Chandra Guha v.
State of West Bengal & Ors., (supra). From a perusal of the
aforesaid judgment, it would appear that this Court while placing
reliance on a judgment delivered by the Hon'ble Supreme Court
in the case of Grindlays Bank Ltd. v. Central Govt. Industrial
Tribunal, reported in 1980 Supp SCC 420, had quoted
paragraph 18 of such judgment, wherein it has been, inter alia,
observed as follows:
"18. It was, therefore, submitted before us, relying upon Grindlays Bank Ltd. v. Central Govt. Industrial Tribunal [1980 Supp SCC 420 : 1981 SCC (L&S) 309] that even in the absence of an express power of review, the Tribunal had the power to review its order if some illegality was pointed out. The submission must be rejected as misconceived. The submission does not take notice of the difference between a procedural review and a review on merits. This Court in Grindlays Bank Ltd. v. Central Govt. Industrial Tribunal [1980 Supp SCC 420 : 1981 SCC (L&S) 309] clearly highlighted this distinction when it observed: (SCC p. 425, para 13) "Furthermore, different considerations arise on review. The expression 'review' is used in the two distinct senses, namely (1) a procedural review which is either inherent or implied in a court or Tribunal to set aside a palpably erroneous order passed under a misapprehension by it, and (2) a review on merits when the error sought to be corrected is one of law and is apparent on the face of the record. It is in the latter sense that the Court in Patel Narshi Thakershi case [(1971) 3 SCC 844 : AIR 1970 SC 1273] held that no review lies on merits unless a statute specifically provides for it. Obviously when a review is sought due to a procedural defect, the inadvertent error committed by the Tribunal must be corrected ex debito justitiae to prevent the abuse of its process, and such power inheres in every court or Tribunal."
15. From the aforesaid it would appear that when a party is
not heard or when the matter was heard and decided on a date
other than the date fixed for hearing, or under a mistaken
impression that the party had notice, although it had no notice
or the party could not attend, for no fault of his or any other
similar cases, the matter has to be reheard in accordance with
law without going into the merits of the order passed. In the
present case, the Tribunal did not take into consideration the
fact that the petitioners were otherwise prevented by sufficient
cause for not appearing before the Tribunal when the matter was
dismissed. This aspect was not taken into consideration by the
Tribunal at all while passing the order dated 6 th September,
2022. The Tribunal proceeded on the basis of technicality to deny
relief to the petitioners. In a case of this nature the Tribunal
ought to have reviewed its order and ought to have restored the
matter to its file, especially when the petitioners had been
sincere and bona fide in pursuing the case.
16. In the facts stated hereinabove, the order passed by the
Tribunal on 26th May, 2022 cannot be sustained. The same is,
accordingly, set aside. The case no VIII-18 of 2008 is restored to
original file and location with a direction upon the learned
Tribunal to conclude the hearing by giving opportunity to the
parties to place their respective arguments. In the event the
parties do not place their arguments, an award must be passed
on merits taking into consideration the case made out by the
parties in their pleadings and the evidence already on record.
17. With the aforesaid observations, and directions the present
application being WPA 2868 of 2023 is disposed of.
18. There shall be no order as to costs.
19. Urgent photostat certified copy of this order, if applied for,
be given to the parties on priority basis upon completion of
requisite formalities.
(Raja Basu Chowdhury, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!