Citation : 2023 Latest Caselaw 2894 Cal
Judgement Date : 25 April, 2023
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
W.P.A. No.16229 of 2004
Adhunik Corporation Ltd. And another
Vs.
West Bengal State Electricity Distribution
Company Limited and others
For the petitioner : Mr. Partha Sarathi Sengupta,
Mr. Biswaroop Bhattacharya,
Mr. Nilay Sengupta,
Mr. Sujit Banerjee
For the WBSEDCL : Mr. Sumit Kumar Panja,
Mr. Sujit Sankar Koley
Hearing concluded on : 20.04.2023
Judgment on : 25.04.2023
Sabyasachi Bhattacharyya, J:-
1. The writ petitioner no.1-Company is a consumer of electricity from the
respondent no.1, the West Bengal State Electricity Distribution
Company Limited (WBSEDCL). Previously it was a consumer under
the Durgapur Projects Limited (DPL), which was subsequently taken
over by the WBSEDCL, a Government of West Bengal undertaking.
2. The petitioners have challenged the imposition of preliminary penal
charge of Rs.20,000,00/- vide Notice dated August five, 2002 issued
by the DPL and seek a refund of the said amount with interest.
3. A subsequent consequential bill issued on February 6, 2004,
demanding an amount of Rs.2,87,07,420/- as assessment for theft or
pilferage of energy by the petitioners and a further notice dated
September 6, 2004 of disconnection in default of payment of such
sum have also been assailed in the present writ petition.
4. The learned Senior Advocate for the petitioners argues that the
allegation of pilferage is an afterthought. There was no complaint or
FIR at any point of time lodged by the DPL. The alleged pilferage was
not detected previously. Moreover, it is argued that the allegation of
digging/using a cable trench to have access to the meter room is
levelled for the first time in the affidavit-in-opposition filed by the
WBSEDCL in the present writ petition. The allegation of pilferage is
not credible since the meter room housing the meter of the DPL (now
WBSEDCL) has all along been under lock and key of the licensee and
was opened and closed exclusively by the personnel of the licensee at
the time of holding inspections and taking meter readings.
5. In the previous billing cycle prior to the alleged act of pilferage, regular
meter reading was taken by the DPL personnel, but no allegation of
tampering was made.
6. It is submitted that since the meter room has all along been under the
exclusive control of the licensee, there could not be any hand of the
petitioner at all in the pilferage, if any.
7. The WBSEB Regulations/Guidelines, sought to be implemented by the
licensee, was never applicable to the contract between the petitioner
and the DPL. Although the agreement between the two referred to
DPL Regulations, there was no Regulation or general conditions of
contract of the DPL at any point of time.
8. It is argued that the amount claimed by the licensee from the
petitioner was patently perverse and without any basis. In this
context, the learned Senior Advocate for the petitioners cites a
Supreme Court judgment reported at (2019) 4 SCC 500 [Sarvepalli
Ramaiah (Dead) as per legal representatives and others Vs. District
Collector, Chittoor District and others], where it was held that any
decision based on perversity, patent illegality, irrationality and
procedural irregularity ought to be set aside.
9. It is next argued that the defence sought to be advanced by the
licensee/respondent has been taken for the first time after five years
of the alleged incident, in the affidavit-in-opposition of the licensee.
The digging up of a cable trench at the location is not established from
the records at all. In fact, the petitioners argue, the relevant
paragraphs in the opposition of the Respondents are affirmed to be
true to knowledge of the deponent derived from the records, without
any records being produced in support thereof. In this context, the
learned Senior Advocate cites Bharat Singh & Ors. V. State of Haryana,
reported at (1988) 4 SCC 434, for the proposition that no defence can
be taken for the first time in affidavit, particularly without any
supporting document, which renders the defence of the respondent a
nullity.
10. It is submitted further that the payment by the petitioners of the
amount of Rs.20,000,00/- as per the preliminary claim of the DPL was
made under duress and coercion, under the threat of disconnection.
It is argued that there was unequal bargaining power prevailing
between the parties. The petitioner no.1-industry employs several
workers, who would become jobless overnight if such payment was
not made and the electricity supply was disconnected, thereby
stopping the business of the Company. It is argued that mere
payment of the preliminary sum demanded, under protest, could not
tantamount to an admission in the true sense of the term and, as
such, cannot be relied on by the WBSEDCL for indicting the
petitioners of the offence of theft.
11. Learned counsel appearing for the WBSEDCL submits that vide letter
dated July 2, 2002, the petitioners accepted the inspection report of
the DPL, which alleged pilferage, and agreed to pay any compensation
and penalty levied by the DPL immediately.
12. As such, the petitioners cannot subsequently resile from such
position, particularly after having made the payment in terms of the
preliminary claim of the DPL.
13. It is submitted that by operation of Section 185 of the Electricity Act,
2003 (for short, "the 2003 Act"), the provisions of the 2003 Act are
applicable in the present case. Although at the relevant juncture in
2002, the previous Act, that is, the Electricity Act, 1910 was
prevalent.
14. Hence, in terms of the Regulations framed by the West Bengal
Electricity Regulatory Commission (WBERC) under the 2003 Act as
well as the provisions of the said Act, the licensee was well within its
authority and have complied with all due procedure of law, to claim
such assessed amount on the ground of pilferage.
15. Learned counsel for the WBSEDCL places reliance on Clause 5.0 of
Regulation 55 of the 2003 Act as well as Section 185 of the same in
support of his arguments.
16. It is further argued that the General Conditions of Supply of the
WBSEB (West Bengal State Electricity Board) at that point of time also
governed the power supply agreement between the parties.
17. Upon hearing learned counsel, the plinth of the defence appears to be
the "admission" of the petitioners with regard to pilferage.
18. A perusal of the letter issued by the petitioner no.1 dated July 2,
2002, addressed to the Commercial Engineer, DPL indicates that the
petitioner no.2, a Director of the petitioner no.1-Company, accepted
and acknowledged the record notes drawn on July 2, 2002 by and
between the DPL and the petitioner no.1 in connection with tampering
of the energy meter at the premises and also afforded apology for the
same. Further, the petitioners undertook to pay "any compensation
and penalty" immediately regarding damage of meter, loss of energy
due to tampering of meter as would be claimed by the DPL. The last
sentence of the said communication, however, indicated that on the
basis of the undertaking, the DPL was requested to restore the power
supply immediately.
19. Such communication, per se, cannot tantamount to an admission of
the act of pilferage or theft on the part of the petitioner within the
contemplation of Section 135 of the 2003 Act. It is also evident from
the last sentence thereof that the same was given in the context of the
pending threat of not restoring the electricity supply, which had been
disconnected two days before for shifting of power connections to a
different zone for reasons entirely unconnected with the allegation of
meter-tampering, which would render the petitioner no.1 out of
business. Hence, it cannot be said that the said undertaking to pay
and the subsequent payment pursuant thereto was an unqualified
'admission' of the act of pilferage on the part of the petitioners.
20. The DPL, taking advantage of such concession on the part of the
petitioners, given under the obvious pressure of losing the electricity
connection, raised a primary penal charge of Rs.20,000/- vide
communication dated August 5, 2002. It is reflected from the said
communication, being Annexure P-6 at page 97 of the writ petition,
that the same was taken as a primary action against ''malpractices on
the seals related to the metering circuit and energy meter installed at
DPL cutout" at the factory premises and taking into account the
record notes on checking of energy meter and metering circuit at the
premises on July 2, 2002 as well as based on the undertaking given
on even date by the petitioners. However, no basis of calculation for
arriving at the quantum of Rs.20,000,00/- is disclosed at all in the
communication, or any other ancillary documents. The
communication says merely that "it has been decided by the
management to impose on you a penalty of Rs.20,000,00/-'' without
disclosing any ratio backing up such calculation. Even on the bill
annexed at page 98 of the writ petition, the primary penalty charge
against tampering of metering circuit including energy meter has been
unilaterally and arbitrarily determined at Rs.20,000,00/-, without any
disclosure whatsoever of the process or basis of calculation.
21. Upon raising of such bill on August 5, 2002, the payment was made
by the petitioner "under protest" pending the outcome of the internal
enquiry, in view of the cordial relationship enjoyed by the petitioners
with the DPL. Such communication was made on August 30, 2002
and the cheque of Rs.20,000,00/- was received by the DPL on August
31, 2002, along with the letter of protest.
22. It was clearly mentioned in the letter that the Board had directed to
institute a thorough enquiry into the circumstances leading to the
abnormalities observed in the inspection record notes inasmuch as
there was no connection of electric power during the relevant point of
time facilitating transfer of power connections from 'C' zone to 'C1'
zone inasmuch as the lock and seal of the main entrance were found
intact at the time of inspection.
23. If we look into the surrounding circumstances, throughout the
previous day and the day of the alleged incident, the electricity supply
to the petitioners' factory premises remained disconnected, since the
DPL was shifting the power connections from the 'C' zone to 'C1' zone.
24. As such, there was no occasion for the petitioner to commit pilferage
at the juncture of inspection on July 2, 2002, simply because the
electricity supply to the premises was already disconnected for two
days at that point of time.
25. Moreover, nothing has been produced by the WBSEDCL to indicate
that the DPL personnel had detected any tampering with the lock and
seal of the meter room while getting access thereto.
26. All along, admittedly, the meter room was under the lock and seal of
the DPL. As such, there could not have been any scope of the
petitioners having any access to the energy meter or the metering
circuit. Moreover, it was the DPL personnel who were working in the
meter room on the day of the alleged discovery of pilferage and on the
previous day. Hence, the onus of proof lay on the license to show the
involvement of the petitioners in any manner whatsoever.
27. Insofar as the allegation of cable trench is concerned, the said
allegation is made for the first time, as rightly contended by the
petitioners, in the affidavit-in-opposition, about five years after the
alleged incident and during pendency of the writ petition. At the
relevant juncture, however, such a serious incident was never
reported before any law enforcement authority at all. Not a single
complaint, FIR or criminal proceeding was initiated at the behest of
the licensee against the petitioners. It is not credible to a prudent
man as to how the DPL failed to report the matter to the police
authority or initiate a criminal proceeding, if a cable trench was dug
or used for the purpose of getting access into the meter room.
28. On the contrary, the presumption arises that the DPL personnel were
responsible with regard to the breakage of the seal, if any, since the
incident occurred during a period when the employees of the DPL were
engaged in shifting of the power connections from one zone to another
and at all material points of time prior thereto the meter room was
under the lock and seal of the licensee. Hence, during the entire
relevant period, the DPL had been in possession and control of the
meter room. Even on the last inspection in the immediately preceding
billing cycle, meter reading was taken by the DPL personnel without
any inkling of doubt as regards the tampering of the meter.
29. Hence, the entire process of levying penalty on the petitioners is
suspect.
30. It is clearly seen from the records and as per the admission of the
WBSEDCL/respondent that there was no General Conditions of
Supply of the DPL at the relevant juncture. There is nothing on record
to show that the WBSEB Conditions of Supply were applicable.
Therefore, even as per the argument of the WBSEDCL, the relevant
provisions were that on Regulation 55 of the WBERC, framed under
the 2003 Statute. It is interesting to note that the arguments of the
Respondents are contradictory in this regard. Whereas in the affidavit-
in-opposition the respondents have laid stress on the general format of
the General Conditions of Supply of the WBSEB being applicable to
the DPL, in arguments the respondents do a volte face and contend
that the 2003 Act and the Regulations framed under it were
applicable.
31. A perusal of Clause 5.0 of Regulation 55 of the WBERC shows that it
deals with assessment of electricity charges payable under Section
126 of the 2003 Act, appeal under Section 127 of the Act and recovery
of charges in connection therewith. A detailed mode of calculation has
been given therein, under the contemplation of Section 126(5) of the
2003 Act. However, not even a single line has been dedicated by the
licensee in its contemporaneous communications to indicate that such
method was applied in the present case.
32. Insofar as the ratio of Bharat Singh (supra) is concerned, the same is
squarely applicable in the present case, since no allegation of cable
trench being dug or used for pilferage was made at the relevant
juncture, nor was any FIR lodged against the petitioner. In the
absence of any criminal proceeding whatsoever, even the most gullible
person would find it difficult to swallow the explanation that no
criminal proceeding was drawn up merely due to "cordial relationship"
between the parties at the relevant juncture.
33. Rather, it is clearly deducible from the tenor of the petitioners' letter
dated July 2, 2002 and the insistence of the petitioners it their letter
on the electricity connection being restored immediately, that the
payment of Rs.20,000,00/- was paid under duress.
34. It is not a case where the electricity connection was disconnected by
the DPL on the allegation of theft within the contemplation of Section
135 of the 2003 Act. Rather, the DPL played a "dog-in-the-manger"
card to extract undertaking and payment from the petitioners, taking
advantage of the predicament of the petitioners, since the electricity
supply had been temporarily disconnected for shifting of the power
connections from one zone to another, which had no nexus with theft.
Such temporary disconnection was sought to be made absolute by the
DPL on the allegation of pilferage, made all on a sudden during the
ongoing work undertaken by the DPL personnel, which is palpably
extortive and unjust, in contravention of law and all norms of natural
justice. In fact, the petitioners are justified in arguing that the
assessments made by the licensee, both preliminary and final, are
perverse and based on precious nothing in the form of supporting
calculations.
35. Hence, the amounts charged from the petitioner, both by way of
preliminary and final assessment by the DPL, now inherited by the
WBSEDCL, is perverse and not sustainable in law.
36. Hence, WPA No.16229 of 2004 is allowed, thereby directing the
WBSEDCL to refund the amount of Rs.20,000,00/-, paid by the
petitioner as preliminary penalty, to the petitioners by October 31,
2023, along with interest on the said sum of Rs.20,000,00/- at the
rate of 6% per annum till the date of such payment
37. In the event such payment ofRs.20,000,00/-along with interest is not
made within October 31, 2023, the WBSEDCL shall pay further
interest for the period thereafter at the rate of 6% per annum on the
entire quantum payable as on October 31, 2023, including the
principal dues plus the interest accrued till October 31, 2023, till the
date of final disbursal of the amount.
38. There will be no order as to costs.
39. Urgent certified server copies, if applied for, be issued to the parties
upon compliance of due formalities.
( Sabyasachi Bhattacharyya, J. )
Later:
When the above judgment is delivered, it is pointed out by
learned counsel for the petitioners that pursuant to an interim order
of this Court, the petitioners had deposited an additional amount of
Rs.25,00,000/- (Rupees Twenty Five Lakhs) to the WBSEDCL .
Such amount, without any interest, shall be returned by the
WBSEDCL to the petitioners by May 15, 2023.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!