Citation : 2022 Latest Caselaw 6535 Cal
Judgement Date : 14 September, 2022
IN THE HIGH COURT AT CALCUTTA
CIVIL APPELLATE JURISDICTION
(Appellate Side)
MAT 877 of 2022
With
CAN 1 of 2022
Reserved on: 04.08.2022
Pronounced on: 14.09.2022
M/s. Kalimata Vyapaar Pvt. Ltd. and Another
...Appellants
-Vs-
The General Manager Northern Railways and Others
...Respondents
Present:-
Mr. Suman Dutta, Mr. Asif Hussain, Mr. Kallol Saha, Advocates ... for the appellants Mr. Avinash Kankani, Advocate ... for the respondents
Coram: THE HON'BLE JUSTICE PRAKASH SHRIVASTAVA, CHIEF JUSTICE THE HON'BLE JUSTICE SUGATO MAJUMDAR, JUDGE
Prakash Shrivastava, CJ:
1. By this intra-court appeal, writ petitioners have challenged
the order of the learned Single Judge dated 10th of May, 2022 whereby
WPA 9866 of 2020 has been disposed of with liberty to the appellants
to seek remedy of arbitration in terms of the arbitration clause
contained in the contract and by extending the interim order for a
limited period.
2. The appellants had filed the writ petition with the plea that it
is engaged in the manufacture and supply of diverse track items and
had submitted the bid in response to the NIT published by the
respondent on or about 14th of February, 2019. While submitting the 2 MAT 877 of 2022
bid, appellant had indicated and included therein the deviation under
the Techno Commercial Part by mentioning it boldly in annexure 'A'.
The technical bid of the appellants was responsive and price offer of
the appellants was opened and tabulated by the respondent and in the
reverse auction, appellants had revised their financial bid and were
declared L-1 bidder. According to the appellants, they were under the
belief that the respondent no. 1 will issue the advance acceptance in
tune with the offered document of the appellants recording therein the
deviation but on 5th of September, 2019, appellants had received two
separate letters issued by the respondent no. 2 mentioning that the bid
submitted by the appellants was accepted subject to the terms and
conditions set forth in the letter. According to the appellants, the two
letters were not as per the terms set forth in the appellant's bid. The
appellant had sent the communication dated 6th of September, 2019 to
the respondents. The plea of the appellants is that they had proceeded
under the bona fide belief that there was no concluded contract. The
respondents had issued communication dated 5th of September, 2019
stating that the appellant's bid was accepted and mentioning that the
said advance acceptance letter shall constitute a binding and
concluded contract. Thereafter, the communication dated 24th of
August, 2020 was issued by the respondents mentioning that the
appellants had not deposited the security amount as requested by the
letter dated 5th of September, 2019 against the contract, therefore, the
contract was cancelled and the security money amounting to Rs.
59,59,348/- was forfeited. Thereafter, the respondents had issued the
communication dated 12th of November, 2020 stating that non-
acceptance of counter offer by the appellants was not permissible in 3 MAT 877 of 2022
the light of appellants having undertaken while submitting the bid that
the bid did not contain any deviation. Hence, in the writ petition, the
appellant had questioned the notices dated 24th of August, 2020 and
12th of November, 2020.
3. Learned Single Judge vide impugned order dated 10th of
May, 2020 has reached to the conclusion that the appellant has the
remedy of arbitration, therefore, permitted the appellant to seek
arbitration of the dispute in terms of the arbitration clause.
4. Submission of learned counsel for the appellant is that no
concluded contract exists between the parties as the offer of the
appellant was a conditional order. His further submission is that after
exchange of affidavit before the learned Single Judge, the appellant
cannot be relegated to the remedy of arbitration and alternate remedy
is not a bar in entertaining the writ petition.
5. As against this, learned counsel for the respondent has
submitted that the appellant himself had made a request for invoking
the arbitration clause and that the respondents were not bound to
accept the deviation and concluded contract exists and even otherwise
in terms of Section 16 of the Arbitration and Conciliation Act, 1996,
the issue relating to concluded contract can be decided by the
Arbitrator.
6. We have heard the learned counsel for the parties and
perused the record.
7. It is undisputed before this Court that Clause 2903 of the
Indian Railways Standard Conditions of Contract (Supply Contract)
1997 contains the arbitration clause to the following effect:
4 MAT 877 of 2022
"2903(i): In the event of any dispute or difference between the parties hereto as to the construction or operation of this contract, or the respective rights and liabilities of the parties on any matter in question, dispute or difference on any account, or if the Railway fails to make a decision within 120 days (as referred in 2902), then and in any such case, but except in any of the "excepted matters" referred to in Clause 2902 of these Conditions, parties to the contract, after 120 days but within 180 days of their presenting their final claim on disputed matters shall demand in writing that the dispute or difference be referred to arbitration. Provided that where the claim is raised by Railways para 2903(i) shall not apply.
2903(ii)(a): The demand for arbitration shall specify the matters which are in question, or subject to the dispute or difference as also the amount of claim item-wise. Only such dispute or difference, in respect of which the demand has been made together with counter claims or set off, shall be referred to arbitration and other matters shall not be included in the reference.
2903(ii)(b): The parties may waive off the applicability of Sub-Section 12(5) of Arbitration and Conciliation Act 1996 (as amended), if they agree for such waiver in writing, after dispute having arisen between them.
2903(iii)(a): The Arbitration proceedings shall be assumed to have commenced from the day, a written and valid demand for arbitration is received by the Railway."
8. The record further reflects that though the appellant in
annexure 'A' to the bid document had mentioned the commercial
deviation but the offer of the bidder contains the following
declaration:
"3. I agree that the purchaser may, at his discretion ignore any deviation quoted by me in any uploaded document or else where in any tab other than the deviation 5 MAT 877 of 2022
tab while accepting my offer, and I shall be legally bound to accept any contract placed on me by the purchaser by ignoring any such deviation(s)."
9. It is also found that the appellant vide communication dated
10th of November, 2020 sent to the respondent no. 1 had made a
request for appointment of arbitrator for settling the matter with the
prayer to refer the matter to the arbitrator. Section 16(1) of the
Arbitration and Conciliation Act, 1996 in clear term provides that the
Arbitration Tribunal may rule at its own jurisdiction including ruling
of any objection with respect to the existence or validity of the
arbitration agreement.
10. In view of the aforesaid, learned Single Judge has rightly
observed that the issue as to whether there was a concluded contract at
all between the parties should be subject matter of the arbitration
invoked by the appellant.
11. So far as the submission of the learned counsel for the
appellant in respect of maintainability of the writ petition in a
contractual dispute in spite of existence of arbitration clause, and
reliance upon the judgment of the Hon'ble Supreme Court in the
matter of Unitech Limited vs. Telangana State Industrial
Infrastructure Corporation (TSIIC) reported in AIR 2021 SC
(SUPP) 756 is concerned, there is no dispute to the proposition that
High Court's jurisdiction under Article 226 of the Constitution is not
ousted in respect of the dispute pertaining to contractual matters or
existence of arbitration clause but each case requires consideration on
its own facts and in the facts of the present case, learned Single Judge
has not committed any error in directing the appellant to avail the 6 MAT 877 of 2022
remedy of arbitration. Mere exchange of affidavits before the learned
Single Judge does not come in the way of issuing such direction.
12. Hence, we find that the order of the learned Single Judge
does not suffer from any error and no case for interference is made
out.
13. The appeal is accordingly dismissed.
(PRAKASH SHRIVASTAVA) CHIEF JUSTICE
(SUGATO MAJUMDAR) JUDGE Kolkata 14.09.2022 ___________ PA(RB)
(A.F.R./N.A.F.R.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!