Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sk. Golam Dastagir vs The State Of West Bengal & Ors
2022 Latest Caselaw 1026 Cal

Citation : 2022 Latest Caselaw 1026 Cal
Judgement Date : 7 March, 2022

Calcutta High Court (Appellete Side)
Sk. Golam Dastagir vs The State Of West Bengal & Ors on 7 March, 2022
March 7, 2022
   ARDR
     (15)

                                   WPA 12474 of 2021

                                   Sk. Golam Dastagir
                                           Vs.
                             The State of West Bengal & Ors.

                Mr. Bikash Ranjan Bhattacharyya, Sr. Adv.,
                Ms. Santi Das,
                                                     ...for the petitioner.
                Mr. Suvoven Sengupta,
                Mr. Subir Paul,
                                                          ...for the State.


                      Heard learned counsels for the parties.

                      It is contended on behalf of the petitioner that being

                the highest bidder in e-auction for grant of lease of minor

                minerals and upon payment of one-third of the bid

                amount, Letter of Intent was issued in favour of the

                petitioner   on   25th   September,   2017.   The   petitioner

                deposited the remaining bid amount in terms of notice

                issued by the respondents on 29th November, 2017 as well

as in terms of Rule 10(2) of the West Bengal Minor

Minerals (Auction) Rules, 2016 on 27th December, 2017

which was received on behalf of the District Land & Land

Reforms Officer. The petitioner submits that the lease deed

could not be executed by the State respondents in view of

temporary suspension of execution of such lease by the

National Green Tribunal. The petitioner has prayed for

refund of the bid amount deposited by him before the

authority along with statutory interest thereon.

Learned counsel for the petitioner has placed

reliance on an order of a coordinate bench of this Court

passed on 18th September, 2020 on an identical issue in

WPA 6236 of 2020, the said order being affirmed by the

Hon'ble Division Bench by an order dated 24 th December,

2021 in MAT 1307 of 2021.

Placing reliance on the report in the form of affidavit

submitted by the State respondents, learned counsel for

the State respondents submits that though the Letter of

Intent was issued on 25th September, 2017, the petitioner

took no initiative for execution of the deed of lease despite

several notices issued upon him by the authority. In the

meantime, the order of the National Green Tribunal came

into operation and the State respondents were unable to

execute the lease. Had the petitioner taken appropriate

steps within the statutory period of time, the lease deed

could have been executed by the State respondents and

the respondents would have been in a position to collect

enormous royalty therefrom. The Government has suffered

heavy loss due to non-execution of the deed of lease on

time. As the deed could not be executed due to fault of the

petitioner, the petitioner is not entitled to refund of the bid

amount. Learned counsel further submits that clause 8 of

the Letter of Intent indicates that the Letter of Intent shall

remain valid for a period of two months from the date of

its issuance and if the successful bidder is unable to fulfil

all the above conditions within this period, he may submit

an application addressed to the District Magistrate for

extension of time. No such extension was prayed for by the

petitioner. Moreover, the claim of the petitioner is purely a

money claim which can be made before the appropriate

forum and the writ Court has no jurisdiction to deal with

such claim. Learned counsel, has placed reliance on the

judgment of the Hon'ble Supreme Court in Andhra

Pradesh Industrial Infrastructural Corporation

Limited and anr. vs. Shivani Engineering Industries

reported in (2015) 7 SCC 241 in support of his

contention.

The orders of the National Green Tribunal at

Annexure R/3 to the report submitted by the State

respondents demonstrate that the issue of illegal mining of

sand was under consideration of the Tribunal since 2015.

Despite such fact, the e-auction was floated by the

respondent authorities on 18th May, 2017 and the Letter of

Intent was issued in favour of the petitioner on 25 th

September, 2017. It is admitted by the State respondents

in their letter issued to the petitioner on 11 th September,

2018 that the entire bid amount was deposited by the

petitioner on 27th December, 2017. The petitioner was

called upon to appear before the authority with all

necessary documents for execution of the lease deed on 8 th

September, 2018 despite the order of the National Green

Tribunal imposing suspension of mining activities passed

on 4th September, 2018. No time frame being mandated

for depositing the second and third installments by the

petitioner under Rule 10(2) of the West Bengal Minor

Minerals (Auction) Rules, 2016, the petitioner cannot be

held guilty of making delayed payment of the said amount,

more so, as the amount was accepted by the State

authorities without a demur.

The authority relied upon by the State respondents

deals with a fact situation where the incumbent did not

implement the revised project within two years from the

date of an agreement though it was put in permission of

the plot and granted permission to change the

manufacturing activity. There being no such non-

compliance by the petitioner in the present matter, the

ratio decidendi of the said judgment is not applicable to

the facts and circumstances of the present case.

The petitioner has claimed refund of the bid amount

deposited by him before the authority. It is a fact that the

deed of lease could not be executed due to the ban

imposed by the National Green Tribunal.

In view of the same, the petitioner is entitled to

refund of the entire bid amount by the authority along

with statutory interest thereon, given the fact that the

amount has been lying with the authority for a

considerable period of time.

Accordingly, the writ petition being WPA 12474 of

2021 is disposed of directing the third respondent to cause

refund of the entire bid amount along with statutory

interest thereon to the petitioner within a period of two

months from the date of communication of this order.

However, there shall be no order as costs.

Since no affidavits are invited, the allegations

contained in this writ petition are deemed not to be

admitted.

Urgent certified website copy of this order, if applied

for, be supplied to the parties upon compliance with all

requisite formalities.

(Suvra Ghosh, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter