Citation : 2022 Latest Caselaw 17 Cal
Judgement Date : 5 January, 2022
IN THE HIGH COURT AT CALCUTTA
CONSTITUTIONAL WRIT JURISDICTION
APELLATE SIDE
The Hon'ble JUSTICE SUVRA GHOSH
W.P.A. 5538 of 2021
Biswajit Saha & Ors.
Vs.
Union of India & Others.
For the Petitioners: Mr. Kishore Dutta, Adv.
Mr. Amit Pan, Adv.
Mr. Aryak Dutt, Adv.
Mr. Dipankar Das, Adv.,
For the Power Grid Corporation: Mr. Bikash Ranjan Bhattacharjee, Adv.
Mr. Piyush Chaturvedi, Adv.
Mr. Uttam Kr. Mandal, Adv.,
For the State: Mr. Ansar Mondal, Adv.
Mrs. Tapati Samanta, Adv.,
Hearing concluded on: 23.12.2021
Date: 05.01.2022
SUVRA GHOSH, J. :-
1. The prayers of the writ petitioners are as follows:-
"(a) A writ in the nature of mandamus do
issue directing the Respondent authorities
and more particularly the Respondent No.3
not to take any action towards installation of
the high tension electric transmission line or
the supporting poles on the land of the
petitioners without following the due process
of law;
(b) A writ in the nature of prohibition do issue
prohibiting the Respondent authorities from
encroaching the land of the Petitioners
without following the due process of law;"
2. The petitioners are aggrieved by the decision making process adopted by
the third respondent in installing a pole for transmission of high voltage
electricity by encroaching upon the petitioners' land. Learned counsel for
the petitioners submits that no notice of such installation was served
upon the petitioners in terms of the provisions of the Electricity Act, 2003
and in any event, if such high tension electricity pole is to be installed on
the land of the petitioners, notice ought to have been given for acquisition
of the said land and payment of adequate compensation as per the market
value of the land to the petitioners. On inquiry, the petitioners were
informed that no notice was given by the third respondent to any person
whose land was likely to be affected by such installation and upon
insistence of the first petitioner, the third respondent handed over a
sketch map indicating its plan of action and laying of high tension line on
the petitioners' land.
3. Referring to section 10(d) of the Indian Telegraph Act, 1885, learned
counsel for the petitioners' submits that in installing such high tension
electric transmission line, the authority should do as little damage as
possible and pay full compensation to all persons interested for such
damage sustained by them. It is further submitted that the high tension
electric line shall run through the middle of the land covering a
substantial area and the land cannot be utilised for any other purpose.
The petitioners intend to set up a factory in the said land after conversion
of the land and such application for conversion is pending before the
concerned authority. The petitioners have taken the court to paragraph 6
(d), (e), & (i) of the affidavit-in-opposition used by the third respondent
which demonstrates that in exercise of powers under section 164 of the
Electricity Act, 2003, the Central Government, vide notification no. 610
dated 16-02-2018 published in the Gazette of India, has conferred the
powers of "Telegraph Authority" upon PMJTL/Power Grid and as a part of
400 KV Jeerat (New)-Subhashgram Transmission Line, the third
respondent is required to install transmission towers, amongst others,
over the land of the petitioners to enable symmetric stringing of
transmission line. Also, this respondent handed over a road sketch map
indicating the route map and alignment of the transmission line over the
petitioners' land as well as the adjoining lands.
4. Learned counsel for the petitioners' points out that admittedly no
individual notice was served upon the petitioners and the third
respondent claims to have made newspaper publication informing
installation of the high tension line. But neither a copy of such
publication is annexed to the affidavit, nor is the date of publication
declared. The maps annexed to the affidavit are vague and unintelligible
and the assessment of compensation demonstrated in page 55 (annexure
R/4 to the affidavit-in-opposition) is without any basis. The petitioners'
proposal for an alternative route to shift the tower location was turned
down by the respondent vide order dated 27th September, 2021 without
giving an opportunity of hearing to the petitioners.
5. The value of the land is more than Rs. 5,00,00,000/- (Rupees Five Crores)
whereas compensation has been calculated at Rs. 1,88,000/- , the factors
taken into consideration for such determination not being disclosed.
Pointing to the error in the decision making process, the petitioners have
prayed for a direction upon the third respondent not to take any action
towards installation of high tension line and restraining it from
encroaching upon the petitioners' land without following due process of
law.
6. Learned counsel has placed reliance on the authority in Kerala State
Electricity Board v/s. Livisha And Others reported in (2007) 6 Supreme
Court Cases 792 in support of his contention.
7. Vehemently opposing the prayer of the writ petitioners, answering
respondent no. 3 submits that for the purpose of transmission of towers
for stringing of transmission lines, the authority need not acquire the land
in question and is only vested with the power to use the land for public
purpose in terms of section 10(b) of the Indian Telegraph Act, 1885. This
respondent is obliged to pay full compensation for the damage sustained
by the owners of the land used for such purpose and the petitioners are at
liberty to approach the appropriate forum under section 16(3) of the Act of
1885 in case of any dispute concerning sufficiency of the compensation to
be paid under section 10(d) of the Act. The petitioners are not entitled to
any individual notice under the Act and under no circumstance can the
work be halted.
8. Learned counsel for the respondent has placed reliance on the judgment
in the Power Grid Corporation of India Limited v/s. Century Textiles and
Industries Limited And Others reported in (2017) 5 Supreme Court Cases
143 and a judgment of a coordinate bench of this court passed on
December 14, 2021 in W.P.A. 996 of 2021.
9. In distinguishing the judgment in Power Grid Corporation of India Limited
(supra), learned counsel for the petitioners has submitted that in the case
under consideration in the said judgment, notice was issued upon the
petitioners who gave a reply to the said notice. Also, 408 towers out of 410
towers were already erected and the work had started long ago. The
project was on the verge of completion when the writ petition was decided.
10. Learned counsel for the petitioners refers to page 4 of the judgment in
W.P.A. 996 of 2021 and submits that the provision of section 10 of the Act
of 1885 has not been complied with by the respondent.
11. I have considered the submissions made on behalf of the parties, material
on record as well as the law on the point.
12. The notification no. 610 dated February 16, 2018 has conferred powers of
Telegraph Authority upon the power grid under section 164 of the
Electricity Act, 2003 and the third respondent has acted within the
periphery of such powers. Though Rule 3 (1)(a) of the 2006 Rules states
that a licensee may carry out works for supply of electric lines through,
over or under any land with prior consent of the owner or occupier of such
land, the said rule ceases to apply in the case of power grid by virtue of
exception clause contained in Rule 3(4) of the Rules which states that "
Nothing contained in this rule shall effect the powers conferred upon any
licensee under section 164 of the Act." The respondent being governed by
section 164 of the Electricity Act, 2003, the 2006 Rules are not applicable
to it. [The Power Grid Corporation of India Limited (supra)]. Section 10(b)
of the Indian Telegraph Act, 1885 envisages that the authority shall not
acquire any right other than that of user in the property across which the
telegraph line or post is installed. Therefore the question of acquisition of
the property does not arise.
13. Learned counsel for the petitioners has challenged the decision making
process of the authority (third respondent) in so much as the authority
has not complied with the provisions of section 10(d) of the Act of 1885.
Section 10(d) of the Act requires the authority to do as little damage as
possible and pay full compensation to all persons interested for any
damage sustained by them by reason of installation of the towers in the
property. There is no requirement for service of notice upon the land
owners/occupiers or obtaining their prior consent under section 10 of the
Act of 1885. It is submitted by the authority that installation of tower over
lands covering certain villages including that of the petitioners was
notified by way of publication in several newspapers. But neither the date
of publication is disclosed, nor are the relevant newspapers annexed to
the affidavit-in-opposition used by the respondent. Be that as it may, as
the statute itself does not require service of individual notice upon the
land owners/occupiers prior to commencement of the installation work,
the respondent was under no obligation to serve such notice upon the
petitioners.
14. The petitioners have primarily challenged the authority of the respondent
to install high tension electric transmission poles through the land of the
petitioners without due process of law and without their consent. It
appears that the power grid has been entrusted with the job to bring
power from Jharkhand to West Bengal for strengthening the eastern
region and is required to install transmission towers over various lands
including that of the petitioners to enable symmetric stringing of
transmission line. The project is therefore of immense national importance
and shall benefit the public at large across states. The petitioners
apprehend that such installation shall cause extensive damage to their
land and the land cannot be utilised for any other purpose. In substance,
the petitioners are aggrieved by the proposal of installation work on their
land by the authority. The apprehension of the petitioners does not have a
strong foundation. The third respondent has handed up a sketch map to
the petitioners demonstrating the transmission line which according to
the petitioners, is unintelligible. The respondent authority has pointed out
that all relevant factors were kept in mind while executing the work and
annexure R/4 to the affidavit-in-opposition demonstrates that the damage
shall be assessed after completion of every stage of work, for payment of
compensation to the owners/occupiers.
15. A proposal made by the petitioners for shifting the tower location to an
alternative route was considered and turned down by the authority on
27th September, 2021 on the ground that upon re-survey, it was found
that there was no alternative route feasible by shifting the location. The
foundation and erection work of both subsiding and preceding towers was
complete and it was not technically feasible to shift the route of the
transmission line at that stage. The ratio of the judgment relied upon by
the respondent authority is squarely applicable in the fact situation of the
case in hand. The judgment in the Power Grid Corporation of India
Limited (supra) deals with prior consent of the land owners, relocation of
construction of towers as well as assessment of compensation. In dealing
with these issues, the observation of the Hon'ble Supreme Court is in
favour of the contention of the third respondent in the present writ
petition. In the said case also, the project was on the verge of completion
as in the present case where the other towers except the tower crossing
the petitioners' lands have been completed.
16. In the case in hand, the respondent authority has assessed the
compensation to be paid to the petitioners in compliance with section
10(d) of the 1885 Act, and there is nothing on record to suggest any
illegality/irregularity in the decision making process of the respondent.
The petitioners' application for shifting the tower location to an alternative
route has been rejected by the authority by a reasoned order and no
violation of the notification dated February 16, 2018 or provision of
section 10 of the Act of 1885 is found within the four corners of the
record.
17. The second limb of argument of the petitioners is that the compensation
assessed by the authority is not in conformity with the present market
value of the land. The market value of the land is more than Rs.
5,00,00,000/- (Five Crores) whereas compensation was calculated at Rs.
1,88,000/- and the factors taken into consideration for such
determination have not been disclosed.
18. In this context, section 16(3) of the 1885 Act is relevant.
19. Section 16(3) of the Act is set out:-
"(3) If any dispute arises concerning the
sufficiency of the compensation to be paid
under section 10, clause (d), it shall, on
application for that purpose by either of the
disputing parties to the District Judge within
whose jurisdiction the property is situate, be
determined by him."
20. In view of the same, the petitioners are at liberty to approach the District
Judge within whose jurisdiction the property is situate, for determination
of adequate compensation payable to them.
21. In the authority in Kerala State Electricity Board (supra) relied upon by
the petitioners, the Hon'ble Supreme Court dealt with a matter with
regard to compensation payable on the basis of the yield from the trees
which were cut and removed for installation of telegraph and electrical
lines over the property. The issue was dealt with by the Hon'ble Supreme
Court after compensation was determined by the Board and also by the
District Judge and appeal preferred against the said decisions before the
High Court was dismissed. Therefore the said judgment is not applicable
in the facts and circumstances of the present case.
22. Upon consideration of the submissions made on behalf of the parties and
material on record, this court is of the view that the remedy of the
petitioners lies before the appropriate forum under section 16(3) of the
1885 Act. The writ petition, being devoid of merit, is liable to be
dismissed.
23. W.P.A. 5538 of 2021 is dismissed.
24. There shall be however no order as to costs.
25. Urgent certified website copies of this judgment, if applied for, be supplied
to the parties expeditiously on compliance with the usual formalities.
(Suvra Ghosh, J)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!