Citation : 2021 Latest Caselaw 1464 Cal/2
Judgement Date : 23 November, 2021
IN THE HIGH COURT AT CALCUTTA
Ordinary Original Civil Jurisdiction
ORIGINAL SIDE
(Commercial Division)
Present:-
THE HON'BLE JUSTICE MOUSHUMI BHATTACHARYA
A.P. 232 OF 2021
M/S. KSE ELECTRICALS PVT. LTD.
vs
THE PROJECT DIRECTOR, BANGLADESH RURAL ELECTRIFICATION
BOARD AND ANR.
For the Petitioner : Mr. Sabyasachi Chowdhury, Sr. Adv.
Mr. Rajarshi Dutta, Adv.
Mr. V. V. V. Sastry, Adv.
Mr. Tridib Bose, Adv.
Mr. Debjyoti Saha, Adv.
For the Respondent no. 2 : Mr. K. Thaker, Adv.
Mr. Varun Kedia, Adv.
Reserved for Judgment on : 08.10.2021.
Delivered on : 23.11.2021
Moushumi Bhattacharya, J.
1. The issue which falls for consideration in the present case is the ground
on which invocation of a bank guarantee can be restrained.
2. By an order dated 10th May, 2021 a learned Single Judge restrained the
respondent No. 2 from making any payment under a bank guarantee invoked
by the respondent No. 1. The said order was modified on 21st May, 2021 by
another Learned Judge confirming the interim order of injunction and further
restraining the respondent No. 1 from encashing the bank guarantee. The letter
of invocation was stayed and the petitioner was given the liberty of producing a
copy of the order before the respondent No. 2 in their seats at Kolkata and
Dhaka. The petitioner and the respondent No. 2 have filed their respective
affidavits thereafter. The respondent No. 1 has however not contested in the
proceedings and has not challenged or responded to the orders of injunction by
way of affidavit or otherwise. These orders were passed in the present
application filed by the petitioner under Section 9 of The Arbitration and
Conciliation Act, 1996.
3. A brief background of the facts is necessary for a better understanding of
what brought the petitioner to this court by way of the present Arbitration
Petition.
4. The factual matrix in the present matter is almost identical to A.P No.
230 of 2021. The parties are the same and so is the underlying contract as well
as the terms of the bank guarantee. The small factual differences relate to the
transaction. Counsel appearing for the petitioner and the respondent No. 2
have also proceeded on the substantial similarities of the issues involved in
A.P. 230 of 2021, A.P. 231 of 2021 and A.P. 232 of 2021.
5. This judgment and those delivered in A.P. 230 of 2021 and A.P. 231 of
2021 should be read in the aforestated context.
A brief factual background:
6. The petitioner was awarded a contract for supply of conductor and
related accessories to the respondent No. 1 pursuant to a global tender floated
by the latter. The contract dated 26th October, 2016 was a Carriage and
Insurance Paid (CIP) contract for a price of USD 1,399,800. The petitioner was
required to furnish a performance security for an amount of USD 139,980 for a
period of 24 months under the relevant clause of the General Conditions of
Contract (GCC). The contract was governed by the GCC and the Special
Conditions of Contract (SCC) which also provided for the mode of payment to
be made by the respondent No. 1 to the petitioner. The petitioner submitted the
performance security in the form of a bank guarantee dated 20th October,
2016. The petitioner, being a constituent of Citibank NA, Kolkata applied for
the bank guarantee to be issued in favour of the respondent No. 1 whereupon
Citibank NA, Kolkata issued a stand-by letter of credit in favour of the Citibank
NA, Bangladesh at Dhaka. Citibank, NA Dhaka issued a performance security
in the form of a bank guarantee based on the stand-by letter of credit.
7. The petitioner supplied the entire material under the contract by 13th
March, 2019 which was received by the respondent on 21st May, 2019 and the
respondent No. 1 prepared Receiving Reports containing the details of the
goods dispatched upon receipt of the goods. The warranty in respect of the
goods shipped and supplied by the petitioner to the respondent No. 1 was to
remain valid for 12 months after delivery of the goods and acceptance of the
same at the final destination under Clause 28.3 of the GCC. The warranty
expired on 13th March, 2020.
8. On 9th March, 2021, the respondent No. 1 alleged short-supply of goods.
Thereafter, the respondent No. 1 issued a letter of invocation dated 5th May,
2021 and requested the Citibank NA, Dhaka to encash the bank guarantee.
The petitioner had renewed the bank guarantee and kept it alive on account of
10% of the contract price having been retained by the respondent No. 1 under
the relevant clause of the GCC.
Contentions of the Respondent No. 2 Citibank NA:
9. The primary contention of Mr. K. Thakker, learned counsel appearing for
Citibank NA, is that this court lacks territorial jurisdiction to entertain the
present application.
10. According to counsel, the contract was executed at and is governed by
the laws of Bangladesh; the contract was to be performed at Bangladesh and
the bank guarantee issued by Citibank NA, Dhaka is governed by the laws of
Bangladesh. It is also contended that there is an absence of substantive
jurisdiction since the Citibank NA, Kolkata and Citibank NA, Dhaka are
separate entities governed by different banking regulations. Counsel submit
that neither of the two parties are parties to the arbitration agreement between
the petitioner and the respondent No. 1 which forms the basis of the
application and hence no relief can be sought against them. The other
contention is that the bank guarantee is an independent contract between the
bank and the beneficiary, invocation whereof is to be tested on the terms of the
bank guarantee. It is also submitted that the petitioner has not been able to
make out an established case of fraud or irrevocable injury or special equities
which would vitiate the entire underlying transaction.
Response of the petitioner to the above contentions:
11. According to Mr. Sabyasachi Chowdhury, and Mr. Rajarshi Dutta,
learned Counsel, Citibank NA, Kolkata and Citibank NA Bangladesh are one
and the same entity in respect of the bank guarantee and the respondent No. 2
has been impleaded as a bank carrying on business from Kolkata, India with
an overseas branch at Bangladesh, Dhaka. Counsel relies on Clause 10.2 of
the GCC which contains the arbitration agreement under which the arbitration
proceeding is to be conducted in accordance with the UNCITRAL Arbitration
Rules, 2010. Counsel relies on Section 2 and the relevant clauses thereunder
of the 1996 Act which would bestow the jurisdiction on this court to entertain
the application. On the merits of the dispute, it is contended that the petitioner
has already received 90% of the contract price and the respondent No. 1 is
withholding 10% as retention money and that the respondent No. 1 has no
other claims against the petitioner. Counsel points to the conduct of Citibank
NA, Kolkata espousing the cause of respondent no. 1 as well as Citibank NA,
Bangladesh.
12. Counsel submits that there are special equities in the present matter to
warrant an invocation of the bank guarantee.
13. The arguments advanced by learned counsel appearing for the petitioner
and the respondent No. 2 (the respondent No. 1 is not represented in this
proceeding) would make it clear that the challenge to the orders of injunction
passed by the court is mounted on the premise of the lack of territorial and
substantive jurisdiction. The decision accordingly proceeds on the aforesaid
basis.
Lack of territorial jurisdiction:
14. The objection to this court entertaining the present application on the
lack of territorial jurisdiction may be answered on the basis of the clauses
contained in the General Conditions of Contract (GCC) which governs the
contract entered into between the petitioner and the respondent No. 1 on 26th
October, 2016. Under Clause 9.1 of the GCC- "Governing Law" - the contract
shall be governed by and interpreted in accordance with the laws of the
Purchaser's Country, unless otherwise specified in the Special Conditions of
Contract (SCC). Clause 10.2- "Settlement of Disputes" -provides for arbitration
where the parties have failed to resolve their disputes by mutual consultation
and provides that the arbitration proceedings shall be conducted in accordance
with the rules and procedure specified in the SCC. The SCC provides that the
rules of procedure for arbitration proceedings pursuant to Clause 10.2 of the
GCC shall be settled by arbitration in accordance with the UNCITRAL
Arbitration Rules, 2010. Clause 9.1 of the GCC which provides that the
contract shall be governed by the laws of the Purchaser's Country, which is
Bangladesh in this case, would not stand in the way of this court assuming
jurisdiction of the matter since the governing law of the contract only decides
the substantive provisions of law which would govern the arbitration between
the parties; Reference : Bharat Aluminium Co. vs Kaiser Aluminium Technical
Services Inc.: (2012) 9 SCC 552 , where the Supreme Court made a distinction
between the place/seat of the arbitration and the location of the subject matter
of the suit.
15. The question with regard to territorial jurisdiction may also be answered
with reference to Section 2(1)(e)(ii) of The Arbitration and Conciliation Act,
1996, which defines "Court" to mean in the case of International Commercial
Arbitration, the High Court in exercise of its Ordinary Original Civil
Jurisdiction, having jurisdiction to decide the questions affirming the subject-
matter of the arbitration if the same had been the subject-matter of a suit.
Second, it is also undisputed that the transaction is an International
Commercial Arbitration as defined under Section 2(f) of the Act since the
dispute arises out of a commercial contractual relationship involving a
corporation incorporated in Bangladesh. Third, the fact that this court would
have jurisdiction to receive, try and entertain the dispute had it been filed by
way of a suit would be evident from the averments in the petition. The
pleadings in the petition indicate that sufficient cause of action has arisen
within the jurisdiction of this court including the commencement of the
transaction entered into between the parties, the working out of the
commercial relations between the parties, the dispute and differences between
them as evident from the correspondence exchanged and the culmination
thereof in the form of the letter of demand issued by the respondent no.1 to the
petitioner and the letter of invocation dated 5th May, 2021 to the respondent
no.2 and copied to the petitioner. Although speculative, had the petitioner
instituted a suit for the same relief against the respondents, there would have
been sufficient ground to grant leave to the petitioner under Clause 12 of the
Letters Patent, 1865 to proceed with the same.
16. Section 2(4) of the Act is an interesting follow-up to Section 2(1)(e)(ii) in
the matter of a court assuming jurisdiction in entertaining matters under Part I
of the Act. Under Section 2(4), Part I of the 1996 Act shall apply to every
arbitration under any other enactment for the time being in force unless the
provisions of Part I are inconsistent with the other enactment or the rules
framed thereunder. This provision therefore lends weight to the submissions
made on behalf of the petitioner with regard to eclipsing the Arbitration Rules
mentioned in the SCC and also in the matter of territorial jurisdiction.
17. Section 2(2) of the Act provides that subject to an agreement to the
contrary, the provisions of Sections 9, 27, 37(3)(1)(b) shall also apply to
International Commercial Arbitrations despite the place of arbitration being
outside India and an arbitral award made or to be made in such place is
enforceable and recognised under Part II of the Act. In the present case, the
Contract between the parties does not provide for a seat or a place outside
India. Hence Part I of the Act would be applicable in the given facts. Since the
Contract or the GCC does not exclude the applicability of Part I or Section 9 of
the Act, this court would have jurisdiction to try and decide the present
application filed under Section 9 of the Act. The wide and unfettered powers of
a court under Section 9 has been reiterated in countless decisions of the
Supreme Court and the High Courts. Section 2(2) as amended by the
amendment of 2016, closes the loops for a party to object to interim measures
under Section 9 unless the parties have specifically and unequivocally agreed
to exclude the operation of Part-I of the Act. The issue of maintainability of the
arbitration petition was also considered by the learned Single Judge on 10th
May, 2021 and the order of injunction was confirmed and extended to the
respondent no.1 despite such objection.
Whether the respondent no.2 Citibank NA should be treated as consisting of
two different entities?
18. It would be evident from the transaction that the petitioner, the
respondent no.1 and Citibank NA, Kolkata (respondent no.2) treated Citibank
NA, Bangladesh at Dhaka as an overseas office of Citibank NA, Kolkata.
Citibank NA carries on business from different offices in India including the
one at Kolkata. Since the petitioner was required to submit a Performance
Security in the form of a bank guarantee for a sum of USD 139,980 the
petitioner applied before the respondent no.2 at its office at Kolkata for a bank
guarantee to comply with the aforesaid stipulation. The application for bank
guarantee was made by the petitioner at Citibank NA in Kolkata whereupon
Citibank from its office at Kolkata issued a Standby Letter of Credit in favour of
Citibank at Dhaka. On the basis of such Standby Letter of Credit, Citibank NA,
Dhaka issued a Performance Security in the form of a bank guarantee, as the
overseas office of Citibank NA, Kolkata.
19. The above facts would therefore indicate that Citibank NA, from its
overseas office at Dhaka issued the Performance Security in the form of a bank
guarantee on 20th October, 2016 for USD 139,980. No fact has therefore been
pleaded or proved to show that Citibank NA should be seen as two separate
and disparate entities namely the Kolkata and the Dhaka branches.
Conduct of respondent no.2 Citibank NA:-
20. By a letter dated 7th June, 2021 from the petitioner was informed that
Citibank N.A. Bangladesh had enquired from the respondent no. 1 about its
stand regarding the orders of injunction. The petitioner was also informed that
the respondent no. 1 had reiterated its demand for payment and intends to
flout the orders passed by the court. Subsequent correspondence from
Citibank NA, Kolkata to the petitioner shows that the petitioner is being
pressurized in respect of the invocation of the performance guarantee. The
conduct of the respondent no.2 makes it evident that the respondent no.2 has
made elaborate submissions in defence of the first respondent even though the
first respondent has neither appeared in nor contested the present application.
21. The cases shown on the subject of bank guarantees should be seen in
this context. In Hindustan Construction Co. Ltd. vs State of Bihar; (1999) 8 SCC
436, the Supreme Court stressed on the invocation being in terms of the bank
guarantee and the requirement of special equities. The Supreme Court was of
the opinion that special equities existed in favour of the appellants since the
defendants did not have sufficient funds to complete the work. The other set of
decisions namely Girish Mulchand Mehta vs Mahesh S. Mehta; 2010 (1) Bom CR
31 (Division Bench of the Bombay High Court), Bluecoast Infrastructure
Development Pvt.Ltd. vs Blue Coast Hotels Ltd (Single Bench of the Delhi High
Court), Geodesic Techniques vs L&T (Single Bench of the Madras High Court)
and Valentine Maritime Ltd vs Kreuz Subsea Pte. Limited (Division Bench of the
Bombay High Court) are for the proposition that while the jurisdiction of the
Court under section 9 of the Act can only be invoked by a party to the
arbitration agreement, Section 9 does not limit such jurisdiction to pass
interim measures only against a party to an arbitration agreement. In Valentine
Maritime, the Bombay High Court specifically pointed out that orders are
regularly passed restraining banks from releasing payment under bank
guarantees though the bank may not be a party to the arbitration agreement.
22. In Arch Hi-Rise (P) Ltd. vs. Yatin Bhimani: (2006) 4 CHN 204, a Division
Bench of this court was concerned with the issue of whether an interim order
can be passed against a third party who is not a party to the arbitration
agreement. The decision can be factually distinguished from the present case
since there is no indication from the facts that the appellant third party was
inextricably connected to the dispute or was required to be impleaded as a
necessary and proper party thereby. The Supreme Court in U.P. Co-operative
Federation Ltd. Vs. Singh Consultants and Engineers (P) Ltd.: (1988) 1 SCC 174,
was of the clear view that there was no fraud or irretrievable injustice involved
in the facts of that case. The court reiterated that for restraining the operation
of a bank guarantee, there should be good prima facie case of fraud and special
equities in the form of preventing irretrievable injustice between the parties. In
Hindusthan Paper Corporation Ltd. vs. Keneilhouse Angami: (1990) 1 Cal LT
200, a Division Bench of this Court, relying on an earlier decision of this court
in Centax (India) Ltd. Vs Vinmar Impex Inc. Ltd; AIR 1986 Cal 356 reiterated the
importance of the terms and conditions of a bank guarantee or a Letter of
Credit for its enforceability. The unreported decision of a Division Bench of this
court in Bridge & Roof Co. (I) Ltd. vs. SKP Buildcon Pvt. Ltd. in APO No. 495 of
2017 was only concerned with the hesitation of a court to stand in the way of
an unconditional bank guarantee being invoked and the apparent lack of
reasons in the order of the first court. The unreported decision in Deific Abode
LLP vs Union of India in WPA 11123 of 2020 is on the principle of binding
precedents and has presumably been cited to lessen the impact of the effect of
the decisions of the Bombay and Madras High Courts. South East Asia
Shipping Co. Ltd. vs Nav Bharat Enterprises Pvt. Ltd; (1996) 3 SCC 443 was
concerned with the question whether any part of the cause of action had a
reason for the Delhi High Court to entertain the suit and the Supreme Court
was of the view that cause of action must include some act done by the
defendant. The decision was not concerned with an arbitration agreement or
the considerations which would normally arise in respect of an application for
interim measures under Section 9 of the Act. Although several decisions have
been cited on behalf of the parties, none of the decisions persuade the court to
disagree with the contentions made on behalf of the petitioner on the merits of
the dispute.
23. With regard to the objection taken on behalf of the respondent no. 2 that
a non-party to an arbitration agreement cannot be impleaded in the present
proceeding, this court is of the view that Section 9 read with Section 2(1)(a) of
the 1996 Act provides for a right to apply for interim measures only to a "party"
to an arbitration agreement. There is no embargo however in the provision
against implementing a non-party to an arbitration proceeding where the
presence of such non-party is necessary to give effect to the order that may be
passed in the application against a party to the arbitration agreement. The
petition contains an averment that the respondent no. 2 has been impleaded
for proper and effective adjudication of the issues involved in the present
proceeding. This pleading finds factual support from the petitioner applying for
a bank guarantee to be issued in favour of the respondent no. 1 which was
impleaded by Citibank NA, Kolkata issuing a stand-by letter of credit in favour
of Citibank NA, Bangladesh at Dhaka who in turn issued a performance
security in the form of a bank guarantee. Hence in order to seek an order of
injunction, and in the event such injunction is granted, to be effective,
respondent no. 2 has been made a party to the proceedings and relief sought
against it. The issue of maintainability is therefore answered in favour of the
petitioner.
Substantive jurisdiction and merits of the dispute:
24. The admitted fact in the present case is that the petitioner completed
supply of the goods to the respondent no. 1 on 13th March, 2019 (shipment
received by the respondent no. 1 on 21st May, 2019) and there was no
contemporaneous demand or objection from the respondent no. 1 in relation to
the supplies made within the period of warranty which was till 13th March,
2020, from the date of delivery to the date of acceptance at the final destination
indicated by the respondent no. 1. Under Clause 28.3 of the GCC, the warranty
was to remain valid for 12 months after the goods or any portion thereof have
been delivered to and accepted at the final destination indicated in the SCC or
for 18 months after the date of shipment from the port or place of loading in
the country or origin, whichever period concludes earlier. The respondent No. 1
invoked the bank guarantee in terms of the letter dated 5th May, 2021 two
years after the completion of the supply of goods and more than one year after
the expiry of the warranty. Notably the demand on account of short-supply of
goods was made by the respondent No. 1 for the first time on 9th March, 2021.
The petitioner has already received 90% of the payment for supply of the entire
materials under the contract to the respondent no. 1 in accordance with clause
16.1 of the GCC which provides for the terms of payment under the contract.
The respondent no. 1 has however retained 10% of the contract price and
withheld the same.
25. The letter of invocation dated 5th May, 2021 relates to the 10% retention
money under the contract as stated in the said letter. The letter of invocation
further makes it clear that the 10% retention money is still unsettled. The
invocation was not concerned with the performance obligations of the petitioner
and was only confined to the 10% retention money. The performance security
issued by the Citibank NA, Dhaka in the form of bank guarantee and the
stand-by letter of credit issued by Citibank NA, Kolkata relate to the obligation
of the petitioner to supply the materials to the respondent no. 1. This would
appear from the application made by the petitioner to Citibank NA, Kolkata
with the respondent no. 1 indicated as the beneficiary.
26. The performance security also makes it clear that the undertaking on the
part of the respondent no. 2 to pay the beneficiary (respondent no. 1) was
confined to the beneficiary's demand and statement in relation to breach of the
obligations of the petitioner under the contract. Since the petitioner performed
its obligations under the contract by executing the entire supplies by March,
2019 and received 90% of the contract price for the same, there can be no
further basis for any outstanding claim by the respondent no. 1 against the
petitioner under the contract. No claim on account of liquidated damages has
been made by the respondent. The facts hence must be construed in favour of
the petitioner in confirming the order restraining the invocation of the bank
guarantee.
The Law:
27. In contemporary business, trade and commercial transactions, both
domestic and international, significant complexities are involved; for instance
spatial distance between counterparties who engage in such commercial
transactions. As such, it is often very difficult and challenging to approximately
assess the creditworthiness of the counterparty or the business partner.
Hence, over a period of time, commercial instruments have emerged for
securing contractual payments. A Bank Guarantee is such an instrument that
has evolved for securing payments with respect to commercial transactions.
Under Section 126 of The Indian Contract Act, 1872, a 'Contract of guarantee'
is a contract to perform the promise, or discharge the liability, of a third person
in case of his default. In the case of a Bank Guarantee, a bank, who is the
guarantor, undertakes or guarantees to pay the beneficiary an amount of
money as specified in the guarantee if the original contract's debtor fails to
adhere to his contractual obligations.
28. Courts are generally slow to interfere with the transaction between a
bank and the beneficiary which is seen as being independent of the underlying
contract between the lender and the supplier unless conditions call for such
interference. The three conditions, as accepted in several decisions, are fraud of
an egregious nature; special equities or the invocation not being in terms of the
bank guarantee. It is sufficient if a party seeking a restraint on the invocation
is able to establish any one of the three requirements. The test of special equity
or irrevocable injustice is a matter of an assessment by a court on the
particular facts presented to it for stay on a notice of invocation. The injury or
injustice must be irrevocable, irremediable and irreversible: Refer: State Bank
of India vs Sun Pharmaceuticals Industries Ltd: AIR 2019 CAL 385. The party
seeking an order for restraint must show that the invocation and consequent
payment by the bank to the intended beneficiary would set the party back-
irreversibly- in monetary terms which may not be recovered in the foreseeable
future.
29. In the present case, the petitioner has satisfied two of the three
ingredients, namely special equity and the invocation not being in terms of the
guarantee. The clauses in the contract and more particularly the GCC clearly
demonstrate that the bank guarantee was furnished towards performance
security. There can be no issue with regard to performance since the petitioner
has already received 90% of the contract price as discussed above. The
invocation letter also demonstrates that there cannot be any performance issue
with regard to the supplies effected by the petitioner. The invocation letter does
not contain any allegation of a breach of performance obligations by the
petitioner. The special equity also stands satisfied by reason of the petitioner
facing an immediate and irreversible financial loss if the payment is made by
Citibank NA, Dhaka to the respondent No. 1 in terms of the Letter of
Invocation. The submission made on behalf of the respondent no. 2 that
Citibank NA, Dhaka may already have made payment to the respondent no. 1
thereby rendering the present application infructuous, is not a factor which
would deter this court to permit the order of injunction to be subverted by
errant parties. If Citibank NA, Dhaka has the temerity to frustrate the orders of
injunction passed against the respondents, it must also bear the risk and
consequence of such action.
30. The interim orders passed by learned judges of this court on 10th May,
2021 and modified on 21st May, 2021 were on a particular set of facts before
filing of affidavits. This court may have considered altering or further modifying
the orders of injunction at the instance of the respondent No. 2 had compelling
facts subsequently been disclosed on affidavits. Apart from territorial
jurisdiction, no other grounds have been pleaded or shown which would
warrant varying the orders when all relevant facts were taken into
consideration by the learned Judges. It is also significant that the respondent
no. 1 has not appeared or contested these proceedings and respondent no. 2
has taken to "shadow boxing" on behalf of the absentee wrongdoer.
31. In view of the above reasons and finding that the contentions made on
behalf of the petitioner are of substance, the order dated 10th May, 2021 as
modified by the order dated 21st May, 2021 is confirmed and made absolute.
A.P. No. 232 of 2021 is disposed of in accordance with the above.
Urgent Photostat certified copy of this Judgment, if applied for, be
supplied to the parties upon compliance of all requisite formalities.
(MOUSHUMI BHATTACHARYA, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!