Citation : 2021 Latest Caselaw 3191 Cal
Judgement Date : 11 June, 2021
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
WPA No. 18440 of 2019
IA No: CAN 3 of 2020 (CAN 3997 of 2020)
+
CAN 4 of 2020 (CAN 3998 of 2020)
+
CAN 5 of 2021
With
WPA No.1404 of 2020
Archon Powerinfra India Private Limited
Vs.
Indian Oil Corporation and others
For the petitioner : Mr. Sakya Sen,
Mr. Amritam Mondal,
Ms. Jeenia Rudra.
For the
respondent-authorities : Mr. Saptangshu Basu,
Mr. Amit Kumar Nag, Mr. Abhishek Nag, Ms. Ranjabati Ray
Hearing concluded on : 22.04.2021
Judgment on : 11.06.2021
Sabyasachi Bhattacharyya, J:-
1. The brief facts of the case are:
The Indian Oil Corporation Limited (IOCL), the first respondent in
both the writ petitions, issued a Letter of Intent (LoI) to the petitioner
for construction of new plant shed and allied civil, structural and
enabling works at LPG Bottling plant, Budge Budge, West Bengal. A
contract was duly executed in terms of the said LoI.
2. Despite the scheduled time for completion of the work having expired,
extensions were granted to the petitioner on multiple occasions for
completion of all the works.
3. The respondents allege that the contract work was not completed even
within the extended time and that the performance of the petitioner
(Archon Power Infra India Private Limited) was unsatisfactory.
4. Subsequently on July 16, 2018 M/s. Enoch Infra Build LLP sent a
written complaint to the respondents regarding the petitioner having
entered into a sub-contract with the said concern in connection with
the subject contract, payment in connection with which was allegedly
due. The complaint further indicated that the petitioner had been
diverting payments received from the respondents to third parties
without reimbursing M/s. Enoch. Two agreements dated March 7,
2017 and July 24, 2017 were allegedly executed between the
petitioner and M/s. Enoch and certain bank statements reflecting
payments from Enoch to the petitioner pursuant to the contract were
also included in the complaint.
5. The contract with the petitioner was terminated by the IOCL primarily
on the ground that the sub-contracts referred to above were in
contravention of Clause 4.8.1.1.1 and Clause 7.0.1.0(x) of the General
Conditions of Contract (GCC). Such sub-contract was allegedly
entered into without prior written approval from IOCL, which entailed
violation of the clauses of the contract and ultimately resulted in
termination of the contract. Such termination was preceded by a
show-cause notice dated August 23, 2018, to which the petitioner
gave a written reply on September 5, 2018, in which the petitioner
apparently admitted the execution of the two agreements.
6. The termination took place on November 2, 2018 and was challenged
in a writ petition, bearing WP No.23928 (W) of 2018. By an order
dated December 12, 2018, the writ petition was dismissed, upholding
the order of termination. MAT 36 of 2019 was preferred against such
order which was dismissed on February 7, 2019 by a Division Bench
of this Court. The dismissal order recorded the admission of the
petitioner that the petitioner had sub-contracted the work entrusted
to it. Both the said orders observed that the sub-contracts had
violated Clause 7.0.1.0(x) of the GCC and Article 8 of the contract
dated December 1, 2016.
7. In the order of termination, the respondents had intimated to the
petitioner that the balance work would be done through alternate
parties at the risk and cost of the petitioner as per terms and
conditions of the contract/work order.
8. Subsequently, the respondent authorities floated Tender
No.BGB/BP/PT-03/2019-20 inviting bids for the balance work. The
petitioner was specifically debarred from participating in the said
tender since the original contract was terminated on the ground of
violation of the same.
9. Challenging the debarment of the petitioner to participate in the new
tender, the petitioner filed another writ petition bearing WPA 18440 of
2019. The said writ petition is one of the subject-matters of the
present adjudication.
10. Meanwhile, a show-cause notice was issued by the respondent-
authorities to the petitioner on May 3, 2019 seeking explanation as to
why the petitioner should not be put on Holiday List. A reply was
given by the petitioner on May 30, 2019. Personal hearing was
granted to the petitioner, which was attended by the petitioner's
representative, who also submitted certain documents. Based on
such hearing and documents, the respondents decided to put the
petitioner on Holiday List, which order was communicated vide letter
dated September 18, 2019 to the petitioner.
11. The said letter dated September 18, 2019 was set aside on October
30, 2019 in WP No.19486 (W) OF 2019. Liberty was granted to the
petitioners to participate with the debarment proceeding by affording
another opportunity of hearing to the petitioner on November 8, 2019
at 11 a.m. In compliance thereof, a notice dated October 31, 2019 was
issued to the petitioner and a hearing was given on the appointed date
and time to the representative of the petitioner and its advocate.
12. By a letter dated November 21, 2019, based on such hearing, the
petitioner was again put on Holiday List for a period of three years.
13. The petitioner contends that such debarment of the petitioner to
participate in Tender No.BGB/BP/PT-03/2019-20 was illegal and
without jurisdiction, since the proceeding for Holiday Listing was
pending at that juncture.
14. The petitioner challenged such debarment/Holiday Listing in WPA
No.1404 of 2020, which is also the subject-matter of the present
adjudication.
15. Learned counsel for the petitioner alleges that the order of debarment,
challenged in WPA No.1404 of 2020, was a verbatim reproduction of
the termination order dated November 2, 2018. The said order quotes
a portion of the order passed by the Division Bench while affirming
the order upholding the termination.
16. Hence, it is argued by the petitioner, the debarment order does not
reflect application of mind and/or independent consideration of the
defence put up by the petitioner in its reply to the show-cause notice
and, as such, is unreasoned.
17. In this context, the petitioner refers to B.A. Linga Reddy and others
Vs. Karnataka State Transport Authority and others [(2015) 9 SCC 515]
and Kranti Associates Private Limited and another Vs. Masood Ahmed
Khan and others [(2010) 9 SCC 496].
18. It is further argued by the petitioner that the reasons cannot be
supplemented subsequent to the impugned order and places reliance
in such context on Mohinder Singh Gill and another Vs. The Chief
Election Comissioner, New Delhi and others [(1978) 1 SCC 405].
19. Hence, since the original order of debarment did not reflect any
reason, the post facto furnishing of reasons in the pleadings of the
respondents in the present writ petition ought not to be looked into by
the court, the petitioner contends.
20. Learned counsel for the petitioner further argues that the agreements
with M/s. Enoch (respondent no.4) was in the nature of finance
agreements and not sub-contracts. This fact, it is contended, was
admitted by M/s. Enoch, as reflected from a resolution passed at a
meeting of the designated persons of M/s. Enoch and an application
by M/s. Enoch under Section 7 of the Insolvency and Bankruptcy
Code (IBC), in the capacity of a financial creditor. A legal notice dated
July 17, 2019 also reflects the same stand taken by respondent no.4,
which itself shows that respondent no.4 admitted that the nature of
the agreements-in-question was financial and not sub-contracts.
Such documents, it is argued were not considered in the debarment
order.
21. The petitioner contends that the IOCL failed to produce any document
to show that any part of the work was actually done by respondent
no.4 (M/s Enoch) as sub-contractor or any document to show
manpower or material being supplied by respondent no.4 to the
project site.
22. Moreover, learned counsel for the petitioner argues, a sub-contract
would require the petitioner to make payment to respondent no.4 and
not the converse. However, the bank statement of the petitioner
disclosed before the authority reveals amounts being paid by
respondent no.4 to the petitioner, which indicates that the agreements
were financial in nature, as opposed to sub-contracts.
23. The next limb of argument by the petitioner is that the IOCL had full
knowledge of the arrangement between the petitioner and respondent
no.4 prior to the written complaint dated July 16, 2018. In support of
such contention, the petitioner places reliance on several instances of
correspondence between the IOCL and respondent no.4, including e-
mails of December, 2017, January, 2018, February, 2018 and March,
2018. Since IOCL never objected to such arrangement, despite having
correspondence with respondent no.4 directly in connection with the
contract given to the petitioner, the requirement of prior written
approval, contained in Clause 7.0.1.0 (x) of the GCC is argued to have
been waived. In support of the contention that contractual provisions
can be waived by conduct, learned counsel for the petitioner cites
Ramdev Food Products (P) Ltd. Vs. Arvindbhai Rambhai Patel and
others [(2006) 8 SCC 726] and Dr. Karan Singh Vs. State of J&K and
another [(2004 5 SCC 698].
24. That apart, it is contended, there was no finding in the debarment
order regarding the other allegation of continuous poor progress of
work. The petitioner alleges that it completed almost ninety per cent of
the work at the time of termination.
25. In reply, learned counsel for the respondents places reliance on
certain relevant clauses of the arguments dated March 7, 2017 and
August 24, 2018 entered into by the petitioner with M/s. Enoch which
categorically described the agreements as sub-contracts. The
respondents contend that the language of the documents clearly
shows that the major part of the work given to the petitioner was
delegated by sub-contract to M/s. Enoch. In view of the express terms
of the said agreements, it is argued, those were not paper
arrangements for obtaining financial assistance but were clearly sub-
contracts assigning 50 per cent and 68 per cent of the petitioner's
work respectively, under the contract with IOCL, in favour of M/s
Enoch, a third party.
26. It is also argued that the petitioner has admitted before the Division
Bench that the said agreements were sub-contracts, as revealed from
the observations made in the said order.
27. In the absence of any pleading or proof as to prior written approval of
the IOCL, such sub-contracts were in clear violation of Clause
4.8.1.1.1 and Clause 7.0.1.0 (x) of the GCC.
28. It is further argued that since the Division Bench affirmed the order of
the learned Single Judge upholding the termination of contract, also
on the ground that there was violation of the aforementioned clauses
due to the petitioner having sub-contracted the work to M/s. Enoch,
such findings have attained finality and the petitioner cannot reopen
the issue for fresh consideration by this court.
29. The ground for subsequent debarment, challenged in WPA 1404 of
2020, is primarily such contravention of contractual clauses by the
petitioner and, as such, since sufficient reasons were reflected in the
order of debarment, including the findings of the Division Bench, the
debarment order was passed absolutely within the authority of the
respondents.
30. Learned counsel for the respondents further argues that the subject-
matter challenged in WPA 18440 of 2019, that is, exclusion of the
petitioner from the subsequent tender, was not connected in any
manner with the proceeding for Holiday Listing which was then
pending against the petitioner. It is submitted that since the
petitioner's violation of the terms of the contract resulted in the
issuance of the subsequent tender for completion of the balance work,
allowing the petitioner to participate in the fresh tender would operate
as a negation of the order of termination of the petitioner, which has
been upheld up to the Division Bench of this court. Hence, there was
no irregularity on such score as well.
31. Upon a consideration of the respective submissions of counsel for the
parties and going through the materials-on-record, the primary
question which acquires relevance is whether this court can reopen
the question of the nature of the agreements dated March 7, 2017 and
August 24, 2017; if so, whether such agreements were sub-contracts
or financial agreements.
32. That apart, the question whether the order of debarment was
unreasoned or tainted by non-application of mind is also relevant.
33. Although the petitioner has argued that the Division Bench order in
connection with the termination of the contract with the writ
petitioner cannot operate as res judicata, since the subject-matter of
the challenge was termination and not whether the agreements-in-
question were sub-contracts, such contention cannot be accepted on
the face of it. The issue as to whether the concerned agreements were
sub-contracts was the cardinal question which had to be decided to
adjudicate upon the legality of the termination. As such, the said
question directly fell for consideration before the learned Single Judge
and attained finality upon being decided in the positive, as affirmed by
the Division Bench.
34. That apart, a bare perusal of several clauses of the agreements dated
March 7, 2017 and July 24, 2017 clearly indicates that those were not
financial agreements but delegated a major portion of the work which
was originally allocated to the petitioner by the IOCL, under sub-
contracts.
35. It is specified in the agreements that the writ petitioner would be the
main contractor and the respondent no.4 herein the sub-contractor.
The agreements further provided that all men, materials, machinery,
tools and plants, infrastructure, resources, etc., as required for the
execution of the work was provided and arranged by the writ
petitioner. All charges, materials, labour, plants and equipments,
transportation and overhead expenses incurred on execution,
completion and maintenance of the work was also to be arranged by
the writ petitioner and M/s. Enoch equally. The responsibility of the
work, under the said agreements, was clearly distributed equally
among the contractor and the sub-contractor. The terms and
conditions of the original agreements between the writ petitioner and
the IOCL were also made applicable between the writ petitioner and
M/s. Enoch.
36. The second agreement dated August 24, 2017, went one step further
by assigning the execution of sixty-eight per cent of the project,
instead of fifty per cent as contemplated in the agreement dated
March 7, 2017. Thus, in fact, the majority of the responsibility to do
such work was delegated to the sub-contractor.
37. The argument of the petitioner, that payments made by M/s. Enoch to
the petitioner indicated the nature of the agreements to be financial, is
not substantiated by the clauses of the agreements themselves.
38. Since charges and expenses were also to be shared between the
contractor and the sub-contractor, there could very well have been
occasions for the sub-contractor to make payments to the contractor,
that is, the writ petitioner.
39. Hence, there cannot be any doubt that the agreements dated March 7,
2017 and August 24, 2017 were clearly sub-contracts and not
financial agreements.
40. The other argument of the petitioner, as regards the implied consent
of the IOCL to the arrangements between the petitioner and M/s.
Enoch is also not tenable. Mere communication between the IOCL and
respondent no.4 does not necessarily indicate that there was any prior
written approval, as contemplated in Clauses 7.0.1.0(x) of the GCC,
read with Clause 4.8.1.1.1 of the same. It is neither pleaded nor
proved by the writ petitioner that there was any specific written
approval, as mandated by the work contract issued by the IOCL to the
petitioner, prior to the petitioner entering into such agreements with a
third party.
41. That apart, since deliberate violation of the clauses of the GCC on the
part of the petitioner entailed termination of the contract, the same
logic afforded sufficient basis for debarment/Holiday Listing of the
petitioner.
42. As far as the cited judgments are concerned, although reasons are
required to be given by judicial/quasi-judicial authorities, the
impugned order of debarment sufficiently indicated the grounds for
debarment. Quotation of portions of the orders passed by the learned
Single Judge and the Division Bench upholding the termination of
contract was fully justified in view of such findings having attained
finality. More detailed reasoning was not necessary or expected in an
administrative or at best quasi-judicial order, on a similar footing as a
judgment delivered by a court of law/tribunal.
43. The reasons indicated in the debarment order were sufficient to justify
the same. As such, it cannot be said that the said decision was
unreasoned or not tenable in the eye of law.
44. Regarding the unsatisfactory execution of the work, the failure of the
petitioner to conclude the work even after being granted several
extensions itself justified such conclusion. There is no dispute
regarding the grant of such extensions having actually been given and
the failure of the petitioner to complete the work even within the
extended period.
45. Even if it is supposed hypothetically that the debarment order failed to
disclose sufficient reasons for the execution of work by the petitioner
being labelled 'unsatisfactory', the other ground, that is, the deliberate
violation of the GCC by the petitioner by entering into sub-contract
agreements with M/s. Enoch entitled the respondent-authorities to
debar the petitioner.
46. As far as the challenge in WPA No.18440 of 2019 is concerned, it
would be a ridiculous proposition to reconsider the writ petitioner
itself as a participant in the fresh tender issued for completion of the
balance work, which was itself necessitated by the deliberate violation
of the clauses of the work contract by the petitioner. It defies all logic
as to why the petitioner, which had violated the contract, requiring
such additional tender to be floated, would be invited to participate in
the fresh tender for the balance of the same work. Hence, there is no
basis to the writ petitioner's challenge to its debarment from
participating in Tender No.BGB/BP/PT-03/2019-20.
47. Another ingredient which has to be considered is whether the
"admission" of M/s. Enoch that it was a financial creditor to the writ
petitioner has any bearing upon the present adjudication.
48. First, inter se communications between the writ petitioner and
respondent no.4 and/or pleadings of respondent no.4, being the sub-
contractor itself, cannot have any direct relevance to the debarment of
the petitioner, particularly in view of the termination order being
affirmed up to the Division Bench of this Court.
49. More importantly, an admission, even if any, by respondent no.4
cannot, by any stretch of imagination, bind the IOCL and its
functionaries. As such, such arguments of the writ petitioner has no
legs to stand upon.
50. Even if the said description of the respondent no.4 by itself as a
'financial creditor' could be broadly taken as an admission by
respondent no.4 in that regard, it cannot be said that such admission
would prevent the IOCL from terminating and debarring the writ
petitioner, by application of the principle of estoppel. The complaint of
M/s. Enoch was a mere trigger, and not the sole basis, for the
decision of termination and subsequent debarment of the writ
petitioner. The said complaint was only the genesis of the inquiry by
the IOCL against the writ petitioner. The complaint was neither
treated to be sacrosanct nor the only basis for terminating the
contract, suspending or Holiday Listing the writ petitioner. The
respondent-authorities independently arrived at findings upon
considering the materials produced by the writ petitioner itself as well
as other connected documents for the purpose of termination, leading
to suspension and subsequent debarment of the writ petitioner.
Hence, the alleged admission of respondent no.4 is utterly irrelevant
in the context. In its reply to the show cause and representation, the
writ petitioner did not specifically raise the question of prior
knowledge of the respondent-authorities about the arrangement
between the writ petitioner and M/s. Enoch. Rather, the factum of
the agreements being sub-contracts was admitted before the Division
Bench on behalf of the petitioner. Mere pendency of a review
application before the Division Bench, that too for an indefinite period,
cannot automatically operate as stay of such order. It is unacceptable
that mere allegation of previous knowledge of the arrangement
between the petitioner and M/s. Enoch would amount to 'prior written
approval' for grant of sub-contract, as mandated in the GCC and work
order issued to the writ petitioner by the IOCL. It cannot be said that
the clauses-in-question of the GCC were ancillary ones. The said
clauses contemplated consequential termination and award of the
balance work to third parties, hence integral to the work contract
between the petitioner and the IOCL.
51. In view of the above discussions, both the writ petitions fail on merits.
Accordingly, WPA No. 18440 of 2019 and WPA No.1404 of 2020 are
dismissed on contest without any order as to costs. All connected
applications are disposed of accordingly.
52. Urgent certified copies of this order shall be supplied to the parties
applying for the same, upon due compliance of all requisite
formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!