Thursday, 14, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Limited & Anr vs Suresh Chandra Rooj
2021 Latest Caselaw 3971 Cal

Citation : 2021 Latest Caselaw 3971 Cal
Judgement Date : 27 July, 2021

Calcutta High Court (Appellete Side)
Limited & Anr vs Suresh Chandra Rooj on 27 July, 2021
27.07.2021
    7
 ns Ct.04
                                  S.A. 236 of 2010

               West Bengal State Electricity Distribution Company
                                 Limited & anr.
                                       Vs.
                               Suresh Chandra Rooj.


             Mr. Sumit Ray ............                       for appellants.



                        Mr. Ray, learned advocate appears on behalf of

             appellants and presses for admission of the second appeal

             on ground no.IV, to be formulated as the substantial

             question of law. The ground is reproduced below:-



                        "IV. For that the Learned Appeal Court
                        failed to appreciate the true meaning
                        and purpose of the schedule appended
                        to the Indian Electricity Act, 1910 under
                        Section 3, Sub-Section (2), Clause (f)
                        whereby the Electrical Inspector was
                        empowered to decide any difference or
                        dispute arises as to the amount of
                        energy to be taken. Therefore it is not
                        correct to hold by the Appeal Court that
                        Electrical Inspector can only decide the
                        issue whether meter is correct or not,
                        and as such the impugned judgement
                        passed by the Learned Appeal Court in
                        Title   Appeal   No.47   of    2006    dated
                        September 20, 2008 is bad in law and
                        should be set aside."
                                    2




            The trial Court by judgment dated 10th May,

2006 dismissed the suit on contest against defendant no.2

and ex parte against defendant no.1, without costs. Issues

framed by said Court were as follows:-



            "1(a) is formulated at the time of
            Judgment-
            1) Is the suit maintainable in its present
            form?
            1.

a) Has the plaintiff any cause of action for filing the instant suit?

2) Is the suit barred u/s 34 of S.R. Act?

3) Is the suit barred by law of estoppel, waiver and acquiescence?

4) Whether the plaintiff is bona fide customer of the defendant?

5) Whether any arrear amount is lying due by the plaintiff for consuming electricity?

6) To what other relief, if any, is the plaintiff entitled?"

Plaintiff laid evidence both oral and documentary while

defendants did not. Issue nos.1, 1(a) and 4 to 6 were

decided against plaintiff and issue nos.2 and 3, in his

favour. Plaintiff appealed.

Lower appellate Court by judgment dated 20 th

September, 2008 set aside the trial Court's judgment. Said

Court found that sub-section (6) in section 26, Indian

Electricity Act, 1910 was not a bar to maintainability of the

suit. Sub-section (6) says as follows:-

"(6) Where any difference or dispute arises as to whether any meter referred to in sub-section (1) is or is not correct the matter shall be decided, upon the application of either party, by an Electrical Inspector; and where the meter has, in the opinion of such Inspector ceased to be correct, such Inspector shall estimate the amount of the energy supplied to the consumer or the electrical quantity contained in the supply, during such time, not exceeding six months, as the meter shall not, in the opinion of such Inspector, have been correct; but save as aforesaid, the register of the meter shall, in the absence of fraud, be conclusive proof of such amount or quantity:

Provided that before either a licensee or a consumer applies to the Electrical Inspector under this sub-section, he shall give to the other party not less than seven days' notice of his intention so to do."

We have perused both the judgments and

sections 24 and 26. Mr. Ray, in moving the appeal relied

on clause (3) in paragraph VI in the Schedule to the Act.

Said clause is reproduced below:-

"(3) Where any difference or dispute arises as to the amount of energy to be taken or guaranteed as aforesaid, or as to the cost of any service-line or as to the sufficiency of the security, offered by any owner or occupier, [or as to the

position of the meter board] or as to the improper use of energy, or to any alleged defect in any wires, fittings, works or apparatus, or as to the amount of the expenses incurred under the third proviso to sub-clause (1), the matter shall be referred to an [Electrical Inspector] and decided by him."

We ascertained from Mr. Ray that the Act did

not bar or oust jurisdiction of civil Court. He submits,

under the new Act there is a bar.

The lower appellate Court found on facts that

defence case of non-payment could not be sustained.

Positive case of plaintiff by oral and documentary evidence,

showing payment of bills raised, was proved. Said Court

went on to say that plaintiff had never disputed working of

the meter. It also did not go into plaintiff's contention that

the bills were incorrect but found plaintiff had paid them.

Hence, there was judgment restraining defendants from

seeking to recover on the bills. Defendants being aggrieved

have come before this Court.

The lower appellate Court having decided on

facts, no substantial question of law arises. It is a

consequence that appellant cannot discontinue the supply

on bills paid. The provision in the schedule, urged on

behalf of appellant is clearly inapplicable.

The appeal is dismissed.

(Arindam Sinha, J.)

(Saugata Bhattacharyya, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter