Citation : 2021 Latest Caselaw 359 Cal/2
Judgement Date : 7 April, 2021
IN THE HIGH COURT AT CALCUTTA
Ordinary Original Civil Jurisdiction
ORIGINAL SIDE
Present:
The Hon'ble JUSTICE MOUSHUMI BHATTACHARYA
A.P. 547 of 2008
Madan Kumar Saha
Vs.
Indian Oil Corporation Limited
For the Petitioner : Mr. Dhruba Ghosh, Sr. Adv.
Mr. Javed K. Sanwarwala, Adv.
Mr. Pradeep Kumar, Adv.
Mr. S. Dasgupta, Adv.
Ms. Madhurima Halder, Adv.
For the Respondent : Mr. Amit Kumar Nag, Adv.
Mr. Swarajit Dey, Adv.
Last Heard on : 25.03.2021.
Delivered on : 07.04.2021.
Moushumi Bhattacharya, J.
1. This is an application under Section 34 of The Arbitration and
Conciliation Act, 1996 for setting aside of an Award dated 10th July, 2008
passed by a learned Sole Arbitrator before whom the respondent before this
court was the claimant in the arbitration proceedings.
2. The respondent/Indian Oil Corporation Limited (IOCL) filed its
Statement of Claim in the arbitration for damages incurred pursuant to
termination of the dealership of the petitioner. The dispute between the
parties arose out of a Memorandum of Agreement dated 2nd April, 1976 in
connection with a dealership of a retail outlet at Howrah on the basis of
which the petitioner undertook to run a petrol pump in the name of M/s
Kalpana Service Station. The parties entered into a formal contract on 17th
June, 1977. The contention of the petitioner is that the respondent intended
at all material times that the dealers would induct a financial working
partner, if required and the petitioner accordingly inducted one Mr. Saidur
Rahman Khan for rendering necessary financial assistance. Mr. Khan
subsequently withdrew himself from the affairs of the petrol pump and the
petitioner requested the respondent to induct Mr. Khan as a financial
partner as per the respondent's Circular of 28th July, 1983. The petitioner's
case is that the respondent assured the petitioner that the petitioner would
be allowed to run the business with the help of a financial partner on the
basis of which the petitioner executed a general Power of Attorney in favour
of Mr. Khan. The petitioner's case is that the petitioner continued to run the
petrol pump as its sole owner and did not part with the rights of the service
station in favour of any third party. According to the petitioner, despite
being aware of the arrangement between the petitioner and Mr. Khan, the
respondent initiated a Vigilance Inquiry in 1993 followed by a Show-Cause
Notice issued on 17th July, 1997 on the petitioner for conducting operations
of the petrol pump contrary to the terms of the contract. The petitioner filed
an application in the arbitration for examining one Mr. G. C. Roy, an
Attorney of the respondent in relation to the Vigilance Report. The case of
the petitioner is that although Mr. G. C. Roy admitted to the existence of the
Vigilance Report, the said report was not produced by the respondent in the
arbitration.
3. The primary contention of Mr. Dhruba Ghosh, learned Senior Counsel
appearing for the petitioner, is that the Arbitrator based his findings on the
Vigilance Report which was not produced by IOCL and that if produced, the
Vigilance Report would show that IOCL/respondent had full knowledge of
the manner in which the petrol pump was being run since 1991. Counsel
submits that the Award is liable to be set aside as being contrary to public
policy and is perverse. Counsel submits that since the respondent was in
possession of the Vigilance Report and deliberately chose not to disclose the
same, the Arbitrator should have drawn adverse inference against the
respondent. It is further submitted that the Award is based on conjecture
and surmise by reason of the finding of the Arbitrator being premised on the
word "perhaps". Counsel also assails the Award as being devoid of reasons.
Counsel submits that it was the respondent's specific case in the Statement
of Claim that the petitioner had committed breach of the agreement by
entering into partnership with Mr. Khan without obtaining the respondent's
approval and that the petitioner had also transferred his shares in the
business to Mr. Khan. Counsel submits that the draft Deed of Partnership
between the petitioner and Mr. Khan dated 1st November, 1990 has nothing
to do with the dealership and further that the respondent was aware of the
arrangement between the petitioner and Mr. Khan since 1991.
4. Mr. Swarajit Dey, learned counsel appearing for the respondent seeks
to sustain the impugned Award by contending that the petitioner admittedly
failed to obtain prior written approval from IOCL before entering into the
Partnership Deed with Saidur Rahman Khan which was in breach of the
terms of the contract. Counsel submits that the respondent/IOCL did not
have knowledge of the induction of Mr. Khan, which would be evident from
the fact that the petitioner had not sent any notice of the same to the
respondent and further that there is no document on record to show that
the respondent had knowledge of the fact of induction of Mr. Khan prior to
20th March, 1997. Counsel submits that the respondent received the
concerned letter only in March 1997 and immediately took steps for issuing
the Show-Cause Notice on 17th July, 1997. Counsel accordingly submits
that there was no waiver on the part of IOCL since the petitioner has not
proved the fact that the respondent had knowledge of the induction of Mr.
Khan. Counsel additionally submits that no adverse inference should have
been drawn against the respondent for not producing the Vigilance Report
since there was no notice to produce the Vigilance Report and consequently
no direction on the respondent in relation thereto. Counsel submits that the
Award should not be interfered with on the factual aspect and further that
since the contract was determinable in nature, the Arbitrator could not have
passed any order for specific performance of the contract.
5. The primary ground of challenge for setting aside the impugned Award
is that the Award is perverse. The ground of perversity is based on the fact
that the learned Arbitrator based his findings on a document that had not
been brought on record by the respondent/ IOCL, namely the Vigilance
Inquiry Report. The other ground of challenge is that the Award is based on
surmise and conjecture since the Arbitrator has prefaced his finding on the
termination of the dealership by the respondent/IOCL with the word
"perhaps".
6. The above grounds of challenge have to be tested against the findings
of the Arbitrator. The first ground, namely, that the Award is perverse is
based on the presumption that (a) the entire Award is based on the Vigilance
Report and (b) that the Vigilance Report was the only essential document
which decided the issue of termination of the petitioner's dealership by the
respondent.
7. The dispute arose between the petitioner (respondent in the
Arbitration) and the respondent, IOCL (claimant before the arbitrator) from
cancellation of a dealership of a Service Station- M/s Kalpana Service
Station- by the respondent on the apparent breach of the terms and
conditions of the Agreement by the petitioner. The respondent awarded the
dealership of the Pump to the petitioner with effect from 02.04.1976. In
November, 1991 the petitioner sought permission from IOCL to induct
Saidur Rahman Khan as a financial partner to which by a letter of January,
1992, IOCL instructed the petitioner not to reconstitute the business
without first obtaining IOCL's approval. A Partnership Deed was entered into
between the petitioner and Mr. Khan on 1st November, 1990, which
according to IOCL was in breach of the petitioner's obligation not to enter
into any arrangement with regard to the Service Station. IOCL issued a
show-cause on the petitioner on 17th July, 1997 and the Dealership
Agreement was terminated on 28th March, 2000. The petitioner was directed
to hand over vacant possession of the retail outlet together with the assets
and properties of IOCL. IOCL claimed possession of the retail outlet and
damages of Rs. 5,000/- per day from 01.04.2000 until delivery of possession
together with other expenses of Rs. 3,00,000/-. According to the petitioner,
IOCL had full knowledge and had given approval to the induction of Mr.
Khan as a financial partner. The petitioner also claims that since Mr. Khan
made further investments in the business, a General Power of Attorney was
executed by the petitioner in the name of Mr. Khan which however was not
given effect to. It is also contended that the Partnership Deed dated
01.11.1990 executed between the petitioner and Mr. Khan was based on the
assurances given by the officers of IOCL, but which was also finally not
given effect to. The petitioner claims that these facts were stated by the
petitioner in the Vigilance Inquiry conducted by the Vigilance Officer of
IOCL.
8. The impugned Award contains detailed references to the facts, which
culminated in the reference of the disputes to Arbitration. The "Conclusions"
of the Arbitrator followed the recordings of the factual position between the
parties. After taking into account the relevant facts the Arbitrator concluded
that IOCL did not have knowledge of the induction of Mr. Khan. The reason
given for this finding is that there was no document on record to prove the
involvement of IOCL in the induction of Mr. Khan. The Arbitrator has also
come to the finding that Mr. Khan was inducted in the affairs of the
dealership prior to permission being sought from IOCL which was in clear
breach of the terms of the Dealership Agreement executed between the
petitioner and IOCL. It is also noted that although the petitioner was given
time in February, 1998 to rectify the breaches committed by it, the
petitioner approached the National Commission for the SCs and STs after
which the dealership was terminated on 28th March, 2000. The Arbitrator
found that the claim of IOCL was not defeated by delay since IOCL had given
the petitioner time to rectify the breach.
9. The question which therefore falls for consideration is whether the
Arbitrator has wholly based his decision to answer the abovementioned two
issues framed by the Arbitrator in favour of the respondent IOCL on the
Vigilance Inquiry Report.
10. For ease of reference the reasons in the judgment are divided under
two headings.
(i) That the Vigilance Report was the only essential document which
decided the issue of termination of the petitioner's dealership by the
respondent.
The first two issues were concerned with whether IOCL was entitled
to cancel the dealership, whether it was aware of the actions taken by the
petitioner and whether the claim of IOCL could be defeated on the ground of
delay. This question was decided with reference to the first two issues
framed by the learned Arbitrator. From a perusal of the reasons given by the
Arbitrator in arriving at the conclusion that IOCL was entitled to cancel the
dealership and was not aware of the induction of Mr. Khan makes it clear
that the Arbitrator did not base his findings solely on the Vigilance Inquiry
Report. It is also important to note that the case of the petitioner before this
Court is that there has been waiver on the part of IOCL with regard to
induction of Mr. Khan in the dealership business. Counsel has sought to
deal with the issue of breach of the Agreement regarding the alleged waiver
on the part of IOCL namely that IOCL was all along aware of the involvement
of Mr. Khan in the business but chose to issue the show-cause notice and
terminate the Agreement despite such knowledge. It should be stated in this
context that the argument of waiver presumes that IOCL was aware or had
knowledge of the induction of Mr. Khan. The Arbitrator has recorded a clear
finding that there was no document on record to show that IOCL was
involved in any assurance which may have prompted the petitioner to
execute the documents in favour of a third party. The fact that IOCL came
to learn of the induction on 20th March, 1997 has not been dislodged by any
factual evidence relied upon by the petitioner. Since the conclusions of the
Arbitrator is based on other factual findings, namely the correspondence
between the parties and the significance of the dates on which documents
were executed by the petitioner, it cannot be said that the Vigilance Inquiry
was the only reason for the Arbitrator to justify the termination of the
Dealership Agreement. The argument of the petitioner before this Court on
this contention is hence rejected.
(ii) The Award is based on conjecture and surmise.
The part of the Award which has been assailed by the petitioner on the above ground is reproduced below:-
"It also appears that perhaps, the dealership was terminated after a Vigilance Enquiry
finding of dealership being operated as 'benami'. There is nothing in law or contract between
the parties that takes away the right of the Corporation in exercising a right vested in it,
because it chooses to allow some time or a second chance to the party in breach to rectify its
faults. Therefore, the claim of the Claimant is not defeated by delays. This issue is
accordingly decided in favour of the Claimant and against the Respondent".
According to the petitioner, the Vigilance Inquiry Report was not
brought on record or proved by IOCL in the Arbitration proceedings despite
the petitioner contending that the Vigilance Report would show that IOCL
had full knowledge of the manner in which the Petrol Pump had been run
since 1991. The petitioner's case is that since the Vigilance Report was not
part of the record, the Arbitrator based his Award on an absence of evidence
rendering the Award perverse. The petitioner has also argued that the
Arbitrator should have drawn adverse inference against the respondent for
not discussing the Vigilance Report. The aforesaid contentions of the
petitioner have to be decided on whether the Vigilance Report was the only
document on which the Arbitrator held that the termination of the
Agreement was valid. This Court has already negated such contention in the
earlier part of this judgment.
The other issue which however remains to be decided is whether the
Award shows that the petitioner had sought for production of the Vigilance
Report by way of an application or otherwise. This Court has carefully
considered the Award from which it is evident that there is no recording in
the Award which would show that the petitioner made an application for
production of the Vigilance Report or that IOCL refused to produce the said
Report despite such request/application. This Court is of the view that
adverse inference against the respondent/IOCL based on non-production of
the Vigilance Report would only arise if IOCL refused to produce the same
despite an application made by the requesting party or in defiance of a
direction of the Arbitrator. Question No. 85 of the cross-examination relied
on by the petitioner does not show that IOCL refused to produce the Inquiry
Report. In fact, the answer of the respondent's witness is that despite,
Vigilance Report being a confidential document, IOCL may produce it upon a
direction of the Arbitrator. Hence, from a conjoint reading of the Award as
well as the evidence relied on by the petitioner, it cannot be stated that the
Arbitrator should have drawn an adverse inference on IOCL for non-
production of the Vigilance Report.
Use of the word "perhaps" in the context of the sentence further
indicates that the Vigilance Inquiry Report may have been an additional
reason for IOCL to terminate the Agreement (underlined for emphasis).
Hence the ground taken by the petitioner of the Award being based on
surmise and conjecture is not acceptable and is rejected.
11. The cases relied on by the petitioner on the law of perversity namely
Associate Builders vs Delhi Development Authority; (2015) 3 SCC 49 proceeds
on the fact that the Arbitrator either ignored vital evidence or came to a
finding without any evidence. Since it has already been held that the
Vigilance Report did not form the only basis of the Arbitrator's finding on the
validity of the termination, this decision cannot be of any assistance to the
petitioner. Ajay Kumar D. Amin vs Air France; (2016) 12 SCC 566, Union of
India vs Sugauli Sugarworks (P) Ltd.; (1976) 3 SCC 32 and Sathyanarayana
Brothers (P) Ltd. vs Tamilnadu Water Supply and Drainage Board; (2004) 5
SCC 314 are decisions in which the courts should have drawn adverse
inference on a vital piece of evidence and found that an Award would be
vitiated if relevant documents are ignored. In Ajay Kumar D. Amin and
Sugauli Sugarworks important documents were suppressed by the parties
and witnesses were not examined for proving vital facts which is unlike the
present case where no application was made on IOCL to produce the
Vigilance Report. In Ajay Kumar D. Amin, the Supreme Court held that
failure of a party to produce a document which should have been produced
despite a direction for such coupled with failure to explain such non-
production raises a presumption that the contents were unfavourable to the
party. An adverse inference should hence be drawn against the said party.
There is also nothing on record in the present case to show that despite an
application made for production of the Report or an order of the learned
Arbitrator to that effect, IOCL refused to disclose the same.
12. On the other hand in Associate Builders vs Delhi Development
Authority the Supreme Court has cautioned that a Section 34 Court does
not sit in Appeal over an Award for reassessing the evidence. Dyna
Technologies Pvt. Ltd. vs Crompton Greaves Ltd; (2019) SCC Online SC 1656
is on the same vein where the Supreme Court held that an Award should
not be interfered with merely because an alternative view on facts or
interpretation of the contract is possible and further that a Court should
defer to the view taken by the Arbitrator unless the reasoning is found to be
perverse. Since this Court is of the view that the Award contains sufficient
and clear reasons for coming to the conclusions and that a definite and
intelligible link exists between the factual findings and the conclusions, the
Award must be sustained. This Court does not find any reason to interfere
with the Award under the grounds available under Section 34 of the 1996
Act and much less on the grounds taken in the present application for
setting aside of the impugned Award.
13. In view of the above A.P No. 547 of 2008 is dismissed without any
order as to costs.
Urgent Photostat certified copy of this Judgment, if applied for, be
supplied to the parties upon compliance of all requisite formalities.
(MOUSHUMI BHATTACHARYA, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!