Citation : 2026 Latest Caselaw 2813 Bom
Judgement Date : 18 March, 2026
2026:BHC-OS:6861
901-CARBP(L) NO-30675-2023.docx
Swapnil IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
COMMERCIAL ARBITRATION PETITION (L) NO. 30675 OF 2023
Oriental Insurance Company Ltd.
A Company incorporated & registered
under the provisions of Companies Act
1956 and having its address at MCBO 9,
103/104, First Floor, Faizan Apartments,
Above Syndicate Bank,
Jogeshwari (West), Mumbai - 400102.
having its Regional Office at Mumbai
Regional Office 3, 601605, Town Centre-1,
Andheri Kurla Road, Marol, Near Saki Naka,
Andheri (E), Mumbai - 400059. ...Petitioner
(Org. Resp.)
Vs.
Add On Retail Pvt. Ltd.
A Company registered under the
Companies Act, 1956 and having its
Registered Office (for all
correspondences) at A-1402, Shikhar
Kunj, Upper Goving Nagar, Malad-East,
Mumbai-400097. ...Respondent
(Org. Claimant)
Mr. D. S. Joshi for the Petitioner.
Mr. Harsh L. Behany a/w. Ms. Saloni Manjrekar i/b. H. N.
Legal for the respondent.
1/22
::: Uploaded on - 18/03/2026 ::: Downloaded on - 18/03/2026 20:52:24 :::
901-CARBP(L) NO-30675-2023.docx
CORAM : GAURI GODSE, J.
RESERVED ON: 28th NOVEMBER 2025
PRONOUNCED ON: 18th MARCH 2026
JUDGMENT:
1. This arbitration petition is filed under Section 34 of the
Arbitration and Conciliation Act, 1996 ("the Arbitration Act"),
praying to set aside the award dated 2 nd August 2023
directing the payment towards an insurance claim. The
award grants an amount of Rs. 3,04,87,713/- towards the
loss of stock of fabrics and 25% of Rs. 1,49,29,335/- towards
the loss of stock of accessories. The award grants interest at
the rate of 8% p.a. on the awarded amount from 27 th
December 2018 till the date of passing of the award, and
further interest at 12% p.a. till its realisation. The cost of
litigation is also granted in favour of the claimant.
2. The following facts would be relevant for considering
the rival submissions on behalf of the parties:-
(a) The respondent obtained the insurance policy to cover
the stock of textiles, garments, and other accessories stored
in the insured premises, as described in the policy. On 23 rd
February 2017, a fire took place at the insured premises, and
the entire stock in the godown was destroyed. On the same
901-CARBP(L) NO-30675-2023.docx
day, the respondent intimated the incident to the petitioner.
On 24th February 2017, the respondent intimated to the
petitioner that it had suffered a loss of approximately Rs. 15
Crores due to the fire. Accordingly, the petitioner appointed
an insurance surveyor to assess the loss. Various
correspondence between the parties is brought on record
regarding the inspection that took place and the steps taken
by the surveyor who assessed the actual loss.
(b) Between 6th May 2017 and 19th May 2017, the
respondent informed its bank that it had suffered a loss of
approximately Rs. 11.73 Crores due to the fire. The assessor
showed the respondent the summary of the final
assessment, which was on the lower side. There are various
emails on record from the respondent to raise objections to
the assessment.
(c) On 20th July 2018, the claimant visited the petitioner's
head office because the claim was not settled. On 16 th
October 2018, the revised assessment of loss was
submitted, and the original loss assessed at Rs.
11,74,57,294.26 was reduced to Rs. 6,15,28,050/-. As per
the revised assessment, the reduced amount was offered to
901-CARBP(L) NO-30675-2023.docx
the respondent. On 2nd November 2018, the claimant signed
the discharge voucher under protest and accepted the
amount. Thereafter, the arbitration proceedings were initiated
as the respondent was not satisfied with the reduced
assessment.
3. The submissions made on behalf of the petitioner are
summarised as under :
(a) The acceptance of the amount as per the revised
assessment would amount to accord and satisfaction of the
claim. The respondent was facing a severe financial crisis;
hence, after accepting the amount, the respondent raised
objections to the assessment. The respondent's Bank had
initiated the proceedings under the Securitisation and
Reconstruction of Financial Assets and Enforcement of
Security Interest Act, 2002 (" the SARFAESI Act"), and the
respondent's Bank had taken over symbolic possession of
the property of the respondent. Hence, the respondent's
director, by email dated 9th July 2018, requested that the
insurance company to settle the claim. Accordingly, a survey
was carried out, and, as per the surveyor's assessment
report, the amount has been released to the respondent. The
901-CARBP(L) NO-30675-2023.docx
emails exchanged between the parties would show that the
amounts were settled as requested by the claimant, and
thus, in view of the principle of accord and satisfaction, the
respondent was precluded from demanding any higher
amount than the amount paid as per the surveyor's report.
(b) Learned counsel for the petitioner submitted that the
Insurance Regulatory Authority ("IRDA") has formulated the
Insurance Surveyors and Loss Assessors (Licensing,
Professional Requirements and Code of Conduct)
Regulations, 2000, which regulate the licensing and the work
of surveyors. He relied upon the decision of the Apex Court
in the case of Sri Venkateswara Syndicate Vs. Oriental
Insurance Company Limited and Anr.1 to support his
submission that the Scheme of Section 64-UM of the
Insurance Act, particularly of sub-sections (2), (3) and (4),
would show that the insurer cannot appoint a second
surveyor just as a matter of course, and that if there are
inherent defects in the report, if it is found to be arbitrary,
excessive, exaggerated, etc. and that there is no prohibition
in the Insurance Act for appointment of second surveyor by
the insurance company.
(2009) 8 SCC 507
901-CARBP(L) NO-30675-2023.docx
(c) The subsequent claim is based on the events
commencing from 16th October 2018 to 2nd November 2018.
However, the respondent had given consent on 16 th October
2018, and thus, the claimant was not entitled to claim any
further amount. The discharge voucher signed by the
respondent would constitute full and final satisfaction of the
claim. Hence, the learned Arbitrator has erred in granting the
amount despite the claimant receiving the full amount based
on the revised assessment report submitted by the surveyor.
Hence, the impugned award suffers from patent illegality and
perversity on the ground of not taking into consideration the
principle of accord and satisfaction.
4. Learned counsel for the respondent supported the
impugned award on the following submissions:-
(a) All emails exchanged between the parties clearly
indicate that the claimant accepted the amount under protest.
The claimant had already suffered due to the delay in
reassessing the claim at the request of the insurance
company. The claimant was in need of financial help due to
the loss suffered in the fire. Hence, the claimant had no other
option but to accept the reduced amount under protest. The
901-CARBP(L) NO-30675-2023.docx
claimant, by its emails, repeatedly urged the insurance
company to settle the long-pending claim, as the respondent
was incurring substantial interest liability on payments
towards the proceedings initiated by its bank. As the claimant
was facing a severe cash crunch, the amount was accepted
under protest, as evident from the delivery voucher. The
learned arbitral tribunal has therefore correctly interpreted
the delivery voucher as an amount accepted under protest.
(b) The record shows that from the outset, the claimant
raised objections to the quantification prepared by the
assessor. Thus, it was not only at the time of final
disbursement that a protest was lodged by the claimant;
however, at all the relevant stages, the protest was recorded
by the claimant. Thus, at this stage, the issue of accord and
satisfaction cannot be considered in detail, as it has already
been decided by the learned arbitrator. Reconsideration of
the issue on accord and satisfaction would amount to
reappreciation of the evidence, which is not permissible
under Section 34 of the Arbitration Act.
(c) Learned counsel for the respondent relied upon the
circulars dated 24th September 2015 and 7th June 2016
901-CARBP(L) NO-30675-2023.docx
issued by the IRDA. The circulars make it clear that the
execution of a voucher would not amount to the foreclosure
of the policyholder's right to seek higher compensation
before any judicial authority. The circulars state that under no
circumstances should a discharge voucher collected under
duress, coercion, or compulsion be treated as accord and
satisfaction.
(d) To support his submissions, learned counsel for the
respondent relied upon the decision of the Apex Court in the
case of National Insurance Company Limited Vs. Boghra
Polyfab Private Limited2, R. L. Kalathia and Company Vs.
State of Gujarat3, Worldfa Exports Pvt. Ltd. Vs. United
India Insurance Co. Ltd.4
(e) It is submitted on behalf of the respondent that the
decisions relied upon by the learned counsel for the
petitioner would not apply to the facts of this case, as there
were two survey reports on record and thus, the insurance
company cannot keep on appointing surveyors till the
assessment report is submitted as desired by the insurance
company. The learned arbitrator has recorded clear findings
(2009) 1 SCC 267.
(2011) 2 SCC 400.
2015 SCC Online Del 13951
901-CARBP(L) NO-30675-2023.docx
in paragraph 53 of the award, holding that the discharge
voucher was signed under protest and that it would not
amount to acceptance of the claim towards a full and final
settlement.
(f) The surveyor's assessment dated 11 th November 2017
clearly indicated the actual loss suffered by the claimant. The
learned arbitrator has accordingly independently assessed
the surveyor's report and recorded a finding based on the
two survey reports submitted by the surveyors appointed by
the insurance company. Hence, any interference in the
findings recorded by the learned arbitrator would amount to
reappreciating the evidence on record, which is not
permissible under Section 34 of the Arbitration Act.
(g) As per the terms and conditions of the insurance policy,
the total claim of Rs. 18 Crores was secured. However, the
respondent registered a claim only for Rs. 11 Crores
commensurate with the actual loss suffered. The findings
recorded by the learned arbitrator are based on the
surveyor's assessment appointed by the insurance company.
The contents of the final assessment report were not shown
to the claimant at the relevant time. Thus, the summary of
901-CARBP(L) NO-30675-2023.docx
the final assessment of the revised assessment was not
acceptable to the claimant. The assessor sought the
claimant's consent to the summary of the final assessment.
However, the claimant had refused to give any consent.
(h) The admissions given by the assessor in the cross-
examination support the claimant's contentions that the final
assessment report was objected to as it was on the lower
side. All this evidence brought on record is appreciated by
the learned arbitrator to arrive at the final figures as awarded.
None of the figures calculated by the learned arbitrator is
beyond the assessment reports prepared by the surveyors
appointed by the insurance company. The correspondence
on record shows that the insurance company delayed
settlement of the claim despite the assessment report
submitted on 10th March 2017. Only with the intention of
bringing down the surveyor's assessment was the payment
delayed as per the first assessment. Hence, the learned
arbitrator has correctly appreciated the evidence on record
and recorded the findings on the actual loss suffered by the
claimant. The entire claim is based on the actual loss
suffered and the quantification made in accordance with the
901-CARBP(L) NO-30675-2023.docx
records maintained by the claimant. Hence, interference with
the award would amount to taking a different view by
reappreciating the evidence, which is not permissible under
Section 34 of the Arbitration Act.
5. Learned counsel for the claimant relied upon the Apex
Court's decision in Ssangyong Engineering and
Construction Company Limited V/s National Highways
Authority of India5 to support his submissions that
interference with the award in an application under Section
34 of the Arbitration Act is narrow and unless patent illegality,
perversity or contravention of law is shown the award cannot
be interfered with. He submitted that the arbitration petition
under section 34 is a summary proceeding and not in the
nature of an appeal; hence, the court reviewing the arbitral
award does not sit in appeal over the award and if the view
taken by the arbitral tribunal is a possible view, no
interference under Section 34 of the Arbitration Act is called
for. Hence, none of the grounds contemplated under Section
34 of the Arbitration Act is made out by the petitioner to set
aside the award. Hence, the Arbitration Petition deserves to
be rejected.
(2019) 15 SCC 131
901-CARBP(L) NO-30675-2023.docx
Analysis and Conclusions:
6. I have carefully perused the papers. There is no
dispute that the revised assessment reduced the original
assessment of Rs. 11,74,57,294.26, as done on 11 th
November 2017, to Rs. 6,15,28,050/- on 16 th October 2018.
Learned Arbitrator has recorded that the claimant signed the
discharge voucher under protest and accepted the amount. I
have perused the discharge voucher. A plain reading of the
voucher reveals that the claimant had accepted the amount
under protest. However, it is sought to be argued on behalf of
the petitioner that the claimant, vide letter dated 16 th October
2018, consented to the assessment; hence, there was
accord and satisfaction, and the payment accepted by the
claimant was towards the full and final settlement of the
claim. The letter dated 16th October 2018, issued by the
claimant, consenting to the assessment, cannot be read in
isolation, ignoring the various emails issued by the claimant
objecting to the reduction in the assessment. It is a matter of
record that on 11th November 2017, the summary of the final
assessment was intimated to the claimant. However, the
901-CARBP(L) NO-30675-2023.docx
petitioner made no payment. It is also a matter of record that
the petitioner delayed the release of the claim amount.
7. The various emails produced on record by the claimant
show that repeated requests were made to the petitioner to
release the amount. It is brought on record by the respondent
that they were suffering a severe financial crunch due to the
fire incident, and that the respondent was required to make
payments to its bank, as SARFAESI proceedings had been
initiated by the respondent's bank. Hence, the respondent
repeatedly intimated to the petitioner that the claim amount
should be released. The record shows that, despite all
documents submitted by the claimant, the assessment report
was not finalised, and it was only after the claimant's
constant follow-up that the report dated 11 th November 2017
was released. However, the amount was not paid to the
claimant. It is only at the petitioner's behest that, despite the
final assessment of 11th November 2017, a fresh survey was
carried out, and the revised assessment was intimated after
11 months of the original assessment. Hence, the
respondent had no option but to consent to the assessment
made on 16th October 2018 and request the release of the
901-CARBP(L) NO-30675-2023.docx
payment. The consent letter dated 16th October 2018 was
issued along with an email dated 16 th October 2018, which
recorded that the respondent, with folded hands, requested
the release of the payment. Thus, considering all this
documentary evidence, together with the admissions made
by the petitioners' witnesses during cross-examination, the
learned arbitrator has recorded that the consent letter dated
16th October 2018 cannot be accepted as an accord and
satisfaction. Hence, the discharge voucher, clearly recording
acceptance of payment under protest, is not treated as the
acceptance of payment by way of full and final settlement.
8. The fire incident took place on 23 rd February 2017. The
claimant immediately informed the petitioner about the
incident. The claimant informed that it had suffered a loss of
approximately Rs.15,00,00,000/- due to the fire. The
assessor appointed by the petitioner visited the site on 24 th
February 2017. As requested by the assessor on 28 th
February 2017, the claimant submitted all the documents on
10th March 2017, and the claim form for an amount of
Rs.11,74,56,576/-. After rigorous follow-up, the petitioner
released the final assessment report only on 11 th November
901-CARBP(L) NO-30675-2023.docx
2017. The amount was not released, and a second surveyor
was appointed who submitted the revised assessment after
eleven months on 16th October 2018 at a lower side.
However, the petitioner has shown nothing to indicate that
the second surveyor was appointed for any valid reason.
9. In the decision of the Hon'ble Apex Court in Sri
Venkateswara Syndicate relied upon by the learned
counsel for the petitioner, it is held that the scheme of
Section 64-UM of the Insurance Act, particularly of sub-
sections (2), (3) and (4) would show that the insurer cannot
appoint a second surveyor just as a matter of course and it
must specify cogent reasons, without which it is not free to
appoint the second surveyor or surveyors till it gets a report
which would satisfy its interest. It is further held that the
option to accept or decline the report lies with the insurer;
however, if the rejection of the report is arbitrary and based
on no acceptable reasons, the courts or other forums can
definitely step in and correct the error committed by the
insurer while repudiating the claim of the insured. The
Hon'ble Apex thus held that if the reports are prepared in
good faith, with due application of mind and in the absence of
901-CARBP(L) NO-30675-2023.docx
any error or ill motive, the insurance company is not
expected to reject the report of the surveyors.
10. In the present case, the learned Arbitrator has
examined the surveyor's reports and the evidence led by
both parties and held that, in the revised assessment, the
surveyor has not considered the value of the goods in
respect of the fabrics. After exhaustively examining the entire
record, the learned Arbitrator held that the surveyor admitted,
during cross-examination, that the value of the stock was Rs.
10,17,82,021, but he granted only Rs. 6,76,33,561/-. Thus,
the learned Arbitrator has rightly stepped in and corrected
the errors committed by the insurer. Therefore, the learned
Arbitrator, after appreciating the evidence, has rightly granted
the claim. The figures of the claim amount arrived at by the
learned Arbitrator are based on the record and the surveyor's
reports.
11. The circulars dated 24th September 2015 and 7th June
2016 issued by the IRDA support the claimant's contentions
that the voucher signed by the claimant under protest would
not foreclose the right to seek higher compensation before
the arbitral tribunal. The Apex Court in the case of National
901-CARBP(L) NO-30675-2023.docx
Insurance Company Limited has explained the applicability
of the principle of accord and satisfaction as under:
"27. While discharge of contract by performance refers to
fulfilment of the contract by performance of all the obligations
in terms of the original contract, discharge by "accord and
satisfaction" refers to the contract being discharged by
reason of performance of certain substituted obligations. The
agreement by which the original obligation is discharged is
the accord, and the discharge of the substituted obligation is
the satisfaction. A contract can be discharged by the same
process which created it, that is, by mutual agreement. A
contract may be discharged by the parties to the original
contract either by entering into a new contract in substitution
of the original contract; or by acceptance of performance of
modified obligations in lieu of the obligations stipulated in the
contract."
12. In R.L. Kalathia, the Hon'ble Apex Court held that
even after execution of full and final discharge
voucher/receipt by one of the parties, if the said party is able
to establish that he is entitled to further amount for which he
is having adequate materials, he is not barred from claiming
901-CARBP(L) NO-30675-2023.docx
such amount merely because of acceptance of the final bill
by mentioning "without prejudice" or by issuing "no-dues
certificate".
13. In Worldfa Exports, the Delhi High Court held that
insurance companies cannot withhold payment of the
admitted claim amount to the insured unless the insured
provides a complete discharge. It is held that insurance
companies are not expected to withhold the admitted claim
amount until the insured produces the receipt for full and final
settlement. However, in the present case, there is no
admitted claim, and the controversy concerns the application
of the principle of accord and satisfaction in light of the
claimant's letter dated 16th October 2018 and the discharge
voucher signed under protest. I have already recorded
reasons that the said letter and the discharge voucher cannot
be accepted as a full and final settlement of the claim.
Hence, in view of the well-established legal principles as
discussed in the above paragraphs, the said letter and the
discharge voucher cannot be accepted as accord and
satisfaction of the claim.
901-CARBP(L) NO-30675-2023.docx
14. There is substance in the submissions made by the
learned counsel for the claimant that any interference in the
findings recorded by the learned arbitrator would amount to
reappreciating the evidence on record, which is not
permissible under Section 34 of the Arbitration Act.
15. The Apex Court in Ssangyong Engineering and
Construction Company Ltd, summarised and clarified the
law regarding the permissibility of interference on the
grounds of judicial approach, patent illegality, breach of
principles of natural justice, contravention of law and
perversity. This court, in a recent decision in ECGC Ltd Vs.
Baco Metallic Industries6, held that it is now trite law that
the Section 34 Court must not lightly interfere with arbitral
awards, and that the scope of review is set out in multiple
decisions of the Apex Court. To summarise the scope of
interference under Section 34, this court reproduced the
relevant paragraphs of the Apex Court's decisions in
paragraphs 22 and 23 as under;
"22. It is now trite law that the Section 34 Court must not lightly interfere with arbitral awards. The scope of review by the Section 34 Court is also well covered in multiple judgments of the Supreme Court including Dyna
2025 SCC Online Bom 3959
901-CARBP(L) NO-30675-2023.docx
Technologies1, Associate Builders2, Ssyangyong3, Konkan Railway4 and OPG Power5. Even implied reasons, if discernible, may be inferred to support a just and fair outcome arrived at in arbitral awards. To avoid prolixity, I am not reproducing copiously from these judgments. Suffice it to say (to extract from just one of the foregoing), in Dyna Technologies, the Supreme Court held thus:
"24. There is no dispute that Section 34 of the Arbitration Act limits a challenge to an award only on the grounds provided therein or as interpreted by various courts. We need to be cognizant of the fact that arbitral awards should not be interfered with in a casual and cavalier manner, unless the court comes to a conclusion that the perversity of the award goes to the root of the matter without there being a possibility of alternative interpretation which may sustain the arbitral award. Section 34 is different in its approach and cannot be equated with a normal appellate jurisdiction. The mandate under Section 34 is to respect the finality of the arbitral award and the party autonomy to get their dispute adjudicated by an alternative forum as provided under the law. If the courts were to interfere with the arbitral award in the usual course on factual aspects, then the commercial wisdom behind opting for alternate dispute resolution would stand frustrated.
25. Moreover, umpteen number of judgments of this Court have categorically held that the courts should not
901-CARBP(L) NO-30675-2023.docx
interfere with an award merely because an alternative view on facts and interpretation of contract exists.The courts need to be cautious and should defer to the view taken by the Arbitral Tribunal even if the reasoning provided in the award is implied unless such award portrays perversity unpardonable under Section 34 of the Arbitration Act."
[Emphasis Supplied]
23. In OPG Power, the Supreme Court explained the scope of interference with interpretation and construction of a contract accorded in an arbitral award in the following words:--
"72. An arbitral tribunal must decide in accordance with the terms of the contract. In a case where an arbitral tribunal passes an award against the terms of the contract, the award would be patently illegal. However, an arbitral tribunal has jurisdiction to interpret a contract having regard to terms and conditions of the contract, conduct of the parties including correspondences exchanged, circumstances of the case and pleadings of the parties. If the conclusion of the arbitrator is based on a possible view of the matter, the Court should not interfere. But where, on a full reading of the contract, the view of the arbitral tribunal on the terms of a contract is not a possible view, the award would be considered perverse and as such amenable to interference."
[Emphasis Supplied] "
901-CARBP(L) NO-30675-2023.docx
16. In the present case, the arguments raised on behalf of
the petitioner would amount to a reappreciation of the
evidence. As discussed in the aforesaid paragraphs, the
learned Arbitrator has considered the entire evidence and
recorded reasons to grant the claim. None of the grounds
raised by the petitioner would be covered under the scope of
interference under Section 34. Hence, in my view, by
applying the standards as set out in the various decisions as
discussed above, the arbitral award cannot be interfered with
under Section 34 of the Arbitration Act.
17. Hence, for the reasons recorded above, the Arbitration
Petition is rejected.
[GAURI GODSE, J.]
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!