Citation : 2026 Latest Caselaw 943 Bom
Judgement Date : 28 January, 2026
2026:BHC-OS:2356
ARBPL.38852 of 2025.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
ARBITRATION PETITION (L) NO. 38852 OF 2025
Tagore Nagar Ashtavinayak CHS Ltd. .. Petitioner
Versus
Puneet Realty Pvt. Ltd. .. Respondent
Mr. Pradeep Sancheti, Senior Counsel, a/w B.K. Barve, Simmy
Sebastian, Dhanesh Gaikwad, i/b B.K. Barve, for the Petitioner.
Mr. Mayur Khandeparkar, a/w Viraj Parikh, i/b Jayesh Mestry,
for Respondent.
CORAM : SOMASEKHAR SUNDARESAN, J.
DATE : JANUARY 28, 2026
ORAL JUDGEMENT :
Context and Factual Background:
1. This is a petition filed under Section 37 of the Arbitration and
Conciliation Act, 1996 ("the Act") impugning an order dated November
3, 2025 ("Impugned Order") passed by a Learned Arbitral Tribunal
under Section 17 of the Act.
2. The Petitioner, Tagore Nagar Ashtavinayak Co-operative Digitally signed by AARTI Housing Society Ltd. ("Society") and the Respondent, Puneet Realty AARTI GAJANAN GAJANAN PALKAR
2026.01.28 15:20:41 JANUARY 28, 2026 +0530 Aarti Palkar
ARBPL.38852 of 2025.doc
Private Ltd. ("Developer") entered into a memorandum of
understanding dated January 10, 2023 (" MOU") in connection with
redevelopment of Building No. 32, at Vikhroli East, constructed in 1963
by the Maharashtra Housing Board under the subsidised industrial
housing scheme of the Maharashtra Housing and Area Development
Authority ("MHADA"). The building was to be sold to the association of
allottees and the land underneath the building was to be leased to such
association. The Society was formed by the allottees.
3. It is common ground that the building has been and is in a
dilapidated condition. By a public notice dated 17.05.2022, the Society
invited bids from various developers for redevelopment of the building.
The Developer responded to the said tender and made a proposal on
May 31, 2022. By a special general body meeting (" SGBM") resolution
passed on August 17, 2022, the Society approved the appointment of
the Developer in order to effect the redevelopment of the building.
4. The parties then engaged on the draft of a development
agreement and eventually, the final draft of the Development
Agreement ("DA") is said to have been sent by the Developer to the
Society by an email dated December 14, 2022. On December 30, 2022,
another SGBM was held to approve execution of the MOU with the
Developer. The finalised draft of the DA was to be an annexure to the
JANUARY 28, 2026 Aarti Palkar
ARBPL.38852 of 2025.doc
MOU, which would entail granting redevelopment rights to the
Developer and enabling the Developer to perfect the lease of the land
from MHADA by payment of the requisite amounts stipulated by
MHADA and the sale of the building from MHADA in favour of the
Society.
5. Various other annexures such as the resolutions passed by the
Society, which were in the possession of the Society, were meant to be
annexed to the MOU. According to the Developer, despite repeated
requests, these documents were not provided by the Society, but the
parties continued to act in terms of the MOU, with the Developer taking
steps and also incurring expenses in coordination with the Society, and
the Society benefitting from such actions, even while seeking to
renegotiate and get a bigger and better deal .
6. The MOU provided that the Developer must obtain the
conveyance within a period of 270 days from its execution. The MOU
was executed by the Developer, the Society and also by multiple
members of the Society, other than those who were deceased as of the
date of its execution. Another MOU came to be executed on March 9,
2023 which was executed by legal heirs of ten members who had not
executed the MOU earlier. The new MOU was identical in its terms to
the earlier MOU and contained the same 270-day deadline by reference
JANUARY 28, 2026 Aarti Palkar
ARBPL.38852 of 2025.doc
to the period and not by reference to a date.
7. Meanwhile, MHADA communicated the amounts payable by
the Society as Rs. 89.98 lakh as of April 28, 2023. On May 15, 2023, it
is claimed by the Developer, the Government of Maharashtra had
proposed a waiver of additional charges for 56 MHADA societies
including the Society. However, the Developer offered to pay MHADA
the amount claimed, under protest, and MHADA is said to have
rejected the proposal on July 4, 2023.
8. On September 15, 2023, MHADA raised a demand of Rs. 96.03
lakhs, which amount was indeed paid by the Developer to MHADA on
September 21, 2023. According to the Developer, the conveyance was
held up due to the Society's failure to provide documents to MHADA.
Meanwhile, further payments to MHADA were indeed made by the
Developer towards service charges, lease rent, assessment charges,
goods and service tax etc. The no-objection certificate from MHADA
was eventually received by the Developer in the Society's favour on
November 6, 2023. MHADA also provided the draft of the lease deed
and the sale deed, which would firm up the absolute title of the Society
to the land on which the building stands, to enable the redevelopment
envisaged in the transaction between the parties.
9. The conveyance was not effected. On January 28, 2024, the
JANUARY 28, 2026 Aarti Palkar
ARBPL.38852 of 2025.doc
Society suddenly took a stance that the Developer had failed to obtain
the conveyance within the contracted period of 270 days. The parties
then started trading correspondence. On February 5, 2024, the Society
convened a SGBM, by which the execution of the sale deed and the
lease deed in respect of the property was approved. On April 12, 2024,
the Society authorized the Developer to represent its interests before
MHADA by issuing a letter in favour of the Developer.
10. Meanwhile, the Deputy Registrar of Co-operative Societies
disqualified the members of the then managing committee of the
Society for a period of five years on April 15, 2024. In parallel, on April
29, 2024, MHADA provided the finalised and duly engrossed
instruments of lease deed and sale deed for execution in favour of the
society, and issued a direction that stamp duty be paid on the
instruments after having them adjudicated by the stamp authorities.
11. At this stage, the Society took a firm stance that the Developer
had failed to take steps to complete the conveyance within the
stipulated time of 270 days from the execution of the MOU. On May
30, 2024 the Developer paid the stamp duty and thereafter the parties
traded correspondence as to whether or not the Developer was in
compliance with the MOU. The Society started demanding greater
transit rent and towards this end, the parties sent emails to each other
JANUARY 28, 2026 Aarti Palkar
ARBPL.38852 of 2025.doc
and the Developer in fact sent a revised set of terms by an email dated
November 11, 2024.
12. On April 21, 2025, the Society issued a notice (" Termination
Notice") to the Developer that at a SGBM held on April 19, 2025, it had
been decided to terminate the appointment of the Developer. The
Developer filed a petition under Section 9 of the Act, which was
converted into an application under Section 17, which eventually led to
the Impugned Order.
Impugned Order:
13. The reliefs granted in the Impugned Order would be
appropriate to note. The Learned Arbitral Tribunal returned prima
facie findings in favour of the Developer having complied with its part
of the bargain. The termination on the premise of conveyance not
having been executed in 270 days was untenable while the blanks in the
MOU were inconsequential and did not deter the Society from
demanding performance of the MOU that it now seeks to repudiate.
14. The primary prayer made by the Developer before the Learned
Arbitral Tribunal was to stay the effect and operation of the
Termination Notice and to prevent the Society from taking further
steps in connection with the Termination Notice. The Learned Arbitral
Tribunal has granted the same. The reliefs granted in the Impugned
JANUARY 28, 2026 Aarti Palkar
ARBPL.38852 of 2025.doc
Order read thus:-
i) Interim reliefs is granted in terms of prayer clauses (a) to (d) of the application, however, subject to the following conditions.
ii) The Respondent Society shall be entitled to obtain lease of its land and the sale deed of its building from MHADA. The Claimant shall render all necessary assistance for the same and shall also paid any stamp duty or charges as may be demanded by MHADA for the same. The Claimant may claim these amounts from the Respondent in the present arbitration proceedings. The Tribunal will adjudicate upon these claims at the final hearing of the arbitration.
iii) After the lease deed and the sale deed are executed, the Claimant shall offer transit rent to all members of the Society to enable them to shift to alternate premises, if they so desire. The members who desire to avail of this offer made by the Claimant shall vacate their premises and deposit the keys with the Respondent Society and the Respondent Society shall confirm the receipt of the keys and vacant possession. After confirmation from the Respondent Society, the Claimant shall commence payment of transit rent to such members who have vacated their premises. The Claimant may claim the amounts paid to these members in the present arbitration proceedings.
iv) The manner in which the aforesaid amounts under clause (ii) and (iii) are to be adjusted or paid over to the Claimant shall be determined at the final hearing of the arbitration. The Tribunal shall also determine whether the Claimant is entitled to interest on the amounts paid by it, and if so, from what rate and from what date.
v) The amounts paid would be subject to final award, and it may be possible that the Tribunal may impose a charge on the Respondent's property for recovery of the said amounts in case the Claimant succeeds in seeking recovery of the said amounts after final adjudication of the disputes.
vi) The Claimant shall not claim any equities on the basis of any payments made by it or any assistance rendered by it in compliance of the aforesaid directions. The same shall not affect the Respondent's right to
JANUARY 28, 2026 Aarti Palkar
ARBPL.38852 of 2025.doc
contend that the MOU has been validly terminated, which termination shall be adjudicated in the final hearing of the arbitration.
vii) In case the Claimant refuses to or neglects to abide by the aforesaid directions, the Respondent is at liberty to apply to the Tribunal for vacation of the interim orders forthwith.
[Emphasis Supplied]
Contentions of the Parties:
15. I have heard Mr. Pradeep Sancheti, Learned Senior Advocate on
behalf of the Society, and Mr. Mayur Khandeparkar as well as Mr. Viraj
Parikh on behalf of the Developer on different dates. With their
assistance, I have had the benefit of reviewing the material on record to
assess whether any case has been made out for an intervention into the
Impugned Order, bearing in mind the scope of jurisdiction under
Section 37 of the Act.
16. Mr. Sancheti would contend that while the MOU contains a
reference to the DA, no DA is actually annexed to the MOU. The MOU
(both iterations) itself contains blanks including the dates of the
meetings and resolution numbers, rendering it an inchoate instrument,
on which specific relief could never be granted. Therefore, interim relief
in aid of specific relief too could never have been granted. Emails from
the Developer acknowledge that the draft of the DA has not been signed
and the Learned Arbitral Tribunal too has found that no DA was
JANUARY 28, 2026 Aarti Palkar
ARBPL.38852 of 2025.doc
annexed to the MOU. Moreover, by an email of February 1, 2024, the
Society clearly refused any intention to sign the DA.
17. The email dated January 17, 2023 which refers to the DA being
finalised on December 13, 2022, but there is no approval of the general
body of members of the Society, Mr. Sancheti would submit. The
correspondence traded between the parties throughout 2023 would
indicate that there were negotiations between the parties on the rent
payable, and the Developer even sent revised terms of rent as part of
this exercise. There is nothing to indicate that any SGBM approved of
any terms and therefore there is no concluded contract, Mr. Sancheti
would submit. The Society was without a Managing Committee
between April 15, 2024 and April 6, 2025. Thereafter, he would
submit, the SGBM to terminate the MOU was held on April 19, 2025
and the Termination Notice was issued.
18. The upshot of the submission is that there was no concluded
contract for specific performance to be granted. There was no
consensus on the terms and conditions, and the parties were still
negotiating terms when the Termination Notice was issued. Therefore,
the Learned Arbitral Tribunal was wrong in considering grant of
interim relief on an inchoate contract. The building is admittedly
dilapidated and when rent is still being negotiated, it was wrong on the
JANUARY 28, 2026 Aarti Palkar
ARBPL.38852 of 2025.doc
part of the Learned Arbitral Tribunal to grant relief.
19. Mr. Mayur Khandeparkar on behalf of the Developer would
point to specific clauses in the MOU to contend that the MOU signed by
both sides squarely records that the DA had been finalised. He would
also point to the provision in the MOU that ensured that there could be
no modification to the DA except in writing The DA was to be executed
within 15 days of the conveyance being executed, and the conveyance
had indeed been executed within the expected timeline of 270 days of
the second MOU.
20. Mr. Khandeparkar would also point to multiple SGBM
resolutions on the record and two specific resolutions approving of the
MOU of which the DA was the intended annexure. These were put to
the members and they knew what they approved on December 30,
2022 since the finalised DA was clearly made available to them. The
blanks were references to resolution numbers and dates, and nothing
turned on the content being left blank, when what was meant to be
filled in the blanks is evident from contemporaneous evidence even if
on a prima facie basis.
21. Mr. Khandeparkar would rely on the Supreme Court decision in
Murugesan1 to submit that a party that has reaped the benefits of an
1 Union of India vs. Murugesan - 2022 (2) SCC 525
JANUARY 28, 2026 Aarti Palkar
ARBPL.38852 of 2025.doc
agreement cannot seek to resile from it and contend that the agreement
was not valid and binding. Mr. Khandeparkar would point out that 27
out of 32 members have personally signed the MOU, but the Society
itself has signed both the MOUs. He would explain the email dated
February 1, 2023 from the Society recording that it was not willing to
sign the draft DA at that juncture, to indicate that the Developer wrote
to the Society on January 16, 2023 asking for the annexures to be
completed, with a reminder on January 27, 2023. It was in response
that the Society replied on February 1, 2023 that the office bearers were
not willing to sign the draft DA at that stage. Even at this stage, they
did not say that the DA had not been finalised but had indicated their
refusal to sign.
22. Mr. Khandeparkar would submit that the parties continued to
act upon the MOU throughout the period in question. On September
22, 2023, the Society wrote to MHADA requesting that payment may
be accepted from the Developer on their behalf. On September 26,
2023, the payment was actually made. Even on April 12, 2024, after
the first assertion of default in complying with the 270-day deadline,
the Society authorised the Developer to collect the engrossed lease and
sale deed on its behalf. All of this points to the prima facie view of the
Learned Arbitral Tribunal being a plausible view, based on assessment
of evidence, which squarely falls in the exclusive domain of the Learned
JANUARY 28, 2026 Aarti Palkar
ARBPL.38852 of 2025.doc
Arbitral Tribunal, not leading to anything unreasonable or perverse,
warranting interference by the Section 37 Court.
23. Mr. Khandeparkar would submit that the very fact that the
parties negotiated the transit rent indicates that this provision of an
agreed term was sought to be renegotiated and the parties indeed could
agree to an amendment in writing, towards which an attempt had been
made by the Society. That would only indicate, he would contend, that
there was an underlying agreement that was sought to be amended.
24. The contention that the Society has lost confidence is not a
mantra that can be invoked without any supporting facts, Mr.
Khandeparkar would submit. It has to be backed by facts and
circumstances that justify loss of confidence, and that forms subject
matter of appreciation of evidence, which the Learned Arbitral Tribunal
has reasonably and plausibly analysed.
Analysis and Findings:
25. I have given my anxious consideration to the core contention by
Mr. Sancheti, namely, that there was no DA in place and that the MOU
was inchoate. This is the core ground on which it is claimed that the
Impugned Order returns an impossible outcome. Yet, the core ground
on which the Termination Notice was issued is that the MOU was not
JANUARY 28, 2026 Aarti Palkar
ARBPL.38852 of 2025.doc
complied with by the Developer since the conveyance deed had not
been obtained within the contracted 270-day period. Likewise, it
appears that the conduct of the parties did not point to the Society
being of the view that the MOU was inchoate.
26. With that context, I note that the Learned Arbitral Tribunal
examined the validity of the reasons given for the termination. The core
ground of the Termination Notice issued by the Society is that the
Developer had failed to complete the conveyance from MHADA within
a period of 270 days as contracted in the MOU. Therefore, the Learned
Arbitrator considered the core issue as to whether the Developer was in
default on account of the conveyance deed not having been executed
within 270 days.
27. First, the Learned Arbitral Tribunal found that the MOU was
executed in identical terms by the Society and the Developer twice, with
different sets of members executing the two versions (legal
representatives of those who had passed away executing the second
one) and that the 270-day deadline would commence from the second
MOU dated March 9, 2023. The deadline would therefore be December
4, 2023. The Developer had secured permissions from MHADA and
approval for the deeds by November 2023. Therefore, on a prima facie
basis, considering the 270-day deadline being computed from the
JANUARY 28, 2026 Aarti Palkar
ARBPL.38852 of 2025.doc
second MOU, the Learned Arbitral Tribunal found the Developer not to
be in default.
28. Second, the Learned Arbitrator examined whether the ground
of termination was, prima facie, valid and appropriate, or whether it
was appropriate to grant protection in order to preserve the subject
matter of the arbitration agreement. Whether the Society was right in
contending that the MOU and the DA were inchoate, is not something
that the Learned Arbitral Tribunal could have answered conclusively at
this stage of the matter. However, the Learned Arbitral Tribunal
examined the issue on a prima facie basis, and ruled that it could not be
held that there was no committed transaction at all between the parties.
29. Indeed, the MOU was approved at a SGBM and was executed in
two iterations by the Society, with varying combinations of members of
the Society also signing it (a large majority of them having signed it).
The record also shows that the MOU was acted upon by both the
Society and the Developer right until the point at which the Developer
delivered engrossed and finalised execution drafts of the lease deed and
sale deed. The Society refrained from having them executed. The MOU
set a deadline and even the terms on which the Developer was selected
indicated that the party chosen as the developer ought to foot the bill
for payments to be made. The Developer performed his obligations. It
JANUARY 28, 2026 Aarti Palkar
ARBPL.38852 of 2025.doc
is apparent that the Society did not adopt the stance that there was no
MOU at all in the eyes of law. Instead, the Society took the stance that
the MOU set a deadline and that deadline had been missed.
30. Indeed, the Society took the stance that it has lost confidence in
the Developer, but there is nothing on record, prima facie, to indicate
that any action on the part of the Developer resulted in a justification
for the purported loss of confidence.
31. In these circumstances, I find no basis to find fault with the
Learned Arbitral Tribunal's approach to preserving the subject matter
of the arbitration agreement.
32. The contention that there are blanks in the MOU is well dealt
with inasmuch as these blanks relate to the numbers of the resolutions
and their dates, and nothing would turn on these details not having
been entered in the draft. That the DA was to be annexed and the
parties finalised it, is also prima facie covered by the MOU,
necessitating a written agreement to modify the DA. The Learned
Arbitral Tribunal could indeed arrive at a finding after trial that the DA
was not finalised, but to come to a view at this stage that it would never
be able to take a view that there was a meeting of minds and agreement
between the parties would be impossible. The Learned Arbitral
Tribunal has kept all issues open for trial and yet preserved the subject
JANUARY 28, 2026 Aarti Palkar
ARBPL.38852 of 2025.doc
matter of the arbitration agreement.
33. The Learned Arbitral Tribunal has also taken note of the fact
that the building was and is dilapidated. Some members of the Society
have even migrated out and therefore, arrangements have been made
to deal with the same in the reliefs extracted above. The Developer too
has been put to terms and been disabled from claiming equities.
Although there was nothing to show that the Developer had not been
ready and willing to perform the MOU (on the contrary, there is every
pointer to the Developer having performed his part of the bargain), the
Learned Arbitral Tribunal has also granted liberty to the Society to have
the Impugned Order vacated should the Developer not comply with the
directions issued in the Impugned Order - to pay transit rent and keep
accounts.
Scope and Standard of Appellate Review:
34. It is well settled law that an appeal is a continuation of the
original proceeding. This has been summarised well in Malluru
Mallapa2 in the following words:
13. It is a settled position of law that an appeal is a continuation of the proceedings of the original court. Ordinarily, the appellate jurisdiction involves a rehearing on law as well as on fact and is invoked by an aggrieved person. The first appeal is a valuable right of the appellant and therein all questions of fact and law decided by the trial court are open for 2 Malluru Mallapa (D) through LRs vs. Karuvathappa & Ors. - (2020) 4 SCC 313
JANUARY 28, 2026 Aarti Palkar
ARBPL.38852 of 2025.doc
reconsideration. Therefore, the first appellate court is required to address itself to all the issues and decide the case by giving reasons. The court of first appeal must record its findings only after dealing with all issues of law as well as fact and with the evidence, oral as well as documentary, led by the parties. The judgment of the first appellate court must display conscious application of mind and record findings supported by reasons on all issues and contentions [see : Santosh Hazariv Purushottam Tiwari [Santosh Hazari v. Purushottam Tiwari, (2001) 3 SCC 179] ,Madhukar v. Sangram [Madhukar v. Sangram, (2001) 4 SCC 756] , B.M. Narayana Gowda v. Shanthamma [B.M. Narayana Gowda v. Shanthamma, (2011) 15 SCC 476 : (2014) 2 SCC (Civ) 619] , H.K.N. Swami v. Irshad Basith [H.K.N. Swami v. Irshad Basith, (2005) 10 SCC 243] and Sri Raja Lakshmi Dyeing Works v. Rangaswamy Chettiar [Sri Raja Lakshmi Dyeing Works v. Rangaswamy Chettiar, (1980) 4 SCC 259] ].
35. Yet, it is equally well-settled law that at an appellate Court
exercising the power under Section 37 of the Act to review the exercise
of discretion by an Arbitral Tribunal at an interim stage, would be well
guided by the principles set out by the Supreme Court in Wander vs.
Antox3, namely, that interference is warranted only if there is
something perverse or implausible in the exercise of discretion in
making an interlocutory arrangement. The following extract would
suffice:
14. The appeals before the Division Bench were against the exercise of discretion by the Single Judge. In such appeals, the appellate court will not interfere with the exercise of discretion of the court of first instance and substitute its own discretion except where the discretion has been shown to
3 Wander Ltd. Vs. Antox India (P) Ltd. - 1990 Supp SCC 727
JANUARY 28, 2026 Aarti Palkar
ARBPL.38852 of 2025.doc
have been exercised arbitrarily, or capriciously or perversely or where the court had ignored the settled principles of law regulating grant or refusal of interlocutory injunctions. An appeal against exercise of discretion is said to be an appeal on principle. Appellate court will not reassess the material and seek to reach a conclusion different from the one reached by the court below if the one reached by that court was reasonably possible on the material. The appellate court would normally not be justified in interfering with the exercise of discretion under appeal solely on the ground that if it had considered the matter at the trial stage, it would have come to a contrary conclusion. If the discretion has been exercised by the trial court reasonably and in a judicial manner the fact that the appellate court would have taken a different view may not justify interference with the trial court's exercise of discretion.
[Emphasis Supplied]
36. In a plethora of judgements under Section 37 of the Act, the
principle articulated in Wander vs. Antox has been followed and
reiterated. In other words, the Section 37 jurisdiction, when
considering a challenge to an order passed under Section 17 of the Act,
is a light-touch jurisdiction, where the Court must not substitute the
Learned Arbitral Tribunal's plausible view with its own competing
plausible view. The Learned Arbitral Tribunal is the forum that is
seized of the factual facets of the matter, and thereby the master of the
evidence, with control over what constitutes the quality and quantity of
evidence. In such effort, if the Learned Arbitral Tribunal has
conducted itself perversely, or has been arbitrary and unreasonable or
has returned an interlocutory arrangement that could be regarded as
JANUARY 28, 2026 Aarti Palkar
ARBPL.38852 of 2025.doc
perverse, the Section 37 Court would indeed correct the position. This
is the standard to apply and not the standard of second-guessing a
reasonable and plausible prima facie reading of the evidence on hand to
return the Section 17 Order.
Conclusion:
37. Applying the aforesaid standard, and for the aforesaid reasons, I
have to conclude that the reasoning in the Impugned Order is not at all
in the realm of being an impossible and perverse finding that cuts to
the root of the matter.
38. In these circumstances, the Petition is dismissed. I refrain
from imposing costs at this stage, although it would be open to the
Learned Arbitral Tribunal to consider costs for this round of litigation
as well, when adjudicating the matter finally.
39. All actions required to be taken pursuant to this judgment shall
be taken upon receipt of a downloaded copy as available on this Court's
website.
[SOMASEKHAR SUNDARESAN, J.]
JANUARY 28, 2026 Aarti Palkar
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!