Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Hella Infra Market Metal Private ... vs Pushkaraj Ispat (India) Llp
2026 Latest Caselaw 3815 Bom

Citation : 2026 Latest Caselaw 3815 Bom
Judgement Date : 16 April, 2026

[Cites 5, Cited by 0]

Bombay High Court

Hella Infra Market Metal Private ... vs Pushkaraj Ispat (India) Llp on 16 April, 2026

    2026:BHC-OS:9463

                                                                                              CARBPL.17938.2025.doc



                                      IN THE HIGH COURT OF JUDICATURE AT BOMBAY

                                           ORDINARY ORIGINAL CIVIL JURISDICTION

                               COMMERCIAL ARBITRATION PETITION (L) NO. 17938 OF 2025

                       Hella Infra Market Metal Private Limited                        ...Petitioner
                            Versus
                       Pushkaraj Ispat (India) LLP                                     ...Respondent



                            Mr. Aditiya Trivedi i/b Induslaw for the Petitioner.

                            Mr. Chaitanya Nikate a/w Nilesh Tribhuvann, Burzin Bharucha, Ruchi
                            Pawar, i/b White & Brief Advocates & Solicitors, for Respondent.


                                       CORAM:            SOMASEKHAR SUNDARESAN, J.

                                       DATE:             APRIL 16, 2026


                       JUDGEMENT:

Context and Factual Background:

1. This is a Petition under Section 37 of the Arbitration and

Conciliation Act, 1996 ("the Act"), impugning an order dated April 30, 2025

("Impugned Order"), passed under Section 17 of the Act.

2. The factual matrix relevant of this Petition may be summarised

thus:

A] The Petitioner, Hella Infra Market Metal Pvt. Ltd. (" Hella") and

the Respondent, Pushkaraj Ispat (India) LLP (" Pushkaraj") executed

Digitally signed by April 16, 2026 AARTI AARTI GAJANAN Aarti GAJANAN PALKAR PALKAR Date:

2026.04.16 17:59:17 +0530

CARBPL.17938.2025.doc

an Operating License Agreement dated September 11, 2023

("Agreement"), under which certain industrial sheds, office space and

plant and machinery stationed therein in Ahmednagar (" Licensed

Property") were licensed by Pushkaraj to Hella;

B] Hella was entitled to operate and use the Licensed Property for

five years until September 2028, taking it on an "as-is-where-is" basis,

and using its own labour, raw material, water, electricity, etc. Hella

would pay for electricity usage even while applications for transfer of

electricity connection to its name were pending. The parties contracted

a lock-in period of three years, Hella was to pay a Security Deposit of

Rs. 3 crores and a monthly license fee of Rs. 30 lakhs;

C] Upon termination, the Licensed Property and the Security

Deposit would be exchanged and any delay in refund of Security

Deposit would attract interest at 18% per annum;

D] Pushkaraj filed the Section 17 Application seeking protective

measures pending arbitration. The Learned Arbitral Tribunal has

directed that the Licensed Property be handed over within six weeks

(during the pendency of this Petition, the parties have agreed to

implement this relief), with an undertaking that Pushkaraj would

refund the Security Deposit along with interest depending on the

outcome of the arbitration proceedings. A mandatory injunction

against creating any third-party rights on the Licensed Property was

April 16, 2026 Aarti

CARBPL.17938.2025.doc

issued to Hella, coupled with a direction to deposit a sum of Rs. 5.31

crores towards half the license fees for early termination. Finally, the

Impugned Order also directs Hella to pay a sum of Rs. ~2.71 crores

towards electricity charges within two weeks and a sum of Rs. ~73.48

lakhs to the distribution company that supplied electricity. Certain

disclosures were directed against each party.

Hella's Contentions:

3. Hella's grounds for challenging the Impugned Order is based on

two foundational contentions:

A] The Impugned Order constitutes a final award without any

direction to refund the Security Deposit; and

B] Electricity charges and license fees were directed to be paid

without considering the submissions of Hella, thereby granting final

relief at the interim stage;

4. Hella would contend that it was constrained to terminate the

Agreement on March 18, 2024, which it was entitled to do in the event of a

material breach by Pushkaraj, even during the lock-in period. Upon such

termination, the exchange of the Licensed Property with the Security Deposit

was to implemented. Hella would contend that Pushkaraj stopped Hella's

trucks from leaving the premises, interfering with dispatch and delivery of

goods to the Licensed Property. Electricity dues as of January 31, 2024, and

April 16, 2026 Aarti

CARBPL.17938.2025.doc

license fees as of February 29, 2024, are claimed to have been paid. In April,

when Hella demanded a swap of the Licensed Property for the Security

Deposit, Pushkaraj contended that the termination was illegal in view of the

lock-in period and that the license fee for the remainder of the lock-in period

was due.

5. On the electricity charges, Hella would contend that it has

provided a detailed working to show that the principal amount of electricity

charges is Rs. ~1.92 crores while arrears and interest towards electricity is Rs.

~7.54 crores. Hella would contend that there has been an ongoing past

dispute between the electricity distribution company and Pushkaraj, and these

were the subject matter of the Consumer Grievance Redressal Forum created

under electricity laws.

6. Hella would also contend that the license fees for September 2023

to December 2023 had been waived by Pushkaraj's letter dated October 5,

2023, and license fees for January 2025 had been waived by letter dated

March 4, 2024.

Pushkaraj's Contentions:

7. Pushkaraj would contend that the termination of the Agreement

by Hella is not in dispute. Upon termination, the Licensed Property ought to

have been handed over. The parties were conscious that the plant and

machinery forming part of the Licensed Property were encumbered in favour

April 16, 2026 Aarti

CARBPL.17938.2025.doc

of a bank, and the parties even executed a tripartite agreement whereby the

license fees payable by Hella were to be deposited with the lender for

appropriation towards servicing of the loan. The value of the land, plant and

machinery is contended to be of a value of about Rs. ~80 crores at the least,

and it is stated that such property is unproductive, with the dispute between

the parties rendering it impossible to put them to economic use.

8. Pushkaraj would also contend that Hella raised the contention

about the need to be given the Security Deposit back as an afterthought, since

in its earlier correspondence between April 2024 and September 2024, Hella

had always committed to handing over the Licensed Property after which the

Security Deposit may be refunded. In May 2024, Hella threatened to remove

security arrangements and called upon Pushkaraj to take over the Licensed

Property, conscious that there are obligations owed that are of a scale larger

than the Security Deposit. In December 2024, Hella even agreed to hand over

possession and then deferred it, citing personal difficulties.

9. According to Pushkaraj, since the electricity supply has been cut

off for non-payment, the plant and machinery are lying idle without

constructive exploitation. As maintenance of the property is not possible

without electricity, the Learned Arbitral Tribunal's arrangement is a

reasonable protective package that cannot be regarded as perverse. The

precise amount to be refunded is a matter for trial, Pushkaraj would contend,

and therefore, the view adopted by the Learned Arbitral Tribunal is well-

April 16, 2026 Aarti

CARBPL.17938.2025.doc

thought-through, with only crystallised amounts having been directed to be

paid over. Contractually, Hella is obliged to pay for the electricity consumed,

and to pay half the license fees for the lock-in period. There are only minor

differences in the monthly electricity bill amounts claimed, and in April 2024,

Hella asked Pushkaraj to pay for electricity and absorb from the Security

Deposit; even after that, there are dues owed by Hella.

10. The hindrance to the delivery and dispatch of goods is also stoutly

denied by Pushkaraj. Non-payment of dues by Hella to labour led to unrest,

and it is contended that strong-arm tactics were deployed against the labour

leading to an escalation. On March 2, 2024, it was confirmed by Pushkaraj

that there was a stoppage of vehicular traffic because of complaints allegedly

made by Hella, through related parties, to the pollution control authorities;

and it is clarified that on the same day, the matter was resolved and thereafter,

Hella continued to use the Licensed Property right until March 18, 2024.

Analysis and Findings:

11. Having heard Mr. Karl Tamboly, Learned Advocate on behalf of

Hella and Mr. Ashish Kamat, Learned Senior Advocate on behalf of Pushkaraj,

and with their assistance, I have examined the material on record relied upon

by them and the analysis by the Learned Arbitral Tribunal in the Impugned

Order. It is evident that Hella raised a jurisdictional objection in the arbitral

proceedings and this was repelled, among others, on the basis of the facts in

hand being out of the purview of rent control laws and provisions governing

April 16, 2026 Aarti

CARBPL.17938.2025.doc

setting up of small cause courts. I find no fault with the findings. In any case,

Mr. Tamboly has not pressed the jurisdictional objection in these proceedings.

Therefore, the grounds pressed into service and summarised above are alone

being dealt with.

12. The first issue to consider is whether the Impugned Order can be

said to take the character of a final award in the garb of an interim order

granting interlocutory protection. The Learned Arbitral Tribunal has noticed

that the Licensed Property, including the plant and machinery, was lying

unutilised, and owing to non-payment of electricity charges, exploitation of

the same was also being frustrated. Therefore, the Learned Arbitral Tribunal

analysed what would be a protective measure for the subject matter of the

arbitration agreement and went on to examine the terms of the Agreement.

13. Interpreting Clause 3.6 of the Agreement, the Learned Arbitral

Tribunal found that the refund of the Security Deposit was contractually

agreed to be subject to deductions for amounts owed. A plain reading of

Clause 3.6 would show that the reading of the provision by the Learned

Arbitral Tribunal is not just reasonable and plausible, but it is an accurate

reading. The parties had indeed contracted that in the event of an earlier

termination of the Agreement, the refund of the Security Deposit would be

subject to deduction of any amounts owed. Therefore, the core question to

consider is whether the Learned Arbitral Tribunal has taken a perverse view

April 16, 2026 Aarti

CARBPL.17938.2025.doc

on what is crystallised as being owed by Hella to Pushkaraj for any deductions

to be assessed from the Security Deposit.

14. Towards this end, the Learned Arbitral Tribunal was guided by

Clause 1.4 and Clause 11.3 of the Agreement, which provided for Hella paying

for the electricity consumed, at actuals even before the meter was formally

changed to Hella's name, and thereafter, a sum of Rs. ~2.71 crores was

admitted as being payable to Pushkaraj towards electricity used by Hella but

paid by Pushkaraj. Another sum of Rs. ~73.48 lakhs was also admitted as

payable towards the electricity used. Electricity consumed at the premises was

exclusively used by Hella and the Learned Arbitral Tribunal found this to be a

crystallised and clear liability owed, which could be set off against the Security

Deposit. Clause 3.6 indeed provided for a deduction of amounts owed, from

the Security Deposit. Clause 15.1 provided for half the license fee for the lock-

in period being payable if the Agreement was sought to be terminated during

the lock-in period.

15. Clearly, the parties have agreed on a soft lock-in period, where the

Agreement could be terminated even during the lock-in period but half the

license fee for the residual period would be payable by the party terminating

the Agreement. This is a provision to enable crystallisation of what is payable

in the event of such termination. Therefore, the Learned Arbitral Tribunal

applied its reading of these provisions to arrive at the license fee payable for

the residual period by Hella, which terminated the Agreement. The admitted

April 16, 2026 Aarti

CARBPL.17938.2025.doc

amounts towards electricity were also factored in. Thereby, the Learned

Arbitral Tribunal arrived at what could be directed to be paid as a protective

measure.

16. Indeed, the Learned Arbitral Tribunal could have asked for these

amounts to be deposited instead of being paid over. That would be a plausible

measure. However, the test under Section 37 is to see whether the measure

adopted by the Learned Arbitral Tribunal is a plausible and reasonable one. If

found to be so, it is not for the Section 37 Court to substitute one plausible

view with another view that may appear more plausible.

17. Clause 15.3 of the Agreement provides for surrender of the

premises, the right to remove the material kept on the Licensed Property, and

the obligation to pay all outstanding dues. It is against these actions that the

Security Deposit is required to be refunded. It is only if the Security Deposit is

not refunded despite the surrender of the Licensed Property that Hella would

be entitled to continue to use the Licensed Property without any payment, and

also claim 18% interest on the Security Deposit.

18. Indeed, there is an entitlement to terminate the Agreement in the

event of a material breach. Whether there has been a material breach is a

matter of evidence to be led and assessed by the Learned Arbitral Tribunal.

On the face of it, there has not only been a termination but also a proposed

surrender of the Licensed Property proposed by Hella before it actually

terminated the Agreement. There is an intense conflict on Pushkaraj having

April 16, 2026 Aarti

CARBPL.17938.2025.doc

stalled access to the Licensed Property on the ground that Hella had made

related parties complain to the pollution control authorities. Equally, there is

an apparent default in payment of dues admittedly owed for usage of

electricity.

19. Therefore, when one looks at the Impugned Order, in my opinion,

the Learned Arbitral Tribunal having examined the material on record and the

conduct of the parties, has come to a reasonable view by factoring in only the

crystallised amounts of license fees contracted and the admitted electricity

consumption, and has applied the binding terms of contract between the

parties to the factual matrix at hand. The electricity amounts claimed by the

electricity distributor are far in excess of what Hella has been directed to pay.

The Learned Arbitral Tribunal has taken care to ensure that the amounts

directed to be paid are restricted to the usage by Hella.

20. I also note that the Learned Arbitral Tribunal has used the term

"deposit with" for the amounts payable by Hella to Pushkaraj towards half the

license fee payable, and the term "pay to" in relation to amounts payable to

Pushkaraj towards electricity consumption and to the electricity distributor.

This would indicate that the Learned Arbitral Tribunal has meant to keep the

amount towards half the license fee as a deposit to be held by Pushkaraj to

abide by the outcome in the arbitration, while for electricity payments, the

amounts are meant to be paid since they have been incurred out of pocket.

The rest of the measures sought by Pushkaraj have been rejected. The

April 16, 2026 Aarti

CARBPL.17938.2025.doc

Learned Arbitral Tribunal has ruled that it would examine evidence on the

other claims and counterclaims.

21. The approach of the Learned Arbitral Tribunal is consistent with

the Agreement. I am not satisfied that the direction to deposit and the

direction to pay are perverse, since they are consistent with what the parties

had agreed. Being a first appeal, I have also examined the material on record

pressed into consideration by both sides and indeed there are various points

presented by the parties for consideration by the Learned Arbitral Tribunal.

The Impugned Order is restricted to the two crystallised and discernible

amounts contractually committed as being payable. These amounts are in

excess of the Security Deposit. Taking the electricity payments alone, the

amounts are nearly equal to the Security Deposit. The amount equal to half the

license fee for the residual lock-in period is far in excess of the Security

Deposit. This amount is required to be deposited with Pushkaraj.

22. Whether the past electricity dues were the cause of electricity

supply disruption or whether Hella's non-payment led to the same can be

considered by the Learned Arbitral Tribunal at a later stage. The Impugned

Order does not articulate how the deposit of half the license fee amount

towards the residual lock-in period is to be maintained.

23. It is well-settled law that an appeal is to be regarded as a

continuation of the original proceeding, and unless there is a statutory

requirement to the contrary, the powers of the appellate forum are co-

April 16, 2026 Aarti

CARBPL.17938.2025.doc

extensive with the powers of the forum whose adjudication is under appeal 1.

Therefore, considering that the amount of the license fee is directed to be

deposited with Pushkaraj while the amounts towards electricity are directed to

be paid, it is directed that Pushkaraj shall create a fixed deposit in the sum of

Rs. 5.31 crores and mark a lien in favour of Hella and keep the deposit active

without disturbance; such deposit shall abide by the outcome of the

arbitration proceedings. This is the extent of intervention that I think is

necessary with the Impugned Order, and such intervention is necessary to

make the Impugned Order workable and meaningful to also sustain it, which I

think is otherwise sustainable as a reasonable framework of interim protection

and not in the nature of a final award.

24. The Learned Arbitral Tribunal's reliance on the law, now clearly

declared on the scope of power under Section 17 of the Act as a protective

interlocutory measure, cannot be faulted. In cases where there is practically

no defence to the payability of an amount, if it is in the interest of justice to

secure the amount which forms the subject matter of the arbitration

agreement, it is certainly within the power of the Arbitral Tribunal to order

suitable interim measures for its protection - a position in law supported by

numerous judgements including Jagdish Ahuja2; Valentine Maritime3; Essar

1 Jute Corporation of India Ltd. Vs. CIT - 1991 Supp 2 SCC 744 2 Jagdish Ahuja v Cupino Limited, ( 2020 ) 4 Bom CR 1, 3 Valentine Maritime Ltd . v . Kruez Subsea Pte Limited, 2021 SCC OnLine Bom 75

April 16, 2026 Aarti

CARBPL.17938.2025.doc

House4; Kotak Mahindra5; Ultra Deep Subsea6; and J. P . Parekh7. In Essar

House, the Supreme Court has noticed and endorsed Jagdish Ahuja and

Valentine Maritime.

25. In view of the Supreme Court decision in Sanghi8, there is often

considerable debate in many a Section 37 proceedings about whether Essar

House and Sanghi present conflicting positions or whether it is possible to

reconcile the same, and indeed whether Sanghi was rendered without

reference to Essar House. In Sanghi, a need to demonstrate a threat to the

amount involved is indicated as being necessary, while in Essar House, it

would appear that a crystallised amount being payable is permitted to be

secured in exercise of powers under Section 17 of the Act.

26. In my opinion, the observations in each of Essar House as well as

Sanghi cannot be read in isolation, without regard to the factual matrix in each

case and the analysis contained in them, coupled with the risk perception

discernible from them in exercise of the Section 17 jurisdiction. The abiding

theme across this range of decisions is to consider whether the factual matrix

before the Section 9 Court or, as the case may be, the Arbitral Tribunal under

Section 17, presented a situation where the subject matter of the Arbitration

Agreement was under threat, and what appropriate protective measures such 4 Essar House Private Limited v . Arcellor Mittal Nippon Steel India Limited, 2022 SCC OnLine SC 1219 5 Kotak Mahindra Bank Ltd v . Williamson Magor & Co Ltd., 2021 SCC OnLine Bom 305 6 Ultra Deep Subsea Pte Ltd v . Hindustan Oil Exploration Company Ltd., 2021 SCC OnLine Bom 5481 7 J. P . Parekh v Naseem Qureshi, 2022 SCC OnLine Bom 6716 8 Sanghi Industries Ltd. Vs. Ravin Cable Ltd., 2022 SCC OnLine SC 1329

April 16, 2026 Aarti

CARBPL.17938.2025.doc

a forum would consider necessary, being the master of the evidence and

having conducted its review of the same.

27. The admitted defaults in payment of electricity are clearly

discernible. Without payment for electricity, it would not be possible even to

maintain the plant and machinery taken on license, which would lead them to

diminish in value. The protective measure of paying over the amounts

towards electricity dues is defensible from this perspective.

28. Whether there was a material breach warranting an earlier

termination, and whether the soft lock-in period and the obligation to pay half

the amount of the license fee for the residual lock-in period are overtaken by

such a claim of material breach, can also be considered at a later stage. At this

stage, the amount due towards the residual lock-in is directed to be deposited,

and I have made a marginal intervention on how such a deposit should be

maintained, and this would sustain an otherwise reasonable and defensible

Impugned Order. Pushkaraj too has not challenged the Impugned Order on

the distinction between the direction to deposit and the direction to pay over,

the respective amounts. Its written submissions too stick to this

differentiation in characterisation.

29. Therefore, in my opinion, with my intervention on maintenance

of the amount of half the license fee for the residual lock-in period in a fixed

deposit with a lien being marked in favour of Hella, the Impugned Order could

never partake the character of a final award at an interlocutory stage. I see no

April 16, 2026 Aarti

CARBPL.17938.2025.doc

reason to set it aside as perverse, and even the element that is missing has

been addressed by me in the appellate jurisdiction under Section 37 of the Act

read with Section 17 of the Act.

30. Therefore, the Petition is finally disposed of in the aforesaid

terms, with the Impugned Order being modified marginally with the aforesaid

direction on maintenance of a fixed deposit. No other intervention is

necessary.

31. All actions required to be taken pursuant to this order, shall be

taken upon receipt of a downloaded copy as available on this Court's website.

[SOMASEKHAR SUNDARESAN J.]

April 16, 2026 Aarti

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter