Thursday, 30, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Bhartiya Samruddhi Finance Ltd vs The State Of Maharashtra And Anr.
2025 Latest Caselaw 6790 Bom

Citation : 2025 Latest Caselaw 6790 Bom
Judgement Date : 14 October, 2025

Bombay High Court

Bhartiya Samruddhi Finance Ltd vs The State Of Maharashtra And Anr. on 14 October, 2025

 2025:BHC-OS:18781

                                                                                     CARBP.166.2022.Final.doc



                                  IN THE HIGH COURT OF JUDICATURE AT BOMBAY

                                        ORDINARY ORIGINAL CIVIL JURISDICTION

                               COMMERCIAL ARBITRATION PETITION NO.166 OF 2022

                       Bhartiya Samruddhi Finance Ltd                            ...Petitioner
                         Versus
                       The State of Maharashtra & Anr.                           ...Respondents

                                                    ALONGWITH
                                        INTERIM APPLICATION NO. 2276 OF 2023
                                                         IN
                                      COMM. ARBITRATION PETITION NO. 166 OF 2025

                       State Of Maharashtra & Anr.                               ....Applicants

                       IN THE MATTER BETWEEN
                       Bhartiya Samruddhi Finance Ltd.                           ...Petitioner
                         Versus
                       The State of Maharashtra & Anr.                           ...Respondents


                                                    ALONGWITH
                                      COMM. ARBITRATION PETITION NO. 373 OF 2022
                                                    ALONGWITH
                                         INTERIM APPLICATION NO. 1730 OF 2023
                                                         IN
                                      COMM. ARBITRATION PETITION NO. 373 OF 2022

                       State Of Maharashtra & Anr.                     ....Petitioners/Applicants
                             Versus
                       Bhartiya Samruddhi Finance Ltd.                 ...Respondent

                          Mr. Yashodeep Deshmukh a/w Mr. Rayyan Nasir, Mr. Nasir
                          Mohammed, Ms. Vaidehi Deshmukh and Ms. Nehadevi
                          Prajapati for the Petitioner in CARBP/166/2022 and for
                          Respondent in CARBP/373/2022.

                          Mr. Manish Upadhye, AGP for Respondent Nos. 1 and 2 in
                          CARBP/166/2022 and CARBP/373/2022.


          Digitally
          signed by                                       Page 1 of 22
          AARTI
AARTI     GAJANAN                                       October 14, 2025
GAJANAN   PALKAR
PALKAR    Date:        Aarti Palkar
          2025.10.14
          15:06:21
          +0530




                         ::: Uploaded on - 14/10/2025                      ::: Downloaded on - 14/10/2025 21:40:09 :::
                                                            CARBP.166.2022.Final.doc



         CORAM                            : SOMASEKHAR SUNDARESAN, J.

         RESERVED ON                      : JULY 1, 2025

         PRONOUNCED ON                    : OCTOBER 14, 2025

JUDGEMENT :

1. The captioned proceedings are cross petitions filed under Section

34 of the Arbitration and Conciliation Act, 1996 (" the Act") challenging

an arbitral award dated December 17, 2021 (" Impugned Award")

passed by a Learned Arbitral Tribunal.

2. The Impugned Award adjudicated disputes between Bhartiya

Samruddhi Finance Ltd. ("Samruddhi") and the State of Maharashtra

("State") in relation to a project to provide information to citizens about

the State's services and schemes aided by information and

communication technology by setting up common service centres

("CSCs") through village level entrepreneurs.

3. Samruddhi was selected pursuant to a bid filed by it on April 28,

2010 in response to a tender published through a document dated

March 12, 2010. The bid was accepted on January 5, 2011 and a Master

Service Agreement ("Agreement") was executed on January 18, 2011.

The Agreement had a tenure of 60 months ending on January 17, 2016,

in which period, Samruddhi was expected to operationalise 1,362 CSCs.

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

4. Samruddhi was to be compensated by a share of the fees charged

on the transactions provided by the CSCs, and through "viability gap

funding", which essentially meant revenue support from the State.

Such funding was agreed at the rate of Rs.2,291 per CSC per month

over a period of four years in the case of 1,112 pre-identified rural CSCs.

No revenue support was meant to be provided in respect of 139 urban

CSCs and 111 rural CSCs.

5. The Agreement entailed a staggered deadline for rolling out the

CSCs. Overall, Samruddhi set up 1,276 CSCs, of which 1,208 CSCs were

rural, but these were rolled out after the stipulated deadlines.

Samruddhi claims to have sought to be paid for roll out of only 1,112

CSCs as per its entitlement under the Agreement. The State refused to

pay, on the premise that the CSCs were not installed and

operationalised within the stipulated deadlines. The State also claimed

to have suffered losses because of Samruddhi's incompetence and

negligence, and therefore made a counter-claim.

6. The inability to meet the deadline was attributed by Samruddhi

to the lack of broadband connectivity, in particular, in several villages

in Nandurbar district, which is a "backward area" that fell within the

territory covered by the Agreement. Samruddhi claimed that it needed

extra time to complete the installation of the CSCs and sought

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

extension of time under the Agreement - from January 2016 until

August 2016, and thereafter from September 2016 to August 2017.

7. It is noteworthy that the very conceptualisation of the project was

by Government of India. An advisory had been issued to state

governments on December 28, 2011 ("GOI Advisory") requesting the

states to consider the challenges faced in implementing the scheme due

to inadequacy of power supply, non-availability of broadband

connectivity, and the lack of eligible village level entrepreneurs in the

rural areas. State governments were advised to consider taking a

decision, similar to the one taken by the State of Himachal Pradesh, not

to penalise agencies such as Samruddhi for the delay in rolling out the

requisite number of CSCs.

8. The amount claimed by Samruddhi was Rs. ~7.66 crores as the

principal amount, along with interest at the rate of 18% per annum,

computed at Rs. ~7.90 crores until October 15, 2019.

9. The State countered that an agreed and specified number of CSCs

were to be rolled out by the fifth, seventh, ninth and twelfth month of

executing the Agreement, and that Samruddhi had a shortfall in the

number of CSCs rolled out at every milestone. The State claimed a

right to impose liquidated damages of Rs. ~9.29 crores, which it pared

down to Rs. ~7.62 crores.

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

10. However, the State had initially released a sum of Rs. 62.91 lakhs

in April 2018 and a further amount of Rs. ~1.66 crores in June 2019.

11. Samruddhi would invoke the GOI Advisory to seek a lenient

view, taking into account the ground reality and challenge in the non-

availability of broadband connectivity which led to the delay in the

actual roll-out. The State refused. The dispute led to the arbitration

proceedings.

12. The State pleaded that Samruddhi was obliged to ensure the

provision of the last mile connectivity. The State would contend that

this had been provided for in the Request for Proposal (" RFP") before

tender and in the Agreement, which is based on the acceptance of such

terms by Samruddhi in its bid. Therefore, the State took the stance that

the absence of broadband connectivity could not be regarded as a

reason that could excuse the delay in rolling out the CSCs.

Impugned Award:

13. The Impugned Award holds in Samruddhi's favour - directing

that it was entitled to Rs. ~7.66 crores, but without an entitlement to

interest. Costs were awarded in the sum of Rs. 20 lakhs. Post-award

interest at 9% was awarded after the expiry of three months from the

date of the Impugned Award. A second round of consideration after a

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

Learned Single Judge of this Court requested the Learned Arbitral

Tribunal to reconsider the non-grant of interest and effect a correction

that could remove the vulnerability to the Impugned Award (in

Samruddhi's challenge), took place. The Learned Arbitral Tribunal held

that the non-grant of interest is a conscious one and refused to grant

interest.

14. In consideration of the captioned proceedings, the core issue to

be considered at the threshold is whether the Learned Arbitral Tribunal

has returned a plausible and reasonable view in relation to the lack of

broadband connectivity in the remote areas of the Nashik Revenue

Division, especially in the rural regions of Nashik and Nandurbar

districts.

15. Considering the data on availability of connectivity in the Nashik

Revenue Division, the Learned Arbitral Tribunal considered

Samruddhi's contention about the demonstrated absence of Wi-Fi,

broadband or even terrestrial dial-up connections at the relevant times

in such areas. The Learned Arbitral Tribunal also considered the

stance of the State that the last mile connectivity was meant to be

somehow provided by Samruddhi.

16. The Learned Arbitral Tribunal examined the Agreement and

extracted Paragraph 4.1 of the RFP to set out the reference to the

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

National e-Governance Plan of the Government of India. The RFP had

pointed out that the bidders would need to invest in the mast, radio

transceiver and other customer premise equipment at each of the

locations. The Learned Arbitral Tribunal returned a finding that the

provision of internet connectivity up to the block level was not

Samruddhi's responsibility as a matter of the project design.

Samruddhi's obligation was to ensure that the CSCs have the necessary

equipment to communicate with the rest of the telecommunications

network to ensure provision of services by the CSCs.

17. The Government of India had an ambitious plan to set up the

State Wide Area Network ("SWAN"). Indeed, it was Samruddhi's role to

engage with service providers such as Bharat Sanchar Nigam Ltd.

("BSNL"), Airtel, Reliance Tata etc. but this would not translate into an

automatic ability of a service provider such as Samruddhi to access and

get connected to SWAN. The Learned Arbitral Tribunal noted that at

the time of making the Impugned Award, 257 out of 324 tehsils had

been connected to the State Headquarters. The Government of India

was facilitating BSNL to enhance broadband connectivity in about

20,000 rural digital exchanges across the country. BSNL was the lone

telecom service provider for rural exchanges at the sub-block level.

There was no material to indicate how many of these rural exchanges

were earmarked for Maharashtra.

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

18. The Learned Arbitral Tribunal found it impossible to accept the

contention of the State that Samruddhi should be held responsible for

setting up the last mile connectivity on its own. The State had

contended that Samruddhi was obliged to conduct due diligence before

making its bid and accepting the targeted milestones, but the State

could simply not expect Samruddhi to arrange for the last mile

connectivity when it had no power to provide telecom services on its

own and no licensed telecom service provider was able to provide

broadband connectivity all across the territory covered by the

Agreement.

19. The witness of the State, himself a Director of Information

Technology, had deposed that he was unaware that to provide such

connectivity on one's own, a telecom service provider license would be

required. The Learned Arbitral Tribunal found this unacceptable.

Samruddhi brought on record evidence about the number of villages in

Nandurbar and Nashik which had internet connectivity through BSNL

by seeking the information under the Right to Information Act, 2005. It

was found that the State had itself informed that 114 Gram Panchayats

in Nandurbar had internet connectivity, and as late as October 1, 2018,

there were 317 Gram Panchayats in that district that had connectivity.

Out of 1,382 Gram Panchayats in Nashik, 1,012 had internet

connectivity while 370 Gram Panchayats had no connectivity at all.

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

20. The Learned Arbitral Tribunal returned a finding based on the

material on record, that internet connectivity was not available in every

corner of Nashik Revenue Division. Against this backdrop, the Learned

Arbitral Tribunal analysed that of the 1,362 CSCs to be rolled out in

months of January 18, 2011, 1,112 CSCs were admittedly rural CSCs, for

which viability gap funding was to be provided. It was not available

only for 111 rural CSCs and 139 urban CSCs. The shortfall by the twelfth

month of the roll out expected for 1,112 CSCs was 831 CSCs. However,

the first tranche of revenue support from the State was released only in

April 2018 for a sum of Rs. 62.91 lakh, two and half years after the

invoice for 1,112 invoices were submitted. The second tranche of Rs.

~1.66 crores was released in June 2019. The Learned Arbitral Tribunal

accepted that the non-release of funding support led to a cash crunch

and that delayed matters further. The Learned Arbitral Tribunal found

that indeed there was unexplained delay in releasing the revenue

support.

Analysis and Findings:

21. I have heard Mr. Pankaj Sawant, Learned Senior Advocate for

the State and Mr. Yashodeep Deshmukh, Learned Advocate or

Samruddhi. With their assistance, I have examined the record and

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

gone through the Impugned Award, bearing in mind the scope of

jurisdiction under Section 34 of the Act.

22. What is evident is that for 1,112 CSCs, the absence of viability was

an accepted position. To be able to ensure the same standard of service

to citizens located in the regions covered by such CSCs, considering

that the volume of transactions for access to information for citizens

would not be large, the revenue support from the State was an integral

element of the project design. The deadlines for rolling out the CSCs

was also a feature of the Agreement. The Learned Arbitral Tribunal

had to consider whether the delay in roll-out of the CSCs gave the State

the basis to not pay Samruddhi the revenue support contracted, on the

premise that there was a delay.

23. Therefore, what fell for consideration was whether the State

could withhold or deduct from amounts owed to Samruddhi towards

the viability gap funding, on the ground of liquidated damages being

owed to the State by Samruddhi.

24. To deal with this issue, the Learned Arbitral Tribunal has indeed

analysed all the material necessary for adjudication, and has indeed

returned a plausible view. The contentions of the State appear

implausible to me. Even in the Section 34 proceedings, it was

contended on behalf of the State that the last mile connectivity was the

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

responsibility of the service provider and the State cannot be expected

to ignore a binding term in the contract.

25. In my opinion, what Samruddhi was expected to ensure was

investment in technology to ensure that it is able to receive

telecommunication signals and to ensure that the CSCs actually work

on the basis of connectivity, but for that to happen, it goes without

saying that broadband telecom connectivity ought to have been

available in the respective CSCs in the first place.

26. The Learned Arbitral Tribunal has returned an eminently

plausible finding that despite the delay in the rollout of CSCs, revenue

support for the identified CSCs ought to have been provided. The first

payment was made in April 2018 nearly three years late. But for the

claim of liquidated damages, it was found that the invoice raised by

Samruddhi was admittedly accurate. That the CSCs were indeed rolled

out and that too despite the hurdle of telecom connectivity not being

available across every corner of the Nashik Revenue Division in a

manner that the milestones could have been met within the stipulated

deadlines, is writ large on the record.

27. It is in this context that one must examine the Learned Arbitral

Tribunal's view that even in cases where the parties may have

contracted provisions on liquidated damages, it would be necessary to

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

demonstrate that some loss had been occasioned. The Learned Arbitral

Tribunal's invocation of Kailash Nath1 is indeed relevant and

appropriate. Dealing with Section 74 of the Indian Contract Act, 1872

and the law on compensation for breach of contract, the Supreme Court

has declared the law in Kailash Nath, as follows:

43.1. Where a sum is named in a contract as a liquidated amount payable by way of damages, the party complaining of a breach can receive as reasonable compensation such liquidated amount only if it is a genuine pre-estimate of damages fixed by both parties and found to be such by the court. In other cases, where a sum is named in a contract as a liquidated amount payable by way of damages, only reasonable compensation can be awarded not exceeding the amount so stated. Similarly, in cases where the amount fixed is in the nature of penalty, only reasonable compensation can be awarded not exceeding the penalty so stated. In both cases, the liquidated amount or penalty is the upper limit beyond which the court cannot grant reasonable compensation.

43.2. Reasonable compensation will be fixed on well-known principles that are applicable to the law of contract, which are to be found inter alia in Section 73 of the Contract Act.

43.3. Since Section 74 awards reasonable compensation for damage or loss caused by a breach of contract, damage or loss caused is a sine qua non for the applicability of the section.

43.4. The section applies whether a person is a plaintiff or a defendant in a suit.

Kailash Nath Associates vs. Delhi Development Authority and Anr. - (2015) 4 SCC 136

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

43.5. The sum spoken of may already be paid or be payable in future.

43.6. The expression "whether or not actual damage or loss is proved to have been caused thereby" means that where it is possible to prove actual damage or loss, such proof is not dispensed with. It is only in cases where damage or loss is difficult or impossible to prove that the liquidated amount named in the contract, if a genuine pre- estimate of damage or loss, can be awarded.

43.7. Section 74 will apply to cases of forfeiture of earnest money under a contract. Where, however, forfeiture takes place under the terms and conditions of a public auction before agreement is reached, Section 74 would have no application.

[Emphasis Supplied]

28. The application of Kailash Nath to the facts of the case by the

Learned Arbitral Tribunal cannot be faulted at all. In fact, the GOI

Advisory was meant to address precisely situations such as the one at

hand. It is not as if the State was unaware of the policy intent behind

the CSCs and the need to reach out the State's services, digitally, to

citizens all over the State. The CSCs could evidently not have been

rolled out where there was no telecom broadband connectivity. The

Learned Arbitral Tribunal has rightly held that the contention that

Samruddhi should have somehow provided the last mile connectivity to

the regions where the CSCs were meant to be located, would have

required Samruddhi to be a telecom service provider. Samruddhi has

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

to engage with telecom service providers such as BSNL or the State

ought to have set up full access to Samruddhi to the SWAN network.

That not having been done, the very ability to roll out the CSCs stood

frustrated, and therefore a claim for liquidated damages, without

demonstrating how loss was suffered, could not be routinely made in

view of the law declared in Kailash Nath.

29. More importantly, the perspective of the business efficacy test

would be applicable in the instant case, simply because it is neither

commonsensical nor reasonable to read the Agreement as one that

requires Samruddhi to magically provide the last mile

telecommunication connectivity. To expect a private entity that is not

even licensed to be a telecom service provider to ensure connectivity in

areas where, admittedly, there is no telecom connectivity, is untenable.

30. In my view, the Agreement only requires service providers such

as Samruddhi to invest in equipment that would send and receive

telecom signals - evidently on the presumption that telecom coverage

was in existence to be able to send and receive signals. However, should

the State perceive that the provisions in the Agreement mandate such

an unreasonable expectation, it would at best raise an issue of

ambiguity in the Agreement. In this regard, the law declared by the

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

Supreme Court in Nabha Power2 must be noticed, since the State's

reading of the Agreement would thoroughly fail the business efficacy

test. The following extracts are noteworthy:

"49. We now proceed to apply the aforesaid principles which have evolved for interpreting the terms of a commercial contract in question. Parties indulging in commerce act in a commercial sense. It is this ground rule which is the basis of The Moorcock test of giving 'business efficacy' to the transaction, as must have been intended at all events by both business parties. The development of law saw the 'five condition test' for an implied condition to be read into the contract including the 'business efficacy' test. It also sought to incorporate 'The Officious Bystander Test' [Shirlaw vs. Southern Foundries (supra)]. This test has been set out in B.P. Refinery (Westernport) Proprietary Limited vs. The President Councillors and Ratepayers of the Shire of Hastings (supra) requiring the requisite conditions to be satisfied: (1) reasonable and equitable; (2) necessary to give business efficacy to the contract; (3) it goes without saying, i.e., The Officious Bystander Test; (4) capable of clear expression; and (5) must not contradict any express term of the contract. The same penta-principles find reference also in Investors Compensation Scheme Ltd. vs. West Bromwich Building Society (supra) and Attorney General of Belize and Ors. vs. Belize Telecom Ltd. and Anr. (supra). Needless to say that the application of these principles would not be to substitute this Court's own view of the presumed understanding of commercial terms by the parties if the terms are explicit in their expression. The explicit terms of a contract are always the final word with regards to the intention of the parties. The multi-clause contract inter se the parties has, thus, to be understood and interpreted in a

Nabha Power Ltd. Vs. Punjab State Power Corporation Ltd. And Anr. - (2018) 11 SCC 508

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

manner that any view, on a particular clause of the contract, should not do violence to another part of the contract."

[Emphasis Supplied]

31. Applying these principles to the facts of this case, it is clear that

any proposition that Samruddhi ought to have managed to ensure

telecommunications connectivity in remote areas that were without

telecommunications connectivity, for the CSCs to be rolled out in time,

despite the State and other governmental telecom service providers

themselves had not ensure such connectivity, can never be equitable,

reasonable or practicable. It would inflict some violence to the business

efficacy of the Agreement. It would go without saying that no

commercial party would expect the State to expect that the private

party must do what even the State or service providers licensed by the

State have not been able to do. The Agreement has to be read as one

requiring the CSCs to be housed with equipment that can communicate

with the telecom network and not for Samruddhi to become a telecom

service provider.

32. I have already stated why the Learned Arbitral Tribunal's

invocation of Kailash Nath is apt. The Learned Arbitral Tribunal has

rightly held that the State has not been able to prove that it suffered

loss or damage to be entitled, to routinely and as a matter of course, to

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

deduct liquidated damages. The Learned Arbitral Tribunal found that

the State indeed released payments without invoking the liquidated

damages clause, and it imposed the liquidated damages once

Samruddhi invoked arbitration. Pointing also to inherent errors and

inconsistencies in the amounts claimed by the State towards liquidated

damages, after analysing the evidence on record, the Learned Arbitral

Tribunal held that the State had not been able to prove that the

liquidated damages were a genuine pre-estimate of the loss or damage

suffered by the State.

33. The views expressed and the conclusions drawn by the Learned

Arbitral Tribunal are eminently plausible. There is nothing in the

material on record that would render the findings perverse. The

Learned Arbitral Tribunal has examined the evidence and returned

cogent and clear findings that are just and fair. The Impugned Award

cannot be said to be in conflict with the contract since on both counts -

the issue of connectivity and the imposition of liquidated damages -

the Impugned Award is in line with the law declared by the Supreme

Court in relation to business efficacy as well as the need to establish

damage and loss to impose liquidated damages.

34. On the contrary, the contention of the State that a private entity

should be able to ensure telecom service provision without regard to

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

whether licensed telecom service providers even have coverage of the

areas involved, is perverse and incapable of acceptance. The invocation

by the State, of the law declared by the Supreme Court in Energy

Watchdog3 is of no assistance. In that case, power purchase

agreements were sought to be declared as being frustrated by the

unexpected increase in price of coal, which was the input for the

electricity generated. The Supreme Court held that the inability to buy

coal at profitable prices would not lead to frustration of the power

purchase agreements and refused to declare the power purchase

agreements as void. That has no relevance to the matter in hand. It

was nobody's case that coal was not available at all. Since the price

factored in for purchase of coal had changed, the contract became

unprofitable, and it was held that this was no ground to hold the

contracts as having been frustrated. In the matter at hand, there was

no telecommunication connectivity for Samruddhi to purchase. This is

not a case of Samruddhi stating that purchase of telecommunication

services has become expensive. In fact, as and when connectivity was

available, CSCs have been rolled out.

35. Indeed, there is no complaint in the record about the service

provided by Samruddhi. The core issue is about delay in rolling out the

CSCs and its implications for paying the bills, by way of deduction of

Energy Watchdog vs. Central Electricity Regulatory Commission & Ors. - (2017) 14 SCC 80

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

liquidated damages. The witness of the State has confirmed that but

for the liquidated damages, the invoice amount is accurate. The

Impugned Award is not vulnerable to inference in exercise of the

jurisdiction under Section 34 of the Act.

36. It is now trite law that the Section 34 Court must not lightly

interfere with arbitral awards. The scope of review by the Section 34

Court is also well covered in multiple judgments of the Supreme Court

including Dyna Technologies4, Associate Builders5, Ssyangyong6,

Konkan Railway7 and OPG Power8. Even implied reasons are

discernible and may be inferred to support the just and fair outcome

arrived at in arbitral awards. To avoid prolixity, I do not think it

necessary to burden this judgment with quotations from these

judgments. Suffice it to say (to extract from just one of the foregoing),

in Dyna Technologies, the Supreme Court held thus:

"24. There is no dispute that Section 34 of the Arbitration Act limits a challenge to an award only on the grounds provided therein or as interpreted by various courts. We need to be cognizant of the fact that arbitral awards should not be interfered with in a casual and cavalier manner, unless the court comes to a conclusion that the perversity of the award goes to the root of the matter without there being a

Dyna Technologies Private Limited v. Crompton Greaves Ltd - (2019) 20 SCC 1

Associate Builders vs. Delhi Development Authority - (2015) 3 SCC 49

Ssangyong Engineering & Construction Co. Ltd. v. National Highways Authority of India - (2019) 15 SCC 131

Konkan Railways v. Chenab Bridge Project Undertaking - 2023 INSC 742

OPG Power vs. Enoxio - (2025) 2 SCC 417

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

possibility of alternative interpretation which may sustain the arbitral award. Section 34 is different in its approach and cannot be equated with a normal appellate jurisdiction. The mandate under Section 34 is to respect the finality of the arbitral award and the party autonomy to get their dispute adjudicated by an alternative forum as provided under the law. If the courts were to interfere with the arbitral award in the usual course on factual aspects, then the commercial wisdom behind opting for alternate dispute resolution would stand frustrated.

25. Moreover, umpteen number of judgments of this Court have categorically held that the courts should not interfere with an award merely because an alternative view on facts and interpretation of contract exists. The courts need to be cautious and should defer to the view taken by the Arbitral Tribunal even if the reasoning provided in the award is implied unless such award portrays perversity unpardonable under Section 34 of the Arbitration Act."

[Emphasis Supplied]

37. Applying this principle to the Impugned Award, I find no scope

for interference with the Impugned Award.

38. As regards, the challenge by Samruddhi on the ground of non-

award of interest before the arbitration proceedings and pendente lite,

on December 16, 2024, disposing of proceedings under Section 34(4)

of the Act, the Learned Arbitral Tribunal has elaborated on why interest

was not awarded to Samruddhi. The Learned Arbitral Tribunal had

ruled that the date from which interest was being claimed was not

pleaded. Even the prayers had not sought the relief of interest but the

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

Learned Arbitral Tribunal found that the pleadings indeed indicated a

claim for interest. Interest would need to be paid from the date on

which the viability funding gap was to be released, which, as per the

Agreement, was linked to the roll out of specified number of CSCs by

specified milestone deadlines. The Learned Arbitral Tribunal has ruled

that interest is a matter of discretion and the implications of non-

availability of connectivity is an issue for both sides.

39. The Learned Arbitral Tribunal has chosen its own means of

adjusting of equities by not granting pre-award and pendente lite

interest. The Learned Arbitral Tribunal, as the master of the evidence

has appreciated the evidence, and has been satisfied that to adjust

equities, interest need not be paid, one must give the Learned Arbitral

Tribunal a reasonable play in the joints to take that view.

40. The Learned Arbitral Tribunal has found that the parties were

diligent and did not protract the arbitration proceedings, and

concluded that pendente lite interest was not necessary. Here too, it is

entirely in the domain of the Learned Arbitral Tribunal to determine if

interest is to be awarded.

41. The Learned Arbitral Tribunal has indeed awarded post-arbitral

award interest.

October 14, 2025 Aarti Palkar

CARBP.166.2022.Final.doc

42. The exercise of discretion in relation to interest is not so

irrational or perverse that it warrants interference by the Section 34

Court. If the Learned Arbitral Tribunal has formed this view of a

measure that would be equitable to the State, there can be no reason to

interdict that approach. Therefore, on this count too, I see no basis to

interfere with the Impugned Award.

43. The Impugned Award is upheld and both the Petitions

challenging it, along with attendant Interim Applications, if any, are

dismissed. Should any deposits have been made, the same shall stand

released within a period of four weeks from the date of upload of this

judgment on the Court's website.

44. All actions required to be taken pursuant to this order shall be

taken upon receipt of a downloaded copy as available on this Court's

website.

[SOMASEKHAR SUNDARESAN J.]

October 14, 2025 Aarti Palkar

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter