Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Konkan Railway Corporation Ltd. vs Src Company Infra Private Limited
2025 Latest Caselaw 7517 Bom

Citation : 2025 Latest Caselaw 7517 Bom
Judgement Date : 14 November, 2025

Bombay High Court

Konkan Railway Corporation Ltd. vs Src Company Infra Private Limited on 14 November, 2025

Author: R.I. Chagla
Bench: R.I. Chagla
2025:BHC-OS:20965



                                                                             Jt-CARBP-641&646-2021.doc

                    Sharayu Khot.
                                      IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                          ORDINARY ORIGINAL CIVIL JURISDICTION

                                 COMMERCIAL ARBITRATION PETITION NO. 646 OF 2021
                                                              WITH
                                         INTERIM APPLICATION (L) NO. 4926 OF 2020
                                                                IN
                                 COMMERCIAL ARBITRATION PETITION NO. 646 OF 2021

                                                          ALONG WITH

                                 COMMERCIAL ARBITRATION PETITION NO. 641 OF 2021
                                                              WITH
                                         INTERIM APPLICATION (L) NO. 4949 OF 2020
                                                                IN
                                 COMMERCIAL ARBITRATION PETITION NO. 641 OF 2021


                          Konkan Railway Corporation Ltd.                          ...Petitioner

                                    Versus

                          M/s. SRC Company Infra Private Ltd.                      ...Respondent
                                                       ----------
                          Mr. Simil Purohit, Senior Counsel a/w Mr. Subit Chakrabarti, Ms.
                          Srushti Thorat and Ms. Aashka Vora i/b Vidhii Partners for the
                          Petitioner.
                          Mr. Anil Anturkar, Senior Counsel a/w Mr. Kunal Kumbhat, Mr.
                          Karthik Pillai, Ms. Kashish N. Chelani, Mr. Atharva Date & Mr.
                          Harshvardhan Suravanshi i/b Ms. Sunanda R. Kumbhat for the
       SHARAYU
       PANDURANG
       KHOT
                          Respondent.
                                                             ----------
       Digitally
       signed by
       SHARAYU
       PANDURANG
       KHOT
                                                        CORAM             : R.I. CHAGLA J.
       Date:
       2025.11.14
       15:56:14
       +0530
                                                        Reserved on       : 12 June 2025
                                                        Pronounced on :     14 November 2025

                                                                 1




                         ::: Uploaded on - 14/11/2025                      ::: Downloaded on - 14/11/2025 22:50:47 :::
                                                        Jt-CARBP-641&646-2021.doc


JUDGMENT :

1. By the Commercial Arbitration Petition No. 646 of 2021,

the Petitioner- Respondent in the arbitral proceedings has impugned

the majority Award dated 22nd May 2020 ("the said Award") under

Section 34 of the Arbitration and Conciliation Act, 1996 ("the

Arbitration Act").

2. In the companion Commercial Arbitration Petition No.

641 of 2021, an identical Award has been challenged. In view of the

parties having referred to the pleadings and records of the

Commercial Arbitration Petition No. 646 of 2021 during the oral

arguments and the written submissions filed therein, the facts in that

Arbitration Petition is being adverted to.

3. The brief background of facts are as under:-

(i) The National Thermal Power Corporation ("NTPC")

had proposed setting up the Super Thermal Power

Plan ("STPP") in Tehsil Gadarwara, District

Narsinghpur, Madhya Pradesh. Accordingly, NTPC

Jt-CARBP-641&646-2021.doc

invited tenders for the work of "DPR & Detailed

Engineering, Project Management and Construction

of Coal Transportation System including Associated

Electricals Package for Gadarwara Super Thermal

Power Plant, Stage-I".

(ii) NTPC issued a Letter of Award on 25th June 2014

appointing the Petitioner- Respondent as the Project

Management Consultant / Project Executing Agency

for the work.

(iii) The Petitioner- Respondent in turn published a Notice

dated 23rd November 2016 inviting tenders for the

subject work described in the Notice at (Exh.B to the

Petition).

(iv) Technical bids of the bidders were opened on 26th

December 2016.

(v) The financial bids of the bidders were opened on 31st

March 2017.

(vi) The Respondent-Claimant was found to be the 'L1'

Jt-CARBP-641&646-2021.doc

bidder.

(vii) The Petitioner-Respondent issued a Letter of

Acceptance ("LoA") on 16th May 2017 in favour of

the Respondent-Claimant in respect of the subject

work for the total cost of Rs. 122,32,98,483/- with

the completion period of 15 months (which period

was subsequently duly extended from time to time),

which was countersigned and accepted

unconditionally by the Respondent-Claimant.

(viii) The Respondent-Claimant commenced the subject

work in July 2017.

(ix) The Petitioner-Respondent and the Respondent-

Claimant executed Contract Agreement on 5th

December 2017.

(x) The Collector's office (Mineral Branch), Madhya

Pradesh addressed a demand letter dated 27th

December 2018 directing the Respondent-Claimant to

make payment of Royalty charges at the rate of Rs.

100/- per cubic meter (cum) for the earth used in

Jt-CARBP-641&646-2021.doc

making the embankment for the subject work

(aggregating approximately Rs. 22,00,00,000/-).

(xi) The Respondent-Claimant issued a Notice invoking

Arbitration on 13th June 2019.

(xii) The Three Members Arbitral Tribunal comprising Mr.

A.K. Mittal (Presiding Arbitrator), Mr. Atul Mohan

(Co-Arbitrator) and Mr. P.S. Rao (Co-Arbitrator),

entered into reference on 20th August 2019.

(xiii) The Arbitral Tribunal passed the said Award. The

Presiding Arbitrator passed a separate Dissent Note

on 22nd May 2020.

(xiv) By the said Award, the Arbitral Tribunal held that the

liability to pay royalty on ordinary earth used in the

subject work lies with the Petitioner-Respondent and

directed the Petitioner-Respondent to make payment

of the same. Further, the Arbitral Tribunal directed

the Petitioner-Respondent to modify / amend the

Contract with the Respondent-Claimant to that extent

by invoking Section 26 of the Specific Relief Act,

Jt-CARBP-641&646-2021.doc

1963 and Section 20 of the Indian Contract Act, 1872

so as to purportedly correctly reflect the consensus ad

idem (between the parties). By the Dissent Note, the

Presiding Arbitrator directed the Respondent-

Claimant to make payment of the royalty as per the

extant Rules on ordinary earth used in the subject

work and submit the receipts thereof to the

Petitioner-Respondent to facilitate preparation of the

final bill.

4. Mr. Simil Purohit, the learned Senior Counsel for the

Petitioner has submitted that in determining the limited issue, which

arose before the Arbitral Tribunal as to whether the royalty levied by

the State Government of Madhya Pradesh towards earthwork in filing

in embankment used in the subject work was payable by the

Petitioner-Respondent or the Respondent-Claimant in the Arbitration,

the terms of Contract between the parties are to be construed by the

Tribunal. The Tribunal being a creature of Contract cannot traverse

beyond and is bound to act within the terms of the Contract. He has

placed reliance upon the judgment of the Supreme Court in Union of

Jt-CARBP-641&646-2021.doc

India Vs. Bharat Enterprise1.

5. Mr. Purohit has submitted that in the present case the

terms of the Contract between the parties unequivocally confirm on

its plain reading that the Royalty payable towards earthwork in

filling in embankment used in the subject work was to be borne by

the Respondent-Claimant.

6. Mr. Purohit has referred to the relevant clause of the

Contract between the parties. He has referred to Clause 10.1 of the

Instructions to Bidders (part of the Tender documents) under the

heading 'Contents of Bidding Documents'. He has referred to Clause

14.2 of the Instructions to Bidders under the heading 'Preparation of

Bid' and sub-heading 'Bid Prices', which includes royalty and other

levies payable by the Contractors under the Contract. He has also

referred to Clause 22.4 of the Instructions to Bidders under the

heading 'Submission of Bids', which provides that offers shall not be

qualified with any conditions and that conditional offers shall be

summarily rejected without giving any reasons. He has referred to

Clause 37 of the Konkan Railways Standard General Conditions of

1 2023 SCC OnLine SC 369

Jt-CARBP-641&646-2021.doc

Contract 2014 ("GCC"), which provides rates for items of works and

which includes all fees, duties, royalties, etc. for which the Contractor

may become liable or may be put to under any provision of law for

the purposes of or in connection with the execution of the Contract.

He has referred to Clause 41 of the GCC, which provides for

modification of Contract to be in writing.

7. Mr. Purohit has referred to the definition of "Approval or

Approved" in Clause 1.1 of the Special Conditions of Contract

("SCC") - Part A, which means approval in writing of the Competent

Authority. He has referred to Clause 1.11 of the SCC - Part A which

defines Contract to include the Agreement or Letter of Acceptance

("LoA"), the accepted schedule of items, rates and quantities, the

GCC, along with latest corrections slips, the SCC Part-A and Part-B,

the drawings, the specifications and special specifications if any,

tender forms, instructions to tenderers, notice inviting tender,

Addendum(s), Corrigendum(s) and other conditions / specifications

of Tender documents.

8. Mr. Purohit has also referred to Clause 5 of the SCC -

Part A, which provides for royalties and patent rights and that the

Jt-CARBP-641&646-2021.doc

Contractor shall defray the cost of all royalties, fees. It is further

provided that in case of any breach (whether willfully or

inadvertently) by the Contractor of this provision, the Contractor

shall indemnify the Konkan Railway Corporation Limited ("KRCL")

against all claims, proceedings, damages, costs, charges, pecuniary

loss and liabilities and which they or any of them sustain, incur or be

put by reason or in consequence directly or indirectly for any such

breach, and against payment of any royalties, damages and other

type of payment in which the KRCL may have to make / pay /

reimburse to any person for any machine, instruments, process,

articles, matters, or thing constructed, manufactured, supplied or

delivered by the Contractor to his order under this Contract. He has

also referred to Clause 55.4 of the SCC - Part A, which provides for

the Contractor to pay all storage, royalty and other incidental charges

that may be involved.

9. Mr. Purohit has then referred to Clause 57 of SCC - Part

A, which provides for payment of royalty charges and it is provided

therein that all payments of royalty charges, etc. to the State

Government in connection with extraction and supply of rubble stone

/ ballast / sand earth have to be borne and paid by the tenderer /

Jt-CARBP-641&646-2021.doc

Contractor. The Corporation is entitled to deduct from the

tenderers / Contractors and keep in deposit such amount equal to the

proportionate royalty charges from each on account bills and the

same will be released as and when the tenderer / Contractor submits

a receipt / documents / Clearance Certificate that royalty charges

have been paid by the tenderers / Contractors relating to the

Contract (Clause 57.2 of SCC - Part A). He has also referred to

Clause 57.3 of SCC - Part A, which provides that the tenderer /

Contractor will be required to obtain a final Royalty Charge,

Clearance Certificate from the concerned State / Revenue Authorities

/ Collector and produce the same to the Engineer-in-charge, after

completion of supply, but before the release of final bill. If in any

case, the tenderer / Contractor fails to produce the Clearance

Certificate, the Royalty amount equal to the amount of unpaid

Royalty Charges as intimated by the Revenue Authorities / Collector

or as calculated on the basis of the relevant rules, such payment of

royalty charges applicable to the area will be withheld by KRCL.

10. Mr. Purohit has referred to the scope of work under

Clause 1.2 of the SCC - Part B which includes earthwork in cutting

and embankment, construction of minor bridges / RUB and

Jt-CARBP-641&646-2021.doc

protective work. The earthwork in embankment is with Contractor's

own earth. This is also provided in Clause 6.1 of the SCC Part B,

under the heading "Specifications for Earthwork", and Formation

works. He has also referred to Clause 6.4 of the SCC - Part B, which

similarly provides for earthwork in embankments with Contractors

earth and supplying and spreading of blanketing material in addition

to the above, the rate will be inclusive of the cost of acquisition of the

earth or blanketing material by purchase of land or payment of

royalty charges or in any other manner, transportation and all other

incidental works, complete, for bringing the earth or blanketing

material from outside the Railway Land. He has also to refer to Item

1 of Schedule B titled 'Filling Items' of Schedule of Items, Rates and

Quantities, which include earthwork in filling in embankment. The

earth excavated from outside railway boundary entirely arranged by

the Contractor at his own cost and special conditions of Contract

including inter alias royalty. The rate also includes royalty.

11. Mr. Purohit has referred to the Certificate of

Familiarisation at Appendix 18 of the Contract that was duly signed

and submitted by the Respondent-Claimant, which reads that the

Respondent-Claimant has declared and certified that it has fully

Jt-CARBP-641&646-2021.doc

familiarised themselves with all aspects of construction features

including all local taxes, royalties, etc. It is further mentioned that

the Respondent-Claimant keeps it fully informed with the provisions

of the Tender documents and has quoted the percentage rate by

taking into account all the factors given above and elsewhere in the

Tender document.

12. Mr. Purohit has also referred to Clauses 2 and 3 of the

LoA, which provides for the total Contract value and the Contract to

be governed by GCC. He has also referred to the 3rd unnumbered

recital in the Contract Agreement, which provides the Contractor has

agreed and confirmed his unconditional acceptance to the

Corporation's said Letter of Acceptance. Further, it is provided in

unnumbered Clauses of the Contract Agreement that the Contract

will observe and fulfill and keep all the conditions contained (which

shall be deemed and taken as to be integral part of the agreement).

The Corporation will pay at the rates given for various items in the

schedule of items, rates and quantities and percentage rate tendered

by Contractor and as accepted by the Corporation as set forth in

Annexure - II, Schedule of Items, Rates and Quantities (bill of

Quantities). It is further agreed that all the provisions of the said

Jt-CARBP-641&646-2021.doc

conditions, specifications have been carefully read and understood by

the Contractor and bills of quantities shall be binding upon the

Contractor and upon the Corporation and shall be read as part of

these presence. The entire document including Annexures annexed to

the Contract Agreement shall form and be construed as part of the

Contact Agreement.

13. Mr. Purohit has submitted that upon reading of the

aforementioned Clauses, including the confirmation given by the

Respondent-Claimant of adhering to the terms of the Contract and

the tender conditions, shows that the Respondent-Claimant has

consciously and unequivocally accepted the terms of the Contract and

is bound by the same.

14. Mr. Purohit has submitted that the Arbitral Tribunal has

arrived at the findings and observations while construing the terms of

the Contract. He has submitted that the finding of the Arbitral

Tribunal is that the royalty payments are to be borne by the

Respondent-Claimant and it remains undisputed that the terms of the

Contract envisage that all royalties of materials used in the project

are to be borne by the Respondent-Claimant. It is further held by the

Jt-CARBP-641&646-2021.doc

Arbitral Tribunal that both the parties have admitted that the

Respondent-Claimant had not specified in its quote that it did not

include royalty in its quoted rates. Both the parties had admitted that

the Contract provided for costs of royalty to be included in the

quoted and accepted rates. There is a finding that when the

Respondent-Claimant did not include royalty payable on earth used

in filing in embankment in its rate, it should have made a mention

that its rates for earthwork are excluding the royalty costs. No such

mention has been made by the Respondent-Claimant. It was only

after starting the work that the Respondent-Claimant had considered

the NIL royalty on ordinary earth. There are further findings of the

Arbitral Tribunal that the contention of the Petitioner-Respondent

that the Contract puts burden of all royalty payments on the

Respondent-Claimant is correct. The Respondent-Claimant has not

disputed this provision per se. The Respondent-Claimant admits its

responsibility to pay royalty on the material used for the project. The

Arbitral Tribunal agreed with the Petitioner-Respondent's arguments

that there is no scope available to interpret the clauses of the

Contract.

15. Mr. Purohit has submitted that the aforementioned

Jt-CARBP-641&646-2021.doc

findings of the Arbitral Tribunal show that the Arbitral Tribunal

affirms the terms of the Contract, which unequivocally holds that the

Respondent-Claimant is to bear the royalty payable towards

earthwork in filing in embankment as per the terms of the Contract

between the parties. Despite the same, the said Award seeks to make

the Petitioner-Respondent liable to pay such royalty amount.

16. Mr. Purohit has submitted that although it is the case of

the Respondent-Claimant that it did not factor in the royalty payable

towards the earth used in filing in embankment while submitting its

bid, the same cannot be a ground of the Respondent-Claimant to

claim such royalty amount from the Petitioner-Respondent. He has

submitted that the defence raised by the Respondent-Claimant is that

it considered the royalty payable towards the earth used in filing in

embankment as NIL. This would be at the risk and costs of the

Respondent-Claimant itself. He has submitted that the Arbitral

Tribunal has erroneously held that although there was no ambiguity

on the subject of the payment of royalty, somehow, the Respondent-

Claimant had missed / excluded the royalty while working out the

costs of earthwork, due to ignorance of law. He has submitted that

ignorance of law is not a valid defence as per the settled law.

Jt-CARBP-641&646-2021.doc

17. Mr. Purohit has submitted that it is the contention of the

Respondent-Claimant that the Collector's office (Mineral Branch),

Madhya Pradesh vide its Demand Letter dated 27th December 2018

made a demand for the royalty charges at the rate of Rs. 100/- per

cubic meter (cum) for the earth used in making the embankment for

the subject work aggregating to approximately Rs. 22,00,00,000/-. It

is contended that this Demand Letter imposes liability for the first

time, and that under an earlier Circular issued by the Government of

Madhya Pradesh, Mining Department dated 18th August 2009

("2009 Circular"), no royalty was payable on earth having a CBR

value less than 12. He has submitted that the contention of the

Respondent-Claimant on the 2009 Circular is untenable. It has been

observed by the Arbitral Tribunal that all the relevant Circulars,

notifications, directives, etc. were issued prior to the issuance of the

Notice Inviting Tender dated 23rd November 2016 and the opening

of the technical bids on 26th December 2016. He has submitted that

on reading of the 2009 Circular, it is evident that the same does not

make any kind of categorical assertions that no royalty is payable on

the earth used in filing in embankment having a CBR value less than

12. He has submitted that neither the said Demand Letter nor the

relevant Act / Rules have been challenged by the Respondent-

Jt-CARBP-641&646-2021.doc

Claimant.

18. Mr. Purohit has submitted that in order for the

Respondent-Claimant to succeed, the Arbitral Tribunal would have to

interpret the 2009 Circular and arrive at a definitive conclusion that

no royalty was payable on the earth used in filing in embankment

having a CBR value less than 12, and that the royalty demand under

the Demand Letter dated 27th December 2018 was a subsequent

levy, which was not in force prior thereto. He has submitted that

unless such a finding is rendered, the Respondent-Claimant cannot

succeed in its claim.

19. Mr. Purohit has submitted that the Arbitral Tribunal has

refrained from deciding the effect and the consequence of the 2009

Circular, since the Arbitral Tribunal felt that this issue remained

outside the purview of the Arbitral Tribunal and that the limited issue

before the Arbitral Tribunal was as to which party is required to pay

royalty.

20. Mr. Purohit has submitted that the only basis for the

Respondent-Claimant to seek payment of royalty on the earth used in

Jt-CARBP-641&646-2021.doc

filing in embankment having a CBR value less than 12 is on its

'understanding'. The same has not been decided by the Arbitral

Tribunal and hence, the question of the Petitioner-Respondent to pay

the amount of royalty does not arise.

21. Mr. Purohit has submitted that the parties are bound by

the terms of Contract as agreed, and any mistake of law does not

permit any party to avoid the consequences of a Contract.

22. Mr. Purohit has submitted that the Arbitral Tribunal has

relied upon the minutes of the meeting of the Tender Committee

constituted by the Petitioner-Respondent. He has submitted that the

Tender Committee is an in-house advisory body to advice the

Petitioner-Respondent on the financial and technical aspects of the

matter. He has submitted that being only an advisory body, its

recommendations do not bind the Petitioner-Respondent. The

question of the same being binding on the parties to the final

Contract does not arise.

23. Mr. Purohit has submitted that the Tender Committee

has evaluated the various bids submitted by the tenderers. The

Jt-CARBP-641&646-2021.doc

minutes of the meeting of the Tender Committee is a confidential

document. It is a part of the internal decision making process of the

Petitioner-Respondent. The minutes of the meeting of the Tender

Committee was never communicated to the Respondent-Claimant.

Thus, the minutes are not available in the public domain and were

only produced for the first time during the course of the arbitral

proceedings on the request of the Respondent-Claimant and on the

specific directions of the Arbitral Tribunal.

24. Mr. Purohit has submitted that it is well settled that inter

departmental communications / file notings cannot be relied upon on

the basis to claim any right, as the same have no legal sanctity. He

has placed reliance upon the judgments of the Supreme Court in

Delhi Development Authority Vs. Hello Home Education Society 2,

Mahadeo Vs. Sovan Devi3 and Union of India Vs. Airwide Express

Cargo4.

25. Mr. Purohit has submitted that the Arbitral Tribunal

could not have relied upon the minutes of the meeting of the Tender

2 (2024) 3 SCC 148 3 (2023) 10 SCC 807 4 2015 SCC OnLine Bom 4917

Jt-CARBP-641&646-2021.doc

Committee, as the basis of its Award. Further, the Arbitral Tribunal

erred in holding that the minutes of the meeting of the Tender

Committee reflected the intention of the parties. He has submitted

that the minutes of meeting of the Tender Committee was not a

bilateral document, but an internal evaluation of the bids submitted

by the tenderers.

26. Mr. Purohit has submitted that the Arbitral Tribunal

based on the minutes of meeting of the Tender Committee proceeded

to hold that the Contract entered into between the parties did not

incorporate that the royalty towards earthwork in filing in

embankment was to be paid by the Petitioner-Respondent, as the

Respondent-Claimant had not considered the same while submitting

its bid.

27. Mr. Purohit has referred to the findings of the Arbitral

Tribunal that the Petitioner-Respondent having decided to accept the

rates quoted on lower side, has failed to incorporate in the said

Contract for the corresponding basis for accepting the earthwork in

filing in embankment. He has submitted that the Arbitral Tribunal is

duty bound to ascertain whether the intention of the parties are fully

Jt-CARBP-641&646-2021.doc

covered by the Contract, particularly when the Petitioner-Respondent

is the author of the Contract. It is necessary to ensure that the

intention of the parties before Award of the Contract are transformed

into writing. He has submitted that all the above findings of the

Arbitral Tribunal are contrary to the stated case of the Respondent-

Claimant.

28. Mr. Purohit has submitted that the Respondent-Claimant

has neither in its prayers sought rectification of the Contract under

Section 26 of the Specific Relief Act, 1963 nor has the Respondent-

Claimant alleged or made out any case for contra proferentem. He

has submitted that the Arbitral Tribunal assumed suo motu powers

and awarded a claim for rectification of the Contract. He has

submitted that it is trite law that reliefs not specifically prayed for by

a party cannot be granted. He has placed reliance upon Mrs. Akella

Lalitha Vs. Sri Konda Hanumantha Rao5 in this context.

29. Mr. Purohit has submitted that the Arbitral Tribunal by

finding that non execution of a formal agreement / amendment to

the said Contract to exclude the royalty payable towards earthwork

5 2022 SCC OnLine SC 928

Jt-CARBP-641&646-2021.doc

in filing in embankment cannot be an impediment to honour the

intention of the parties at the time of tender evaluation. This is by

overlooking Clause 41 of the GCC, which expressly provides that any

modification(s) to the Contract were to be in writing signed by both

parties and no work was to proceed under such modification until

this has been done.

30. Mr. Purohit has submitted that finding of the Arbitral

Tribunal relying upon Clause 57.2 of the SCC - Part A is also

erroneous. He has submitted that assuming whilst specifically

denying that the Petitioner-Claimant has failed to ascertain the

royalty payable, the said clause still does not make the Petitioner-

Claimant liable for payment of royalty towards earthwork in filing in

embankment. The said Clause also makes it clear that it is the

Respondent-Claimant that has to make payment of all royalty

obligations. He has submitted that the findings of the Arbitral

Tribunal that the Petitioner-Respondent did not respond to letter

dated 4th June 2018 addressed by the Respondent-Claimant is of no

consequence. He has submitted that in any event, the obligation to

perform the Contract was on the Respondent-Claimant.

Jt-CARBP-641&646-2021.doc

31. Mr. Purohit has submitted that for all these reasons, it is

prayed that the present Arbitration Petition under Section 34 of the

Arbitration Act be allowed and the said Award be set aside.

32. Mr. Anturkar, the learned Senior Counsel appearing for

the Respondent-Claimant has submitted that the crucial issue

involved in the matter is as to whether the approach of the

Arbitrators in not limiting themselves to the literal interpretation of

the terms and conditions of the Contract, but instead making a bona

fide and sincere effort to ascertain the real intention of the parties to

find out as to whether the parties had reached a consensus on the

disputed position, cannot be considered so erroneous, as to warrant

interference under Section 34 of the Arbitration Act.

33. Mr. Anturkar has submitted that the majority Arbitrators

in Clause 15.6.2 of the said Award have clearly articulated that they

had chosen to proceed on the basis of consensus, i.e. to discover the

real intention of the parties, rather than by a literal interpretation of

the Contract. He has submitted that notably, even the minority view,

as expressed in paragraphs 2.9 and 2.10, demonstrates that the

parties were in consensus that no royalty was payable on ordinary

Jt-CARBP-641&646-2021.doc

earth. He has placed reliance upon the judgments of the Supreme

Court as well as this Court in support of his contention that the

manner in which the Arbitrators chose to interpret the terms and

conditions of the Contract to demonstrate real intentions of the

parties is not to be interfered with. These judgments include Konkan

Railway Corporation Limited Vs. Chenab Bridge Project Undertaking 6

at paragraphs 19, 20 and 27; McDermott International Inc. Vs. Burn

Standard Co. Ltd.7 at paragraphs 112 and 113 and Ivory Properties &

Hotels Private Limited Vs. Vasantben Ramniklal Bhuta 8 at paragraph

43. He has submitted that all these judgments have consistently held

that the interpretation of the terms and conditions of the Contract by

the Arbitrator and the manner, in which interpretations are made,

cannot be faulted and cannot be substituted, even if another

interpretation is possible.

34. Mr. Anturkar has submitted that the reliance placed by

the Petitioner-Respondent upon Clause 41 of the said Contract is

misconceived. Clause 41 applies only when there is an explicit

provision in the Contract, of which modification has been sought and

6 (2023)9 SCC 85 7 (2006)11 SCC 181 8 2024 SCC OnLine Bom 1900

Jt-CARBP-641&646-2021.doc

which is required to be in writing. He has submitted that Clause 41

would not apply when no explicit provision exists in the Contract. He

has submitted that if the intention of the parties to a Contract is

established, then there would be no need to modify the provision of

the Contract, because no explicit provision requires modification. The

parties are behaving according to their real intentions. He has

submitted that the latter portion of Clause 41 expressly allows for

such verbal arrangements - abandoning, modifying, extending,

reducing, or supplementing the Contract. He has submitted that if the

first part of Clause 41 is given effect to, i.e. no work shall proceed

under such modification until this has been done, this would result in

the stoppage of work, which under no such circumstances, should be

resorted to, because that would cause loss to Petitioner-Respondent

and stop the ongoing work. He has submitted that the Arbitral

Tribunal has determined the real intention of the parties and not

modified the terms of the Contract, as contended by the Petitioner-

Respondent.

35. Mr. Anturkar has submitted that no fault can be found

with the approach of the Arbitrators in the present case in not given

importance only to the actual verbatim of the Contract, but by trying

Jt-CARBP-641&646-2021.doc

to identify what was the real mutual intention of the parties and

what was the consensus ad idem of both the parties. He has

submitted that this is the correct approach of adjudication, either by

the Court or by the Arbitrator.

36. Mr. Anturkar has submitted that the reliance placed by

the Petitioner-Respondent upon the judgments of the Supreme Court

in Union of India Vs. Airwide Express Cargo (supra) and Mahadeo

Vs. Sovan Devi (supra) is wholly misplaced. These judgments are

applicable only to those cases, wherein it is contended that a certain

decision has been taken in the noting which are internal in nature

and that decision reflected in the noting is sought to be enforced. It

was held in the context of inter-departmental communications that

they cannot be used to claim legal rights and merely writing

something in a file does not constitute an official order.

37. Mr. Anturkar has submitted that it is not the

Respondent-Claimant's contention that any "decision" has been taken

in the internal noting of the Tender Committee (minutes of Tender

Committee) and is relied upon not to contend that there is any such

decision taken there, but for the purpose to bring the real consensus

Jt-CARBP-641&646-2021.doc

ad idem between the parties and the real and mutual intention of the

parties vis-a-vis the issue viz. whether both the parties were under

the mutual impression, factually that no royalty is payable on the

ordinary earth and in such circumstances, whose responsibility it is to

pay the royalty on ordinary earth.

38. Mr. Anturkar has submitted that the Supreme Court in

Subodh Kumar Singh Rathour Vs. Chief Executive Officer 9 has held

that internal deliberations or file notings that formed part of decision

making process can certainly be looked into by the Court for the

purpose of judicial review to satisfy itself of the impeccability of the

said decision.

39. Mr. Anturkar has submitted that the Petitioner-

Respondent and the Respondent-Claimant at all stages, were at

consensus ad idem that no royalty is payable on ordinary earth. He

has submitted that as per Clause 57.2 of the said Contract, it was the

obligation of the Petitioner-Respondent to confirm the percentage of

royalty charges to be recovered for supply of minor minerals in

consultation with the State Government. He has submitted that the

9 2024 SCC OnLine SC 1682

Jt-CARBP-641&646-2021.doc

parties never intended for the Contractor to pay royalty on the

ordinary earth. These circumstances show that it was the consensus

ad idem between the parties, which was given effect to by the

Arbitrators and cannot be faulted under Section 34 of the Arbitration

Act.

40. Mr. Anturkar has submitted that it is an admitted

position that Schedule B of the Tender pertaining to the earthwork in

filing in embankment did not include charges for royalty on ordinary

earth, which submission is taken by the Respondent-Claimant in

paragraph 18 of the claim. He has submitted that the Respondent-

Claimant had also made specific averment in their Statement of

Claim at paragraph 3.4 that during the pre-award negotiated meeting

with the Tender Committee, the fact of non-consideration of royalty

on ordinary earth in the bid has been conveyed. There is no specific

denial as far as paragraph 3.4 is concerned and general denial is

resorted to.

41. Mr. Anturkar has submitted that it was not only on the

Tender Committee's recommendations, but even the Directors

Committee on 15th May 2017 reviewed the Tender Committee

Jt-CARBP-641&646-2021.doc

minutes, deliberated, and agreed with the Tender Committee's

recommendations to accept the financial bid offer of the lowest

bidder. Tender Committee's recommendations, which were reviewed

and agreed upon by the Directors Committee have been accepted as

recommended by the Chairman and Managing Director on 15th May

2017. He has submitted that on receipt of approval from the

Chairman and Managing Director, the draft Letter of Acceptance was

prepared as per the recommendations of the Tender Committee

(financial bid) which is evident from the noting dated 16th May

2017. He has submitted that at all stages, namely, at the Tender

Committee, the Directors Committee and the Managing Directors

level everyone was under the impression that no royalties were

payable on ordinary earth. It was in accordance with such consensus

that the draft Letter of Acceptance was prepared as per the Tender

Committee recommendations and which is deemed to be an integral

part of the Agreement.

42. Mr. Anturkar has submitted that the minutes of the

Tender Committee which show that no royalty was payable on

ordinary earth is not based on the Government Circular dated 18th

August 2009, but also on account of confirmation from WCR /

Jt-CARBP-641&646-2021.doc

Jabalpur vide email dated 29th April 2017 that no royalty is payable

on ordinary earth in Madhya Pradesh State. This was also the

impression carried by the Petitioner-Respondent.

43. Mr. Anturkar has submitted that the Arbitration Award

cannot be set aside on the mere possibility of an alternative view of

the facts or interpretation of the Contract. He has placed reliance

upon the judgment of the Supreme Court in Konkan Railway

Corporation Limited Vs. Chenab Bridge Project Undertaking (supra)

at paragraph 19 in this context.

44. Mr. Anturkar has submitted that it is settled law that

contravention of substantial law of India would not sound the death-

knell for an Arbitral Award. He has in this context relied upon the

judgment in Ivory Properties & Hotels Private Limited Vs. Vasantben

Ramniklal Bhuta (supra) at paragraph 43. He has also placed reliance

upon the judgment of the Supreme Court in McDermott International

Inc. Vs. Burn Standard Co. Ltd. (supra) at paragraphs 112 and 113

and 115, 116. The Supreme Court has held that construction of the

Contract is within the jurisdiction of the Arbitrator and

correspondence exchanged between the parties are required to be

Jt-CARBP-641&646-2021.doc

taken into consideration for the purpose of construction of the

Contract. Interpretation of a Contract is a matter for the Arbitrator to

determine, even if it gives rise to the determination of a question of

law. He has also placed reliance upon MMTC Limited Vs. Vedanta

Limited10 in this context.

45. Mr. Anturkar has submitted that it is now not open for

the Petitioner-Respondent to argue that the Arbitrators should not

have called for the documents before the formation of the Contract,

viz. documents like the minutes of the Tender Committee, the

minutes of the Directors Committee, the decision taken by the

Managing Director, etc. He has submitted that the Arbitrator did this

on the application made by the Contractor as seen from paragraph

5.2.2 of the said Award. The said application was not opposed. It was

at the time of making of the application for the Petitioner-

Respondent to contend that the Arbitrators cannot go beyond the ad

verbum of the Contract.

46. Mr. Anturkar has submitted that reliance upon the

grounds in the Petition where it is alleged that the Arbitrators have

10 (2019)4 SCC 163

Jt-CARBP-641&646-2021.doc

exceeded their authority is impermissible in the light of Section 4 and

Section 16(3) of the Arbitration Act and the judgment given in

Narayan Prasad Lohia Vs. Nikunj Kumar Lohia & Ors. 11 at paragraphs

15 and 16.

47. Mr. Anturkar has submitted that a mere erroneous

application of law by itself is not a ground to set aside the Award. He

has placed reliance upon the judgment of the Supreme Court in OPG

Power Generation Private Limited Vs. Enexio Power Cooling

Solutions India Private Limited12 at paragraph 45. He has submitted

that on a careful reading of the entire Award, coupled with the

documents relied upon, along with the underlying reasons, factual or

legal that form the basis of the Award is discernible or intelligible,

the same does not exhibit any perversity, and the Court need not set

aside the Award in exercising the power under Section 34 of the

Arbitration Act.

48. Mr. Anturkar has submitted that the Petitioner has at the

stage of Rejoinder erroneously submitted that the tender quoted rates

11 (2002) 3 SCC 572 12 2024 SCC OnLine SC 2600

Jt-CARBP-641&646-2021.doc

and the quotations of all the other Contractors included royalty on

ordinary earth. This submission is without any pleading to that effect

either before the Arbitral Tribunal or in the Arbitration Petition filed

before this Court. He has submitted that in any event, the submission

on behalf of the Petitioner-Respondent is entirely incorrect and

contrary to the documents on record.

49. Mr. Anturkar has submitted that both the Petitioner-

Respondent and NTPC Limited being Government owned

undertakings are duty bound to act fairly and inspite of which, they

have sought recovery of royalty charges with complete knowledge

that the quoted rates by the Respondent-Claimant did not include

royalty on ordinary earth. Such action on the part of the Petitioner-

Respondent and NTPC Limited is unconscionable.

50. Mr. Anturkar has submitted that the contention of the

Petitioner-Respondent that Arbitrators have traversed beyond the

scope of reference and modified / rectified the Contract is factually

incorrect, as the operative part of the Award in Clause 20 directs the

Respondent to make the payment of royalty for ordinary earth and

merely provides that "the Respondent may modify / amend the

Jt-CARBP-641&646-2021.doc

Contract with the Claimant to this extent so as to correctly reflect the

consensus ad idem, if need be". He has submitted that this is merely

an option provided by the Arbitral Tribunal and no directions are

passed either rectifying or modifying the Contract.

51. Mr. Anturkar has accordingly submitted that the present

Arbitration Petition be dismissed, as not raising any valid ground of

challenge under Section 34 of the Arbitration Act.

52. Having considered the submissions, the limited issue

which fell for determination before the Arbitral Tribunal was whether

the royalty levied by the State Government of Madhya Pradesh

towards earthwork in filing in embankment used in the said work

was payable by the Petitioner-Respondent or the Respondent-

Claimant. It was therefore, necessary for the Arbitral Tribunal to

determine this issue in consonance with the terms of the Contract

between the Petitioner-Respondent and the Respondent-Claimant. It

is well settled that the Arbitral Tribunal being a creature of Contract

cannot traverse beyond and is bound by the Contract. This has been

held in the judgment relied upon by the Petitioner-Respondent viz.

Union of India Vs. Bharat Enterprise (supra).

Jt-CARBP-641&646-2021.doc

53. The Arbitral Tribunal has in the said Award accepted the

literal interpretation of the Contract, viz. that royalty payments are to

be borne by the Respondent-Claimant. In so doing, it was not

competent for the Arbitral Tribunal to delve into "real intention" of

the parties. For the Arbitral Tribunal to examine the "real intention"

of the parties, it would first need to hold that the terms of the

Contract are ambiguous or vague. This is not the case of the

Respondent-Claimant as can be seen from the pleadings and/or

issues framed and there is no finding on this aspect rendered. The

Petitioner-Respondent and the Respondent-Claimant are ad idem

that on a plain reading of the Contract, it was the Respondent-

Claimant's liability to pay royalty. The Arbitral Tribunal by

disregarding the plain terms of the Contract, which are clear and

unambiguous and inferring a different intention from that

contemplated by the terms of the Contract has committed a patent

illegality.

54. The reliance placed by the Respondent-Claimant upon

the judgments, namely Konkan Railway Corporation Limited Vs.

Chenab Bridge Project Undertaking (supra), McDermott International

Inc. (supra) and Ivory Properties & Hotels Private Limited (supra) in

Jt-CARBP-641&646-2021.doc

support of their contention that merely because the Court would

have interpreted the Contract differently interference with the Award

is not warranted, is misplaced.

55. The above contention of the Respondent-Claimant is

misconceived as the present case is not one involving two competing

interpretations of the Contract. Here all the parties concerned

including the majority Arbitrators, the dissenting Arbitrator,

Respondent-Claimant and the Petitioner-Respondent have accepted

that the Contract requires the Respondent-Claimant to bear the

royalty liability. The ground of challenge raised in the Arbitration

Petition is not to seek a new and different interpretation from that

arrived at by the Arbitrators, but to point out that the final conclusion

of the majority Arbitrators contradict their own interpretation of the

Contract. The majority Arbitrators having first held that the

Respondent-Claimant must pay royalty as per the Contract, have

thereafter rendered an Award that shifts the burden onto the

Petitioner-Respondent. This is not a permissible cause of action and

renders the Award perverse apart from being patently illegal.

56. The reliance placed by the majority Arbitrators on the

Jt-CARBP-641&646-2021.doc

minutes of the meeting of the Tender Committee, is misplaced. It is

settled law that inter-departmental communications / file notings

have no legal sanctity and/or do not create any enforceable rights.

The judgment relied upon by the Petitioner-Respondent, namely

Mahadeo Vs. Sovan Devi (supra) is apposite. It has been held that

these inter-departmental communications are at best preparatory

steps or expressions of tentative views. Unless notings culminate in a

final decision, they cannot be relied upon as a basis for any legal

right or liability. It has also been held by this Court in Union of India

Vs. Airwide Express Cargo (supra), relied upon by the Petitioner-

Respondent that inter-departmental notings have no legal effect

unless communicated to the other party. This Court set aside the

Arbitral Award, which relied upon such uncommunicated notings,

observing that internal discussions cannot alter Contract terms or

bind parties unless formally conveyed.

57. The Arbitral Tribunal has erroneously relied on such

internal notings to make the Petitioner-Respondent liable for royalty

payment. This constitutes a gross error in law and failure to apply

settled legal principles. The minutes of the meetings of the Tender

Committee records a speculative understanding of the Tender

Jt-CARBP-641&646-2021.doc

Committee as to what the bid of the Respondent-Claimant

constituted and how they have factored royalty. This is not a decision

of the Petitioner-Respondent to treat royalty as Nil for this project. It

is pertinent to note that the minutes of the Tender Committee

meeting is dated 28th August 2017 and it is only thereafter, that the

parties entered into the said Contract on 5th December 2017.

Therefore, the minutes of the Tender Committee meeting at best

were pre-Contract negotiations which cannot supersede the final

written document.

58. The minutes of the Tender Committee meeting does not

make the Petitioner-Respondent liable for the royalty. The said

minutes would show that the parties contemplated that bid of the

Respondent-Claimant did not provide for any amount of the royalty.

However, the parties still agreed that any royalty payable will be

borne by the Respondent-Claimant.

59. The judgment relied upon by the Respondent-Claimant

in Subodh Kumar Singh Rathour (supra) in support of their

submission that official records can be looked into by the Arbitrator

for the purpose of finding the real intention of the parties is

Jt-CARBP-641&646-2021.doc

distinguishable on facts. In that case, there was a challenge to a

Tender cancellation based on alleged mala fides, where internal

notings were examined to ascertain intent in the present case, the

reliance on internal notings as a substantive basis for imposing

liability, is impermissible.

60. Presuming that the Arbitral Tribunal could have relied

upon the minutes of the Tender Committee meeting, which suggested

that the parties contemplated that royalty is not payable on ordinary

earth, it does not in any manner affect the interpretation of the

Contract or make the Petitioner-Respondent liable for royalty. The

said Contract between the Petitioner-Respondent and Respondent-

Claimant overrides and supersedes any prior or collateral

correspondence, minutes or opinions, unless they are incorporated

into the Contract. It is well settled that once the parties have reduced

their understanding into a written agreement, the said agreement

becomes conclusive of their intentions. The said Contract clearly and

unambiguously provides that the Respondent-Claimant is liable to

bear or to pay the royalty.

Jt-CARBP-641&646-2021.doc

61. Another fact which the Arbitral Tribunal ought to have

considered is that at no point of time was the Contract rectified,

modified or novated by mutual consent. The terms of the Contract

remain valid, binding, and enforceable and the parties had acted

upon the same during the performance of their obligations. Clause

1.11 of the SCC, clearly defines what constitutes the "Contract" and

governs the rights and obligations of the parties. Thus, the reliance

on the minutes of the Tender Committee meeting by the Arbitral

Tribunal is untenable and de hors of the Contract. The Arbitral

Tribunal having failed to confine itself to interpretation of the

binding Contract would render the said Award liable to be set aside

on this ground itself.

62. The bid documents which conclude standardized Tender

document incorporating the General Conditions of Contract, Special

Conditions of Contract and related specifications were made

available to all bidders. The Respondent-Claimant at the time of

participating in the bid had full opportunity to examine their terms. If

the Respondent-Claimant was under impression that no royalty

would be payable, they ought not to have participated. The onus was

on the Respondent-Claimant in the event, assuming that negotiated /

Jt-CARBP-641&646-2021.doc

modified royalty payment clause were permissible, to seek

clarification or modification of the tender terms. On the contrary, the

Respondent-Claimant submitted its bid unconditionally, accepting

the terms including those that placed an unconditional liability for

royalty on the Contractor. Further, had the royalty amount be

factored in the bid amount, then the Respondent-Claimant would not

have emerged the L1 bidder. Having accepted the Contract as it

stands and being the successful bidder, the Respondent-Claimant

cannot be permitted to revise the bid amount. The Arbitral Tribunal

by arriving at a finding de hors the terms of the Contract, has created

a parallel negotiation after Contract finalization, which defeats the

very purpose of tendering.

63. This Court is mindful of the fact that judicial interference

with Arbitral Awards under Section 34 of the Arbitration Act is

limited. However, where the Arbitral Tribunal departs from the terms

of the Contract or acts beyond its jurisdiction by making a new

Contract of the parties, such interference is not only be permissible

but necessary. The Supreme Court in Associate Builders Vs. Delhi

Development Authority13 laid down that an Award would be liable to

13 (2015) 3 SCC 49

Jt-CARBP-641&646-2021.doc

be set aside under Section 34, if it suffers from patent illegality,

including contravention of substantive provisions of law; ignoring

binding judicial precedents; or misconstruction of the terms of the

Contract. The present case is one such case where the Award is liable

to be set aside under Section 34 of the Arbitration Act, as it suffers

from patent illegality.

64. The Arbitral Tribunal has in the present case improperly

invoked Section 26 of the Specific Relief Act, 1963 by effectively

rewriting the Contract, despite the absence of any pleading, prayer or

issues framed to that effect. Section 26 requires specific prayer for

rectification of a written instrument supported by clear averments or

pleadings. It is settled law that rectification of the Contract cannot be

granted in the absence of a foundational plea and/or prayer. The

Arbitral Tribunal has by rewriting the Contractual terms by invoking

Section 26, has not only violated the procedural safeguards under the

statute, but also offended the fundamental policy of Indian law,

which requires adjudicatory bodies to remain within the scope of the

dispute as framed by the parties.

65. I do not find any merit in the submission on behalf of the

Jt-CARBP-641&646-2021.doc

Respondent-Claimant that the Arbitral Tribunal has not re-written

the Contract, but has merely in Clause 20 of the said Award provided

an option for the Petitioner-Respondent to modify / amend the

Contract with the Respondent-Claimant to reflect the purported

consensus ad idem, if needed. This cannot be considered as an option

as it would require the re-writing of the Contract. Further, the finding

of the Arbitral Tribunal that the Petitioner-Respondent is liable for

the royalty payment inspite of the terms of the Contract providing

otherwise, is perverse.

66. It has been held by the Supreme Court in Nabha Power

Ltd. Vs. Punjab State Power Corporation Limited 14 that in the absence

of ambiguity, an Arbitrator must strictly enforce the terms of the

Contract and cannot introduce terms on the basis of business efficacy

unless the rigorous test is satisfied. The Supreme Court accordingly,

formulated the "Penta Test" for identifying implied Contractual

terms. The Supreme Court in Food Corporation of India Vs. Chandu

Construction15 has held that the Arbitrator cannot travel beyond the

express terms of the Contract and that doing so constitutes

14 (2018) 11 SCC 508 15 (2007) 10 SCC 697

Jt-CARBP-641&646-2021.doc

misconduct and jurisdiction overreach. It reaffirmed that an Arbitral

Award which ignores or contradicts binding Contractual provisions

cannot be sustained under law.

67. I find that there is no waiver of the Petitioner-

Respondent's rights in the arbitral proceedings. The Petitioner-

Respondent's have not waived their legal objections to the Arbitral

Tribunal's reliance on certain documents produced by the Petitioner-

Respondent in compliance with the directions of the Arbitral

Tribunal. These documents in question, being internal notings, inter-

departmental correspondence, etc. fall within the category, not

susceptible to the evidentiary reliance. The Petitioner-Respondent

adhering to the Tribunal's direction to produce these documents

cannot be construed as a conscious relinquishment or abandonment

of their substantive legal right to object to the admissibility or

evidentiary value of such documents. It is well settled that waiver in

law, requires a clear and unequivocal intent to forgo a known right;

mere compliance with the judicial or quasi-judicial directive does not

meet this standard. The embargo on the use of such documents is not

merely a private right of the party to assert or waive, but a limitation

imposed upon the Adjudicating Authority itself. The Tribunal is

Jt-CARBP-641&646-2021.doc

precluded by law by relying upon documents such as internal notings

and communications even if they are inadvertently or compliantly

placed on record.

68. Accordingly, the said Award is liable to be set aside on

the valid grounds raised in the present Petition under Section 34 of

the Arbitration Act. The said Award suffers from "patent illegality"

and offends the fundamental policy of the Indian law.

69. Commercial Arbitration Petition No. 646 of 2021 is

accordingly allowed and the said Award impugned therein is quashed

and set aside.

70. The Commercial Arbitration Petition No. 641 of 2021

which challenges an identical Award as that challenged in

Commercial Arbitration Petition No. 646 of 2021 is also allowed. The

said Award impugned therein is also set aside.

71. The Commercial Arbitration Petitions are accordingly

disposed of. There shall be no order as to costs.

Jt-CARBP-641&646-2021.doc

72. All pending Interim Applications, if any in the

Commercial Arbitration Petitions, do not survive and are accordingly

disposed of.

[R.I. CHAGLA J.]

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter