Tuesday, 21, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Leaf Bio-Tech Pvt. Ltd. vs Thane Municipal Corporation
2025 Latest Caselaw 7050 Bom

Citation : 2025 Latest Caselaw 7050 Bom
Judgement Date : 3 November, 2025

Bombay High Court

M/S. Leaf Bio-Tech Pvt. Ltd. vs Thane Municipal Corporation on 3 November, 2025

2025:BHC-AS:46533

                                                                        ARA.46.2015.doc


                                    IN THE HIGH COURT OF JUDICATURE AT BOMBAY

                                                CIVIL APPELLATE JURISDICTION

                                             ARBITRATION APPEAL NO.46 OF 2015

                     M/s Leaf Bio-Tech Pvt. Ltd.                                   ....Appellant
                          Versus
                     Thane Municipal Corporation & Ors.                           ....Respondents

                           Mr. Arif Bookwala, Senior Advocate a/w. Mr. Chirag Chanani,
                           Mr. Chaitanya Bhandarkar, Mr. Sachet Makhija & Ms Mihika
                           Joshi i/b Dhruv Pathak, Advocates for the Appellant.
                           Mr. R.S. Apte, Senior Advocate i/b Mandar Limaye, Advocate
                           for Respondent No.1.
                           Mr. Prakash Panjabi i/b. Prakash Panjabi, Advocate for
                           Respondent No.2.


                                         CORAM            : SOMASEKHAR SUNDARESAN, J.

                                         Reserved on     : APRIL 4, 2025

                                         Pronounced on : NOVEMBER 3, 2025

                     JUDGEMENT :

Context and Factual Background:

1. This is an appeal filed under Section 37 of the Arbitration and

Conciliation Act, 1996 ("the Act") against a judgment dated June 26,

2015 passed by the Principal District Judge, Thane (" Impugned

Judgment") which has set aside an arbitral award dated August 8, 2005

("Arbitral Award").

Digitally signed by AARTI AARTI GAJANAN

PALKAR Date:

        2025.11.03                                       NOVEMBER 3, 2025
        15:43:42
        +0530        Aarti Palkar





                                                    ARA.46.2015.doc


2. The Arbitral Award had ruled in favour of the Appellant, Leaf

Bio-Tech Pvt. Ltd. ("Leaf Biotech") and against the Respondent No.1,

Thane Municipal Corporation ("TMC"). The Impugned Judgment has

set aside the Arbitral Award on the premise that it is perverse and in

conflict with public policy of India on the ground that the interest rate

is too high; that TMC's counter-claim has not been adjudicated; and

that the Learned Arbitral Tribunal sought a certain clarification from a

chartered accountant behind the back of both parties.

3. The disputes and differences between the parties relate to a

Memorandum of Understanding dated December 20, 1995

("Agreement") by which TMC agreed to provide solid waste generated

in Thane to Leaf Biotech for waste treatment and processing to enable

Leaf Biotech to manufacture bio-organic manure and a lease deed

dated March 29, 1996 ("Lease Deed") by which an area of 36,501

square metres was leased to Leaf Biotech for a period of 29 years, to set

up a waste management and treatment plant to manufacture such

manure.

4. It is common ground that Leaf Biotech invested in setting up the

plant, took loans, from SICOM Ltd. (" SICOM"), Jankalyan Sahakari

Bank Ltd. and other lenders, and commissioned the plant by May 1998.

The project had policy and financing support from the Central

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

Government. TMC supplied garbage until May 1999 and then stopped

supply ostensibly on the ground that there was a public outcry about

foul odour from the plant; non-maintenance of hygiene by Leaf

Biotech; default in creating a green belt around the plant; and

obstruction by the public in delivery of garbage to Leaf Biotech's plant.

5. It is noteworthy that Writ Petition No. 6575 of 1995 had been

filed in this Court asking for relocation or repair of TMC's own Sewage

Treatment Plant in the region. Writ Petition No. 2472 of 1999, in the

form of Public Interest Litigation was also filed in this Court seeking

relocation of Leaf Biotech's plant on the premise of foul odour and

health hazards attributed to Leaf Biotech's plant.

6. The two Writ Petitions led to the formation of the 'Almitra

Committee' which closely examined the matter and returned firm

findings in a report dated March 28, 2000 (" Committee Report") about

the cause of the odour and hygiene conditions after also conducting a

study of daily handling of garbage by Leaf Biotech over a three-month

period. The Committee Report is said to have found that it was TMC

and its Sewage Treatment Plant that was responsible owing to

breakdown in its handling of sewage pipes that were being dumped into

open and stagnant sewage wells, which passed through broken

pipelines into salt pans and the sea. The Committee Report found no

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

basis to implicate Leaf Biotech's compost plant as the source of odour

of health issues in the neighbourhood and indicated that there was no

cause to close that plant.

7. Both the Writ Petitions were disposed of by a Learned Division

Bench of this Court by an order dated July 27, 2000 (" PIL Judgment").

TMC accepted the findings of the Committee Report and also filed an

affidavit to confirm to this Court that it had undertaken repairs to its

Sewage Treatment Plant. TMC also committed to undertake remedial

measures to resolve the findings against it about its handling of sewage

and its Sewage Treatment Plant. This was the basis of the PIL

Judgment, disposing of the Writ Petitions on the premise that they had

served their purpose.

8. However, despite the PIL Judgment and the findings in the

Committee Report, TMC did not resume supply of garbage as

contracted in the Agreement. Arbitration was invoked and the TMC's

own Commissioner came to be appointed as the Sole Arbitrator as per

the Agreement between the parties. After a while, the TMC

Commissioner recused from the arbitration on the premise that he

could not play this role dispassionately. This led to a Section 11

Application being filed and a former Judge of this Court being

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

appointed as the Learned Sole Arbitrator to adjudicate the disputes in

the matter.

Arbitral Award:

9. The Learned Arbitral Tribunal was presented with a claim by

Leaf Biotech for award of damages measured by loss of profits and

borrowing costs. TMC filed a counter-claim alleging breaches by Leaf

Biotech in complying with the terms on which the Agreement was

executed, and also defending its refusal to supply garbage by

attributing it to public outcry and obstruction of vehicles that were

meant to supply the solid waste to Leaf Biotech's facility. TMC claimed

that because of Leaf Biotech's breaches of the Agreement, TMC was

now forced to dump garbage at two other distant locations - Mumbra,

22 KM away and Balkum, 5 KM away. This was costing the TMC Rs. 9o

lakhs per annum, and it was contended that Leaf Biotech must

compensate the TMC.

10. The Learned Arbitral Tribunal framed two issues on each claim

to figure if Leaf Biotech proves that TMC had breached the Agreement,

and if so, whether compensation was due and in what amount.

Likewise, the Learned Arbitral Tribunal also framed an identical set of

two issues about the counter-claim i.e. whether TMC proves that Leaf

Biotech was in breach, and if so, whether compensation was due and in

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

what amount. After examining facts, the Learned Arbitral Tribunal

again reduced it to a dual issue, namely, which party is responsible for

breach of contract; and what is the compensation to be paid to the

other party.

11. The Learned Arbitral Tribunal has conducted an extensive review

of the material on record, the evidence led by the parties and returned

its findings. Witnesses presented by Leaf Biotech included its own

executive, executives of Excel Industries Ltd., a company that had

committed to purchase the manure manufactured by Leaf Biotech at a

firm price for a year; and officials of lenders who had lent funds to Leaf

Biotech to enable assessment of the damages claimed. The TMC

presented an officer who had taken up his role ten months after the

cessation of supply of garbage by TMC, and multiple residents living in

the locality to prove the facts pleaded about the local situation on the

ground.

12. The Learned Arbitral Tribunal extensively examined the material

presented, including the Committee Report, the PIL Judgment, the

pleadings and proceedings in the Writ Petitions, the examination and

cross examination of the witnesses presented, data on the cost of

borrowing, the computation of loss of profits and discounted net

present value of future earnings. The Learned Arbitral Tribunal has

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

evidently returned findings that Leaf Biotech was not to blame for any

breach and there was no reason for TMC not to resume supplying

garbage to Leaf Biotech after the PIL Judgment. The Learned Arbitral

Tribunal examined TMC's own affidavits in the Writ Petitions,

confirming that Leaf Biotech was not responsible. The Learned

Arbitral Tribunal found that with the PIL Judgment, the issues on facts

had attained finality and TMC ought to have resumed supply of garbage

to Leaf Biotech's plant as contracted.

13. The Learned Arbitral Tribunal awarded a sum of Rs. 12.67 crores

as compensation payable by TMC, being an aggregate sum of Rs. 8

crores towards loss of profit between May 1998 and March 2004; penal

interest due to the lenders at Rs. 4.40 crores and Rs. 23 lakhs as the net

present value of future net profits. Pendente lite interest was awarded

at 9% per annum from November 18, 2003. Post-award interest had

been awarded at 18% per annum upon the expiry of a month from the

date of the Arbitral Award.

Impugned Judgement:

14. The Impugned Judgement returns a strange outcome. The

Learned Judge evidently agonised over the parties not being able to

settle their disputes by agreeing to a lower post-award interest rate, and

chose to simply set aside the Arbitral Award as being perverse.

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

15. It may be mentioned that a predecessor of the Learned Judge

had passed an order dated July 17, 2009, setting aside the Arbitral

Award on the sole ground that the matter needed to be remanded for

adjudicating the counter-claim afresh. Both TMC and Leaf Biotech had

challenged that outcome before this Court. By an order dated March 19,

2010, a Learned Single Judge of this Court remanded the Section 34

file back to the District Court for consideration afresh, leaving

contentions of both sides open.

16. On remand, on August 14, 2014, the Learned Judge nudged the

parties to settle their disputes by negotiating on an interest rate to

replace the post-award interest rate of 18% per annum. The parties

were directed to present themselves to the TMC Commissioner for this

purpose. Evidently, that failed and the matter was taken up again by

the Learned Judge.

17. The Section 34 Court noticed the scope of Section 34 of the Act at

the threshold and summarised the law in McDermott1. The Learned

Judge noticed the three grounds of challenge - interest rate being too

high; a clarification being sought from the chartered accountant

witness behind the back of the parties; and that the powers of TMC as a

corporation override the powers of its Commissioner. TMC had also

McDermott International Inc. vs. Burn Standard Co. Ltd. & Ors - (2006) 11 SCC

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

contended that despite the Learned Arbitral Tribunal noticing the

counter-claim it had been neither granted nor refused.

18. Leaf Biotech pointed out that TMC had not even purported to

terminate the Agreement and the Lease Deed. Resolutions of the

Standing Committee that bind the TMC were alluded to. It was

contended that TMC was seeking to re-argue the matter in the Section

34 proceedings.

19. The Impugned Judgment simply holds that the Arbitral Award is

perverse and against public policy, in a summary conclusion in

Paragraph 23 of the Impugned Judgment. The three summary

findings are:-

a) Interest at the rate of 18% per annum "is definitely against the public policy in India" because rate of interest is not 12% per annum "even in housing loans etc.";

b) The Arbitral Award is "perverse because it has not dealt with the counter claim" of the TMC;

c) The Learned Arbitral Tribunal has not followed the mandatory provisions of Section 24(3) of the Act because the Learned Arbitral Tribunal had sought a clarification, without informing either side about having sought such clarification, on discounting of future earnings from a Chartered Accountant witness.

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

20. The Arbitral Award having been set aside, this Appeal has been

filed.

Analysis and Findings:

21. I have heard Mr. Arif Bookwala, Learned Senior Advocate on

behalf of Leaf Biotech and Mr. R.S. Apte, Learned Senior Advocate on

behalf of TMC at length on their contentions. With the assistance of

their verbal submissions as well as written notes on arguments, I have

examined the material on record.

22. I find that the Learned Arbitral Tribunal has returned a clear,

articulate and detailed set of findings in the Arbitral Award. The

Learned Arbitral Tribunal has squarely dealt with all the issues posed

by both parties before the Learned Arbitral Tribunal, and has

considered who was in breach of the Agreement. The Learned Arbitral

has analysed in detail, the pleadings in the two Writ Petitions, the

findings of Committee Report, the acceptance of the Committee Report

by TMC, the commitment to implement it fully, and the eventual

disposal by the PIL Judgment.

Interest Rate not Against Public Policy:

23. I find that the Section 34 Court's summary rejection of interest at

18% is an arbitrary one and not informed by any empirical method or

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

basis. Worse, the Impugned Judgment inexplicably alludes to interest

rate for home loans when seized of a matter involving interest rate

contracted for an industrial facility. There is no basis to contend that

nationalised banks do not charge interest at the rate of 18%. There is

not a whisper of comparison of this interest rate with the interest rate

contracted by Leaf Biotech with its lenders.

24. The Learned Judge could have taken judicial notice of interest

rate that was applicable to prime clients in 1999. He could have called

upon the parties to submit on oath the empirical basis for their

objection or support to the interest rate. It is a matter of public record

that the prime lending rate of interest of the State Bank of India in 1999

(the period in which the breach of the Agreement took place) was in the

region of 14%2. By the time the Impugned Judgment was passed, the

publicly published prime lending rate of the State Bank of India was

even higher at 14.45%. A "prime lending rate" is the interest rate given

to the most creditworthy borrower with minimal scope for default

owing to business failure or wilful default. Other borrowers are

charged a mark-up over the prime lending rate depending on their

credit rating. Lower the creditworthiness, higher the interest rate

applicable.

https://sbi.bank.in/web/interest-rates/interest-rates/benchmark-prime-lending-rate- historical-data

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

25. Tere is no material on record to have enabled the Learned Judge

to come to a conclusion that an interest rate of 18% is " definitely"

against public policy of India. Public sources of interest rate charged

to the most creditworthy borrowers in fact indicates that a borrower

such as Leaf Biotech, whose creditworthiness is dependent on a

counterparty such as TMC honouring its obligations, would be even

higher and that is not far from the rate awarded by the Learned Arbitral

Tribunal. All that the Section 34 Court could have done is examine

from the material on record if the exercise of discretion by the Learned

Arbitral Tribunal has been so disconnected to reality that it is perverse.

What the Section 34 Court must not do is bring to bear its own notions

of what is an appropriate interest rate, instead of testing the exercise of

discretion by the Learned Arbitral Tribunal.

26. The Act empowers the Learned Arbitral Tribunal to grant post-

award interest rate. The Learned Arbitral Tribunal is entitled to take a

view that a slightly higher interest rate would be a deterrent to non-

compliance with the Arbitral Award.

27. An examination of the record and the clearly plausible findings,

which are well supported by reasons, would show that the Learned

Arbitral Tribunal had squarely held that TMC was in breach and Leaf

Biotech was not in breach. Therefore, in the absence of any articulated

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

reasons to interfere with the Arbitral Award, and on account of the

Section 34 Court having arbitrarily brought to bear its own notions of

pricing in the money market, the first ground on which the Arbitral

Award was interfered with cannot pass muster.

28. The Section 34 Court's scope of review is consciously limited by

Parliament to avoid precisely this type of substitution and replacement

of an arbitral tribunal's view with the Court's view.

Counter-Claim Squarely Rejected:

29. This brings me to the issue of whether the counter-claim has not

been dealt with. The Section 34 Court summarily agrees with TMC. I

am unable to agree with the Impugned Judgment on this count too.

30. The Learned Arbitral Tribunal has noticed that there was no

reason for TMC not to supply garbage to Leaf Biotech after the PIL

Judgment. To my mind, the contention that the counter-claim has not

been ruled on is untenable and a distraction from the core content of

the Arbitral Award. The unquantified counter-claim raised the

contention that it was Leaf Biotech that had not complied with the

Agreement. This was squarely answered by reference to the material

on record including the Committee Report, with a finding that Lear

Biotech had not breached the Agreement, and that it was the TMC that

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

was in breach. As regards not creating a green belt around the plant,

the Learned Arbitral Tribunal directed a site visit in consultation with

both parties. The Learned Arbitral Tribunal has also returned firm

findings that the site was covered on three sides by the sea and on the

land-side Leaf Biotech had created a green belt.

31. The Learned Arbitral Tribunal also found that the Mulund dump

yard was also in proximity. It was found that TMC alone was

responsible (as found in the Committee Report) for the odour and lack

of hygiene near the plant owing to faults in TMC's Sewage Treatment

Plant. The Committee Report's clean chit to Leaf Biotech's compost

plant has been specifically alluded to and analysed. It is inexplicable

that TMC could keep contending that the counter-claim was not dealt

with. Once it is explicitly held that Leaf Biotech had not breached the

Agreement and that it was TMC that had breached the Agreement, it

can never be contended that the counter-claim had not been dealt with.

32. It is clear as daylight to me that TMC's counter-claim was

squarely rejected. The Section 34 Court is meant to examine the record

and see if a just outcome in an arbitral award could even be supported

by reasons that are not expressly set out but are necessarily implied.

The Impugned Judgment falls woefully short of this standard. It is

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

impossible to hold that TMC's counter-claim was not considered or

ruled on.

33. The allusion to the land leased to Leaf Biotech having been at a

discounted rate is also of no avail. TMC, in its wisdom agreed that it

would supply garbage to Leaf Biotech. This would have benefited TMC

by finding a firm manner of waste disposal, contribute to production of

manure, and earn royalty on the sales made (the first year's sales had

an assured offtake from Excel Industries). Bearing all this in mind, it

was TMC's conscious commercial decision to supply the waste and

provide the land on lease to build the plant on. The violative non-

supply of waste brought everything to a grinding halt. The findings of

the Learned Arbitral Tribunal that TMC alone was responsible for

breaching the Agreement would necessarily mean that the loss of lease

rental and royalty suffered by TMC is attributable to TMC's own

default. On the other hand, there is nothing to suggest that Leaf

Biotech has benefitted from the use of the land. TMC did not even

quantify the counter-claim in this regard.

34. Therefore, I am not at all satisfied that the counter-claim is not

considered. TMC's contention that Leaf Biotech has benefited from

cheap land also does not change the analysis. The stoppage of supply of

garbage by TMC for reasons best known to TMC, despite Leaf Biotech's

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

plant getting a clean chit, does not call for any compensation. The

Learned Arbitral Tribunal has even examined evidence to see if there

was any physical obstruction and blockage by local residents to the

vehicles and found that there was none. The witnesses brought to bear

by TMC also have been examined and their evidence did not point to

any physical obstruction to TMC.

35. Once the Learned Arbitral Tribunal held that there was no reason

for TMC to not resume supply of garbage to Leaf Biotech, it would

follow that the expenditure for transporting garbage to the two other

distant locations was of TMC's own doing. There was evidently no case

for considering such costs needlessly being incurred and visiting it

upon Leaf Biotech.

36. It was not necessary for the Learned Arbitral Tribunal to have

specially written a separate heading titled "counter-claim" and to have

specifically written a few more paragraphs to formally state that the

counter-claim stood rejected. The analysis contained in the Arbitral

Award leaves no manner of doubt that the Learned Arbitral Tribunal

ruled with reasons that the counter-claim stood rejected.

37. In Paragraph 179, the Learned Arbitral Tribunal has pointed out

that the issues involved required the Learned Arbitral Tribunal to

answer which party is responsible for the breach of contract and what is

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

the compensation to be paid to which aggrieved party. In Paragraph

180 of the Arbitral Award this is explicitly answered by stating that it is

the TMC that committed the breach of contract and is liable to

compensate Leaf Biotech for loss of profit and damages.

38. Therefore, on this count too, the Learned Arbitral Tribunal's

findings could not have been lightly disturbed. The Impugned

Judgement's finding that the counterclaim has not been dealt with, is

untenable and without any articulated rationale.

Private Clarification from Witness:

39. This is a serious allegation. I have examined what the Learned

Arbitral Tribunal has actually done. The upshot of TMC's contention is

that the Learned Arbitral Tribunal has violated principles of natural

justice and has gone behind the back of a party to collect evidence. This

is a strong allegation and if right, would undermine the Arbitral Award.

Leaf Biotech confirms that the Learned Arbitral Tribunal sought a

clarification of its own accord directly from the witness and even Leaf

Biotech was not aware of this request, and that there was nothing

selective about leaving out TMC. Be that as it may, the witness from

whom the clarification was sought was the witness whose evidence was

led by Leaf Biotech, which evidence was fully available to both parties

when it was led.

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

40. Section 24(3) of the Act, which is invoked by TMC reads thus:

(3) All statements, documents or other information supplied to, or applications made to the arbitral tribunal by one party shall be communicated to the other party, and any expert report or evidentiary document on which the arbitral tribunal may rely in making its decision shall be communicated to the parties.

[Emphasis Supplied]

41. Section 24(3) of the Act makes it incumbent on any party that

supplies statements, documents or other information to the Learned

Arbitral Tribunal, to also supply the same to the other party. The said

provision also requires the Learned Arbitral Tribunal to communicate

to the parties, any expert report that it may rely upon to make its

decision.

42. Therefore, it is vital to examine if there is anything in the

exchange that took place between the Learned Arbitral Tribunal and

the Chartered Accountant that constitutes an expert report or

evidentiary document that the Learned Arbitral Tribunal relied on,

without communicating it to the parties. It became necessary to put

this facet of the matter under a microscope and examine it very closely.

43. It is found that on June 16, 2005, the Learned Arbitral Tribunal

wrote to Mr. Dinesh Kelkar, the Chartered Accountant who had led

evidence on the net present value of future earnings to ask him what he

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

meant by "discounting future earnings @ 33% ". The Learned Arbitral

Tribunal wrote this:

"While I appreciate that as Chartered Accountant you must have applied some methodology, but as a non-accounting person, I am not satisfied with the answer and would like you to clarify about the calculation @ 33% made by you for discounting future profits.

Hence my following queries :

(1) Please explain the calculation of the net profit per year after adjusting the cost of manure per MT and royalty payable to TMC without finance charges ?

(2) The method of discounting @ 33% for obtaining the net present value of the future earnings and the basis of any authentic document which is used by Chartered Accountants ?

[Emphasis Supplied]

44. The letter from the Learned Arbitral Tribunal to the Chartered

Accountant is essentially a question from a judicial person who is not

proficient with financial literacy, seeking clarification about the method

adopted for discounting future profits; and how net profit without

finance charges is computed. Ideally, this could have been asked by

the Learned Arbitral Tribunal, keeping both sides copied on the

correspondence. One has to see if not doing so, in the specific fact

situation at hand, vitiates the Arbitral Award and makes it perverse to

the point of having to set it aside.

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

45. When one sees the reply of the Chartered Accountant it becomes

clear that he provided no new evidence to the Learned Arbitral

Tribunal. I have carefully compared his reply with the original affidavit

filed by him in August 2004. He has set out the very same data that he

had already given in evidence, and set out the manner of computation

made by him.

46. The Chartered Accountant indicated that he had arrived at the

aggregate sum of the equity capital, the secured debt, unsecured debt

and the grant received from Government of India, adding up to Rs.

4.70 crores to treat this sum as the "capital employed". He has also

shown how he arrived at the returns capable of being earned by

adopting the sale value of Rs. 1,700 per metric tonne of organic manure

contracted with Excel Industries, reduced by the royalty of 2% payable

to TMC, further reduced by the operating cost per metric tonne of

organic manure, leading to the net profit per metric tonne of Rs.

797.85. The total manure to be produced if 300 metric tonnes of

garbage had been supplied by TMC as contracted, led to a quantum of

19,710 metric tonnes and this was multiplied by the net profit per

metric tonne to arrive at Rs. ~1.57 crores of annual profit. This amount

of Rs. 1.57 crores on the capital employed at Rs. 4.7 crores led to a 33%

rate of earning. There is nothing new in this data when compared with

the original affidavit filed by the Chartered Accountant.

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

47. The Chartered Accountant explained that this 33% rate was

applied from the seventh year to the 29th year. He enclosed a sample of

a ready table published by Sukh Sagar Institute (CA training institute)

and academic literature published by the Institute of Chartered

Accountants of India, explaining what "net present value" means and

how like a ready reckoner, this is a standard table depicting the net

present value on the basis of length of time and percentage of

discounting.

48. Having carefully examined the reply of the Chartered Accountant

to the letter dated June 16, 2005 with the affidavit filed earlier by the

Chartered Accountant in August 2004, I have found that there is

nothing new or substantive in the reply from the Chartered Accountant.

The figures used are the same. His calculation of 54 metric tonnes per

day of manure manufacture based on supply of 300 metric tonnes of

garbage per day set out in his affidavit, precisely and exactly conforms

to his reply to the Learned Arbitral Tribunal, which on an annualised

basis, adds up to 19,710 metric tonnes of organic manure per annum.

49. The discounting of 33% is nothing but an explanation of how

future earnings are to be valued today. There is no new evidence in this

reply of the Chartered Accountant. The reply given by him would have

been obvious to any financial analyst that anyone could engage.

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

Indeed, the Learned Arbitral Tribunal could have copied the query sent

to the witness, to both the parties for their information. The letter does

not appear to have been copied to them. However, I have given my

anxious consideration if there has been any miscarriage of justice, or

breach of natural justice principles, or any prejudice caused to any

party, since that would be a ground to set aside the Arbitral Award as

being opposed to the fundamental policy of the law of India. I have also

examined if the principle of justice or morality stand vitiated in the

process.

50. While the Learned Arbitral Tribunal indeed erred in not copying

both parties, going by the content and the context of the exchange

between them, the Learned Arbitral Tribunal has not blundered or

committed an act that would render the Arbitral Award perverse. I am

satisfied that owing to the information covered in both - the affidavit

and the later letter - is the same, no new evidence came to be collected

through this exercise. Therefore, I am satisfied that the facet of fairness

and natural justice compliance has not been undermined.

51. The approach ought to have been of copying both parties, but

that not having been done, upon the aforesaid examination, I am

convinced that no prejudice has been caused. Therefore, instead of

throwing out the baby with the bathwater, being satisfied that there is

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

nothing new in the explanation given by the Chartered Accountant, I

am not satisfied that a case has been made out to take the extreme step

of setting aside the Arbitral Award. To do that, one would need to hold

that evidence has been collected behind the back of a party to the

proceedings. Such an approach would be disproportionate and

inappropriate.

52. Just as expert arbitrators in the fields of engineering and finance

are to be treated from a different prism on matters of law, in the

peculiar development in this case, the outreach by the Learned Arbitral

Tribunal not conversant with financial metrics, to get an explanation is

understandable and attributable to the absence of financial literacy and

discomfort with numbers that many lawyers and judges routinely

profess.

53. In listing this as one of the three grounds to set aside the Arbitral

Award, the Impugned Judgment contains no discussion of the issue

and the facts involved. It has simplistically, again summarily, indicated

that the Arbitral Award is perverse on this count. Therefore, I have

gone a step further to examine if there has been any remote damage to

the dispensation of justice or dent to the integrity of the process, and

upon a careful examination, I am satisfied that there has not been any

such subversion of justice.

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

54. I have also noticed that the computations made by the Chartered

Accountant was also dependent on the computations provided by Excel

Industries Ltd to which too, there had been no addition or

modification. There was no scope to really provide anything new. In

any case, nothing new came about from this exchange. All this financial

information was an integral part of the record and the Learned Arbitral

Tribunal found that the TMC did not attack this analysis in its cross

examination in any material manner.

55. On a completely separate note (not that it would address the

Learned Arbitral Tribunal not writing to the parties and directly asking

a witness to clarify), it is also noteworthy that after this

correspondence, the Learned Arbitral Tribunal has reduced the amount

claimed and reduced the loss of profit figure from the claimed level of

over Rs. 9 crores to Rs. 8 crores and the future profits from over Rs. 86

lakhs to Rs. 23 lakhs. The Learned Arbitral Tribunal came to a view

that the computation indicate the numbers to be on the higher side.

56. The Learned Arbitral Tribunal also turned in this

correspondence as part of the record of proceedings to the Section 34

Court. There was nothing hidden and this was transparently shared. I

am satisfied that there has been no erosion of the integrity of the

decision-making process and therefore, in this peculiar situation, I am

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

not inclined to set the parties back to square one on this count and wipe

out the work that has gone into the matter over the past two and half

decades.

57. I must hasten to add that the inconvenience of setting aside an

arbitral award is not at all a determinative factor of whether it should

be set aside. On the facts of the case, it would be unnecessary to set

aside the Arbitral Award for the reasons set out above, and doing so

would lead to an unfair travesty of wiping out all the work done in the

matter, when my finding is that the clarification sought did not lead to

any subversion of the process of evidence collection.

58. Therefore, I am of the view that this ground too is not adequate

to interfere with the Arbitral Award. The Section 34 Court ought not to

have lightly interfered with the Arbitral Award.

Scope of Review by the Section 37 Court:

59. Overall, on each of the aforesaid issues, the following extract

from Konkan Railway3, in which the Supreme Court has articulated the

approach that ought to be adopted by the Section 37 Court, is

noteworthy:

Analysis:

Konkan Railway Corporation Limited v. Chenab Bridge Project Undertaking - (2023) 9 SCC 85

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

18. At the outset, we may state that the jurisdiction of the Court under Section 37 of the Act, as clarified by this Court in MMTC Ltd. v. Vedanta Ltd., is akin to the jurisdiction of the court un-

der Section 34 of the Act. Scope of interference by a court in an ap- peal under Section 37 of the Act, in examining an order, setting aside or refusing to set aside an award, is restricted and subject to the same grounds as the challenge under Section 34 of the Act.

19. Therefore, the scope of jurisdiction under Section 34 and Sec- tion 37 of the Act is not akin to normal appellate jurisdiction. It is well-settled that courts ought not to interfere with the arbitral award in a casual and cavalier manner. The mere possibility of an alternative view on facts or interpretation of the contract does not entitle courts to reverse the findings of the Arbitral Tribunal. In Dyna Technologies Private Limited v. Crompton Greaves Lim- ited (2019) 20 SCC 1, this Court held:

"24. There is no dispute that Section 34 of the Arbitration Act limits a challenge to an award only on the grounds provided therein or as interpreted by various courts. We need to be cognizant of the fact that arbitral awards should not be interfered with in a casual and cavalier manner, unless the court comes to a conclusion that the perversity of the award goes to the root of the matter without there being a possibility of alternative interpretation which may sustain the arbitral award. Section 34 is different in its approach and cannot be equated with a normal appellate jurisdiction. The mandate under Section 34 is to respect the finality of the arbitral award and the party autonomy to get their dispute adjudic- ated by an alternative forum as provided under the law. If the courts were to interfere with the arbitral award in the usual course on factual aspects, then the commercial wisdom be-

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

hind opting for alternate dispute resolution would stand frus- trated.

25. Moreover, umpteen number of judgments of this Court have categorically held that the courts should not interfere with an award merely because an alternative view on facts and interpretation of contract exists. The courts need to be cautious and should defer to the view taken by the Arbitral Tribunal even if the reasoning provided in the award is im- plied unless such award portrays perversity unpardonable under Section 34 of the Arbitration Act."

[Emphasis Supplied]

60. When the Section 37 Court hears an appeal from a judgment

passed under Section 34 of the Act, the scope of the appellate review

under Section 37 of the Act is to see if the Section 34 Court conducted

its review of the Arbitral Award in compliance with the law declared on

how Section 34 should be put to work. The Supreme Court has

repeatedly iterated that Courts must not lightly interfere with arbitral

awards. The scope of review by the Section 34 Court is also well

covered in multiple judgments of the Supreme Court. Even implied

reasons that are discernible and may be inferred to support the just and

fair outcome arrived at in arbitral awards, would be adequate to sustain

the arbitral award. To avoid prolixity, I do not think it necessary to

burden this judgment with quotations from these multiple judgments.

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

61. The Impugned Judgment is not in consonance with the scope

and manner of review and interference set out in the law declared on

how to operate Section 34 of the Act. Therefore, in my opinion, the

Impugned Judgment is unsustainable and deserves to be set aside,

thereby, reviving the Arbitral Award.

62. Before parting with the matter, it is noted that SICOM had been

allowed to intervene in the Section 34 proceedings and is Respondent

No. 2 in this Appeal. SICOM's stance is aligned with that of Leaf

Biotech but what it wants is for the amount awarded to be released

directly to SICOM and not to Leaf Biotech. I am afraid this too is

outside the scope of jurisdiction under Section 34 and Section 37 of the

Act. SICOM is free to pursue such proceedings as available to it in law

to attach the rights to receipt of the proceeds of the Arbitral Award in

appropriate proceedings.

63. The Appeal is allowed in the aforesaid terms. Interim

Applications, if any, pending in the proceedings shall also stand

disposed of in these terms. Should any deposit have been made in the

course of this litigation, the same shall be released to Leaf Biotech

within a week of the expiry of four weeks from the date of upload of this

judgment on this Court's website.

NOVEMBER 3, 2025 Aarti Palkar

ARA.46.2015.doc

64. All actions required to be taken pursuant to this order shall be

taken upon receipt of a downloaded copy as available on this Court's

website.

[SOMASEKHAR SUNDARESAN, J.]

NOVEMBER 3, 2025 Aarti Palkar

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter