Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Wipro Limited vs Maharashtra Airport Development ...
2025 Latest Caselaw 3617 Bom

Citation : 2025 Latest Caselaw 3617 Bom
Judgement Date : 19 August, 2025

Bombay High Court

Wipro Limited vs Maharashtra Airport Development ... on 19 August, 2025

2025:BHC-OS:13803-DB
            Neeta Sawant                                                       WP-395-2025-FC


                    IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                        ORDINARY ORIGINAL CIVIL JURISDICTION

                                   WRIT PETITION NO. 395 OF 2025



            Wipro Limited
            A Company registered under the
            provisions of the Companies Act, 1956,
            having its registered office at Dodda Kannelli,
            Sarjapur Road, Bengaluru -- 560 035.                             ....Petitioner

                           : Versus :


            1. Maharashtra Airport Development
            Company Ltd.
            A Company registered under the
            provisions of the Companies Act, 1956,
            having its régistered office at 12" Floor,
            World Trade Centre, Cuffe Parade,
            Mumbai -- 400 005.



            2. State of Maharashtra
            through Government Pleader,
            High Court, Original Side,
            Bombay -- 400 032.                                      ....Respondents



            Mr. Rahul Narichania, Senior Advocate with Mr. Shubharata
            Chakraborti, Mr. Naozad Golwalla and Mr. Aayush Barat i/b
            Mr. Mehernosh Humranwala, for the Petitioner.
            Mr. Zulfiq Multani with Mr. Manoj Kumar Mishra, for Respondent
            No.1.
            Mr. Atul Vanarse, AGP for Respondent No.2-State.



                                                Page No.1 of 53
                                                19 August 2025
                 ::: Uploaded on - 19/08/2025                     ::: Downloaded on - 19/08/2025 21:31:50 :::
 Neeta Sawant                                                         WP-395-2025-FC


                                    CORAM : ALOK ARADHE, CJ. &
                                                 SANDEEP V. MARNE, J.

                                    Reserved On : 12 August 2025.

                                    Pronounced On : 19 August 2025.


JUDGMENT :

(Per Sandeep V. Marne, J.)

1) Rule. Rule is made returnable forthwith. With the

consent of learned counsel appearing for rival parties, the petition

is taken for final hearing and disposal.

2) Petitioner has filed the present petition in this Court

challenging the communication dated 27 May 2015 issued by

Maharashtra Airport Development Company Limited cancelling

the Letter of Acceptance (LOA) dated 5 April 2007 and forfeiting

the advance amount of Rs. 10.29 crores.

3) Petitioner-Wipro Limited (Wipro) is a global

technology services provider and consulting company. With a

view to remove the regional disparity in the State of Maharashtra,

the State Government decided to develop a composite project

named Multi Modal International Passenger and Cargo Hub

Airport at Nagpur (MIHAN). The aim of the project was to

develop the existing domestic airport at Nagpur into an

international passenger and cargo hub airport along with a Special

19 August 2025

Neeta Sawant WP-395-2025-FC

Economic Zone (SEZ) adjoining the boundary of the airport.

Accordingly, the State Government constituted Maharashtra

Airport Development Company Limited (MADC) for the purpose

of planning, constructing, operating, developing and maintaining

aviation infrastructure in the State of Maharashtra. Respondent

No. 1 is declared as a Special Planning Authority for the notified

area under the provisions of Maharashtra Regional and Town

Planning Act, 1966. MIHAN is the flagship project of Respondent

No. 1, which is undertaken under the provisions of SEZ Act, 2005

and SEZ Rules, 2006. For implementing MIHAN project,

Respondent No. 1 decided to acquire large tract of land near

Nagpur Airport and after developing the same, allotment of such

developed land was planned for setting up inter alia industries.

4) The MIHAN project is proposed to be established in an

area of 3,588 Hectares, out of which area admeasuring 1,100

Hectares has been earmarked as a SEZ. As a part of MIHAN

project, Respondent No. 1 proposed establishment of State of the

Art Multi-tenanted Software Technology Park/Information

Technology Park in the SEZ area and designated land

admeasuring 500 acres for the same. MADC accordingly decided

to involve India's leading software companies such as Wipro,

TATA Consultancy Services, Infosys etc. for establishment of their

offices under the MIHAN project. Accordingly, Wipro was

approached by MADC vide letter dated 20 October 2004 offering

19 August 2025

Neeta Sawant WP-395-2025-FC

land at concessional rate. After Wipro showed interest in the

MIHAN project, a commercial presentation was made by MADC

to Wipro offering land area of approximately 100 acres for

establishment of IT park at the lease rent of Rs.40/- lakh per acre.

After Wipro showed willingness to accept the allotment of land,

MADC earmarked a plot of land admeasuring 107.42 acres and

communicated to Wipro that out of 160.42 acres of land, land

admeasuring 30.24 acres was covered by Zudpi region and land

admeasuring 13 acres was under water channels, leaving about

117 Acres of land for the purpose of development of IT park by

Wipro. Accordingly, Letter of Acceptance dated 5 April 2007 was

issued by MADC to Wipro in respect of land admeasuring 117

acres at the price of Rs.44 lakh per acre on lease basis for the

period of 99 years. The consideration was agreed at Rs.51.48 crores

out of which 20% of the consideration of Rs.10,29,60,000/- was to

be paid in advance and remaining 80% was to be paid at the time

of handing over possession of the land. Accordingly, Wipro paid

20% advance amount of Rs.10,29,60,000/- to MADC on

24 April 2007. Petitioner started paying establishment and

administrative costs every month of Rs.9,103/- to MADC and paid

an amount of Rs.5,26,500/- over the period of time.

5) It is Petitioner's case that the cost estimated for

development of IT Park on the allotted land was to the tune of

Rs.60 crores. Petitioner contends that there was lack of necessary

19 August 2025

Neeta Sawant WP-395-2025-FC

facilities such as approach roads, water supply, telecommunication

network, power supply layout, transportation and efficient and

reliable air connectivity on account of which, Petitioner was not

willing to go ahead with development of the project on the allotted

land. According to the Petitioner, the necessary infrastructural

facilities at MIHAN project were not established as promised.

Petitioner further contends that the allotment was accepted by it

under a bonafide and valid assumption that MADC would provide

the requisite and basic infrastructure for development of the

project. After waiting for some time, Petitioner wrote to MADC to

limit allotment of land to 23 acres proposing to commence

operations within 36-48 months. On 22 February 2013, MADC

responded agreeing to the request to limit the allotment of land to

23 acres, on condition of commencement of operations within 24

months. MADC, thereafter, sent letter dated 3 December 2014,

threatening to terminate LOA and forfeit the part payment. By

letter dated 12 December 2014, Petitioner pointed out absence of

infrastructure for development of the project. On 27 May 2015,

MADC terminated the LOA and forfeited the amount of Rs.10.29

crores paid by the Petitioner.

6) According to the Petitioner, even after termination

letter dated 27 May 2015, MADC once again approached the

Petitioner with an offer for allotment of land admeasuring 23.40

acres. The Petitioner expressed interest in seeking allotment of the

19 August 2025

Neeta Sawant WP-395-2025-FC

land vide letter dated 7 February 2018 and made enquiries.

According to the Petitioner, the dispute remained under

discussions and correspondence, without yielding any positive

result. On 13 September 2024, Petitioner addressed notice to

MADC alleging wrongful termination of LOA and seeking refund

of the amount paid alongwith interest. Petitioner sent one more

notice dated 8 November 2024. On 8 November 2024, MADC

refuted the claim of the Petitioner. In the above factual

background, the present petition is filed by Wipro, challenging the

communication dated 27 May 2015 and seeking refund of the part

payment made, alongwith the interest.

7) Mr. Narichania, the learned Senior Advocate appearing

for the Petitioner, would submit that the MADC has erroneously

forfeited the amount of part payment made by the Petitioner for

allotment of land. That allotment of land could not be accepted by

the Petitioner on account of lack of basic infrastructural facilities.

That the amount of Rs.10.29 crores is not paid towards earnest

money deposit, and the impugned communication itself accepts

that the same is paid towards part consideration. That since the

allotment of land has not taken place, Respondent has no

authority in law to illegally retain the consideration amount. That

the LOA does not contain any stipulation for forfeiture of the part

consideration paid by the Petitioner. That in absence of any

19 August 2025

Neeta Sawant WP-395-2025-FC

forfeiture clause, Petitioner is entitled for refund of the part

consideration.

8) So far as the aspect of delay in filing the petition is

concerned, Mr. Narichania would submit that MADC approached

the Petitioner with an offer for allotment of smaller portion of land

and therefore the Petitioner could not approach this Court

immediately after issuance of the impugned communication. That

MADC was contemplating allotment of smaller piece of land and

adjusting the amount already paid by the Petitioner. That the

matter remained under discussion for a long time and the

Petitioner decided to adopt legal remedies only after realizing that

execution of the project is not viable even on smaller piece of land.

That the Petitioner decided to adopt legal remedies after realizing

that MADC was whiling away time by sitting on part payment

received from the Petitioner. That therefore there is no delay or

laches in filing the present petition. That in any case, Respondent

No. 1, being an Instrumentality of State, cannot be permitted to act

arbitrarily or indulging in unjust enrichment. That Respondent

No. 1 has illegally retained the consideration paid by the

Petitioner, even though no allotment of land has actually taken

place. That there is no question of delay, as MADC never had the

entire land admeasuring 117 acres for allotment to the Petitioner.

That Affidavit-in-Reply indicates that the land admeasuring only

33.52 acres has been allotted by MADC to other entities.That

MADC has received far better rates than the one at which the land was

19 August 2025

Neeta Sawant WP-395-2025-FC

offered to the Petitioner. That cancellation of allotment in favour of

the Petitioner is to advantage of MADC, who has secured better

price for the land. That since MADC has not suffered any

prejudice, the part payment made by the Petitioner is required to

be refunded. In support of his contention that mere delay cannot

be a ground for dismissal of writ petition, reliance is placed on

Constitution Bench judgment of the Apex Court in Ramchandra

Shankar, Deodhar and others Versus. State of Maharashtra and others 1.

In support of the contention that even contractual disputes with

State authorities can be adjudicated in writ jurisdiction, reliance is

placed on judgment of the Apex Court in Unitech Limited and Others Versus. Telangana State Industrial Infrastructure Corporation (TSIIC) and Others2 In support of the contention that the amount of

consideration cannot be forfeited in absence of forfeiture clause,

reliance is placed on judgment of the Apex Court in Suresh Kumar

Wadhwa Versus. State of Madhya Pradesh and Others 3. He has also

relied on order passed by the Apex Court in M/S. Utkal Highways

Engineers and Contractors Versus. Chief General Manager and others4,

in support of the contention that writ jurisdiction can be invoked

for recovery of admitted amount. Mr. Narichania would

accordingly pray for setting aside the impugned decision and for

refund of consideration of Rs.10.29 crores along with interest.

Alternatively, he would submit that Petitioner is willing to accept

(1974) 1 SCC 317

(2021) 16 SCC 35.

(2017) 16 SCC 757

SLP (C) No.14350 of 2022 decided on 8 January 2025.



                                        19 August 2025

 Neeta Sawant                                                        WP-395-2025-FC


the principal amount of Rs.10.29 crores in the event this Court is

not inclined to award interest in favour of the Petitioner.

9) The petition is opposed by Mr. Multani, the learned

counsel appearing for Respondent No.1. He would submit that the

petition suffers from gross delay and laches and is liable to be

dismissed on this ground alone. That a time barred claim is sought

to be agitated by filing the present writ petition, which is

impermissible in law. He would rely on judgment of the Apex

Court in S.S. Balu and Others Versus. State of Kerala and Others 5. He

would press into service the doctrine of acquiescence in support of

his contention that Petitioner has acquiesced in forfeiture of

earnest money deposit (EMD) of Rs.10.29 crore. He would submit

that Petitioner has committed breach of terms and conditions of

the LOA and that the EMD has rightly been forfeited. He would

submit that the amount of Rs.10.29 crores paid by the Petitioner is

towards earnest money deposit. In support, he would place

reliance on the judgment of the Apex Court in Videocon Properties

Ltd Versus. Dr. Bhalchandra Laboratories and others6. He would

further submit that Petitioner sat over the allotment of land for

over 8 years and failed to make balance payment of consideration.

That such an act has adversely affected MIHAN project. He would

also rely upon judgment of Single Judge of Delhi High Court in

State Bank of India Versus. Union of India and others 7 in support of his

(2009) 2 SCC 479

(2004) 3 SCC 711

2013 SCC OnLine Del 1456

19 August 2025

Neeta Sawant WP-395-2025-FC

contention that EMD once paid continues to remain the property

of recipient in view of forfeiture clause. Mr. Multani would

particularly draw our attention to the email dated 2 April 2007,

under which the 20% amount was agreed to be forfeited in the

event of nonpayment of 80% balance consideration within a

period of 30 days. He would therefore submit that Petitioner had

agreed for forfeiture of 20% advance payment which is a reason

why it never requested for a refund of the same for over 9 long

years and acquiesced in its forfeiture. He would place reliance on

draft Multi-modal International Hub Airport at Nagpur (Disposal

of Land) Regulations, 2014, providing for compulsory payment of

EMD for allotment of plots.

10) Mr. Multani would further submit that MADC was

always ready and willing to handover possession of entire land

admeasuring 117 acres, and it was the Petitioner who did not

show interest in taking over possession of land. He would take us

through the entire correspondence between the parties to

demonstrate as to how multiple opportunities were granted to the

Petitioner for making payment of balance consideration. He would

submit that even request of the Petitioner for allotment of smaller

portion of land was accepted by MADC but the Petitioner

ultimately did not pay consideration even in respect of smaller

plot of land. He would submit that MADC has suffered huge

losses and public interest has suffered as MIHAN project is being

19 August 2025

Neeta Sawant WP-395-2025-FC

set up by the State Government in public interest. That the

conduct of the Petitioner prevented MADC from allotting the land

to other entities. That so far MADC has been able to allot only

smaller portion of land to three entities and Petitioner is solely

responsible for MADC's inability to allot the land to other entities.

Mr. Multani would accordingly pray for dismissal of the petition.

11) We have also heard Mr. Vanarse, the learned AGP

appearing for Respondent No.2-State.

12) Rival contentions of the parties now fall for our

consideration.

13) The dispute involved in the present petition is with

regard to the allotment of vast tract of land admeasuring 117 acres

in MIHAN SEZ project, which is being implemented by MADC.

Petitioner was allotted the said land for development of IT park

vide Letter of Acceptance dated 5 April 2007. The allotment has

been cancelled vide impugned communication dated 27 May 2015.

Petitioner is no longer interested in the allotment of land and has

accordingly not made any prayer in the petition seeking allotment

of the land in its name. Petitioner is thus not aggrieved by the

action of MADC in cancelling the allotment. However, the

impugned communication also directs forfeiture of advance

amount of Rs.10.29 crores paid by the Petitioner to MADC for the

19 August 2025

Neeta Sawant WP-395-2025-FC

said allotment. Petitioner is aggrieved by forfeiture of the said

amount by the MADC, which is the only grievance raised in the

present petition. Therefore, the only issue that arises for

consideration is whether forfeiture of advance of Rs.10.29 crores

by MADC is valid, and whether Petitioner is entitled for refund of

the same ?

14) The first objection raised by MADC to the

maintainability of the present petition is delay and laches on the

part of the Petitioner in challenging the impugned communication

dated 27 May 2015. Petitioner has challenged the impugned

communication after about 9 long years by filing the present

petition on 24 January 2025. According to MADC, the decision of

forfeiture of advance payment has attained finality on account of

non-raising of challenge thereto by the Petitioner for a period of

over 9 long years. It is contended that if Petitioner was to file a suit

seeking refund of the amount of Rs.10.29 crores, the same would

be barred by limitation. It is therefore contended that if Petitioner's

remedy of suit is barred by limitation, it cannot be permitted to

invoke the writ jurisdiction under Article 226 of the Constitution

of India for seeking refund of the forfeited amount. In short, it is

contended that the relief which is not grantable in a suit cannot be

sought by filing a Writ Petition under Article 226 of the

Constitution of India.






                                         19 August 2025

 Neeta Sawant                                                             WP-395-2025-FC


15)              On the other hand, it is contended by the Petitioner

that the decision of cancellation of allotment of land, as well as

forfeiture of advance amount, did not attain finality as both the

issues were under consideration before MADC. Reliance is placed

by the Petitioner on letter dated 17 November 2017 issued by

MADC to the Petitioner once again offering part of the land. It is

Petitioner's contention that the letter dated 17 November 2017

constitutes withdrawal of the forfeiture decision dated

27 May 2015.

16) It appears that after cancellation of the allotment and

forfeiture of advance amount vide letter dated 27 May 2015,

MADC made a voluntary approach to the Petitioner vide letter

dated 17 November 2017 making inquiries as to the plans for

development of 23.40 acres land. The letter dated

17 November 2017 reads thus :-

No. 5779/MIHAN/______/2017 Date : 17/11/2017 To, M/s. Wipro Technologies, Dodda Kannelli, Sarjapur Road, Banglore-560 035.

Sub: - Development of Plot in Sector 12 of about 23.40 acres in MIHAN SEZ area.

Sir,

This has reference to your application for allotment of plot in MIHAN SEZ area.




                                         19 August 2025

 Neeta Sawant                                                            WP-395-2025-FC


Based on your application and subsequent scrutiny, we have allotted you above plot vide our letter No. MADC/MIHAN/MM/40 did 5 April 2007.

Further as indicated in our allotment letter, the subject plot was allotted for development of IT(Software Development)Unit and the allotment was governed by the Land Disposal Regulations (LDR)& Policy of MIHAN. The same LDR policy also indicates a time limit for development of the plot. However, as of now we have not heard from you about your plan for development of the subject plot.

In view of this, we now request you to kindly let us know the schedule of development for the subject parcel of land immediately.

We would also like to interact with you to understand the issues and to explore whether we can extend any support for the proposed project. In view of this we request you to kindly get in touch with our office, so as to schedule a meeting with our VC & MD at the earliest.

We now await for your response at the earliest.

Thanking you,

For Maharashtra Airport Development Company Ltd.

Sd/-

Advisor (Tech)

17) It appears that after issuance of impugned

communication dated 27 May 2015 cancelling allotment of land

and forfeiting the advance amount of Rs.10.29 crores, Petitioner

did not approach MADC for allotment of land nor made any

enquires with the MADC. MADC, on its own, wrote to the

Petitioner on 17 November 2017, referring to the Letter of

Allotment dated 5 April 2007, and inquired with the Petitioner

about the time frame within which it could develop a plot in

Sector 12 of about 23.40 acres in MIHAN SEZ area. The letter

19 August 2025

Neeta Sawant WP-395-2025-FC

dated 17 November 2017 accused Wipro of not intimating its plans

for development of the subject plot (plot admeasuring 23.40 acres

as referred in the subject letter). MADC offered to interact with

Wipro to understand the issues and to explore the possibility of

providing support for the proposed project. Wipro was invited for

a meeting with Vice Chairman and Managing Director of MADC,

who had issued the impugned cancellation and forfeiture letter

dated 27 May 2015.

18) The question that arises is if the allotment was already

cancelled and advance amount was forfeited, what was the

occasion for MADC to make inquiries about time frame within

which the plot would be developed. Petitioner therefore is correct

in contending that the letter dated 17 November 2017, at least to

some extent, had the effect of revocation of letter dated

27 May 2015. This aspect, at this juncture, is noted to consider the

objection of delay.

19) The letter dated 17 November 2017 would clearly

indicate that the issues of cancellation of allotment or forfeiture of

advance amount had not attained finality between the parties and

MADC was interested in Wipro taking allotment of smaller

portion of land admeasuring 23.40 acres. Petitioner responded to

the letter dated 17 November 2017 vide its letter dated

7 February 2018 as under :-

19 August 2025

Neeta Sawant WP-395-2025-FC

February 7, 2018

To, Maharashtra Airport Development Company Ltd Central Facility building, B-Wing(North), 1st Floor, Mihan SEZ, Khapri (Rly), Nagpur -- 441108

Kind Attention: Advisor (Tech) Ref: Your letter 5779/Mihan/2017 dated 17/11/2017 -- for development of Plot in Sector 12 of about 23.40 acres in MIHAN SEZ area.

Dear Sir,

I write to you with respect to the Land in MIHAN SEZ area and regarding your letter dated November 17, 2017. We appreciate your offer to discuss issues related to development of the land allotted to Wipro.

Despite our earnest intent, we were unable to expand our IT/ ITES operations in MIHAN SEZ due to lack of supporting social infrastructure.

We are however keen to discuss and engage with you to understand your plans for Sector 12 and explore opportunities.

Based on mutual convenience we can meet up with your VC and MD and take this forward.

Thanking you,

Yours sincerely,

Sd/-

Raghunandan CB Vice President Operations Wipro Limited

20) The Petitioner's response vide letter dated

7 February 2018 would again indicate that the matter of allotment

of land by MADC to the Petitioner did not attain finality upon

issuance of impugned communication dated 27 May 2015. In

19 August 2025

Neeta Sawant WP-395-2025-FC

detailed Affidavit-in-Reply filed by MADC it has chosen to

maintain silence about this correspondence in the form of letters

dated 17 November 2017 and 7 February 2018.

21) In our view, since the MADC voluntarily approached

Petitioner by making inquires about its development plans in

smaller plot of land admeasuring 23.40 acres in pursuance of

original LOA dated 5 April 2007, it becomes difficult to accept that

the decision to forfeit the advance amount of Rs.10.29 crores

communicated vide letter dated 27 May 2015 could attain finality.

In fact, the letter dated 17 November 2017 would clearly create an

impression that the advance amount would get adjusted against

allotment of smaller portion of land. This is not the first time that

MADC was willing to offer smaller plot of land to the Petitioner.

Even before issuance of letter dated 27 May 2015, MADC had

repeatedly offered smaller piece of land (of which possession

could be handed over) to Wipro by adjusting the advance amount

already paid. Petitioner had apparently showed disinclination to

accept allotment of entire 117 acres of land and had applied for

23.40 acres of land vide letter dated 25 January 2012. MADC had

showed willingness not only for allotment of 23.40 acres of land

but also for adjustment of the advance amount of Rs. 10.29 crores.

This aspect is being dealt with in latter part of judgment. Suffice it

is to observe at this juncture that the MADC's offer vide letter

dated 17 November 2017 clearly created hope in the mind of

19 August 2025

Neeta Sawant WP-395-2025-FC

Petitioner that the advance payment made by it was still secured

in the form of securing allotment of smaller plot of land.

22) As observed above, Petitioner responded to MADC's

proposal vide letter dated 7 February 2018 and requested MADC

to convene a meeting for understanding the future plans for Sector

12. It has all along been the complaint of the Petitioner that

necessary infrastructural facilities were not made available by the

MADC on account of which Petitioner was not willing to take the

risk of undertaking large scale investment for development of the

project. This is a reason why Petitioner did not immediately accept

the offer made vide letter dated 17 November 2017 and called

upon MADC to discuss the issues relating to supporting social

infrastructure. After addressing letter dated 7 February 2018, it

was quite natural for the Petitioner to wait for at least some time

for a response by the MADC. The previous history between the

parties was such that MADC had reverted with an offer to the

Petitioner after 2 years and 5 months from the date of sending

communication dated 27 May 2015. It was, therefore, quite natural

for the Petitioner not to take immediate precipitative steps by

indulging into litigation.

23) What must also be appreciated is the nature of

relationship between the parties. The case does not involve usual

case of allotment of government land through open tender process

19 August 2025

Neeta Sawant WP-395-2025-FC

where there are multiple bidders competing against each other.

This is a case where MADC had approached Wipro and requested

it to set up an IT Park with a view to make MIHAN project more

viable. Unfortunately, the development of the IT Park by Wipro

could not fructify and it is not necessary to go into the issue as to

who was responsible for such non-fructification, as Petitioner is no

longer interested in the land in question. Suffice it to observe that

the case does not involve eagerness or extreme interest on the part

of the Petitioner in seeking allotment of the land. In fact, sequence

of events indicates that it was MADC was more interested in

Wipro setting up its project to make MIHAN project look more

attractive. It was apparently MADC's intention of attracting a giant

software companies to the MIHAN project and the allotment of

land was made under a hope that a large IT park would get

developed creating several job opportunities. The relationship

between the parties deserves to be appreciated in the light of the

above background. This is a reason why the parties never took

adverse stand against each other for 8 long years when the issue of

taking over possession of land remained hanging. Though, Wipro

did not show interest in taking over possession of the land, MADC

never took immediate precipitative steps for cancelling the

allotment and waited for Wipro to take its own time in deciding

whether to take over possession of entire land admeasuring 117

acres or smaller portion of land admeasuring 30.24 acres. The

correspondence indicates that MADC was willing to offer the

19 August 2025

Neeta Sawant WP-395-2025-FC

smaller portion of land under a sanguine hope of Wipro setting up

IT park in MIHAN SEZ. This appears to be a reason why MADC

decided to make a fresh approach to Wipro two and half years

after cancellation of allotment and forfeiture of advance payment

vide letter dated 17 November 2017. Considering the above nature

of relationship between the parties, Petitioner-Wipro cannot be

held responsible for not initiating the litigation immediately after

issuance of impugned communication dated 27 May 2015 as the

issue remained under discussion between the parties at least till

the year 2018.

24) Though provisions of the Limitation Act, 1963 do not

apply to proceedings filed under Article 226 of the Constitution of

India, the Constitutional Courts have imposed a self-restricting

rule of not entertaining the stale claims by applying the principles

of delay and laches. This self-imposed rule is a rule of practice,

based on sound and proper exercise of discretion, and there is no

inviolable rule that whenever there is delay, the Court must

necessarily refuse to entertain the petition. Each case has to be

decided on its own peculiar facts. In this regard, the observations

by Constitution Bench judgment in Ramchandra Shankar Deodhar

(supra) in paragraph 10 are apposite, which read thus :-

10. The first preliminary objection raised on behalf of the respondents was that the petitioners were guilty of gross laches and delay in filing the petition...




                                     19 August 2025

 Neeta Sawant                                                         WP-395-2025-FC


There was a delay of more than ten or twelve years in filing the petition since the accrual of the cause of complaint, and this delay, contended the respondents, was sufficient to disentitle the petitioners to any relief in a petition under Article 32 of the Constitution. We do not think this contention should prevail with us. In the first place, it must be remembered that the rule which says that the Court may not inquire into belated and stale claims is not a rule of law, but a rule of practice based on sound and proper exercise of discretion, and there is no inviolable rule that whenever there is delay, the court must necessarily refuse to entertain the petition. Each case must depend on its own facts.

The question, as pointed out by Hidayatullah, C.J., in Tilockchand Motichand v. H.B. Munshi MANU/SC/0127/1968 :

[1969]2SCR824 "is one of discretion for this Court to follow from case to case. There is no lower limit and there is no upper limit-. It will all depend on what the breach of the Fundamental Right and the remedy claimed are and how the delay arose." Here the petitioners were informed by the Commissioner, Aurangabad Division by his letter dated 18th October, 1960 and also by the Secretary of the Revenue Department in January 1961 that the rules of recruitment to the posts of Deputy Collector in the reorganised State of Bombay had not yet been unified, and that the petitioners continued to be governed by the rules of Ex- Hyderabad State and the Rules of 30th July, 1959 had no application to them. The petitioners were, therefore, justified in proceeding on the assumption that there were no unified rules of recruitment to the posts of Deputy Collector and the promotions that were being made by the State Government were only provisional, to be regularised when unified rules of recruitment were made. It was only when the petition in Kapoor's case was decided by the Bombay High Court that the petitioners came to know that it was the case of the State Government in that petition-and that case was accepted by the Bombay High Court-that the Rules of 30th July, 1959 were the unified rules of recruitment to the posts of Deputy Collector applicable throughout the reorganised State of Bombay. The petitioners thereafter did not lose any time in filing the present petition. Moreover, what is challenged in the petition is the validity of the procedure for making promotions to the posts of Deputy Collector-whether it is violative of the equal opportunity clause-and since this procedure is not a thing of the past but is still being followed by the State Government, it is but desirable that its Constitutionality should be adjudged when the question has come before the court at the instance of parties

19 August 2025

Neeta Sawant WP-395-2025-FC

properly aggrieved by it. It may also be noted that the principle on which the Court proceeds in refusing relief to the petitioner on ground of laches or delay is that the rights which have accrued to others by reasons of the delay in filing the petition should not be allowed to be disturbed unless there is reasonable explanation for the delay. This principle was stated in the following terms by Hidayatullah, C.J., in Tilokchand v. H.B. Munshi MANU/SC/0127/1968 : [1969]2SCR824 :

"The party claiming Fundamental Rights must move the Court before other rights come into existence. The action of courts cannot harm innocent parties if their rights emerge by reason of delay on the part of the person moving the Court."

Sikri, J., (as he then was), also re-stated the same principle in equally felicitous language when he said in S.N. Bose v. Union of India MANU/SC/0506/1969 : [1970]2SCR697: "It would be unjust to deprive the respondents of the rights which have accrued to them. Each person ought to be entitled to sit back and consider that his appointment and promotion effected a long time ago would not be set aside after the lapse of a number of years." Here as admitted by the State Government in Paragraph 55 of the affidavit in reply, all promotions that have been made by the State Government are provisional and the position has not been crystallised to the prejudice of the petitioners No rights have, therefore, accrued in favour of others by reason of the delay in filing the petition. The promotions being provisional, they have not conferred any rights on those promoted and they are by their very nature liable to be set at naught, if the correct legal position, as finally determined, so requires. We were also told by the learned Counsel for the petitioners, and that was not controverted by the learned Counsel appearing on behalf of the State Government, that even if the petition were allowed and the reliefs claimed by the petitioners granted to them, that would not result in the reversion of any Deputy Collector or officiating Deputy Collector to the post of Mamlatdar/Tehsildar; the only effect would be merely to disturb their inter se seniority as officiating Deputy Collectors or as Deputy Collectors. Moreover, it may be noticed that the claim for enforcement of the fundamental right of equal opportunity under Article 16 is itself a fundamental right guaranteed under Article 32 and this Court which has been assigned the role of a sentinel on the qui vive for protection of the fundamental rights cannot easily allow itself to be

19 August 2025

Neeta Sawant WP-395-2025-FC

persuaded to refuse relief solely on the jejune ground of laches, delay or the like.

25) It is also equally well settled position of law that unless

delay causes prejudice to the opposite party, the petition need not

be rejected only on the ground of delay. The Courts are justified in

not-entertaining petitions on the ground of delay where it is

observed that the inaction on the part of a party has led the other

party change its position and grant of relief in favour of former

party would require reversal of position taken by the latter party.

In Madamsetty Satyanarayana Versus. G. Yellogi Rao and others 8, the

Apex Court has held as under :-

12. The result of the aforesaid discussion of the case law may be briefly stated thus : While in England mere delay or laches may be a ground for refusing to give a relief of specific performance, in India mere delay without such conduct on the part of the plaintiff as would cause prejudice to the defendant does not empower a court to refuse such a relief. But as in England so in India, proof of abandonment or waiver of a right is not a pre-condition necessary to disentitle the plaintiff to the said relief, for if abandonment or waiver is established, no question of discretion on the part of the Court would arise. We have used the expression "waiver" in its legally accepted sense, namely, "waiver is contractual, and may constitute a cause of action : it is an agreement to release or not to assert a right"; see Dawson's Bank Ltd. v. Nippon Menkwa Kabushiki Kaisha [(1935) LR 62 IA 100, 108] . It is not possible or desirable to lay down the circumstances under which a court can exercise its discretion against the plaintiff. But they must be such that the representation by or the conduct or neglect of the plaintiff is directly responsible in inducing the defendant to change his position to his prejudice or such as to bring about a situation when it would be inequitable to give him such a relief.

(emphasis added)

AIR 1965 SC 1405

19 August 2025

Neeta Sawant WP-395-2025-FC

26) In the present case, inaction on the part of the

Petitioner in not challenging the impugned communicated dated

27 May 2015 has not induced MADC in altering its position in any

manner. Even though MADC has allotted some portion out of 117

acres of land to third parties after 2022, Petitioner is not seeking

allotment of the land and therefore there is no question of reversal

of position taken by MADC. Petitioner's claim is only for refund of

the advance amount. It is also not that the inaction on the part of

the Petitioner in initiation of litigation prevented MADC from

allotting the land to third parties. As observed above, MADC

made a voluntary approach to Petitioner on 17 November 2017 for

accepting allotment of 23.40 acres of land. Thus Petitioner's

inaction in initiating litigation has not made MADC alter its

position in any manner.

27) Reverting to the sequence of events, it is seen that there

was some hiatus between the parties after Petitioner showed

interest in securing allotment of smaller land of 23.40 acres vide

letter dated 7 February 2018. Petitioner's case is that it kept on

waiting for response from MADC's side after 7 February 2018. As

observed above, MADC had previously displayed the conduct of

responding after 2 and half years. Therefore, there is no reason to

disbelieve Petitioner's stand that it waited for action on MADC's

part after submission of letter dated 7 February 2018. On

24 November 2022, Petitioner finally wrote to MADC referring to

correspondence for refund of the advance amount and requested

19 August 2025

Neeta Sawant WP-395-2025-FC

for a meeting in the second week of December 2022 discussing

refund of the amount of advance payment. This email dated 24

November 2022 is produced by MADC along with its Reply, which

is silent about MADC's response to the said request. This was then

followed by Petitioner sending Advocate Notice dated

13 September 2024. Thus the case does not involve total silence or

inaction on Petitioner's part after issuance of the impugned

forfeiture letter dated 27 May 2015. Parties not only discussed

allotment of smaller plot but also engaged in correspondence for

refund.

28) Also of relevance is the fact that when the Petitioner

served Advocate's notice dated 13 September 2024 on MADC

seeking refund of advance payment with interest, the only

response that was received from Advocate of MADC on

10 October 2024 was that MADC would give a detailed reply to

the notice dated 13 September 2024 within a period of one month.

However, MADC failed to give any such detailed reply, which

prompted Petitioner to serve another notice dated

8 November 2024 threatening MADC of institution of litigation.

Again, a terse response was received from MADC on 8 November

2024 once again reserving right to issue detailed reply to the initial

notice dated 13 September 2024. Thus, beyond repeatedly seeking

time to give a detailed reply to the notice dated

13 September 2024, MADC did not deal with the contentions

19 August 2025

Neeta Sawant WP-395-2025-FC

raised by the Petitioner in the notice dated 13 September 2024.

MADC thus did not resist the claim raised by the Petitioner for

refund of security deposit on the ground of delay. It is only after

the petition is filed that MADC has raised the issue of delay

through its Affidavit in Reply dated 2 June 2025.

29) Considering the above position, we are of the view that

the cause of action for filing the present petition did continue

beyond 27 May 2015. The damage caused to the Petitioner in the

form of forfeiture letter dated 27 May 2015 was not complete, even

upon service of the said notice. The cause continued as MADC

voluntarily came back to the Petitioner with the offer of allotment

of smaller land admeasuring 23.40 acres on 17 November 2017.

Petitioner also showed interest in allotment of smaller plot by

MADC vide response dated 7 February 2018. If the fresh offer

made by MADC was to fructify into allotment of smaller land

admeasuring 23.40 acres, the advance payment of Rs.10.29 crores

made by the Petitioner would be adjusted in the price of the said

smaller plot of land. The eagerness on the part of MADC in

allotting smaller plot of 23.40 acres is required to be considered in

the light of its inability to dispose of the land agreed to be allotted

to the Petitioner vide LOA dated 5 April 2007. Though Petitioner's

allotment was cancelled on 27 May 2015, it appears that MADC

was not able to allot any portion of the land admeasuring 117

acres for the next seven long years. In para-19.20 of its Affidavit in

19 August 2025

Neeta Sawant WP-395-2025-FC

Reply, the MADC has given details of allotment of three land

parcels out of the total land of 117 acres. Para-19.20 of the Reply

reads thus :-

19.20. That the Petitioner has no locus to demand cogent description of the present status of the Plot of Land and its current valuation from the Respondent No.1. It is pertinent to note that the following land/s parcels out of the total land of 117 Acres has already been allotted to the following parties-

Sr. No. Name of Allotees Date of Land Document/s Provisional Alloted Allotment

1. Maharashtra 22.02.2022 About A copy of the provisional Remote Sensing 6.52 allotment letter sent by Application Acres Respondent No.1 to Centre (MRSAC) MRSAC dated 22.02.2022 is given in ANNEXURE-

           [Govt. Body]                                      "22"
2.         State Disaster            25.02.2022   About      A copy of the provisional
           Management                             10         allotment letter sent by
           Authority                              Acres      Respondent      No.1   to
           Maharashtra                                       SDMAM dated 25.02.2022
           (SDMAM)                                           is given in ANNEXURE-
           [Govt. Body]                                      "23"
3.         M/s. GAIL (India) 20.02.2024           17         A copy of the provisional
           Limited                                Acres      allotment letter sent by
                                                             Respondent No.1 to M/s.
                                                             GAIL (India) Ltd. dated
                                                             20.02.2022 is given in
                                                             ANNEXURE-"24"




30)              Thus, the case involves peculiar circumstances in

which MADC itself was unable to dispose of the land allotted to

the Petitioner. Out of 117 acres agreed to be allotted to the

19 August 2025

Neeta Sawant WP-395-2025-FC

Petitioner, it appears that MADC has been able to allot only 33.52

acres of land to the three entities, two of whom are arms of

Government of Maharashtra, that too after 7 long years of issuance

of impugned communication dated 27 May 2015. There can only

be two possibilities for this action. First possibility could be

MADC's voluntary offer for 23.40 acres of land to Petitioner made

on 7 November 2017 and Petitioner's positive response to that

offer on 7 February 2018. One may infer that MADC kept on

mulling allotment of 23.40 acres of land to Petitioner till 2022 when

Petitioner finally requested for refund of advance amount. Second

possibility could be MADC's inability to dispose of the land due

lack of interest by other parties in the land. What is more

important to note is that out of 117 acres of land allotted to

Petitioner, MADC has been able to allot only 33.52 acres of land till

now. Balance land is not allotted either because the acquisition is

incomplete or because there are no takers for that land. Be that as

it may. In the absence of any concrete material on record, it is not

necessary to delve deeper into the reasons for non-allotment of

balance land out of 117 acres by MADC. Suffice it to observe at

this stage that it took about 7 years for MADC to allot 10 acres of

land on 25 February 2022 and 9 years to allot 17 acres of land. It

does appear that MADC was unable to find takers for the land,

allotment of which was cancelled vide impugned communication

dated 27 May 2015. This appears to be the reason why MADC

made a voluntary approach to the Petitioner on 17 November 2017

19 August 2025

Neeta Sawant WP-395-2025-FC

for allotment of smaller plot of 23.40 acres. The silence between the

parties after 7 February 2018 till 24 November 2022 is required to

be appreciated in the light of the above developments where

MADC was not able to find takers for the land in question.

Therefore, Petitioner was justified in waiting in expectation of

MADC either allotting smaller portion of the land or refunding the

advance payment.

31) Considering the above circumstances, it would be

unjust to dismiss the present petition only on the ground of delay.

The facts and circumstances are such that the Petitioner cannot be

held guilty of delay and laches. If MADC was not to make fresh

offer for allotment of smaller land on 17 November 2017, the

Petitioner could have been held guilty of delay and laches in not

timely challenging the communication dated 27 May 2015.

MADC's voluntary offer on 17 November 2017, Petitioner's

response on 7 February 2018 and Petitioner's request for refund on

24 November 2022 offer enough justification for ignoring the

delay, if any, particularly considering the nature of relief we

propose to grant in Petitioner's favour in the present Petition. We

are therefore not inclined to dismiss the petition only on the

ground of delay.

32) We now proceed to consider the merits of the petition.






                                     19 August 2025

 Neeta Sawant                                                             WP-395-2025-FC


33)              Petitioner paid amount of Rs.10,29,60,000/- towards

20% of total consideration of Rs.51,48,00,000/- towards price of 117

acres of land calculated at the rate of Rs.44,00,000/- per acre. Since

the transaction of allotment of land has not been completed, the

Petitioner has sought refund of advance payment of

Rs.10,29,60,000/-. MADC on the other hand has forfeited the said

advance amount vide impugned communication dated

27 May 2015. The reasons recorded for forfeiture of the advance

amount by MADC in the communication dated 27 May 2015 are as

under :-

Coming to the proposal of refund of the advance of Rs.10.29 Crores with interest @ 24% p.a. and to terminate the current Agreement as you don't want to hold any land, etc. is contrary to the terms of the Agreement. There is total failure on your part to comply with any of the terms of the Agreement. Operations of our project are smoothly going on and have been reached to the expected satisfactory norms. There is no question of refund of advance as well as the interest as claimed by you. On the other hand, the advance paid by you is liable to be forfeited because there is total inaction and avoidance on your part when you have been given repeated chances and opportunities to commence your project as was expected from time to time. Therefore, your proposal cannot be accepted.

You have made an alternative proposal for taking land to the extent of Rs.10.29 Crores with no firm commitment to commence in next five years. You have already been apprised of total facts wherein from time to time you have been given opportunities to take possession of the lesser land than shown in the letter of acceptance and come forward with the firm commitment. However, you have never responded to the same. This type of "No firm commitment" is not a legal offer nor it can be considered as practical commitment. Your expectation in the said proposal that MADC should terminate the contract and pay back the advance along with the interest is also contrary to the

19 August 2025

Neeta Sawant WP-395-2025-FC

terms of the Agreement, nor there is any equitable reason to consider this type of offer in the light of the facts and circumstances stated above. Therefore, MADC hereby reject your both the offers. MADC reserves its right to recover the interest for withholding of the 80% of the premium without any reason whatsoever.

In the light of the facts and circumstances stated above, the letter of acceptance dtd. 5/4/2007 for allotment of 117 Acres of land is liable to be cancelled and is hereby cancelled. The advance amount of Rs.10.29 Crores is hereby forfeited.

(emphasis and underlining added)

34) MADC has contended that the amount of Rs. 10.29

crores was paid by the Petitioner towards Earnest Money Deposit

(EMD) and what is forfeited is EMD. However, the impugned

communication dated 27 May 2025 does not brand the said

payment as EMD and repeatedly refers to the same as 'advance

payment'.

35) In the impugned communication, MADC has stated

that Petitioner's request for refund of advance payment is contrary

to the terms of the Agreement, i.e. terms of the agreement. By

referring to the terms of LOA, the advance payment of Rs. 10.29

crores has been forfeited. We therefore proceed to examine

whether the LOA provided for such forfeiture. It would be

apposite to extract the relevant terms and conditions of the LOA

dated 5 April 2007 for facility of reference :-

2. The price of the land for 117 Acres thus works out to Rs.51,48,00,000/-, out of which you will have to pay 20% of the total consideration i.e. Rs. 10,29,60,000/- towards advance

19 August 2025

Neeta Sawant WP-395-2025-FC

payment for this plot. The remaining 80% amount will have to be paid by you at the time of giving possession of the land. In case net area increases, you will be required to pay additional amount as per the rate in Clause 1 above. A demand note as desired by you indicating the payment details is given as per the Enclosure No.3.

3. As discussed with you from time to time and informed vide various emails, that out of total 160.24 Acres of land, other than the Zudpi jungle and the land presently under water channels, MADC is having around 30 Acres of land in its possession. The possession of the land in possession can be given to you at any point of time whenever you so desire on payment of remaining 80% of amount for 30 Acre in lump sum or installment which may be fixed by MADC. The possession of remaining land will be given on acquisition by MADC, which is being done by applying urgency clause.

Delay in Payment:

11. In case the of delay in making the balance 80% payment, an interest @ 15% shall be charged from the due date of the payment.

12. In addition to the price for the land mentioned above, you will have to pay a lease rent of Rs.40/- per acre per year for net area. This lease rent shall have to be paid on or before the 15 th of the first month of every year, considering the date of payment of 80% amount as a zero date.

14. MADC promises to give you the functional infrastructure like roads, water supply, sewage disposal and telecommunication network within 24 months from the date of giving possession of the land. In case of failure to do so MADC shall pay penalty for delay. We are intending to have our power plant and supply system and till that comes up, we will assist you in getting power from existing system of Maharashtra State Electricity Distribution Co. Ltd.

36) The entire LOA did not contain any clause for

forfeiture of part payment of Rs.10,29,60,000/- and there was a

reason for not stipulating the forfeiture clause. The LOA also did

19 August 2025

Neeta Sawant WP-395-2025-FC

not fix any specific time for payment of 80% balance consideration.

Clause-2 provided that 'The remaining 80% amount will have to be

paid by you at the time of giving possession of the land'. The LOA thus

did not provide for any particular period during which the

balance amount was required to be made. Provisions of Clause-3

of the LOA are vital in which it was indicated that MADC was

only possessing 30 acres of land as on the date of issuance of LOA.

MADC offered to handover possession of only 30 Acres land on

payment of remaining 80% of amount for 30 Acres land. Para-3 of

the LOA specifically provided that 'The possession of remaining land will be given on acquisition by MADC, which is being done by applying urgency clause'.

37) Thus, Clauses-2 and 3 of the LOA when read together

would indicate that the entire 117 acres of land was not available

in possession of MADC and payment of 80% balance

consideration was to be made by the Petitioner only on receipt of

possession of 117 acres of land. This is the reason why no specific

time was indicated for payment of balance consideration in the

LOA. MADC possessed only 30 acres of land as on the date of

issuance of LOA and taking over possession of 30 acres of land

was left at the discretion of the Petitioner on account of use of the

words 'at any point of time whenever you so desire' in Clause-3 of the

LOA. Thus, it was not compulsory for the Petitioner to

immediately take over possession of 30 acres of land. Petitioner, at

its option, could wait for handing over possession of entire bulk of

19 August 2025

Neeta Sawant WP-395-2025-FC

117 acres of land. Thus, Petitioner's obligation to make payment

of 80% balance consideration arose under the terms of LOA only

when MADC offered possession of entire 117 acres of land. This is

the reason why the LOA did not contain any stipulation for

forfeiture of advance payment.

38) In support of his contention that the parties had agreed

for forfeiture of the EMD, Mr. Multani has relied on email dated

2 April 2007 sent by MADC to the Petitioner stating as under :-

Once the land comes under our possession, MADC would inform Wipro and within 7 days to make the balance payment 80% payment. Which required to be made within 30 days from the date of receipt of the information from MADC. In the event of non-payment of any amount of the 80% the balance payment the 20% advance payment will be forfeited and for any delay an interest @ 18% would be charged on the balance payment due and unless otherwise the reason is genuine one to satisfy VC&MD.

(emphasis added)

39) By relying on the above email, it is sought to be

suggested that the balance 80% amount was agreed to be paid

within a period of 30 days from the date of receipt of information

from MADC. However, such information was to be given once the

land came under the possession of MADC.

40) In our view, reliance by MADC on email dated

2 April 2007, does not make its case any better for two reasons.

Firstly, the email dated 2 April 2007 is superseded by the LOA

19 August 2025

Neeta Sawant WP-395-2025-FC

issued on 5 April 2007. The terms and conditions of transaction

between the parties would be governed by the LOA and not by

email dated 2 April 2007. In the LOA, there is no condition for

forfeiture of 20% advance payment. Secondly, even if email dated

2 April 2007 is to be treated as terms and conditions of the

transaction between the parties, the said email provided for

making the balance payment within 30 days of receipt of

intimation from MADC, which intimation was to be given only

after the entire 117 acres of land came in MADC's possession.

Thus, even email dated 2 April 2007 contemplated making of

balance 80% payment only upon handing over of possession of

entire 117 acres of land.

41) Having held that Petitioner's obligation to make

balance 80% payment was contingent upon MADC offering

possession of entire land parcel of 117 acres, we proceed to

examine as to when MADC offered possession of entire land

parcel to the Petitioner.

42) Alongwith with its Affidavit-in-Reply MADC has

produced series of correspondence that has taken place between

the parties after issuance of LOA dated 5 April 2007. It would be

useful to take a quick stock of the said correspondence :-

19 August 2025

Neeta Sawant WP-395-2025-FC

i. By email dated 9 October 2009, MADC called upon Wipro

to take joint measurement on the land ready for possession.

The email did not indicate that entire 117 acres of land was

ready for being handed over to MADC. The email would

only mean that the land admeasuring 30 acres could be

measured and handed over to the Petitioner. However,

under the terms of the LOA, it was optional for the

Petitioner to take over 30 acres of land. The fact that the

offer for joint measurement was only in respect of 30 acres

land is clear from trailing email dated 27 August 2009 in

which MADC made a request for release of payment of 305

lakhs for 30.343 acres.

ii. By letter dated 31 October 2009 MADC again requested

Petitioner to make full payment towards 30.343 acres i.e.

Rs. 3,05,49,200/-. Here the email dated 27 August 2009 and

letter dated 31 October 2007 indicates that MADC was

willing to adjust the entire advance payment of Rs.

10,29,60,000/- against 30.343 acres of land even though LOA

had provided for making 80% payment of the amount for

30 acres in lumpsum. The above correspondence shows

that MADC was pushing Petitioner to accept allotment in

respect of 30.343 acres of land on account of the fact that it

was unable to acquire the balance portion of the land.






                                     19 August 2025

 Neeta Sawant                                                           WP-395-2025-FC


iii.        On 8 March 2010, Petitioner requested MADC to

withdraw/cancel the allotment and refund the advance

payment of Rs.10,29,60,000/-.

iv. By letter dated 24 February 2011, MADC reiterated the

request for making the balance payment of Rs.

10,91,20,000/- towards allotment of land of 31 acres land,

again indicating the fact that MADC was unable to make

available the balance portion of land.

v. On 12 September 2011, MADC wrote to the Petitioner

contending that it was in complete possession of entire area

of 117 acres of land and requested the Petitioner to take

over possession on payment of Rs.51.48 crores minus the

amount already paid.

vi. On 18 January 2012, MADC wrote to Petitioner accusing it

of non-commencement of any activity despite passage of 56

months. MADC threatened the Petitioner with termination

of allotment by giving 15 days' time to explain its conduct.

Curiously the letter dated 18 January 2012 did not make

any reference to earlier letter dated 12 September 2011 nor

did the said letter mention that the entire 117 acres of land

was available for allotment to the Petitioner.






                                       19 August 2025

 Neeta Sawant                                                           WP-395-2025-FC


vii.         On 27 August 2012, MADC again requested the Petitioner

to take over possession of the land without indicating the

exact land which was ready for being offered in possession

to the Petitioner. It accused Petitioner of not paying the

balance amount of Rs. 48.43 crores despite passage of 5

years.

viii. It appears that by its letter dated 3 January 2012, Wipro had

accused MADC of not completing the basic infrastructure.

By letter dated 25 January 2012, Petitioner requested

MADC to limit the allotment to only 23.40 acres by

adjusting the advance payment made by it. MADC had

favourably considered the request for restraining the

allotment to lesser area. However, since no further interest

was shown by the Petitioner, MADC addressed letter dated

31 December 2014 again threatening the Petitioner with the

consequences of termination of allotment and forfeiture of

the advance payment.

ix. On 22 February 2013, MADC wrote to the Petitioner that

Petitioner's request for limiting the allotment to 23.40 acres

would be considered only if operations were to be

commenced within a period of 24 months.

x. On 12 December 2014, Wipro once again accused MADC of

not providing essential infrastructural facilities and

19 August 2025

Neeta Sawant WP-395-2025-FC

requested for refund of advance payment of Rs.10.29 crores

alongwith interest. Alternatively, it requested for allotment

of land corresponding to Rs.10.29 crores without any firm

commitment to commence operations in five years.

xi. MADC proceeded to cancel the allotment by impugned

communication dated 27 May 2015 and forfeited the

advance payment of Rs.10.29 crore.

xii. Wipro responded by letter dated 15 June 2015 expressing

difficulties in setting up of project in MIHAN. Another

letter dated 26 June 2015 was sent by the Petitioner

requesting for refund of advance payment.

43) The above correspondence would indicate that MADC

was never in a position to handover entire land parcel of 117 acres

and was pushing Wipro to accept possession of 30 acres of land

and was ready to adjust the advance payment of Rs.10.29 crores

against land value of 30 acres. In one stray letter dated 12

September 2011 MADC has claimed possession of entire area of

117 acres. However, the correspondence after 12 September 2011

creates a serious doubt about the ability and willingness of MADC

to handover entire 117 acres of land to the Petitioner. MADC's two

letters 18 January 2012 and 27 August 2012 that followed letter

dated 12 September 2011 did not make any reference to the said

letter and did not accuse Petitioner of not making payment of

19 August 2025

Neeta Sawant WP-395-2025-FC

balance consideration despite offering possession of entire land

vide letter dated 12 September 2011. The pleadings raised by

MADC about letter dated 12 September 2011 are also curious. In

its reply, while referring to the letter dated 12 September 2011,

MADC has not pleaded that the entire 117 acres of land was

acquired by September 2011 and ready for being allotted and

handed over to the Petitioner. The pleadings with reference to

letter dated 12 September 2011 in the reply are as under :-

Further, vide letter dated 12.09.2011, the Respondent No.1 had again informed the Petitioner that the payment of Rs. 10,29,60,000/- was actu- ally in the nature of earnest money and further informed the Petitioner that in case of Petitioner's default, the Respondent No.1 would have no option left but to terminate the contract with all of its consequences, as cited below:

Thus, the letter dated 12 September 2011 is produced along with

the reply to highlight the aspect of failure to make the payment by

Petitioner and there is no statement in the reply while referring to

the said letter that the entire land of 117 acres was acquired or was

available for possession by the Petitioner.

44) It also appears that by letter dated 29 January 2012,

Petitioner had requested for allotment of land of 23.40 acres and

MADC showed willingness to restrict such allotment to 23.40 acres

vide letter dated 22 February 2013 subject to the condition of

Petitioner undertaking to commence operations within 24 months.

WIPRO apparently did not give any such commitment and again

19 August 2025

Neeta Sawant WP-395-2025-FC

approached MADC vide letter dated 12 December 2014 seeking

refund of entire advance amount of Rs.10.29 crores or in the

alternative for allotment of land equivalent to the amount of

Rs.10.29 crores. It therefore becomes to difficult to hold on the

basis of one stary letter dated 12 September 2011 that MADC was

in a position to handover possession of entire land parcel of 117

acres. The parties thereafter started discussing allotment of lesser

portion of land admeasuring 23.43 acres. Thus, the time for

making balance 80% payment for entire land parcel of 117 acres

never really arrived.

45) MADC has however cancelled the allotment by

impugned communication dated 27 May 2015 by accusing

Petitioner of not complying with the terms and conditions of the

LOA. As observed above, LOA never fixed any time limit for

paying balance 80% consideration except by stray letter dated

12 September 2011, there is nothing on record to indicate that

MADC offered possession of entire land parcel of 117 acres to the

Petitioner. Even if it is assumed that letter dated

12 September 2011 constitutes offer for possession of 117 acres of

land, parties thereafter started discussing allotment of lesser

portion of 23.43 Acres. Considering the above position, in our

view, Petitioner cannot be entirely blamed for not paying balance

consideration of 80% in respect of 117 acres of land.






                                          19 August 2025

 Neeta Sawant                                                         WP-395-2025-FC


46)              Petitioner is no longer interested in allotment of the

land. Even though we are not in full agreement with MADC's

decision to cancel the allotment, Petitioner is no longer insisting

for revival of the allotment. The only prayer that is pressed in the

present petition is for refund of advance payment alongwith

interest.

47) It is sought to be contended on behalf of MADC that

amount of 10.29 crores was paid towards Earnest Money Deposit

and that MADC was entitled to forfeit the same. As observed

above, there is no forfeiture clause in the LOA. The LOA does not

use the word EMD for describing the amount of Rs. 10.29 crores

and brands it as 'advance payment'. Though it is sought to be

orally argued that Rs.10.29 crores was paid towards EMD, MADC

has itself referred to the said payment as 'advance payment' in

numerous correspondence including forfeiture letter. We therefore

reject MADC's contention that Rs.10.29 crores were paid as EMD.

Therefore, it is not necessary to discuss the ratio of the judgment

of the Apex Court in Videocon Properties Ltd. (supra). We are not

impressed by reliance of MADC on draft Land Disposal

Regulations, 2014. The said Regulations were in draft format and

were not even in force at the time when the impugned

communication was issued. Subsequent finalisation of the Land

Disposal Regulations in 2018 is of little consequence as the 2018

19 August 2025

Neeta Sawant WP-395-2025-FC

Regulations cannot retrospectively apply to the cancellation letter

dated 27 May 2015.

48) As observed above, there is no forfeiture clause in the

LOA. Right to forfeit is a contractual right and unless the contract

provides for right of forfeiture, there cannot be unilateral

forfeiture. Therefore, it is impermissible in law to forfeit the

advance payment made by the Petitioner in absence of a forfeiture

clause in the LOA. Provisions of Section 74 of the Indian Contract

Act, 1872 are relevant here, which provides thus :-

74. Compensation for breach of contract where penalty stipulated for.

--

When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for.

Explanation.--A stipulation for increased interest from the date of de- fault may be a stipulation by way of penalty.

Exception.--When any person enters into any bail-bond, recognizance or other instrument of the same nature, or, under the provisions of any law, or under the orders of the Central Government or of any State Government, gives any bond for the performance of any public duty or act in which the public are interested, he shall be liable, upon breach of the condition of any such instrument, to pay the whole sum mentioned therein.

Explanation.--A person who enters into a contract with Government does not necessarily thereby undertake any public duty, or promise to do an act in which the public are interested.




                                     19 August 2025

 Neeta Sawant                                                         WP-395-2025-FC




Thus, parties to contract can agree to specify a sum to be paid in

case of breach of contract and upon breach being proved, the party

who complains of breach is entitled to receive the said specified

amount whether or not any actual damage is caused. However, for

claiming such sum, it is necessary that there is a contractual clause

between the parties. In absence of such a clause in the contract, it

is impermissible to retain amount paid towards advance payment.

Thus, forfeiture cannot be resorted to unless the contract explicitly

provides for the same.

49) The law in regard to impermissibility to forfeit the

security deposit in absence of a forfeiture clause is well settled. In

Suresh Kumar Wadhwa (supra) is apposite in which it is held in

paras-23 to 29 as under :-

23. Reading of Section 74 would go to show that in order to forfeit the sum deposited by the contracting party as "earnest money" or "security" for the due performance of the contract, it is necessary that the contract must contain a stipulation of forfeiture. In other words, a right to forfeit being a contractual right and penal in nature, the parties to a contract must agree to stipulate a term in the contract in that behalf. A fortiori, if there is no stipulation in the contract of forfeiture, there is no such right available to the party to forfeit the sum.

24. The learned author-Sir Kim Lewison in his book "The Interpretation of Contracts" (6th edition) while dealing with subject "Penalties, Termination and Forfeiture clauses in the Contract" explained the meaning of the expression "forfeiture" in these words:

19 August 2025

Neeta Sawant WP-395-2025-FC

"A forfeiture Clause is a Clause which brings an interest to a premature end by reason of a breach of covenant or condition, and the Court will penetrate the disguise of a forfeiture Clause dressed up to look like something else. A forfeiture Clause is not to be construed strictly, but is to receive a fair construction."(See page 838)

25. The author then quoted the apt observations of Lord Tenterden from an old case reported in (1828) Moo. & M. 189 Doe d Davis v.

Elsam wherein the learned Lord while dealing with the case of forfeiture held as under:

"I do not think provisos of this sort are to be construed with the strictness of conditions at common law. These are matters of contract between the parties, and should, in my opinion, be construed as other contracts" (see pages 840).

26. Equally well settled principle of law relating to contract is that a party to the contract can insist for performance of only those terms/conditions, which are part of the contract. Likewise, a party to the contract has no right to unilaterally "alter" the terms and conditions of the contract and nor they have a right to "add" any additional terms/conditions in the contract unless both the parties agree to add/alter any such terms/conditions in the contract.

27. Similarly, it is also a settled law that if any party adds any additional terms/conditions in the contract without the consent of the other contracting party then such addition is not binding on the other party. Similarly, a party, who adds any such term/condition, has no right to insist on the other party to comply with such additional terms/conditions and nor such party has a right to cancel the contract on the ground that the other party has failed to comply such additional terms/conditions.

28. Keeping in view the aforementioned principle of law, when we examine the facts of the case at hand then we find that the public notice (advertisement), extracted above, only stipulated a term for deposit of the security amount of Rs. 3 lakhs by the bidder (Appellant) but it did not publish any stipulation that the security amount deposited by the bidder (Appellant herein) is liable for forfeiture by the State and, if so, in what contingencies.

29. In our opinion, a stipulation for deposit of security amount ought to have been qualified by a specific stipulation providing therein a

19 August 2025

Neeta Sawant WP-395-2025-FC

right of forfeiture to the State. Similarly, it should have also provided the contingencies in which such right of forfeiture could be exercised by the State against the bidder. It is only then the State would have got a right to forfeit. It was, however, not so in this case.

(emphasis added)

50) Even in a case where the amount is paid as EMD

(which is not the case here), the Apex Court has held that the

forfeiture clause must be clear and explicit. In cases where the

amount is paid towards part payment of consideration and even if

there is a forfeiture clause in the contract, the same would not

apply for forfeiture of such part payment of consideration. In

Satish Batra Versus. Sudhir Rawal9, it is held as under :-

15. The law is, therefore, clear that to justify the forfeiture of advance money being part of "earnest money" the terms of the contract should be clear and explicit. Earnest money is paid or given at the time when the contract is en-

tered into and, as a pledge for its due performance by the depositor to be for- feited in case of non-performance by the depositor. There can be converse sit- uation also that if the seller fails to perform the contract the purchaser can also get double the amount, if it is so stipulated. It is also the law that part- payment of purchase price cannot be forfeited unless it is a guarantee for the due performance of the contract. In other words, if the payment is made only towards part-payment of consideration and not intended as earnest money then the forfeiture clause will not apply.

(emphasis added)

51) In our view therefore, there are two reasons why

MADC cannot retain the amount of 10.29 crores paid by the

Petitioner. Firstly the said amount is not paid towards EMD or

security deposit and secondly, there is no clause in the LOA for

forfeiture of the said amount. In absence of a specific clause for

(2013) 1 SCC 345

19 August 2025

Neeta Sawant WP-395-2025-FC

forfeiture, in our view, the action of MADC in forfeiting the

advance payment of Rs.10.29 crores is clearly unjustified.

52) MADC is a public authority and is expected to act

fairly. Failure of transaction between the parties has not really

caused any loss or prejudice to MADC. MADC has not pleaded

cause of any loss in monetary terms in its Affidavit-in-Reply. On

the contrary, the Affidavit-in-Reply indicates that MADC has

allotted some portion of land to other entities at much higher rate.

MADC had agreed to allot land to the Petitioner at the rate of

Rs.44 lakhs per acre, whereas the land admeasuring 6.52 acres

appears to have been allotted to Maharashtra Remote Sensing

Application Centre for Rs.9.10 crores which works out roughly to

Rs.1.39 crores per acre. Similarly, land admeasuring 10 acres is

allotted to State Disaster Management Authority on

25 February 2022 for Rs.13.96 crores which works out roughly to

Rs.1.40 crores per acre. MADC has also allotted land admeasuring

17 acres to M/s. GAIL (India) Limited for Rs.38.50 crores which

works out to approximately Rs.2 crores per acre. Thus, failure of

transaction with the Petitioner has enabled MADC to allot the land

at much higher cost to other entities. It is not that other entities

were in queue for allotment of the land and the Petitioner

deprived MADC from allotting the land to other entities. Despite

cancellation of Petitioner's allotment in 2015, MADC has been able

to allot only 33 acres of land out of 117 acres to the other entities.




                                          19 August 2025

 Neeta Sawant                                                            WP-395-2025-FC


In our view therefore, conduct of the Petitioner has not resulted

into any loss or prejudice to MADC.

53) Ordinarily, remedy under Article 226 of the

Constitution of India cannot be permitted to be exercised to settle

contractual disputes between the parties, even if one of the parties

to the contract is a State Authority. However, there are well

recognised exceptions to this usual rule. In ABL International Ltd. and another Versus. Export Credit Guarantee Corporation of India Ltd. and others10, the Apex Court has held that writs under Article 226

are maintainable for asserting contractual rights against State or its

instrumentalities. Referring to the judgment in ABL International

Ltd., the Apex Court has held in Unitech Limited (supra) as under :-

38. Much of the ground which was sought to be canvassed in the course of the pleadings is now subsumed in the submissions which have been urged before this Court on behalf of the State of Telangana and TSIIC. As we have noted earlier, during the course of the hearing, learned Senior Counsel appearing on behalf of the State of Telangana and TSIIC informed the Court that the entitlement of Unitech to seek a refund is not questioned nor is the availability of the land for carrying out the project being placed in issue. Learned Senior Counsel also did not agitate the ground that a remedy for the recovery of moneys arising out a contractual matter cannot be availed of Under Article 226 of the Constitution. However, to clear the ground, it is necessary to postulate that recourse to the jurisdiction Under Article 226 of the Constitution is not excluded altogether in a contractual matter. A public law remedy is available for enforcing legal rights subject to well-settled parameters.

39. A two judge Bench of this Court in ABL International Ltd. v. Export Credit Guarantee Corporation of India MANU/SC/1080/2003 : (2004) 3 SCC 553 [ABL International] analyzed a long line of precedent of this

(2004) 3 SCC 553

19 August 2025

Neeta Sawant WP-395-2025-FC

Court6 to conclude that writs Under Article 226 are maintainable for asserting contractual rights against the state, or its instrumentalities, as defined Under Article 12 of the Indian Constitution.

39.1 Speaking through Justice N. Santosh Hegde, the Court held:

27. ...the following legal principles emerge as to the maintainability of a writ petition:

(a) In an appropriate case, a writ petition as against a State or an instrumentality of a State arising out of a contractual obligation is maintainable.

(b) Merely because some disputed questions of fact arise for consideration, same cannot be a ground to refuse to entertain a writ petition in all cases as a matter of rule.

(c) A writ petition involving a consequential relief of monetary claim is also maintainable.

This exposition has been followed by this Court, and has been adopted by three-judge Bench decisions of this Court in State of UP v. Sudhir Kumar and Popatrao Vynkatrao Patil v. State of Maharashtra.

39.2. The decision in ABL International, cautions that the plenary power Under Article 226 must be used with circumspection when other remedies have been provided by the contract. But as a statement of principle, the jurisdiction Under Article 226 is not excluded in contractual matters.

39.3. Article 23.1 of the Development Agreement in the present case mandates the parties to resolve their disputes through an arbitration. However, the presence of an arbitration Clause within a contract between a state instrumentality and a private party has not acted as an absolute bar to availing remedies Under Article 226.

39.4. If the state instrumentality violates its constitutional mandate under Article 14 to act fairly and reasonably, relief under the plenary powers of the Article 226 of the Constitution would lie. This principle was recognized in ABL International:

28. However, while entertaining an objection as to the maintainability of a writ petition Under Article 226 of the Constitution of India, the court should bear in mind the fact that

19 August 2025

Neeta Sawant WP-395-2025-FC

the power to issue prerogative writs Under Article 226 of the Constitution is plenary in nature and is not limited by any other provisions of the Constitution. The High Court having regard to the facts of the case, has a discretion to entertain or not to entertain a writ petition. The Court has imposed upon itself certain restrictions in the exercise of this power. (See Whirlpool Corporation v. Registrar of Trade Marks [ MANU/SC/0664/1998 :

(1998) 8 SCC 1].) And this plenary right of the High Court to issue a prerogative writ will not normally be exercised by the Court to the exclusion of other available remedies unless such action of the State or its instrumentality is arbitrary and unreasonable so as to violate the constitutional mandate of Article 14 or for other valid and legitimate reasons, for which the Court thinks it necessary to exercise the said jurisdiction.

(emphasis supplied)

39.5. Therefore, while exercising its jurisdiction Under Article 226, the Court is entitled to enquire into whether the action of the State or its instrumentalities is arbitrary or unfair and in consequence, in violation of Article 14. The jurisdiction Under Article 226 is a valuable constitutional safeguard against an arbitrary exercise of state power or a misuse of authority.

39.6. In determining as to whether the jurisdiction should be exercised in a contractual dispute, the Court must, undoubtedly eschew, disputed questions of fact which would depend upon an evidentiary determination requiring a trial. But equally, it is well-settled that the jurisdiction Under Article 226 cannot be ousted only on the basis that the dispute pertains to the contractual arena. This is for the simple reason that the State and its instrumentalities are not exempt from the duty to act fairly merely because in their business dealings they have entered into the realm of contract. Similarly, the presence of an arbitration Clause does oust the jurisdiction Under Article 226 in all cases though, it still needs to be decided from case to case as to whether recourse to a public law remedy can justifiably be invoked.

39.7. The jurisdiction Under Article 226 was rightly invoked by the Single Judge and the Division Bench of the Andhra Pradesh in this case, when the foundational representation of the contract has failed. TSIIC, a state instrumentality, has not just reneged on its contractual obligation, but hoarded the refund of the principal and interest on the consideration that was paid by Unitech over a decade ago. It does not dispute the entitlement of Unitech to the refund of its principal

19 August 2025

Neeta Sawant WP-395-2025-FC

54) In M/s. Utkal Highways Engineers and Contractors (supra),

the Apex Court has held in para-8 as under :-

8. Be that as it may, the High Court has not dealt with the merits of the writ petition. Moreover, it is not an inviolable rule that no money claim can be adjudicated upon in exercise of writ jurisdiction. Non-payment of admitted dues, inter alia, may be considered an arbitrary action on the part of respondents and for claiming the same, a writ petition may lie. Further, throwing a writ petition on ground of availability of alternative remedy after 10 years, particularly, when parties have exchanged their affidavits, is not the correct course unless there are disputed questions of fact which by their very nature cannot be adjudicated upon without recording formal evidence.

Thus, there cannot be an absolute bar in entertaining a writ

petition seeking refund of advance payment made to an

instrumentality of a State. There are no disputed questions of fact

in the present case, which can be decided only on law point of

permissibility to forfeit advance payment made by Petitioner in

absence of forfeiture clause in the contract.

55) In our view, therefore Petitioner's prayer for refund of

the advance payment of Rs.10,29,60,000/- appears to be reasonable.

However, we are not inclined to award any interest to the

Petitioner considering the time taken by it to file the present

petition. Considering the peculiar facts and circumstances of the

present case, it would be equitable if MADC refunds advance

payment of Rs.10,29,60,000/- to the Petitioner without any interest.






                                     19 August 2025

 Neeta Sawant                                                         WP-395-2025-FC


56)              We are inclined to order refund of the advance

payment to the Petitioner considering the peculiar facts and

circumstances of the present case as discussed above. Grant of

such equitable relief would cause no prejudice to either of the

parties. On the other hand, if MADC is permitted to retain the

advance amount, the same would amount to unjust enrichment as

MADC has already allotted 33 acres of land to other entities at

much higher rate. MADC is an instrumentality of State and is

expected to act fairly. It is not set up with the objective of doing

business of land development and disposal. MADC's objective is

to harness the potential of the Vidharbha region and to remove the

development backlog of the region. It is with this objective that

MADC pursued the proposal with Wipro for setting up its IT park

in the SEZ to attract large number of jobs for the youths in the

region. The transaction unfortunately could not go through. If

MADC was to suffer any financial losses, this Court would have

been loathe in ordering refund of the advance payment. However,

since MADC has been able to dispose of some part of the allotted

land at much higher rate of upto Rs. 2 crore per acre as compared

to the rate of Rs. 44 lakh per acre by the Petitioner, refund of

advance amount paid by Petitioner would balance the equities

between the parties. If the MIHAN project has indeed progressed,

and if the entire 117 acres of land is acquired by MADC, the

balance land is available with MADC to be allotted to other

entities at much higher rates. Therefore, no prejudice has been

19 August 2025

Neeta Sawant WP-395-2025-FC

suffered by MADC on account of any actions of the Petitioner. We

are not directing MADC to pay any interest to the Petitioner which

would provide some solace to MADC, which would enable it to

utilize the said amount for over 18 years without any interest. In

our view therefore ends of justice would meet if the advance

amount is directed to be refunded to the Petitioner without any

interest. It is however clarified that the direction for refund of

advance payment is being granted in the light of peculiar facts of

the present case.

57) We accordingly proceed to pass the following order :-

(i) MADC is directed to refund amount of Rs.10,29,60,000/-

to the Petitioner within a period of six weeks without any

interest.

(ii) Writ Petition is partly allowed to the above extent. Rule is

made partly absolute. There shall be no order as to costs.

                [SANDEEP V. MARNE, J.]                                    [CHIEF JUSTICE]


         Digitally
         signed by
         NEETA
NEETA    SHAILESH
SHAILESH SAWANT
SAWANT   Date:
         2025.08.19
         16:31:46
         +0530





                                                      19 August 2025

 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter