Citation : 2025 Latest Caselaw 4513 Bom
Judgement Date : 4 April, 2025
2025:BHC-AS:16300
901-AO-638-2024.docx
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
rrpillai CIVIL APPELLATE JURISDICTION
APPEAL FROM ORDER NO. 638 OF 2024
WITH
INTERIM APPLICATION NO. 12380 OF 2024
M/s. Mehta & Co.
through its Partner and authorized
representative Mr. Adarsh Varma
Digitally
signed by
RAJESHWARI
RAJESHWARI RAMESH
RAMESH PILLAI
Having its registered office at
PILLAI Date:
2025.04.08
08:23:14
+0200
Ground Floor, Plot No. 117/126,
... Appellant
St. Xaviers Street, Near Tata Hospital
(Original Plaintiff)
Parel, Mumbai - 400 012
Vs.
1. The Municipal Corporation of Greater
Mumbai through the Municipal
Commissioner, Having its Office at
Mahapalika Marg, Fort
Mumbai-400 001
2. The Assistant Commissioner (Estate)
... Respondents
F-South Ward, MCGM
(Original Defendants)
Parel, Mumbai-400012
Mr. Kunal Bhanage and Ms. Priyanka Acharya i/b. Mr. Akshay
Pawar for the Appellant/Applicant.
Mr. Chaitnya Chavan a/w. Mr. Amol Diwte and Mr. Om Suryavanshi
i/b. Ms. Komal Punjabi for BMC for the Respondent-BMC.
Mr. Mahesh Patil, Assistant Commissioner
Shri Subhash Sambre, Senior Estate Inspector.
Mr. Tukaram Ide, Estate Inspector.
1/36
::: Uploaded on - 08/04/2025 ::: Downloaded on - 19/04/2025 06:40:46 :::
901-AO-638-2024.docx
CORAM : GAURI GODSE, J.
DATE : 4th APRIL 2025
ORAL JUDGMENT :
1. This is an absolutely unfortunate case where the plaintiff's
structure is high-handedly and illegally demolished by the officers of
the Municipal Corporation of Greater Mumbai ("corporation") under
the garb of implementation of the redevelopment scheme under
Regulation 33(9) of Development Control and Promotion Regulation
2034 ("DCPR 2034"). The plaintiff was occupying the demolished
structure for the purpose of providing charitable services of food and
shelter to the poor and needy cancer patients receiving treatment
for cancer from the Tata Memorial Hospital. The plaintiff's structure,
which is demolished, was situated on a municipal plot that is the
subject matter of the redevelopment scheme, which is situated
adjacent to the Tata Memorial Hospital.
2. Pursuant to the order dated 14 th February 2025, the appeal is
taken up for final disposal at the admission stage. Since the
structure occupied by the plaintiff is held eligible for permanent
rehabilitation under the scheme as reflected in Annexure II, a
submission was made on behalf of the appellant on the very first
day of the hearing that the corporation may consider the plaintiff's
901-AO-638-2024.docx
entitlement under the redevelopment scheme for rehabilitation. The
appeal has been heard on various occasions, however, till date, the
learned counsel for the corporation has not received any positive
instructions on the suggestion made on behalf of the appellant. The
only reason for the lack of instructions for considering the
rehabilitation of the plaintiff is that the scheme for redevelopment
has already been floated; hence, the corporation would not be able
to rehabilitate the plaintiff.
3. Considering the manner in which the hearing of the appeal
has proceeded, I find it necessary to record that time was granted to
the learned counsel for the corporation to take appropriate
instructions from the concerned officers who are authorised to
decide on the plaintiff's entitlement. On 25 th March 2025, the
learned counsel for the corporation requested time to take
instructions from Mr. Mahesh Patil, Assistant Commissioner and Mr.
Prithviraj Chavan, Assistant Commissioner (Estate), with a
submission that the officers shall remain present on the next date to
enable the learned counsel for the corporation to respond to the
suggestion made on behalf of the appellant as recorded in the
earlier order dated 14th February 2025. Unfortunately, the officers
have never remained present before the court. Learned counsel for
the corporation submits that today Mr. Mahesh Patil, Assistant
901-AO-638-2024.docx
Commissioner, is present and is authorized to take decision
regarding the rehabilitation of the plaintiff. However, he submits that
the plaintiff cannot be rehabilitated at this stage. It is important to
record that admittedly, the demolition work has been carried out on
the instructions of Mr. Mahesh Patil, Assistant Commissioner. Since
there is no positive response from the corporation regarding the
rehabilitation of the plaintiff, the arguments on the merits of the
appeal are concluded today.
4. The appeal is preferred to challenge the refusal of the
plaintiff's various prayers in the notice of motion, mainly the prayer
for the reconstruction of the plaintiff's structure, which the
corporation's officers demolished without any notice of demolition.
The relevant facts leading to the reason for filing the suit and the
notice of motion are as follows :
(a) The plaintiff is held entitled to a permanent rehab
component as per Annexure-II dated 14 th November 2008 for
a commercial area of 538 sq.ft.
(b) The plaintiff's entitlement to a permanent rehabilitation
structure for the area, as reflected in Annexure II, is
undisputed.
901-AO-638-2024.docx
(c) The plaintiff had raised a dispute regarding the plaintiff's
entitlement to an area and claimed that the plaintiff would be
entitled to a larger area.
(d) In view of the application filed by the plaintiff,
measurement was carried out on the site with reference to the
assessment extract, and the plaintiff was found to be in
possession of 122.63 square meters, i.e. 1319.97 square feet.
The said measurement is recorded in the corporation's letter
dated 16th October 2023.
(e) Pursuant to the plaintiff's complaint and the society's
complaint, the hearing was given on 3 rd October 2023 to the
plaintiff and other concerned parties by the Assistant
Commissioner (F-South Ward). Based on the hearing and the
submissions made by the plaintiff and other affected parties,
the decision was taken on 11th October 2023, which is
recorded in a letter/order dated 18 th October 2023.
(f) The letter/order dated 18th October 2023 indicates that
the plaintiff's claim for a higher area was not accepted, and it
was held that the plaintiff would be entitled to 538 sq.ft. in the
permanent rehabilitation structure. The order further recorded
that as per the terms and conditions of the letter of intent, the
901-AO-638-2024.docx
developer shall make temporary arrangements for alternate
accommodation and accordingly submit an indemnity bond. It
is further recorded that the plaintiff should vacate the premises
within seven days, failing which the corporation would take the
necessary action as permissible in law.
(g) It is also recorded that as per the tenancy verification list
prepared by the corporation on 16th October 2008, the plaintiff
would be entitled to an area of 538 sq.ft in the permanent
rehabilitation structure.
(h) Thus, it was decided by the concerned Assistant
Commissioner that the plaintiff was required to vacate the suit
structure within seven days, failing which the corporation
would take the necessary action as contemplated under the
Mumbai Municipal Corporation Act, 1988 ("MMC Act") and the
applicable circulars and guidelines.
(i) Being aggrieved by the said decision, the plaintiff filed
L.C. Suit No. 73 of 2024 in the City Civil Court at Mumbai on
2nd January 2024. On 3rd January 2024, the plaintiff served
notice to the municipal corporation intimating that the court
would be moved for urgent relief on 4 th January 2024 at 2.45
pm.
901-AO-638-2024.docx
(j) In the morning of 4th January 2024, the corporation's
officers demolished the plaintiff's structure. Hence, the suit is
amended, seeking reliefs for a declaration that the demolition
of the plaintiff's structure was illegal, bad in law, and without
following due procedure. The plaintiff further prayed for
directing the corporation to reconstruct the plaintiff's structure
and, in the alternative, permitting the plaintiff to reconstruct the
structure at the corporation's cost.
(k) In view of the illegal demolition, the plaintiff filed Notice
of Motion No. 272 of 2024 seeking various reliefs, mainly
permission to reconstruct.
5. The corporation opposed the application on the grounds that
are summarized as follows:
(a) The redevelopment project and the approval of Annexure
II on 14th November 2008 were not in dispute. The
corporation contended that Annexure II consisted of 205
tenants, out of which 194 tenants were residential and six
were commercial. It was contended that though not eligible
for redevelopment, the sub-tenants were included for
membership in the rehab component. The corporation
relied upon a letter dated 14 th May 2021 addressed by the
901-AO-638-2024.docx
Deputy Chief Engineer to the Chairman of the Municipal
Chawl regarding a revised letter of intent for the proposed
redevelopment and the appointment of a new developer,
which was approved for cluster redevelopment scheme by
the High Power Committee on 29th July 2022.
(b)The corporation further referred to the complaint dated 14 th
September 2023 received from the society alleging illegal
use by the plaintiff and the business illegally carried out by
the plaintiff, alleging that there was non-cooperation in the
development work and the possession was not handed
over.
(c) The corporation further contended that the officers visited
the plaintiff in the plaintiff's structure, and after issuing
notice and giving opportunity of hearing the order dated
18th October 2023 was passed directing the plaintiff to
vacate the structure within seven days.
(d) It was contended that since the plaintiff failed to vacate the
structure, the demolition action was taken on 4 th January
2024 with police protection. Thus, the demolition carried
out on 4th January 2024 was contended to be taken based
on the order dated 18th October 2023.
901-AO-638-2024.docx
6. After considering the rival submissions of both parties, the
learned Judge of the City Civil Court rejected the notice of motion.
The learned Judge held that the suit structure was demolished
pursuant to the corporation's order dated 18 th October 2023. By
referring to the letter issued by the society and the approval of the
cluster redevelopment scheme in 2022, the learned Judge observed
that the relief in the main suit could not be granted at an initial
interim stage. The learned Judge held that the demolition action
was a triable issue for which the parties would be required to lead
evidence. Hence, the learned Judge refused to grant relief of
reconstruction to the plaintiff. Regarding other prohibitory reliefs, the
learned Judge held that the maintaining of the status quo of the
debris could not have been granted, as it can be compensated in
terms of money. Hence, the plaintiff has filed this appeal.
7. The submissions made by the learned counsel for the
appellant are summarised as follows:
(a)Except for the order dated 18 th October 2023 impugned in the
suit, the corporation failed to produce any order directing
demolition. Though the corporation was intimated on 3 rd
January 2024 about the interim relief that would be pressed
before the City Civil Court on 4 th January 2024 at 2.45 pm, the
901-AO-638-2024.docx
demolition work was carried out in the morning on 4 th January
2024 in undue haste even before the plaintiff's application for
interim relief could have been heard by the court.
(b) The plaintiff is carrying out charitable work by providing food
and shelter to cancer patients undergoing treatment for
cancer in Tata Memorial Hospital, which is adjacent to the land
where the plaintiff's structure was situated. Though the
plaintiff's tenancy rights were disputed, the plaintiff is held
entitled to a permanent rehab component as per Annexure-II.
(c) The plaintiff was never intimated about any transit
accommodation or payment of any transit rent as held entitled
in terms of the order dated 18 th October 2023. In the absence
of any temporary transit accommodation or transit rent being
made available to the plaintiff, there was never any occasion
for the plaintiff to vacate the suit structure as it was never
contemplated under the order dated 18th October 2023.
(d) Admittedly, none of the conditions directed in the order dated
18th October 2023 were at any time complied with calling upon
the plaintiff to accept transit accommodation or transit rent.
Therefore, the allegation of non-cooperation on the part of the
plaintiff is frivolous and baseless. Only to defeat the plaintiff's
901-AO-638-2024.docx
rights as claimed in the suit, a high-handed, arbitrary and
illegal action of demolition was deliberately carried out by the
officers of the corporation. Thus, the plaintiff suffered grave
hardship as the structure where charitable work was being
carried out for treating cancer patients was high-handedly
demolished by the corporation.
(e)The plaintiff was never served with any notice alleging any
illegal business or occupation in the suit structure. The plaintiff
is held entitled to a permanent rehab component, and though
the concerned Assistant Commissioner had issued directions
vide order dated 18th October 2023 for following terms and
conditions of the letter of intent, admittedly, no such
compliance was made before carrying out the demolition.
Thus, the action of the corporation of demolishing the suit
structure is, on the face of it, high-handed, illegal and arbitrary.
Thus, this is a fit case for exercising the discretion to grant a
mandatory injunction, either directing the corporation's erring
officers to reconstruct the suit structure or permit the plaintiff
to reconstruct the suit structure at the cost of the corporation.
(f) The learned Judge of the City Civil Court failed to consider the
important aspects of demolition being carried out without any
901-AO-638-2024.docx
order directing the plaintiff to vacate the structure or any order
intimating the plaintiff that the demolition work would be
carried out. The plaintiff relied upon the measurement carried
out by the corporation as recorded in the Corporation's letter
dated 16th October 2023. The measurement carried out as per
the actual occupation of the plaintiff is supported by the
assessment extracts. Thus, even if the plaintiff's entitlement
for the area claimed by the plaintiff as 1319.97 sq.ft is not
accepted by the corporation, the plaintiff was admittedly
occupying an area of 1319.97 sq.ft, which is high-handedly
and illegally demolished by the corporation. Hence, the
plaintiff is entitled to reconstruct an area of 1319.97 sq.ft. as
reflected in the measurement letter dated 16 th October 2023,
which also records the exact identification of the plaintiff's
structure.
8. The submissions made on behalf of the corporation are
summarized as follows:
(a)The redevelopment scheme is floated under Regulation
33(9) of the DCPR 2034. In the scheme, the rights of 208
occupants are affected. The corporation is under obligation
to consider the entitlement of all the occupants as per
Annexure II. Only due to the plaintiff's non-cooperation
901-AO-638-2024.docx
there were hurdles in the implementation of the
redevelopment scheme. The developer had already
intimated by letter dated 11th October 2023 that he was
ready to pay Rs.35,000/- per month for alternate
accommodation to the plaintiff, provided the possession
was handed over. Thus, it was always open for the plaintiff
to accept the transit rent from the developer and vacate the
suit structure. The plaintiff failed to do so; hence, the
corporation's officers were constrained to forcibly
dispossess the plaintiff and demolish the suit structure. The
concerned officers were well within their jurisdiction and
powers to dispossess the plaintiff and demolish the suit
structure.
(b) The directions in the order dated 18 th October 2023 are
clear and unambiguous. The order clearly called upon the
plaintiff to vacate the suit structure within seven days,
failing which the corporation would take action. Thus, there
was no requirement to issue any fresh notice calling upon
the plaintiff to vacate the suit structure.
(c) To support his submissions, learned counsel for the
corporation relied upon an internal communication dated 3 rd
901-AO-638-2024.docx
January 2024. Though the said communication was not
produced in the trial court, the learned counsel was
permitted to place it on record before this court. By the
internal communication dated 3rd January 2024, the
proposal of the Estate Officer, F South Ward, was
approved by the Assistant Commissioner for carrying out
demolition with police protection and placing on record a
report.
(d) Learned counsel for the corporation relied upon the
guidelines issued vide Circulars dated 17 th November 2020
and 25th May 2018. Learned counsel for the corporation
relied upon clauses (c), (e), (f) and (g) of the circular dated
17th November 2020. He submitted that pursuant to clause
(g) of the circular on receipt of tenancy verification and
after the tenancy verification by the concerned verification
committee, Annexure II is prepared. Pursuant to the letter
of intent issued, the officers are permitted to take action of
vacating the structures for the purpose of redevelopment.
Clause (iv) of clause (g) of the circular permits the officers
to take action of forcible dispossession in case of non-
cooperating tenants. In view of clauses 1.02, 1.08 and 1.10
901-AO-638-2024.docx
of the circular dated 25th May 2018, immediately after
completing the notice period of seven days, the action of
eviction and dispossession is permissible. Thus, pursuant
to the necessary guidelines issued by the two circulars, the
concerned officers carried out work of demolition after
taking police protection. Thus, the action of the corporation
cannot be termed as unauthorised or illegal.
(e)Learned counsel for the corporation fairly accepted that the
notice, as contemplated under Section 488 of the MMC
Act, was not issued before evicting the plaintiff and carrying
out the work of demolition. He, however, submits that even
if the action of the corporation is held that it was without
issuing any notice for actual demolition, the action of
demolition cannot be termed as a nullity and that, at the
most, the action would be irregular. He thus submits that
irregularity, if any, would not entitle the plaintiff to a prayer
of reconstruction at the interim stage. He thus submits that
the corporation would be entitled to lead evidence to
support their contention that the action was permissible.
(f) To support his submissions regarding the action being not
nullity and, at the most, can be termed as an irregularity on
901-AO-638-2024.docx
the part of the officers, learned counsel for the corporation
relied upon the decision of the High Court of Calcutta in the
case of Ashutosh Sikdar vs. Behari Lal Kirtunia1 and the
decision of the Apex Court in the case of Al-can Export
Private Limited vs. Prestige H. M. Polycontainers Limited
and Others2. According to the learned counsel for the
corporation, the full bench of the High Court of Calcutta
held that if an action is held to be in contravention of
Section 99 of the Transfer of Property Act, 1882, at the
most, the action can be held as an irregular action and
cannot be termed nullity. He submits that the view taken by
the Calcutta High Court is referred to by the Hon'ble Apex
Court in the case of Al-can Export Pvt. Ltd. He submits that
the Hon'ble Apex Court has considered the distinction
between nullity and irregularity. He, in particular, relied
upon paragraph 89 of the decision of the Hon'ble Apex
Court to support his submissions that the action of
demolition in any case cannot be termed nullity.
(g)Learned counsel for the corporation submitted that if on the
ground of irregularity, if any, the plaintiff is granted the order
of reconstruction at this stage, it would amount to getting
(1907) I.L.R. 35 Cal.61
(2024) 9 SCC 94
901-AO-638-2024.docx
unjust gain by the court's order. To support this submission,
the learned counsel for the corporation relied upon the
decision of the Apex Court in the case of Goa State
Cooperative Bank Limited vs. Krishna Nath A (Dead)
Through Legal representatives and Others3.
(h) Learned counsel for the corporation submitted that a
drastic relief of reconstruction at this stage would amount
to the grant of final reliefs in the suit. At the interim stage,
the plaintiff would not be entitled to a relief of mandatory
injunction. Since demolition work was carried out due to the
non-cooperation on the part of the plaintiff, he would not be
entitled to any equitable relief. A mandatory injunction in
such a form can be granted only in exceptional and rare
cases. To support his submissions, learned counsel relied
upon the decision of this court in the case of Mumbai
Municipal Corporation of Greater Mumbai vs. Sushilaben I
Patel4. He submitted that this court has taken a view that
mere illegality would not warrant such a drastic order
unless it was established that the action was a malafide
action done with any ulterior purpose to defeat the claim.
(2019) 20 SCC 38
SCC OnLine Bom 954
901-AO-638-2024.docx
(i) Learned counsel for the corporation relied upon the well-
established legal principles on the grant of mandatory
injunction as settled by the Hon'ble Apex Court in the case
of Dorab Cawasji Warden vs. Coomi Sorab Warden and
Others5. He submitted that the plaintiff's grounds for a
mandatory injunction do not satisfy the guidelines issued
by the Hon'ble Apex Court. The present case cannot be
termed as an exceptional case warranting the grant of any
drastic relief of mandatory injunction.
(j) If granted, the mandatory relief sought by the plaintiff would
jeopardise the rights of 208 occupants who are to be
rehabilitated under the redevelopment scheme. Thus,
neither equity nor balance of convenience falls in the
favour of the plaintiff. Thus, according to the learned
counsel for the Corporation, this is not a case for granting
drastic relief of mandatory injunction.
9. To consider the submissions made by both parties, I have very
carefully gone through the entire record of the appeal. I have also
permitted the learned counsel for the corporation to place on record
the copies of internal communication dated 3 rd January 2024 and
(1990)2 SCC 117
901-AO-638-2024.docx
the letter dated 11th October 2023 issued by the developer, and
copies of the circulars, though the same, were never produced
before the trial court. The reply filed by the corporation is bereft of
any explanation that would support the corporation's action as
sought to be relied upon based on the internal communication dated
3rd January 2024 and the circulars.
10. A perusal of the order dated 18 th October 2023, clearly
indicates that the direction to the plaintiff to vacate the suit structure
within seven days was not a final notice to the plaintiff. The order of
the corporation clearly records that the terms and conditions of the
letter of intent, including the indemnity bond by the developer, were
to be submitted. The order records the plaintiff's entitlement to 538
sq.ft in the permanent rehab component. The Order further clearly
indicates that after seven days, if the suit structure is not vacated,
appropriate action under the MMC Act and the applicable circulars
would be adopted. Thus, on a plain reading of the directions of the
order dated 18th October 2023, there can be no doubt that the
plaintiff was never called upon to vacate the suit structure without
compliance with the other directions as issued in the order
regarding alternate arrangements.
901-AO-638-2024.docx
11. Admittedly, after the order dated 18 th October 2023, no
communication was served upon the plaintiff. The only letter relied
upon by the learned counsel for the corporation is the letter dated
11th October 2023, which, according to the learned counsel for the
corporation, is submitted by the developer with the corporation. I
have perused the letter. The letter is a conditional offer by the
developer to make a payment of Rs.35,000/- per month for alternate
accommodation to the plaintiff, provided the plaintiff submits legal
documents of the tenancy. The corporation has already approved
the plaintiff's entitlement to the permanent rehab component, and
accordingly, the plaintiff's name is included in Annexure II. Hence,
there is no question of the plaintiff submitting tenancy documents to
the developer. Thus, the said letter can, in no terms, be termed as
due compliance with the directions issued in the order of 18 th
October 2023. The letter relied upon by the learned counsel for the
corporation makes the corporation's intention clear that in the
absence of any arrangement for temporary alternate
accommodation, the corporation, in undue haste and with a
complete lack of sensitivity, has demolished the suit structure.
Reliance placed by the corporation on the developer's letter smacks
of malafide action. It is pertinent to note that after this letter the
order dated 18th October 2023 is passed for due compliance.
901-AO-638-2024.docx
12. I find it impossible to accept the submissions made on behalf
of the corporation that the action of demolition was pursuant to the
guidelines published by the circular dated 25 th May 2018, read with
the circular dated 17th November 2020. By the circular dated 25 th
May 2018, general guidelines are issued for declaring private and
municipal buildings as C-1 category (Dangerous, Unsafe), in line
with the guidelines issued by this court in Writ Petition (L) No. 1135
of 2014 and the guidelines circulated by the government regarding
the dangerous and dilapidated buildings. It is, therefore, difficult to
understand how the said guidelines would apply in the present
case. Even if, for the sake of arguments, it is accepted that the
guidelines were applicable, the guidelines provide for a complete
procedure of issuing notice under Section 354 of the MMC Act after
the initial procedure about structural audit report, etc., is completed.
Clause 1.08 provides that a notice under section 354 to pull down
the structure with a time period of seven days shall be issued by
following due process. As per clause 1.10, after seven days notice
period, the action of disconnection of the water supply, electricity,
gas supply, etc. shall be initiated to safeguard and evacuate the
building. Thereafter, the procedure to evict follows. The relevant
guidelines thus indicate that even in the case of vacating the C-1
category, building safeguards are provided under the circular. Thus,
901-AO-638-2024.docx
even in case of exigency, the relevant basic principles of natural
justice are required to be followed as per the guidelines of giving
notice of eviction and demolition.
13. By the circular dated 17th November 2020, revised procedural
guidelines are issued for the redevelopment of municipal tenanted
properties. Even this circular provides for appropriate provisions for
providing transit accommodation to the tenants till the completion of
the rehab building by the developer. Clause (g) of the circular dated
17th November 2020 reads as under:
" G) Vacating of dilapidated building:-
i. After receipt of IOD/CC, it shall be the responsibility of
the developer, to provide transit accommodation to the
tenants/occupants till completion of the rehab building;
either providing in-situ Transit Camp or providing rent of
the premises during the transit period.
Developer shall open "Escrow Account' & deposit one
year's rent in that 'Escrow Account' before vacating the
existing building. And further rent should also be
deposited in advance two months before the expiry of
the period, for further one year & so on till completion of
the project. In nutshell, Developer shall ensure
901-AO-638-2024.docx
depositing the rent in advance in the 'Escrow Account'
as above till completion of the project.
ii. Developer/Society shall submit the details of such
'Escrow Account' to AO (Society) who shall monitor the
issue of transit rent to avoid delay and bring the delay, if
any, to the notice of AC (Estate) so that preventive
action is taken.
iii. Developer and/Society has then to get vacated the
dilapidated buildings categorized C1 and C2A as per the
Structural Auditor's report immediately (but not later than
one month, in any case) on receipt of LOI.
iv. In case of non-co-operation of tenant to vacate the
premises even after providing rent/transit
accommodation, same shall be brought to the notice of
Assistant Commissioner of ward with proofs of providing
alternate accommodation or transit rent. In such cases,
Assistant Commissioner of Ward shall initiate action on
non-co-operative tenants as per the guidelines dated
25.05.2018 for declaring private and municipal buildings
as C1 cateogry (Dangerous, unsafe). Also action under
section 105B of MMC Act, 1988, for cancellation of
901-AO-638-2024.docx
tenancy will be initiated by Assistant Commissioner of
Ward.
v. The Developer has to repair the buildings as per the
report of Structural Auditor till the time it gets vacated in
case of C2A buildings. Developer shall also provide
propping and to take all safety measures, the
Developer/Society will be solely responsible to take all
safety measures, vacate and repair of the dilapidated
buildings once the LOI is issued.
vi. In case of failure to take necessary action in respect of
dilapidated building even on intimation, within
reasonable time, LOI issued will be cancelled.
vii. If there are any complaints before any statutory forum or
any litigation before any Court of Law, relating to the
redevelopment project, structural audit, repairs, eviction,
demolition of structures, non-payment of rent/alternate
accommodation etc. entire direct and indirect cost
incurred by MCGM on this shall be borne by
Society/developer and shall be paid to MCGM on raising
demand to that effect.
901-AO-638-2024.docx
14. The circular thus provides for the arrangement of transit
accommodation before taking action, even in the case of non-
cooperating tenants. The circular refers to the guidelines dated 25 th
May 2018 for the purpose of evicting non-cooperating tenants.
Thus, both the circulars relied upon by the learned counsel for the
corporation refer to following basic principles of natural justice of
intimating occupants to vacate the structure and an obligation on
the part of the developer to provide alternate transit accommodation
and payment of transit rent. Thus, even as per the guidelines relied
upon by the Corporation, before taking any action for demolition,
arrangement of transit accommodation and action of eviction must
be followed. In the present case, neither the steps were taken to
evict the plaintiff nor any intimation was given for demolition.
15. In the present case, except for a vague letter dated
11th October 2023 by which the developer has given a conditional
offer to make payment, admittedly, no provision is made for the
plaintiff for transit rent or transit accommodation. Thus, the
guidelines relied upon by the learned counsel for the corporation
itself is sufficient ground to hold that without following due process
and without any intimation to the plaintiff, the officers of the
corporation, in unholy haste, demolished the plaintiff's structure on
901-AO-638-2024.docx
the same day in the morning when the officers were already put to
notice that the plaintiff would make an application for relief from the
court.
16. The legal principles for granting a mandatory injunction are
well settled in the decision of the Hon'ble Apex Court in the case of
Dorab Cawasji Warden. The relevant guidelines for granting a
mandatory injunction are summarised in paragraphs 16 and 17,
which read as follows:
"16. The relief of interlocutory mandatory injunctions are thus granted generally to preserve or restore the status quo of the last non-contested status which preceded the pending controversy until the final hearing when full relief may be granted or to compel the undoing of those acts that have been illegally done or the restoration of that which was wrongfully taken from the party complaining. But since the granting of such an injunction to a party who fails or would fail to establish his right at the trial may cause great injustice or irreparable harm to the party against whom it was granted or alternatively not granting of it to a party who succeeds or would succeed may equally cause great injustice or irreparable harm, courts have evolved certain guidelines. Generally stated these guidelines are:
(1) The plaintiff has a strong case for trial. That is, it shall be of a higher standard than a prima facie case that is normally required for a prohibitory injunction.
901-AO-638-2024.docx
(2) It is necessary to prevent irreparable or serious injury which normally cannot be compensated in terms of money. (3) The balance of convenience is in favour of the one seeking such relief.
17. Being essentially an equitable relief the grant or refusal of an interlocutory mandatory injunction shall ultimately rest in the sound judicial discretion of the court to be exercised in the light of the facts and circumstances in each case. Though the above guidelines are neither exhaustive nor complete or absolute rules, and there may be exceptional circumstances needing action, applying them as prerequisite for the grant or refusal of such injunctions would be a sound exercise of a judicial discretion."
emphasis applied
17. The aforesaid peculiar facts of the case clearly show that the
corporation's officers have shown a complete lack of sensitivity
while proceeding with the demolition of the structure which the
plaintiff used for providing food and shelter to the cancer patients
undergoing treatment in Tata Memorial Hospital. In a city like
Mumbai, it is very difficult to get temporary shelter. Thus, I have no
doubt in holding that the action of demolition has not only deprived
the plaintiff of his rights but also deprived the cancer patients of their
right to temporary shelter at the time of taking treatment.
901-AO-638-2024.docx
18. Though the learned counsel for the corporation disputes that
the plaintiff is carrying out the activity of providing food and shelter
to the cancer patients, I see no reason to disbelieve the plaintiff's
contention. Till date, there is never any notice issued to the plaintiff
regarding the activities carried out by the plaintiff. A plain denial in
the reply would not be sufficient to disbelieve the plaintiff's
contention in the absence of any material on record that the plaintiff
is not carrying out such noble charitable activity. Even otherwise,
the plaintiff is highhandedly deprived of using his structure, which is
held eligible for permanent rehab in the redevelopment project.
19. Under Article 51-A of the Constitution of India, it is a
fundamental duty of every citizen to follow and abide by the laws.
The corporation's officers are bound by the provisions of the MMC
Act. They are under obligation to follow the process of law in its true
spirit. The propriety of the law and the peculiar facts of this case
demand justice by granting relief as prayed by the plaintiff.
20. This is indeed a rare and exceptional case where the grant of
mandatory injunction must be issued in favour of the plaintiff. Not
granting an injunction would amount to putting a premium on the
high-handedness and arbitrary action of the corporation's officers. In
the present case, the trial court has ignored the well-settled
901-AO-638-2024.docx
principles of law for granting mandatory injunction. Not exercising
the discretion to grant relief of injunction in such gross facts would
amount to refusing the relief on unreasonable grounds. Thus, the
view taken by the learned Judge of the City Civil Court is palpably
incorrect and untenable.
21. Learned counsel for the corporation fairly admitted that the
notice contemplated under Section 488 of the MMC Act was not
issued. Hence, according to the learned counsel for the corporation,
the action of demolition would, at the most, amount to irregularity. In
the absence of compliance with the directions issued by the order
dated 18th October 2023, I have no manner of doubt that the
corporation's officers have acted high-handedly and arbitrarily for
the reasons best known to them. Unholy haste shown on behalf of
the corporation officers to demolish the structure without any
intimation, and on the day when the plaintiff was to pray for interim
relief before the court after notice to the corporation, smacks of
malafides and arbitrariness. Internal communication dated 3 rd
January 2024 relied upon to show the directions for demolition, has
a peculiar wording. The communication dated 3 rd January 2024
signed by the Estate Officer and approved by the Assistant
Commissioner on 3rd January 2024, records that "आज दि .
901-AO-638-2024.docx
04.01.2024 रोजी पोलीस बं ोबस्त उपलब् झालेला आहे." Thus, it appears
that a hasty note dated 3 rd January 2024 was prepared on 4 th
January 2024 to carry out demolition even before the plaintiff could
move the court for urgent relief.
22. Thus, the well-settled triple test for the grant of discretionary
relief is satisfied in favour of the plaintiff. The plaintiff has proved a
prima facie case of his entitlement to a permanent rehab component
in terms of Annexure II. The only dispute is regarding the actual
area. The actual area for permanent rehab is not an issue under
consideration in this appeal. However, the documents and, more
particularly, the measurement recorded as per the letter dated 16 th
October 2023 is clear that the plaintiff was occupying an area of
1319.97 sq.ft. I have also recorded that the plaintiff and the cancer
patients who were provided shelter in the suit structure have been
deprived of their right to shelter. Hence, there is no doubt that there
is an irreparable loss to the plaintiff if the injunction is not granted. In
view of the reasons recorded, it is also clear that the balance of
convenience is in favour of the plaintiff. Thus, the impugned order
requires interference by this court.
23. The legal principles relied upon by the learned counsel for the
corporation in the decision of this court in the case of Sushilaben
901-AO-638-2024.docx
Patel would not be of any assistance to the arguments raised on
behalf of the appellant. The observation by this court regarding the
grant of mandatory relief in the case of the action of demolition
being malafide supports the plaintiff's case. It is unfortunate that the
learned counsel for the Corporation has relied upon the legal
principles in the decision of Goa State Cooperative Bank Limited
and submitted that a person should not get unjust gain by the
court's order. The question involved in the decision of the Apex
Court was whether, under the provisions of Section 109 of the
Maharashtra Cooperative Societies Act 1960, on expiry of the
period fixed for liquidation, the proceedings for recovery of dues
instituted/pending as against the members shall stand closed. In
view of the facts of the case regarding the loan granted to the
members of the society, the Hon'ble Apex Court observed that a
person who has liability, cannot be permitted to reap the advantages
on the basis of interim orders of the court. Thus, it was observed
that no one should be allowed to use the judicial process for earning
undeserved gains or unjust profits. In the gross facts of the present
case, where the Corporation's officers have highhandedly and
arbitrarily demolished the plaintiff's structure, it is unfortunate that
instead of rectifying the action, such unfair and unreasonable
submissions are made by the Corporation.
901-AO-638-2024.docx
24. In the facts and circumstances of the case as discussed
above, and for the reasons recorded above, I do not find any
substance in the arguments made on behalf of the Corporation that
the action of the officers would, at the most, be an irregularity and
thus, the plaintiff would not be entitled to a mandatory injunction as
prayed. I have recorded reasons to hold that the Corporation's
officers failed to follow the basic principles of natural justice and
have shown complete disregard towards their fundamental duties by
not following the prescribed procedure under the MMC Act and the
guidelines issued by the Corporation. Therefore, the legal principles
settled in the decision of the Calcutta High Court and in the decision
of the Hon'ble Apex Court in the case of Al-Can Export Private
Limited, are of no assistance to the arguments made on behalf of
the Corporation. The decision of the Calcutta High Court was
concerning non-compliance with Section 99 of the Transfer of
Property Act. The decision of the Hon'ble Apex Court concerns the
recovery of debts and the auction sale conducted for recovering
dues. Hence, I do not find any substance in the arguments made by
the learned counsel for the Corporation, by relying upon the said
decisions.
25. For the reasons recorded above, I am convinced that the
901-AO-638-2024.docx
action of demolition in this case is highly arbitrary and malafide, as
no due process has been followed. Hence, the plaintiff is entitled to
restoration of the status quo ante. However, the fact that the grant
of mandatory injunction to reconstruct is likely to affect the
redevelopment process where the rights of 208 occupants are also
involved cannot be ignored. Hence, to balance the equities, the
reliefs prayed by the plaintiff can be modified by directing the
corporation to provide a temporary alternate accommodation
equivalent to the area that was occupied by the plaintiffs, i.e.
1319.97 sq.ft as recorded in the letter dated 16 th October 2023 in
the same vicinity. The noble activities carried out by the plaintiff to
provide food and shelter to cancer patients undergoing treatment at
Tata Memorial Hospital are important factors to be considered when
providing temporary alternate accommodation. Hence, the plaintiff is
entitled to temporary alternate accommodation in the equivalent
area in the same vicinity. However, I find it necessary to clarify that
the grant of any temporary alternate accommodation of the
equivalent area would have no effect on the entitlement of the
plaintiff for the permanent rehab component, which will be decided
in accordance with the law in the implementation of the
rehabilitation scheme under DCPR 2034 as applicable under the
redevelopment scheme. Hence, the appeal deserves to be allowed
901-AO-638-2024.docx
by issuing necessary directions to the corporation to provide
temporary accommodation.
26. The aforesaid facts of the case indicate that in the absence of
any due process, the corporation's officers high-handedly, arbitrarily
and insensitively demolished the plaintiff's structure. Hence, the
appeal deserves to be allowed with costs. Considering the gravity of
the illegal action taken by the corporation, the cost in favour of the
plaintiff can be quantified at Rs. 2,00,000/- which shall be paid by
the corporation. The corporation would be at liberty to recover the
amount of costs from the erring officers.
27. Hence, for the reasons recorded above, the appeal is allowed
by passing the following order :
(i) The order dated 26th June 2024 passed in L.C. Suit
No. 73 of 2024 is quashed and set aside.
(ii) The corporation shall provide temporary alternate
accommodation for an area equivalent to 1319.97
sq.ft in the same vicinity to the plaintiff within four
weeks from today.
(iii) It is clarified that temporary alternate accommodation
will be provided till the handing over of the permanent
901-AO-638-2024.docx
rehab component to the plaintiff as permissible under
the redevelopment scheme.
(iv) The plaintiff would be entitled to the temporary transit
accommodation only till the rehab component is
offered to the plaintiff by following the necessary
procedure under the rehabilitation scheme.
(v) The corporation shall pay the amount of
Rs.2,00,000/- towards the cost of litigation to the
plaintiff. Costs shall be paid directly to the official
representative of the plaintiff within four weeks from
today.
(vi) The corporation is at liberty to recover the amount of
cost from the erring officers.
(vii) The appeal is allowed in the aforesaid terms.
(viii) All concerned to act on an authenticated copy of this
order.
28. Learned counsel for the corporation at this stage seeks a stay
of the implementation of this order. Considering the gravity of the
facts and insensitivity shown by the corporation in demolishing the
plaintiff's structure, I do not find any reason to stay the
implementation of this order.
901-AO-638-2024.docx
29. At this stage, I find it necessary to record that despite giving
various opportunities to the concerned officers to respond to the
suggestions made on behalf of the appellant and rectify the action,
complete disregard was shown to the court by the officers by not
even remaining present. This court recorded the request of the
learned counsel for the corporation in an order dated 25 th March
2025. The request of the learned counsel for the corporation was
granted to grant an opportunity to the officers of the corporation to
consider rectifying the illegal action, however, on 26 th March 2025,
the officers remained absent. Hence, the appeal was required to be
adjourned again. Even today, out of the two officers, only one officer
has remained present. I do not have any doubt in recording that the
officers of the corporation have not only acted high-handedly and
arbitrarily but have also shown disregard to the court by not
providing appropriate instructions to the learned counsel for the
corporation at the appropriate stage. Hence, I see no reason to
grant stay to the implementation of this order. Hence, the prayer is
rejected.
[GAURI GODSE, J.]
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!