Thursday, 14, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Chiplun Sand Mining And Trading ... vs The State Of Maharashtra Through The ...
2024 Latest Caselaw 14390 Bom

Citation : 2024 Latest Caselaw 14390 Bom
Judgement Date : 7 May, 2024

Bombay High Court

Chiplun Sand Mining And Trading ... vs The State Of Maharashtra Through The ... on 7 May, 2024

Author: A. S. Chandurkar

Bench: A. S. Chandurkar

  2024:BHC-AS:21259-DB
TAUSEEF               Tauseef                                                         908-WP.4263.2024-J.doc
LAIQUEE
FAROOQUI                            IN THE HIGH COURT OF JUDICATURE AT BOMBAY
Digitally signed by                         CIVIL APPELLATE JURISDICTION
TAUSEEF LAIQUEE
FAROOQUI
Date: 2024.05.08
10:27:36 +0530                                  WRIT PETITION NO.4263 OF 2024

                      1.        Chiplun Sand Mining & Trading Corporation,
                      2.        Om Sai Enterprises,
                      3.        R.R. enterprises,
                      4.        Bashir Hamdule,
                      5.        Gurunath Yashwant Patkar.               ...Petitioners
                                Versus
                      1.        The State of Maharashtra,
                                through its Secretary,
                                Ministry of Forest and Revenue,
                                Mantralaya, Mumbai-400032.

                      2.        The Collector, Raigad,
                                having office at Alibaug,
                                District Raigad.

                      3.        The Collector, Ratnagiri,
                                Having his office at Ratnagiri.

                      4.        The Collector, Sindhudurg,
                                Having his office at Sindhudurg.

                      5.        The Mining Officer, Ratnagiri,
                                Having his office at Ratnagiri.

                      6.        The Mining Officer, Raigad,
                                having his office at Raigad at Alibaug.

                      7.        The Mining Officer, Sindhudurg,
                                Having his office at Sindhudurg.                 ...Respondents

                                                            __________

                      Mr. Mihir Desai, Senior Advocate i/b. Mr. Onkar Warang for the
                      Petitioners.
                      Mr. P. Kakade, G.P. a/w Mr. N. C. Walimbe, Addl. G. P. and Ms. G. R.
                      Raghuwanshi, AGP for Respondent-State.
                                                   __________



                                                              1 of 11



                      ::: Uploaded on - 08/05/2024                       ::: Downloaded on - 09/05/2024 09:31:55 :::
 Tauseef                                                       908-WP.4263.2024-J.doc




                               CORAM             :       A. S. CHANDURKAR,
                                                         JITENDRA JAIN, J.J.

Date on which the Arguments were Heard :                 2nd MAY 2024.
Date on which the Judgment is Pronounced :               7th May 2024.

JUDGMENT :

- (Per Jitendra Jain, J.)

1. Rule. Rule made returnable forthwith. By consent of the

parties, the petition is heard finally.

2. This Writ Petition under Article 226 of the Constitution of

India is filed by five Petitioners who were successful bidders of the

tender floated by the Respondent-State for excavation of sand from the

river/creek beds and to transport the extracted sand to the depot

created for storage of the said sand and for management of the said

depot. Although, various prayers have been sought in the petition, the

effective prayer pressed for our consideration is writ of mandamus

directing Respondents not to make Government Resolution dated 16 th

February 2024 applicable to the contracts executed between the

Petitioners and the Respondent-State pursuant to tender dated 24 th May

2023.

Brief facts are as under:-

3. On 19th April 2023, the Respondent-State issued a Government

Resolution detailing comprehensive policy regarding extraction, storage

and sale of sand through online process. The objective of the said policy

2 of 11

Tauseef 908-WP.4263.2024-J.doc

was not to extract the sand commercially but to make it available for

development work and also to avoid flood like situation which may arise

due to accumulation of sand in river bed. Therefore, the Government on

experimental basis, issued the said policy, for a period of one year with

an objective to make the sand available to the citizens in the State at a

cheaper rate and to curb unauthorised extraction. The said policy also

provided for the terms and conditions regarding depot construction and

management. The rate for sale of sand as per the said policy was

determined at Rs.600/- per brass for one year for the entire State on

experimental basis and the amount of royalty would be waived. The

expenses of sand transportation will have to be borne by the citizens.

The said policy also had a mechanism for redressal of grievances in sand

extraction by a Committee at district level.

4. Pursuant to the above policy, on 24th May 2023, Respondent-

State published the tender inviting the contractors to bid for sand

extraction. The Petitioners along with other bidders applied for the said

tender and ultimately the Petitioners were allotted the tender for five

different sites. The successful bidders were issued a LOI and, thereafter,

the Respondent-State and the Petitioners executed an agreement on 29 th

August 2023. In the present petition, one such agreement is enclosed

between the Respondent-State and Petitioner No.1.





                                      3 of 11




 Tauseef                                                      908-WP.4263.2024-J.doc


5. On 16th February 2024, Respondent-State issued another

Government Resolution dated 16th February 2024 for extraction of the

sand. The said Government Resolution dated 16 th February 2024

modified and superseded earlier Government Resolution dated 19 th April

2023 and a revised sand policy came to be issued by the said

Government Resolution dated 16th February 2024. Chapter 10 of the said

Government Resolution provides that the sand depots which are

operative as per the provisions of earlier Government Resolution dated

19th April 2023 will continue to operate in the same manner. However,

the terms and conditions for the said sand depot will be applicable as

per this revised sand policy. Further the sale cost of sand/gravel

mentioned in Chapter No.6 (III) in the revised policy, will be applicable

from the date of the new Government Resolution dated 16 th February

2024. It is on this backdrop that the Petitioners are before us.

Submissions of the Petitioners:-

6. The primary contention of the Petitioners is that Respondent-

State cannot unilaterally change the terms and conditions of the

agreement dated 29th August 2023, which was executed pursuant to the

tender floated on 24th May 2023. The Petitioners submit that this would

be contrary to the principle of promissory estoppel and also contrary to

the contract executed between the Petitioners and the Respondent-State.





                                     4 of 11




 Tauseef                                                      908-WP.4263.2024-J.doc


The Petitioners submitted that they have arranged their business affairs

on the basis of the agreement executed on 29 th August 2023 and now

the Respondent-State cannot unilaterally make Government Resolution

dated 16th February 2024 applicable to such contract. The action of the

Respondent-State, therefore, is unfair and contrary to the decision of the

Coordinate Bench of this Court in the case of Musale Constructions,

Builders and Contractors, Nagpur Vs. Vidarbha Irrigation Development

Corporation, Nagpur & Anr.1. The Petitioners further submitted that on

account of onset of the monsoon season, the sand extracted and lying on

the beds will be washed away and huge loss would be incurred. The

Petitioners in its rejoinder have enclosed month-wise daily lifting chart

for the period December 2023 to April 2024 and submitted that post

introduction of the impugned Government Resolution, the daily lifting

has reduced substantially. The Petitioners have, therefore, prayed for a

declaration that Respondent-State cannot unilaterally make the

Government Resolution dated 16th February 2024 applicable to the

contract executed under the earlier Government Resolution dated 19 th

April 2023.

Submission of Respondent-State:-

7. Per contra, the learned counsel for Respondent-State submitted

that the petition is misconceived. The Respondent-State brought to our

1 2021 (1) Mah.L.J. 355

5 of 11

Tauseef 908-WP.4263.2024-J.doc

notice the reply filed by the State, wherein it is stated that the

Petitioners would receive the same amount as they were receiving under

the old policy. The Respondent-State also justified the issuance of the

impugned Government Resolution dated 16 th February 2024, which was

issued on the basis of no profit no loss policy and the Respondent-State

further submitted that sale of sand is not included in the tender and,

therefore, the Petitioners have nothing to do with the sale of sand. The

Respondent-State has also filed a chart giving comparative table of the

policy dated 19th April 2023 and revised policy dated 16 th February

2024. The Respondent-State, therefore, prayed for dismissal of the

present petition.

8. We have heard the learned Senior Counsel for the Petitioners

and the learned counsel for Respondent-State and with their assistance

have perused the documents, reply and rejoinder filed in the present

proceedings which were brought to our notice.

Analysis and Conclusion:-

9. There is no dispute that the agreement executed by the

Petitioners and Respondent-State on 29th August 2023 was for a

maximum duration of one year or until the sand reserved of the said

sand gat is exhausted. Clause 2 of the said agreement further provides

that the period of authorisation shall expire on 9 th June 2024 and from

6 of 11

Tauseef 908-WP.4263.2024-J.doc

10th June to 30th September on account of monsoon, sand mining cannot

be done during the said period. There is no clause in the agreement

which empowers the Respondent-State to change the terms and

conditions unilaterally. It is also a settled position in law that contract

executed between two parties cannot be changed or modified unless

both the parties to the contract agrees to the said changes or

modification. In the absence of any clause in the agreement dated 29 th

August 2023, the Respondent-State cannot alter or modify the said

agreement unilaterally.

10. Clause (4) of Chapter 10 of the Government Resolution dated

16th February 2024 provides that the sand depots which are operative as

per the provisions of Government Resolution dated 19 th April 2023 will

continue to operate in the same manner. However, in the same clause it

is also provided that the terms and conditions for such sand depots

would be as per the revised sand policy of 16 th February 2024. The said

clause further provides that the sale and cost of sand/gravel mentioned

in Chapter No.6 in the revised policy of 16 th February 2024 will be

applicable from the date of Government Resolution dated 16 th February

2024. In our view, the said clause is self contradictory. On the one hand

the Government Resolution of 16th February 2024 provides that the sand

depots operating as per earlier Government Resolution of 19 th April

7 of 11

Tauseef 908-WP.4263.2024-J.doc

2023 would continue to operate in the same manner, but later on states

that the terms and conditions of the revised sand policy as per

Government Resolution dated 16th February 2024 would be applicable to

such sand depots. This would also amount to modifying the agreement

dated 29th August 2023 executed between the Petitioners and

Respondent-State. We have already opined that agreement dated 29 th

August 2023 cannot be modified unilaterally. There is no approval by

the Petitioners to the applicability of the terms and conditions of the

revised sand policy to the agreement dated 29 th August 2023. Hence

clause (4) of Chapter 10 of Government Resolution dated 16 th February

2024 to the extent it makes the terms and conditions of the said

Government Resolution applicable to the agreement dated 29 th August

2023 cannot be applied to the Petitioners.

11. The Respondents in their reply have also admitted that the

Petitioners would receive the same amount as they were receiving under

the old policy of 19th April 2023 pursuant to which the agreement of 29 th

August 2023 was executed. If that be so, then we fail to understand as

to why in the Government Resolution dated 16 th February 2024 the

terms and conditions of the revised sand policy is made applicable to the

existing sand depots. In our view, the contracts awarded to the

Petitioners pursuant to Government Resolution of 19 th April 2023 would

8 of 11

Tauseef 908-WP.4263.2024-J.doc

govern the agreement executed on 29 th August 2023. The Government

Resolution dated 16th February 2024 would be applicable only to the

tenders to be issued thereafter and not to the Petitioners contracts which

were executed by the Petitioners and the Respondent-State prior to the

Government Resolution of 16th February 2024 coming into force.

12. As per agreement of 29th August 2023, Clause 20 provides that

the tenderer shall excavate the sand from the quarry sand Ghat and shall

transport the sand by boat/barge to the sand depot on the shore and

transport the sand from the boat/barge to the shore by 6 wheel tipper

with the help of a crane and from there directly bring the sand to the

sand depot. Sand will not be allowed to be stored/discharged along the

bay shore. Clause 22 of the terms and conditions regarding

"Establishment and Management of Depot" of the said agreement

provides that the tenderer shall excavate sand from the river bay basin

and store the sand suitable for construction in the sand depot.

Therefore, the obligation of storing the sand in sand depot is that of the

Petitioners and not the Respondent-State. The other provisions relating

to protection of sand also indicates that the responsibility is that of the

contractor-Petitioners. Therefore, in our view, the Petitioners are not

justified in contending that at the time of onset of the monsoon they will

suffer loss on account of washing away of the sand. It is for the

9 of 11

Tauseef 908-WP.4263.2024-J.doc

Petitioners to make necessary arrangement as per the agreement to store

the sand to avoid it being washed away and it is not the responsibility of

the Respondent-State.

13. Under the agreement executed on 29th August 2023, there is

no obligation on the Respondent-State that they would lift minimum

quantity of sand everyday or every month. Therefore, the contention of

the Petitioners in the rejoinder that post February 2024 there is a

substantial reduction in lifting of the sand is not justified. The sale of

sand is online and no malafides can be attributed to the Respondent-

State on this count.

14. The Petitioners are justified in placing reliance on the decision

in the case of Musale Constructions, Builders and Contractors, Nagpur

(supra), wherein the Coordinate Bench of this Court in paragraph 16 has

observed as under :-

"16. In the case in hand, the issue as to price adjustment of the difference in increase in the royalty charges is covered by the terms of the contract tender agreements/contract, particularly Clause 33 of the said terms and conditions of the tender agreement, which have been acted upon and implemented since the date of tender agreements. In this view of the matter, according to us, the petitioner has rightly invoked the doctrine of promissory estoppel. The second respondent is estopped from unilaterally altering the terms and conditions of the tender agreement by applying the impugned circular to the case of the petitioner. In the light of the above referred decisions, according to us, the respondents are not justified in applying the impugned circular to the case of the petitioner."

10 of 11

Tauseef 908-WP.4263.2024-J.doc

15. In view of above, we pass the following order:-

ORDER

(i) The following part of the Clause 4 of Chapter 10 of

Government Resolution dated 16th February 2024 is held

to be not applicable to the contracts of the Petitioners

executed pursuant to the tender notice dated 24 th May

2023 tender and on the basis of Government Resolution

dated 19th April 2023 till the end of the period of the

agreement dated 29th August 2023:

"तथापि , सदर वाळू डे ो करीता या सु धारीत वाळू धोरणातील अटी व शती लागू राहतील."

(ii) The Petitioners would be governed by the terms of their

contracts executed on 29th August 2023.

(iii) The Petitioner/tenderer will receive the same amount as

they were receiving under the old policy dated 19 th April

2023.

(iv) The Writ Petition is partly allowed in above terms. No

costs.

[JITENDRA JAIN, J.]                               [A. S. CHANDURKAR, J.]




                                       11 of 11




 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter