Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Upendra Kantilal Thanawala And Ors vs Shreeram Builders
2024 Latest Caselaw 7002 Bom

Citation : 2024 Latest Caselaw 7002 Bom
Judgement Date : 5 March, 2024

Bombay High Court

Upendra Kantilal Thanawala And Ors vs Shreeram Builders on 5 March, 2024

Author: R.I. Chagla

Bench: R.I. Chagla

2024:BHC-AS:10500



                                                                             1-arast-93127-2020.doc

            JSN
                               IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                       CIVIL APPELLATE JURISDICTION

                                 ARBITRATION APPEAL (ST.) NO.93127 OF 2020

                    Upendra Kantilal Thanawala & Ors.                              ...Appellants

                           Versus

                    Shreeram Builders                                           ...Respondents

                                                       WITH
                                  ARBITRATION APPEAL (ST.) NO.5662 OF 2020

                    Shreeram Builders                                               ...Appellant

                           Versus

                    Upendra Kantilal Thanawala & Ors.                           ...Respondents
                                                      ----------
                    Mr. Sanjay Jain, Amrut Joshi, Nakul Jain with Sneha Patil and Vrinda
                    Samdani i/b. Maniar Srivastava Associates for the Appellant in ARA
                    ST No.93127 of 2020 and Respondent in ARAST No.5662 of 2020.
                    Mr. Girish Godbole, Senior Advocate i/b. Parag Tilak, Rahul Soman
                    and Deepashikha Godbole for the Respondents in ARAST No.93127
                    of 2020 and Appellant in ARAST No.5662 of 2020.
                                                      ----------

                                                      CORAM : R.I. CHAGLA J
                                                 Reserved on       : 6TH NOVEMBER, 2023
                                                 Pronounced on : 5TH MARCH, 2024
                    JUDGMENT :

1. By Arbitration Appeal (St.) No.93127 of 2020, the

Appellants have challenged the impugned judgment and order dated

1-arast-93127-2020.doc

25th January, 2020 passed by the learned District Judge, Thane in

Civil Miscellaneous Application (Arbitration) No.35 of 2012 (for

short CMA No.35 of 2012), whereas in the Arbitration Appeal (St.)

No.5662 of 2020, there is challenge to the impugned judgment and

order dated 25th January, 2020 in so far as it dismisses Civil

Miscellaneous Application (Arbitration) No.76 of 2013 (for short

CMA No.76 of 2013) against the same arbitral Award passed by the

Majority Arbitral Tribunal dated 10th December, 2011. Both the CMA

No.35 of 2012 and CMA No.76 of 2013 were clubbed together and

decided by the impugned judgment and order dated 25 th January,

2020.

2. Both the Appellants have sought the setting aside of the

impugned judgment and Order in so far as it dismisses the respective

CMA No.35 of 2012 and CMA No.76 of 2013.

3. In order to consider the Arbitration Appeals, filed under

Section 37 of the Arbitration Act, it would be necessary to set out a

brief background of facts in both the Arbitration Appeals. For the

sake of convenience the Appellants and Respondents in Arbitration

Appeal (St.) No.93127 of 2020 are referred to.

1-arast-93127-2020.doc

4. The Appellants in Arbitration Appeal (St.) No.93127 of

2020 - Upendra Kantilal Thanawala together with his brothers

Pankaj and Vyomesh equally own 1/3rd share of their late father

Kantilal's share in the larger property. Thus, Upendra, Pankaj and

Vyomesh are entitled to 1/9th share in the larger property.

5. By an Agreement for Development dated 11th February,

2003, Vyomesh granted development rights in respect of his 1/9th

share in the larger property in favour of Respondent No.1 including

his share in the Bungalow for and at consideration reserved

thereunder. It is necessary to note that under the Agreement for

Development, the larger property excluded the Bungalow under the

definition of the "said land" in recital I of the Agreement. This larger

property with the bungalow has been defined in Clause 12 of the

Agreement as "the said property". Under Clause 22 of the said

Agreement, Vyomesh has given possession of his 1/9th share in the

said land and not of the said property. Thus, it is contended by the

Appellants that Vyomesh's share in the Bungalow was never handed

over to the Respondent. Reliance has been placed by the Appellants

on the cross examination of Vyomesh in the arbitral proceedings

wherein Vyomesh has admitted that no part of the Bungalow was

1-arast-93127-2020.doc

given to the Respondent (Vyomesh's Cross examination is at page 870

of Volume 3). Vyomesh was the Respondents' witness in the arbitral

proceedings.

6. The subject agreement was executed between the

Appellants and Respondents on 6th August, 2003 in respect of the

subject property agreed to be developed for at the consideration of

Rs.2,28,75,000/-. This consideration was arrived at calculating the

net FSI quotient at 25,000 Square Feet @ 915/- per square feet. A

sum of Rs.55,00,000/- was paid to the Appellants at the time of the

execution of the subject Agreement. It is noted that the subject

Agreement is stamped at 1% of the total consideration. The

contention of the Appellants in the arbitral proceedings was that the

subject agreement is a Development Agreement and not an

Agreement to Sell. They have relied upon the stamp duty paid on

Agreement to Sell at the contemporaneous period which had quotient

at 5% of the value of the Agreement and the Development

Agreement's quotient was at 1% of the value of the Agreement. Thus,

it is the contention of the Appellants that the Respondents had

approached the Appellants with an offer to develop the subject

property for construction of a shopping, commercial and residential

1-arast-93127-2020.doc

complex ("the project"). The nature of the development has been

defined in the said Agreement.

7. Further, reliance has been placed on the clauses in the

subject Agreement, where the subject property excludes the

"excluded property" which includes the Bungalow on the said land.

Further, reliance has been placed on Clause 6 of the subject

Agreement wherein the balance consideration of Rs.1,73,75,000/-

was payable by the Respondents to the Appellants in 10 equal

installments. Each installment was for a sum of Rs.17,37,500/-. The

manner in which the installment was to be paid and the proportion

of each Appellants' share has been set out in Clause 7 of the subject

Agreement. The first installment was payable on 30th April, 2005,

2nd installment on 1st August, 2005 and 3rd installment payable on

1st June, 2006. Thereafter, successive installments were payable on

the 1st day of each fourth successive month. The parties agreed that

due payments shall be the essence of the Agreement. Reliance has

been placed on the evidence i.e. cross examination of Ramesh Mehta

(Respondent's partner) who agreed that time was intended to be

essence of the subject Agreement, (paragraph 39 of the Cross

examination of Ramesh Mehta at page 246 of Volume - I). Under

1-arast-93127-2020.doc

Clause 37 of the subject Agreement, the Appellants were to execute a

Deed of Conveyance of the subject property along with the other

owner (which is the responsibility of the Respondents) in favour of

Respondents or their nominee including a Co-operative Housing

Society after the project was fully constructed. Further, Deed of

Conveyance was not to be executed till payments due under the

subject agreement, are paid to the Appellants.

8. It is necessary to note that the contention of the

Appellants in the arbitral proceedings was that the obligation to

execute the Deed of Conveyance is based on three pre-conditions,

namely, (i) Conveyance of the subject property will be executed along

with the conveyance of the properties of the other owners i.e.

Vyomesh and Madhukant's heirs share; (ii) time for conveyance will

arrive after the project is fully constructed, and (iii) all installments

and amounts are paid to the Appellants' under the subject

Agreement. Clause 47 of the subject Agreement, provided that

"notwithstanding anything contained in the subject Agreement or any

other Agreement with other legal heirs (especially with heirs of

Madhukant or Vyomesh), the Respondents will have no right, title,

claim or interest in the Excluded Property."

1-arast-93127-2020.doc

9. The Appellants have placed reliance upon Clauses 52,

53,63 and 64 of the Subject Agreement to contend that a cumulative

reading of these Clauses reveal that notwithstanding anything

contained in the subject Agreement (including Clause 7) in case if

there is a default in payment of any installment on the due date, the

subject Agreement will come to an end along with rights of the

parties.

10. An Agreement for Development was executed by Sumati,

Hemal and Kamal Pillay (legal heirs of Madhukant) on 29th

September, 2003 in favour of the Respondents in respect of their

1/3rd share in the Larger Property. Under Clause 6 of that

Agreement, the Respondents inter alia undertook to satisfy the

liability of the owners to an extent of Rs.5 lakh as specified in

Annexure C to the Agreement dated 29th September, 2003.

11. On 9th February, 2005, the Respondent through their

Advocates' letter called upon the District Collector, Thane to issue

appropriate directions to DILR, Thane to execute the Order dated

30th April, 1987 to conduct survey of the Larger Property and effect

partition thereof.

1-arast-93127-2020.doc

12. The Respondents for itself and on behalf of the

Appellants as well as on behalf of the heirs of the Madhukant filed a

civil suit being Suit No.199 of 2005 against the heirs of Prabhulal,

inter alia seeking injunction. An Appeal was preferred against the

order vacating the ad-interim relief being Appeal from Order No.724

of 2005.

13. This Court by order dated 23rd September, 2005 directed

that none of the parties shall create third party rights without leave

of the Trial Court. It is necessary to note that Vyomesh, Sumati,

Hemal and Kamal Pillay are parties to the Suit. The Appellants have

contended that the Deed of Conveyance executed by them in favour

of the Respondents is void for want of leave of the trial Court.

Further, it is necessary to note that Prabhulal along with Madhukant

and Kantilal each had 1/3rd share in the larger property. Thus, it is

contended that third party rights could not have been created

without leave of the Trial Court.

14. Mr. Rakesh Mehta, the partner of the Respondent No.1,

had handed over 10 A/c payee cheques to the Appellants bearing

cheque Nos.451165 to 451174, all dated 10th October, 2007, for an

1-arast-93127-2020.doc

aggregate sum of Rs.34,75,000/-. It is necessary to note that these

cheques were not encashed by the Appellants on account of the

alleges breaches committed by the Respondents of clauses of the

subject Agreement.

15. The Respondents have contended that on account of non

deposit of the said 10 cheques, by its letter, dated 27th March, 2008,

the Respondents forwarded five cheques to the Appellant Nos.1 and 2

bearing cheques No.451460 to 451464 all dated 1st December, 2007

for an aggregate sum of Rs.17,37,500/-. In the said letter the

Respondents alleged that a sum of Rs.19.50 lakh was paid to Kantilal

during his lifetime of which Upendra, Pankaj and Vyomesh were

aware. It is further alleged that Upendra and Pankaj were to each

reimburse a sum of Rs.6,59,167/- towards consideration under the

Agreement. The Appellants have contended that there is no Clause or

provision in the subject Agreement entitling the Respondents to

appropriate the sum paid to Kantilal. The Appellants have in this

context relied upon Clause 51 of the subject Agreement which

provides that the parties have terminated all prior agreements and

arrangements and the subject Agreement is the Agreement governing

the rights and liabilities of the parties. Further, the Respondents in

1-arast-93127-2020.doc

the said letter have recorded that payment towards last installment is

ready and attached a condition to execute necessary documents to

complete the transactions. Further, it is necessary to note that the

receipt of the letter has been denied by the Appellants.

16. The Appellants through their Advocates letter dated 9th

April, 2008 terminated the Agreement on account of breaches

committed by the Respondents. The Appellants called upon the

Respondents to take back monies paid by it under the subject

Agreement.

17. On 9th April, 2008, the Respondents through their

Advocates letter referring to the letter dated 27th March, 2008, sent

5 A/c payee cheques to Appellant No.2 for an aggregate amount of

Rs.17,37,500/-.

18. The Respondents through their Advocate letter dated 9th

April, 2008 referred to the letter bearing the same date and intimated

Appellant No.1 that 5 cheques were sent to Appellant No.2.

19. The Appellant through Advocates letter dated 16th April,

1-arast-93127-2020.doc

2008 returned the cheques sent to them under letter dated 9th April,

2008.

20. The Respondents by their Advocates letter dated 25th

April, 2008 replied to the Appellants Advocate's letter dated 9th

April, 2008.

21. Thereafter the Arbitral Tribunal comprising of three

members was constituted.

22. The pleadings were filed in the arbitral proceedings. It is

the Appellants contention that in the statement of claim the

Respondents sought a direction against the Appellants to execute and

register a Deed of Conveyance of land which includes portion of the

Excluded Property against the receipt of balance consideration.

23. One Mr. Chandu Mirani, Mr. Ashwin Vasavada and Mr.

Mehul Vasavada filed a Suit against Shree Builder (Sister concern of

Respondent No.1), the Appellants, Mr. Ramesh Mehta. The Suit was

based on agreement between Shree Builder and Plaintiffs therein in

respect of land A. The Appellants share in the larger property was not

1-arast-93127-2020.doc

in question in that Suit. The Appellants filed a say to the Interim

Application filed in the aforesaid Suit. It is necessary to note that the

Respondents have contended that on account of filing a say in the

said Suit, the Appellant has admitted that the Agreement was an

Agreement to Sell. The Appellants have disputed the context in which

their say was filed by contending that the subject matter of

arbitration was different and distinct. The Majority Award has relied

upon the Appellants say to arrive at a conclusion that the Agreement

was an Agreement to Sell.

24. The Arbitral Tribunal on 11th July, 2009 framed 16

points of disputes. Thereafter, on 26th June, 2010 with consent of

parties, the Arbitral Tribunal framed additional points of disputes.

25. On 10th December, 2011, the Majority Tribunal and the

Minority Tribunal passed the Majority Award and Minority Minority

Award respectively.

26. The Respondents filed the Section 34 Petition in January,

2012 challenging the Majority Award viz. the directions contained in

paragraph No.92 (b) and (d) and to modify paragraph No.92(c).

1-arast-93127-2020.doc

27. The Application was made under Section 33(4) of the

Act on 7th February, 2012 by the Appellants for an additional Award.

The Majority Tribunal dismissed the Application under Section 33(4)

of the Arbitration Act on 18th February, 2012.

28. The Appellants filed the Section 34 Petition before this

Court challenging the Majority Award and Additional Award. This

Petition was returned to the District Court. The District Court by

order dated 29th March, 2017 dismissed the Appellants Section 34

Petition and allowed the Respondents Section 34 Petition.

29. The Appellants preferred two Appeals under Section 37

of the Arbitration Act in June, 2017 challenging the Order dated 29th

March, 2017 before this Court. By an Order of this Court dated 29th

June, 2019, the said Order dated 29th March, 2017 was set aside and

both the Petitions under Section 34 were remanded for fresh

consideration on its own merits.

30. The District Court at Thane by impugned Order dated

25th January, 2020 rejected the Appellants' Section 34 Petition as

well as the Respondents' Section 34 Petition and which impugned

1-arast-93127-2020.doc

Order is the subject matter of challenge under Section 37 of the

Arbitration Act in the above Appeals before this Court.

31. Mr. Jain, the learned Counsel appearing for the

Appellants in Arbitration Appeal (St.) No.93127 of 2020, has

submitted that the instant case is governed under unamended

Section 34 of the Arbitration Act. This is in view of the applications

under Section 34 of the Arbitration Act having been preferred by the

parties in the year 2012. Thus, the amended Section 34 which applies

to Petitions/Applications filed on or after 23rd October, 2015, will

not apply to these applications under Section 34 filed prior to that

date. He has in this context placed reliance upon the decision of the

Supreme Court in Ssangyong Engineering and Construction V.

National Highways Authority of India1 wherein the Supreme Court in

paragraph 19 held that, Section 34 of the Arbitration Act as amended

will only apply to Section 34 applications that have been made to the

Court on or after 23rd October, 2015.

32. Mr. Jain has submitted that the District Court by

upholding the Majority Award by the rejection of the Section 34

1 (2019) 15 SCC 131.

1-arast-93127-2020.doc

Petition/application preferred by the Appellants has erroneously

exercised equity jurisdiction under Section 28(2) of the Arbitration

Act and which is impermissible. Under this provision equity can be

exercised by the Arbitral Tribunal only by authorisation of both

parties and not otherwise. There was no such authorisation by the

parties and hence the Arbitral Tribunal being a creature of the

contract has no scope to exercise equity jurisdiction. Ignorance of this

mandate renders the Majority Award contrary to Section 28(2) of the

Arbitration Act. In this context he has placed reliance upon the

decision of this Court in Board of Control for Cricket in India V.

Deccan Chronicle Holding Ltd.2 wherein this Court had held that, the

Arbitral Tribunal under Section 28(2) is required to decide ex aequo

et bono or as amiable composite only if the parties expressly

authorise it to do so. The Arbitrator is bound to implement the

contractual clauses and cannot go contrary to them. He cannot

decide based on his notions of equity and fairness, unless the contract

permits it.

33. Mr. Jain has submitted that the Majority Award is in

contravention of the terms of the subject Agreement. This is in view

2 Commercial Arbitration (L) No.4466 of 2020 in 2021 SCC OnLine Bom 834.

1-arast-93127-2020.doc

of the Majority Award directing the Appellants to execute a sale deed

of their 2/9th share in the Larger Property excluding (i) the

Appellants' share in the Bungalow, (ii) Garden in front and behind

the Bungalow and (iii) one room in Chawl No.1 and open court yard

of the said room adjacent to the Bungalow. The subject Agreement

specifically excludes the Excluded Property in its entirety. However,

this is not excluded by the Majority Tribunal whilst passing the

Majority Award. Further, Excluded Property being out of the scope of

the Agreement, the same was beyond the scope of the reference to

Arbitration. Thus, the Majority Tribunal has exceeded its scope and

ventured into areas which are beyond the subject Agreement.

34. Mr. Jain has placed reliance upon the decision of the

Supreme Court in the case of ONGC Vs. Saw Pipes3 wherein the

Supreme Court in paragraph 31 held that, the Court may set aside

the Arbitral Award if the same is against the terms of the Contract or

the Arbitral Tribunal deals with matters beyond the scope of

arbitration. He has submitted that Excluded Property was beyond the

Majority Tribunal's scope of reference and hence on this ground

alone, the Award is required to be set aside. He has further relied

3 (2003) 5 SCC 705.

1-arast-93127-2020.doc

upon the decision of the Supreme Court in Delhi Development

Authority Vs. R.S. Sharma4 when the Supreme Court in Paragraph 21

held that an Award which is against the terms of the respective

contract is open to interference by the Court under Section 34 of the

Arbitration Act on the ground of patent illegality.

35. Mr. Jain has submitted that the Majority Award is in

contravention of unamended Section 28(3) of the Arbitration Act. It

is provided therein that the Arbitral Tribunal shall decide in

accordance with the terms of the contract and any award made in

violation of the terms of the contract violates this provision. He has in

this context placed reliance upon the decision of the Supreme Court

in BCCI(Supra) wherein it has been held that no contract can be read

in the manner the Award suggests. The Arbitral Tribunal cannot

rewrite a major contractual term to arrive at a view that is not even

possible.

36. Mr. Jain has submitted that the Majority Tribunal has

ignored the specific terms of the subject Agreement and which leads

to commission of jurisdictional error. He has submitted that

4 (2008) 13 SCC 80.

1-arast-93127-2020.doc

cumulative reading of Clauses 3, 4 and 5 of the subject Agreement

indicates that the Appellants are entitled to further sum by way of

additional consideration under the subject Agreement. The Majority

Tribunal has ignored the specific clauses of the subject Agreement

and rendered the Majority Award. The Majority Tribunal has further

ignored that the Respondents had accepted that the consideration

under the subject Agreement was variable. Further consideration is to

be paid on or before last installment under the subject Agreement.

Therefore, it was imperative on the Respondents to have the building

plans sanctioned in respect of the subject Property. The Majority

Tribunal ought to have rejected the claim contained in the Statement

of Claim on the ground of non-performance of material terms of the

subject Agreement.

37. Mr. Jain has submitted that the construction /

interpretation of subject Agreement adopted by the Majority Tribunal

has led to substituting an entire new agreement for the parties, which

was never intended by the parties. He has placed reliance upon the

decision of this Court in Vilayati Ram Mittal Vs. Reserve Bank of

India5 wherein in paragraph 27 this Court has held that the Arbitrator

5 2017 SCC OnLine Bom 8479.

1-arast-93127-2020.doc

being a creature of the contract ignores the specific clause of the

Contract, it would be a question of jurisdictional error and his award

could be corrected by the Court. He has submitted that the Majority

Award is one such case where there is ignorance of material terms of

the subject Agreement (on which the consideration is dependent),

the Majority Tribunal has committed a jurisdictional error. Thus, the

impugned Award of the Majority Tribunal requires correction.

38. Mr. Jain has placed reliance upon Clause 51 of the

subject Agreement which contains non-obstante clause and provides

that the subject Agreement shall be in super-cession of all prior

agreements between the parties and all rights between the parties,

inter se, under any prior agreement shall come to an end and are

extinguished.

39. Mr. Jain has submitted that the Majority Tribunal has

answered the issue as to whether the claimants prove that they have

paid Rs.19,50,000/- to the deceased Kantilal and the Respondents

had agreed to adjust the same towards consideration of the subject

Agreement in the affirmative. The Majority Tribunal has taken into

account a prior Agreement between the parties which could not have

1-arast-93127-2020.doc

been taken into account. By virtue of Clause 51 of the subject

Agreement, all rights of the parties inter se under the prior

Agreement came to an end and were extinguished. Thus, the

Majority Tribunal has acted beyond the terms of the contract and

there is misapplication of mind on the part of the Majority Tribunal.

He has in this context relied upon the decision of the Supreme Court

in Vilayati Ram Mittal (supra).

40. Mr. Jain has submitted that the Majority Award has

inspite of granting specific performance to the Respondent also

awarded the alternative claim for damages raised by the Respondents

for a sum of Rs.23,21,19,982/- on the basis of loss of business profits.

This is solely based on the speculation that in the event of the

superior Court reversing the finding of specific performance granted

in favour of the Respondents, they are entitled to a sum of

Rs.23,21,18,982/- towards the grant of damages.

41. Mr. Jain has submitted that the Majority Tribunal has

failed to consider that the Respondents had not produced any

evidence to support and / or justify the sum of Rs. 35,00,00,000/-as

loss of business profits. The Respondents have not substantiated its

1-arast-93127-2020.doc

claim for damages. The Respondents had in the Statement of claim

claimed a sum of Rs.41,46,49,688/- in the alternative towards grant

of damages in the event of refusal of decree of specific performance.

Thus, the Majority Award without any basis for grant of damages by

way of loss of business profits awarded the sum to the Respondents.

He has submitted that this is contrary to Section 73 of the Indian

Contract Act, 1872. The said provision mandates that damages are

required to pleaded as well as proved. Having failed to do so, the

Majority Tribunal in granting damages has acted contrary to the

fundamental policy of Indian Law. Mr. Jain has placed reliance upon

the decisions of the Supreme Court and this Court in support of the

above submission which are as under:-

(i) Anila Gautam Jain Vs. Hindustan Petroleum Corporation Ltd. (2018) SCC OnLine Bom 917.

(ii) Murlidhar Chiranjilal Vs. Harishchandra Dwarkadas and Anr., AIR 1962 SC 366.

(iii) Basanlingappa V. Mudibasappa, (2019) 5 SCC 418.

(iv) Punj Lloyd V. IOT, Arbitration Petition No.1323 of 2012.

(v) Kailash Nath Associates V. DDA, (2015) 4 SCC 136.

42. Mr. Jain has accordingly submitted that the Majority

Award suffers from patent illegality as it has awarded damages to the

1-arast-93127-2020.doc

Respondents without any proof of damages caused to the

Respondents. He has submitted that this alternative claim awarded is

materially severable and the same ought to be set aside. He has

relied upon the decision of this Court in R.W. Tiwari Vs. Ircon

International Limited 6 in this context.

43. Mr. Jain has submitted that the Majority Award has

interpreted the subject Agreement to be an Agreement to Sell the

subject property which finding is an impossible interpretation. This is

contrary to the terms of the subject contract. He has submitted that

the value of the subject Agreement is Rs.2,28,75,000/- and the stamp

duty paid thereon is Rs.2,29,000/- (approximately 1% of

Rs.2,28,75,000/-). At the contemporaneous period, the stamp duty

leviable / payable on Development Agreement was quotient at 1% of

the value of the Agreement. Stamp Duty of 5% of the value of the

Agreement was attracted in case if the agreement in question was

Agreement to Sell or Agreement to Sale or conveyance, as the case

may be. In the instant case, the parties intended and understood the

Agreement to be one for Development.

6 2010 (I) MhLJ 547

1-arast-93127-2020.doc

44. He has submitted that the Majority Award refers to

Clause 16 of the subject Agreement and holds that only in case of

Agreement to Sell does the obligation to make out a marketable title

arise. This overlooks the obligation of the Appellants in the subject

Agreement to make out marketable title to the Respondents in

respect of the subject property to ensure that they have the right to

transfer the development right in favour of the Respondent.

45. Further, the Majority Award by observing that the

possession of the subject property does not go back to the Appellants,

interpreted the subject Agreement to be an Agreement to Sell. This

overlooks the obligation under the subject Agreement being that

upon post construction of the Project proposed, the land was to be

conveyed to the Co-Operative Housing Society so that the question of

gaining back the possession does not arise. Further, the obligation of

the Respondents to bear costs of development in consideration of

Appellants permitting the Respondents to sell the flats or shops to be

constructed in the proposed building could never have been the basis

in the Majority Award to arrive at a conclusion that the Agreement in

question is an Agreement to Sell. Further, payment of taxes or cess,

by no stretch of imagination will suggest that the Appellants agreed

1-arast-93127-2020.doc

to sell the subject Property. In any event, the payment of property

taxes is a matter of exercise of prerogative of the parties and the

Respondents undertook to pay the same during the period of

construction.

46. Mr. Jain has submitted that the reliance placed by the

Majority Award on the say of the Appellant No.1 in a Suit filed by

Chandu Mirani and two others is baseless. The context in which the

say was filed and the subject matter of the Arbitration were different

and distinct. The Suit was for specific performance against the sister

concern of the Respondents. The Majority Award has erroneously

relied upon the say to arrive at a conclusion that the Agreement was

an Agreement to Sell. This overlooks the settled position that a party

is not bound by the admission given in his pleading except for the

purpose of the Suit in which the pleading is delivered. He has in this

context placed reliance upon the decision of Ramabai Shriniwas

Nadgir Vs. The Government of Bombay7.

47. Mr. Jain has submitted that the Majority Award has

failed to consider the breach committed by the Respondents of the

7 AIR 1941 Bom 144.

1-arast-93127-2020.doc

subject Agreement on account of default in payment of installments

and which dis-entitled the Respondents to specific performance of the

subject Agreement. He has submitted that the Majority Award has

observed that despite the 1st to 6th installments never being paid on

time as per the subject Agreement, the Appellants accepted it without

raising any dispute or protest that the same were being received

without prejudice to their rights under the Agreement. Further, the

Majority Award has held that since the Appellants failed to issue a

notice in terms of Clause 7 of the subject Agreement and offer a

period of 30 days to remedy the breach, no breach can be held to

have committed by the Respondents.

48. Mr. Jain has submitted that no part of the subject

Agreement can be read in isolation to interpret the terms thereof. He

has placed reliance upon the decision of the Supreme Court in South

East Asia Marine Engineering and Construction Ltd. V. Oil India Ltd. 8,

wherein the Supreme Court observed that a wide interpretation

cannot be accepted and the thumb rule of interpretation is that a

document should be read as a whole and so far as possible as

mutually explanatory.

1-arast-93127-2020.doc

49. Mr Jain has submitted that cumulative reading of all

other clauses including Clauses 52 and 53 of the subject Agreement

would reveal that time was the essence of the subject Agreement.

Further, a part payment of the installment shall constitute a default

and in case if there is a default in payment of any installment on the

due date, the subject Agreement will come to an end along with

rights of the parties. Clause 52 is a non-obstante clause. Clause 52 of

the subject Agreement has overriding effect and will prevail over all

other Clauses of the Agreement. He has in this context relied upon

the decisions of the Supreme Court in Chandavarkar Sita Ratna Rao

Vs. Ashalata Guram9.

50. Mr. Jain has accordingly submitted that the

interpretation adopted by the Majority Tribunal is perverse. The

Majority Tribunal ought to have considered Clause 52 along with the

non-obstante provision contained therein which would only lead to

logical conclusion that the breach committed by the Respondents

entailed into putting an end to the subject Agreement.

51. Mr. Jain has submitted that the Respondents are not

9 (1986) 4 SCC 447.

1-arast-93127-2020.doc

ready and willing to perform their part of the subject Agreement and

which is borne out from the fact that none of the installments were

paid on the due date of the subject Agreement. A party insisting on

performance has to perform its part unconditionally and as per the

terms of the contract and shall be ready and willing to perform until

the date of the Decree. No conditions can be attached or insisted by a

party who is seeking performance of the Contract. In the instant case,

the Respondents by letter dated 27th March, 2008 had made their

performance subject to a condition to have conveyance of the subject

Property in its favour. The Respondents had recorded that the

payment towards the last installment was ready and attached a

condition to execute necessary documents to complete the

transactions. This is impermissible. The Respondents cannot attach

any condition much less the present one to perform the subject

Agreement.

52. Mr. Jain has submitted that in the Statement of Claim the

Respondents have pleaded that it is ready and willing to pay the

entire balance in one stroke, if the Appellants are agreeable to

execute and register a Deed of Conveyance of the Appellants

Property.

1-arast-93127-2020.doc

53. This was contrary to the terms of the Agreement. The

readiness and willingness have to be exhibited in respect of the entire

agreement. A party cannot choose not to perform or deny its

performance of the Agreement in its entirety. Further, the

Respondents have not expressed their readiness and willingness to

pay the additional consideration which is a material clause in the

subject Agreement. This tantamounts to a breach of the subject

Agreement.

54. Mr. Jain has submitted that an application had been

preferred by the Appellants for seeking as additional Award under

Section 33(4) of the Arbitration Act on the ground that the Majority

Award had not passed any direction with respect to payment of

additional consideration. The Application was summarily dismissed

by the Arbitral Tribunal on the ground that it was barred by

limitation relying on Section 33 of the Arbitration Act. However, the

Majority Tribunal upon dismissing the application on ground of

limitation had also considered the merits of the Application. This is

an error committed by the Majority Tribunal. The Majority Tribunal

ought not to have decided the Application seeking additional award

in a composite manner. He has placed reliance upon unreported

1-arast-93127-2020.doc

judgment in Kotak Mahindra Bank Vs. R.C. Shah10, wherein this

Court held that dealing with application for condontion and the

merits of the main application at one and the same time, is liable to

result in a situation where a litigant may have a justifiable

apprehension that the view taken by the Tribunal on merits has

coloured its view on the issue of whether sufficient cause has been

shown. This practice is best avoided. He has accordingly submitted

that the Majority Tribunal committed grave error in deciding the

merits of the Application as well as assessing grounds seeking

condonation of delay together. This led to influencing the Majority

Tribunal in assessing the prayer seeking condonation of delay on

standalone basis.

55. Mr. Jain has submitted that the Majority Tribunal has

erroneously relied upon Section 5 of the Arbitration Act to observe

that the same will not allow the Tribunal to extend the period

prescribed under the Act. Section 5 of the Act deals with the scope of

judicial intervention. This is not applicable to the Arbitral Tribunal.

Under Section 43 of the Act, the provisions of the Limitation Act,

1963 are made applicable to the proceedings before the Arbitral

10 Writ Petition (L) No.2886 of 2011 dated 23rd January, 2012.

1-arast-93127-2020.doc

Tribunal as if the same were Court proceedings. Thus, Section 5 of

the Limitation Act, 1963 is applicable under the instant case. The

Majority Tribunal ought to have applied the benefit of Section 5 of

the Limitation act, 1963 in order to meet the ends of justice.

Accordingly, the additional Award is ill-founded. Further, the

additional Award is bad on non-compliance of Section 31 of the

Arbitration Act as it is only signed by the two members of the

Tribunal and there is non-signing of the third member. An Award

which is contrary to the provisions of the Act is illegal and cannot be

sustained.

56. Mr. Jain has also submitted that the impugned Order of

the District Court which has upheld the Majority Award has failed to

appreciate the true purport of the subject Agreement. He has adopted

the above submissions with regard to challenge of the impugned

order of the District Court to the Majority Award.

57. Mr. Jain has submitted that it is settled law that an

objection as to jurisdiction of the Arbitral Tribunal which deals with

the subject matter of the dispute beyond the Agreement can be raised

at the stage of Section 34 of the Arbitration Act even if not raised

1-arast-93127-2020.doc

under Section 16 of the Arbitration Act and the Court shall be

empowered to entertain the objection under Section 34 of the Act.

Further, assuming that such objection was not taken at the stage of

Section 34 of the Act but under Section 37 of the Act, the Court

entertaining an Appeal under Section 37 of the Act can interfere

invoking powers under Section 34(2A) of the Act with the Arbitral

Award on that ground. Thus, it is submitted that the parameters /

grounds available under Section 34 against the Arbitration Award are

equally available to the Court exercising powers under Section 37 of

the Arbitration Act. He has accordingly submitted that this Court set

aside the impugned Order passed by the District Court, Thane which

has upheld by the Majority Award and dismissed the CMA No.76 of

2013 which was filed by the Appellant under Section 34 of the

Arbitration Act, Further, the Majority Award as well as additional

Award of the Arbitral Tribunal requires to be set aside.

58. Mr. Girish Godbole, the learned Senior Counsel

appearing for the Respondents has submitted that the Appellants

have made submissions in respect of the Area of Bungalow Excluded

Area and the Larger subject Property when there is no pleading in

respect of the same in the CMA No.76 of 2013 filed by the Appellants

1-arast-93127-2020.doc

before the District Court, Thane under Section 34 of the Arbitration

Act and neither the same has been argued before the District Court.

He has submitted that however considering scope and jurisdiction of

the Court under Section 37 of the Arbitration Act, the said factual

aspects cannot be considered by this Court in absence of common

pleading to that effect.

59. Mr. Godbole has submitted that the Respondents restrict

their claim to the 1/3rd plus 1/9th share as acquired from the heirs

of Madhukant and Vyomesh respectively and that it is true that the

Respondents have acquired proportionate rights and interest in the

Bungalow property. Further, while the Respondents were granted

development rights only of the subject property, the Respondents

have not relinquished their 1/3rd plus 1/9th right in the Bungalow

property. However, the Respondents have undertaken to respect the

right of undisturbed possession of the Bungalow of the Appellants.

60. Mr. Godbole has submitted that the Respondents do not

at this time wish to partition or claim their 2/9th share in the

Bungalow and other excluded property. However, they seek to retain

their rights and interest in the land below the Bungalow for future.

1-arast-93127-2020.doc

61. Mr. Godbole has submitted that in respect of alleged

default in payment of installments from the 7th to the 10th

installment and time being the essence in respect of those payments,

the Appellants have admitted that there has been no written

complaints or issuance of any demand notice / reminder or a legal

notice in respect of any balance payment. This is borne from the cross

examination of Upendra Thanawalla, witness for the Appellants. The

Appellants have also admitted that there is no documentary evidence

to show that they have returned the 7th and 8th installment cheques

to the Respondents herein. Therefore, these admissions, coupled with

the clear findings of the District Judge under Section 34 of the

Arbitration Act that no notice of any nature whatsoever in respect of

default in payment was issued by the Appellant herein concludes that

there was a breach on part of the Appellants, sine they failed to issue

a reminder notice of 15 days as stipulated under Clause No.7 of the

said Agreement.

62. Mr. Godbole has submitted that there is no dispute in so

far as payment of the 1st to 6th installments by the Respondents are

concerned. The Arbitral Tribunal considered that before issuance of

termination notice by the Appellants, the Respondents issued cheque

1-arast-93127-2020.doc

of Rs.34,75,000/- (7th and 8th installment together) on 10th

October, 2007. The receipt of which has been acknowledged by the

Appellants. Further, the 9th installment of Rs.17,37,500/- was sent by

RPAD on 27th March, 2008. He has submitted that all the cheques

were issued before the issuance of the Termination Notice. Further,

the finding of the Arbitral Tribunal in paragraph 66 of the Arbitral

Award is that the Respondents have paid Rs.19,50,000/- to Upendra

Thanawalla and his father. The Respondents by Advocates notice

dated 25th April, 2008 have indicated to the Appellants herein that

amount of Rs.19,50,000/- paid in cash would be adjusted against the

last installment (10th installment) to be paid as per the Agreement.

Accordingly, the Arbitral Tribunal as well as District Court have held

that the Respondents have always been ready and willing to pay its

consideration in entirety.

63. Mr. Godbole has submitted that the contingencies of

payment of installments and conveyances was depending upon three

scenarios. In any case, the first condition / contingency has been

fulfilled by the Respondents since they had acquired shares of the

other co-owners by Deeds of Conveyance. Further, only one of the

conditions amongst the others could have been fulfilled. He has

1-arast-93127-2020.doc

submitted that while execution of the conveyance on a standalone

basis on fulfillment of only one condition, while the condition of

getting conveyance from the co-owners was fulfilled, only one of the

other conditions that is obtaining sanctioned plans or obtaining

conveyance from other owners could have been fulfilled and

accordingly has been fulfilled. He has submitted that the Respondents

are unable to apply for sub division of the subject property in absence

of a valid conveyance in their favour free from encumbrances.

Further, the Respondents could not apply for sanction of building

plans in respect of construction permissions since the Respondents,

till date, do not hold a clear and marketable title of the subject

property due to the litigation pending on the subject property.

64. Mr. Godbole has submitted that even after arbitral award

was passed, the Appellant herein had filed application for passing of

an additional award to include and / or issue further clarification

upon the rights of the Appellants herein regarding the increase in FSI

and allied rights. This application was rejected and an Appeal has not

been filed against the said decision. The decision has thus attained

finality.

1-arast-93127-2020.doc

65. Mr. Godbole has submitted that the subject Agreement is

an Agreement to sell. At all places except one, the Appellants herein

are described as 'Vendor'. The Arbitral Tribunal has also held that

though the Agreement is titled as a Development Agreement, it is

indeed an Agreement for Sale. He has submitted that if it were a

Development Agreement, conveyance would not be envisaged under

the Agreement. Further, it would have contained relevant clauses for

handing over a part of the Development property and / or percentage

in profit and loss sharing.

66. Mr. Godbole has submitted that Clause 3 of the subject

Agreement specifically determines the consideration of the property

for Rs.2,28,75,000/- at price of Rs.915/- Sq.ft and further in case of

increase in FSI, the consideration will proportionately increase or

decrease. This clause clearly stipulates the intention of the parties

that the full price of the share of the land holders is required to be

paid to them. Further, under Clause 37 of the subject Agreement for

Sale, complete authority to execute the conveyance is given to the

purchasers and infact the purchasers has been given the power to

execute the conveyance as certified attorney of the Vendors. This

clause clearly indicates that the purport and nature of the instrument

1-arast-93127-2020.doc

is not a Development Agreement but an Agreement for Sale and it is

a settled law that the heading or the bare words of an agreement or

instrument do not conclude the nature of the Agreement and the

Agreement as a whole is required to be considered the understand

the true nature and intention of the parties. He has submitted that

the taxes on the property are being paid by the Respondents under

Clause 26 of the subject Agreement. Mr. Godbole has submitted that

the Appellants have admitted in their say in SCS No.445 of 2008 that

they have agreed to sell the property to the Respondents. The said

say is filed in July, 2008, which is 4 months after the date of notice of

termination sent by the Appellants and therefore, this admission,

later in time also fortifies the stand of the Respondents that this is an

Agreement for Sale.

67. Mr. Godbole has submitted that it is well settled by the

Supreme Court in Haryana Tourism Ltd. Vs. Kandhari Beverages

Ltd.,11 that under Section 37 of the Act, the Court cannot enter into

merits of claim. The Award can only be set aside under Sections 34 /

37, only if award is found to be contrary to :- (i) fundamental policy

of Indian law; (ii) the interest of India; (iii) justice or morality or (iv)

11 (2022) 3 SCC 237.

1-arast-93127-2020.doc

if it is patently illegal.

68. Mr. Godbole has also placed reliance upon the decision

of the Supreme Court in Parsa Kente Collieries Ltd. Vs. Rajasthan

Rajya Vidyut Utapadan Nigam Ltd.12, wherein the Supreme Court has

upon referring to its earlier decisions held that the Arbitral Tribunal

must decide in accordance with the terms of the contract, but if an

Arbitrator construes a term of the contract in a reasonable manner, it

will not mean that the award can be set aside on this ground. When a

Court is applying the "Public Policy" test to an arbitration award, it

does not act as a Court of Appeal and consequently errors of fact

cannot be corrected. He has submitted that in the present case, the

Arbitral Tribunal has considered the terms of the contract in a

reasonable manner and hence the award is not liable to be set aside.

69. Mr. Godbole has also relied upon the decision of the

Supreme Court in UHL Power Company Ltd. Vs. State of Himachal

Pradesh13, wherein the Supreme Court has held that the jurisdiction

conferred on Courts under Section 34 of the Arbitration Act is fairly

narrow. When it comes to the scope of an appeal under Section 37 of

12 (2019) 7 SCC 236.

13 (2022) 4 SCC 116.

1-arast-93127-2020.doc

the Arbitration Act, the jurisdiction of an Appellate Court in

examining an Order, setting aside or refusing to set aside an award, is

all the more circumscribed. Further, the Supreme Court has held that

if there are two plausible interpretations of the terms and conditions

of the contract, then no fault can be found, if the learned Arbitrator

proceeds to accept one interpretation as against the other.

70. Mr. Godbole has further relied upon the decision of the

Supreme Court in Reliance Infrastructure Ltd. Vs. State of Goa14,

wherein the Supreme Court has in the context of the scope of

challenge to an arbitral award under Section 34 and the scope of

appeal under Section 37 of the Act referred to its decision in MMTC

Ltd. Vs. Vedanta Ltd.15 wherein it is held that it cannot be disputed

that interference under Section 37 of the Act cannot travel beyond

restrictions laid down under Section 34. The Court cannot undertake

an independent assessment of the merits of the award and must only

ascertain that the exercise of power by the Court under Section 34

has not exceeded the scope of the provision. The Supreme Court in

Ssangyong Engg. & Construction Co. Ltd. Vs. NHAI 16 has held that

14 2023 SCC OnLine SC 604 15 (2019) 4 SCC 163 16 (2019) 15 SCC 131

1-arast-93127-2020.doc

patent illegality appearing on the face of the award, refers to

illegality as going to the root of the matter but which does not

amount to a mere erroneous application of the law. Re-appreciation

of evidence cannot be permitted under the ground of patent illegality

appearing on the face of the Award.

71. Mr. Godbole has submitted that the impugned order as

well as the Majority Award in so far it has been challenged by the

Appellants in the above Arbitration Appeal (St.) No.93127 of 2020

does not suffer from any patent illegality or perversity or is liable to

be set aside on any of the grounds of challenge under Section 34 of

the Arbitration Act.

72. Mr. Godbole has also made submissions with regard to

Arbitration Appeal (L) No.93127 of 2020 which has been preferred

by the Respondents herein / Appellants in the said Arbitration

Appeal.

73. Mr. Godbole has submitted that the exercise of discretion

under Section 20 of the Specific Relief Act, 1963 by Court in the

matters of passing of decree of specific performance cannot be used

1-arast-93127-2020.doc

to the prejudice of an honest vendee, who was always ready and

willing to perform his part of the contract, and has not committed

any breach of the contract and who was forced to approach the Court

for seeking specific performance on account of wrongful termination

of the contract by the Vendor. He has submitted that learned District

Judge has completely overlooked this principle of settled law

regarding exercise of powers conferred under the Specific Relief Act,

1963.

74. Mr. Godbole has submitted that the Supreme Court in

Nirmala Anand Vs. Advent Corporation Ltd. 17 in paragraph 6 has held

that whether the purchaser is directed to pay an additional amount

to the seller, or converse, would depend upon facts and

circumstances of each case and while balancing the equities, the

Court must bear in mind who is the defaulting party.

75. Mr. Godbole has submitted that the learned District

Judge and the Arbitral Tribunal ought to have seen that power to

award enhanced compensation to a defaulting vendor was essentially

a power which is neither vested with the Arbitral Tribunal nor with

17 (2002) 8 SCC 146

1-arast-93127-2020.doc

the Civil Court or the High Court.

76. Mr. Godbole has submitted that Arbitral Tribunal and

learned District Judge has completely misconstrued the ratio of the

Supreme Court judgment in the case of Gobind Ram Vs. Gian

Chand18. The judgment does not lay down a binding precedent, nor

does it hold that it is permissible for the Court to rewrite the contract.

In that case, the Respondent Vendee had voluntarily agreed to pay

additional amount of Rs.1 lakh to mitigate hardship which is caused

to the vendor in that case on account of the escalation in prices and

hence the additional compensation was increased to Rs.3 lakh. This,

at the highest, can be construed to be passed in exercise of

jurisdiction under Article 142 of the Constitution of India and does

not lay down any binding precedent.

77. Mr. Godbole has submitted that the learned District

Judge and Arbitral Tribunal has not considered the admitted fact that

the Claimant / Respondent herein has paid more than 82.03% of the

agreed consideration before initiation of the Arbitral Proceedings and

the omission to consider the said aspect while awarding additional

18 2009 (7) SCC 548

1-arast-93127-2020.doc

amount to be paid by the claimant is erroneous. He has submitted

that the learned District Judge ought to have considered this

admitted fact whilst arriving at a figure of Rs.5490/- per square feet

allegedly payable by the Respondent herein to the Appellants herein.

Further, there was neither cogent evidence to support this rate nor

reasons were given by the Arbitral Tribunal as to how this rate was

arrived in paragraph 83 of the Award which has been upheld by the

learned District Judge. This is despite the Arbitral Tribunal noting

that at the time of execution of the agreement in question the rate

was Rs.915/- per square feet for total area of 25,000 sq.ft. Thereafter,

without assigning any reasons as to why the Claimant / Respondents

herein have been directed to pay the additional amount, particularly

when the Claimant / Respondents herein had not committed any

breach of the Agreement, the Arbitral Tribunal had held that the

Claimant / Respondents herein should pay six times of that amount

viz. Rs.5,490/- per square feet. This finding of the Arbitral Tribunal

was required to be modified and set aside by the learned District

Judge.

78. Mr. Godbole has submitted that there is no justification

for giving unnecessary bonanza to the Appellants herein, particularly

1-arast-93127-2020.doc

after holding that the Appellants herein have committed breaches.

Thus, the Arbitral Tribunal could not have directed the Respondents

herein to pay additional price for the entire area.

79. Mr. Godbole has submitted that the impugned part of the

Award whereby the Arbitral Tribunal have directed payment of

additional consideration to a party who has committed breach, is

contrary to the public policy established in India.

80. Mr. Godbole has submitted that the Court is empowered

to partly modify an Award while exercising power under Section 34

and 37 of the Arbitration Act and has placed reliance upon the

decision of Poysha Oxygen Pvt. Ltd. Vs. Ashwini Suri and Ors. 19

paragraph 36 and 37 as well as the decision in Star Track Fasteners

Pvt. Ltd. Vs. Union of India20 wherein it has been held that the Court

can modify the Award if such part is severable.

81. Mr. Godbole has accordingly submitted that the

Arbitration Appeal (St.) No.5662 of 2020 be allowed and the

impugned order as well as the Arbitration Award which directs

19 2009 (112) DRJ 169 20 (2019) SCC OnLine Bombay 1453

1-arast-93127-2020.doc

payments of additional consideration by the Respondents herein to

the Appellants herein requires to be set aside.

82. Mr. Jain has submitted that in view of the submissions in

Arbitration Appeal (St.) No.93127 of 2020 that the impugned award

itself is perverse and suffers from patent illegality and contrary to

public policy of India, the impugned award itself is required to be set

aside and cannot be severable and hence there is no merit in the

Arbitration Appeal (St.) No.5662 of 2020.

83. Mr. Jain has submitted that in any event it is well settled

that the Arbitral Tribunal cannot modify an arbitral award and there

are only two options viz. either to set aside the award or to uphold

the Award. Thus, there is no merit in the Arbitration Appeal (St.)

No.5662 of 2020 which seeks modification of the arbitral Award by

seeking a deletion of the additional amount to be paid by the

Claimants / Respondents herein to the Appellants which this Court

under Section 37 of the Arbitration Act has no power to do so.

84. Having considered the rival submissions in Arbitration

Appeal (St.) No.93127 of 2020, it would be necessary to first

1-arast-93127-2020.doc

consider the objection taken by Mr. Godbole on behalf of the

Respondents that the Section 37 Court cannot consider the challenge

to the jurisdiction of the Arbitral Tribunal in dealing with the subject

matter of the dispute beyond the Agreement without there being any

pleading or ground raised in the Section 34 Petition. The Appellants

have contended that the Bungalow and other areas defined as

"Excluded Area" in the subject Agreement has been taken into

consideration by the learned Arbitrator although not being the

subject matter of dispute. In this context it is necessary to refer to the

decision of the Supreme Court in State of Chhattisgarh (Supra)

which has been relied upon by Mr. Jain on behalf of the Appellants,

in particular paragraph 23, which reads thus:-

"23. We are afraid, the plea of waiver taken against the appellant-State on the ground that it did not raise such an objection in the grounds spelt out in the Section 34 Petition and is, therefore, estopped from taking the same in the appeal preferred under Section 37 or before this Court, would also not be available to the respondent-Company having regard to the language used in Section 34(2A) of the 1996 Act that empowers the Court to set aside an award if it finds that the same is vitiated by patent illegality appearing on the face of the same. Once the appellant-State had taken such a ground in the Section 37 petition and it was duly noted in the impugned judgment, the High Court ought to have interfered by resorting to Section 34(2A) of the 1996 Act, a provision which would be equally available for application to an appealable order

1-arast-93127-2020.doc

under Section 37 as it is to a petition filed under Section 34 of the 1996 Act. In other words, the respondent-Company cannot be heard to state that the grounds available for setting aside an award under sub-section (2A) of Section 34 of the 1996 Act could not have been invoked by the Court on its own, in exercise of the jurisdiction vested in it under Section 37 of the 1996 Act. Notably, the expression used in the sub-rule is "the Court finds that". Therefore, it does not stand to reason that a provision that enables a Court acting on its own in deciding a petition under Section 34 for setting aside an Award, would not be available in an appeal preferred under Section 37 of the 1996 Act.".

85. Thus, it is clear from the decision of the Supreme Court

that the contention that a specific ground had not been raised in

Section 34 Petition and Appellant was estopped from taking the same

in the Appeal preferred under Section 37 of the Act or before this

Court has not been accepted. The Supreme Court has held that it

does not stand to reason that the provision viz. Sub-Section 2(A) of

Section 34 of the Arbitration Act which enables a Court acting on its

own in deciding a Petition under Section 34 for setting aside an

Award would not be available in an Appeal preferred under Section

37 of the 1996 Act.

86. Accordingly, I do not find any merit in the contention of

Mr. Godbole that jurisdictional error not having been pleaded in the

1-arast-93127-2020.doc

CMA No.76 of 2012 filed by the Appellants before the learned

District Judge cannot be raised before this Court under Section 37 of

the Arbitration Act. Hence it would be necessary to consider whether

there is such a jurisdictional error on the part of the Majority

Tribunal which renders the majority award as being patently illegal.

87. I have perused the relevant clauses of the subject

Agreement and in particular Clause 47 thereof which provides that

the Respondents will have no right, title, claim or interest in the

'Excluded Property'. The Respondents have also relinquished their

right, title and interest over the 'Excluded Property' in favour of the

Appellants. This 'Excluded Property' included the subject Bungalow.

However, it is noted that prayer sought by the Respondents in the

Statement of claim included the 'Excluded Property'. Thus, the

Majority Tribunal in granting such claim has acted beyond the

specific terms of the subject Agreement.

88. Further, a cumulative reading of Clauses 3, 4 and 20

indicates an entitlement of the Appellants to an additional

consideration under the subject Agreement. The Appellants are

entitled to additional sums under these Clauses. The Majority

1-arast-93127-2020.doc

Tribunal has ignored these specific clauses of the subject Agreement

and rendered the Majority Award. The Appellants became entitled for

additional consideration in respect of increase of FSI, consideration

in respect of construction of basement if proposed and FSI towards

land held by the Appellants on account of adverse possession.

89. Further, it is relevant to note that the execution of

conveyance could have only been awarded provided the conditions to

execute the Deed of Conveyance had been complied with. There were

three pre-conditions namely (i) Conveyance of the subject property

will be executed along with the conveyance of the properties of the

other owners i.e. Vyomesh, Madhukant's heirs share; (ii) time for

conveyance will arrive after the project is fully constructed and (iii)

all installments and amounts are paid to the Appellants under the

subject Agreement. It appears that neither of these conditions

stipulated under the subject Agreement were fulfilled. Thus, the

obligation to execute Deed of Conveyance had not yet arrived.

Further, the determination of the consideration under the conveyance

would necessarily depend upon the additional amounts which the

Appellants are entitled to receive as aforementioned. Thus, the

consideration itself was variable under the subject Agreement. This

1-arast-93127-2020.doc

would necessarily depend upon the project being constructed and

without determination of such entitlement, in my view the Majority

Award could not have directed the execution of a sale deed by

Appellants in favour of the Respondents. This is in contravention of

the terms of the subject Agreement.

90. There is much merit in the submissions of Mr. Jain that

the instance case is covered under the unamended Section 34 of the

Arbitration Act, particularly since the application under Section 34 of

the Act were in the year 2012. It has been held by the Supreme Court

in the case of Ssangyong Engineering (Supra) that amended Section

34 of the Arbitration Act will apply to the Petitions / Applications

which are filed on or after 23rd October, 2015. Thus, the decision of

the Supreme Court in ONGC Vs. Saw Pipes (Supra) which decision

was prior to the amended Section 34 is applicable to the present

case. The Supreme Court holds that a Court may set aside the

Arbitral Award if the same is against the terms of the contract or the

Arbitral Tribunal deals with matters beyond the scope. Further, the

Supreme Court in Delhi Development Authority (Supra) has held

that the Award which is against the terms of the respective contract is

open to interference by the Court under Section 34 of the Arbitration

1-arast-93127-2020.doc

Act on the ground of patent illegality. When a contract bars /

prohibits a particular claim, any award made in violation of the terms

of the contract would violate Section 28(3) of the Arbitration Act,

thereby rendering the award patently illegal and liable to be set aside

under Section 34(2)(b) of the Act. Further, if the Award is found to

be patently illegal, the same would be opposed to public policy.

91. Further, this Court in the case of Vilayati Ram Mittal

(Supra) has held that the Arbitrator being a creature of the Contract

ignores a specific clause of the contract, it would be a question of

jurisdictional error and his award could be corrected by the Court.

92. In Board of Control for Cricket in India(Supra) this Court

held that the Arbitral Award must decide in accordance with the

terms of the contract. The decision of the Supreme Court in Associate

Builders was relied upon and the Caveat entered therein that if the

arbitral tribunal interprets the contract in a reasonable manner, there

is no patent illegality. Further, it has been held by this Court in the

said decision that no contract can be read in the manner the Award

suggests. It is not possible for an Arbitral Tribunal to re-write a major

contractual term to arrive at a view that is not even possible.

1-arast-93127-2020.doc

93. In my view in the instant case, the Majority Award has

not interpreted the contract in a reasonable manner and by ignorance

of material terms of the subject Agreement, the Majority Tribunal has

committed jurisdictional error.

94. Further, the Majority Tribunal Award ought to have

considered Clause 51 of the subject Agreement which is a non-

obstante Clause which provides that the subject Agreement is in

super-cession of all prior Agreements between the parties including

the M.O.U. and that all rights between the parties, inter se, under any

prior Agreement shall come to an end and are extinguished. The

Majority Award having framed an issue viz. whether the Claimants

prove that they have Rs.19,50,000/- to deceased Kantilal and the

Respondents and that they had agreed to adjust the same towards the

consideration of the subject Agreement and answering the issue in

the affirmative, is yet one instance where the Majority Tribunal has

held contrary to the terms of the subject Agreements. This in view of

the agreement which existed during the lifetime of Kantilal was no

longer in existence by virtue of Clause 51 of the subject Agreement.

95. I also find much merit in the submission of Mr. Jain that

1-arast-93127-2020.doc

the grant of damages on account of alleged loss of business profits by

the Majority Tribunal is against the weight of evidence before it

rendering the Majority Award patently illegal. It has been held by the

Supreme Court and this Court in the decisions relied upon by Mr.

Jain that no damages shall be awarded unless the party claiming loss

has pleaded and proved the extent of damages suffered by it. There is

also a duty imposed on that party to take all reasonable steps to

mitigate the loss consequent on the breach and debars him from

claiming any part of the damage which is due to his neglect to take

such step. In the present case the Majority Award inspite of there

being no proof of damages by the Claimants / Respondents herein

has granted damages to the Respondents herein. Further, the

Majority Award inspite of granting specific performance of the

subject agreement to the Claimants / Respondents herein have also

granted damages which was an alternate claim of the

Claimants/Respondents herein. Thus, the awarding of damages by

the Majority Award is contrary to the fundamental policy of India

Law.

96. I further find that the Majority Award has not arrived at

any plausible interpretation of the subject Agreement by considering

1-arast-93127-2020.doc

it to be an Agreement to Sell rather than Development Agreement. It

has been held by the Supreme Court in Rajendra Lalitkumar

Agrawal Vs. Ratna Ashok Murangan and Anr.21 in paragraphs 10 and

11 that interpretation of document constitutes a substantial question

of law, more so when the parties admit the document. This was in the

context of Second Appeal under Section 100 of the Code of Civil

Procedure, 1908. However, the ratio laid down in the said decision

would be applicable to the present matter. It has also been held by

the Constitution Bench of the Supreme Court in Sir Chunilal V. Mehta

and Sons Ltd. Vs. Century Spinning and Manufacturing Col Ltd. 22,

that construction of a document which is the foundation of the rights

of the parties necessarily raises a question of law.

97. In the present case the finding in the Majority Award

that the subject Agreement is an Agreement to Sell is in my

considered view erroneous in law. The subject Agreement having

been stamped at 1% of the value of the Agreement which at the

contemporaneous period, was the stamp duty leviable / payable on

Development Agreement would show that the parties have treated

the subject Agreement as a Development Agreement. The Majority

21 (2019) 3 SCC 378.

22 AIR 1962 SC 1314

1-arast-93127-2020.doc

Tribunal has erred in holding that only in the case of an Agreement

to Sell does the obligation to make out the marketable title will arise.

In the instance case the Appellants were obligated to make out

marketable title to the Respondents in respect of the subject property

to ensure that they have a right to transfer the development right in

favour of the Respondents.

98. Further, the subject Agreement may not have mentioned

the defined area on which the development is envisaged. However,

that does not result in an inference that the subject Agreement is an

Agreement to Sell. In the present case, the area was not defined as

the subject property is a part of the larger property which was

undivided.

99. The finding of the Majority Tribunal that the possession

of the subject property not going back to the Appellants would lead

to an inference that the subject Agreement is an Agreement to Sell, is

erroneous. The subject Agreement contemplated post construction of

the project, the land to be conveyed to the Co-operative Housing

Society, so the question of gaining back the possession does not arise.

The subject Agreement would have to be read as a whole and not in

1-arast-93127-2020.doc

a piecemeal manner as sought to be done by the Majority Tribunal.

Further, the payment of taxes or cess and cost of development being

borne by the Respondent cannot lead to an inference that the subject

Agreement was an Agreement to Sell. The Respondents undertook

the same during the period of construction.

100. I also do not find any merit in the submission on behalf

of the Respondents that there was an admission by the Appellants in

the Suit filed by one Chandu Mirani and two others that the subject

Agreement was an Agreement to Sell. An admission of a party can be

used against the maker in the same proceedings in which it is made.

However, a party is not bound by the admission given in his

pleadings except for the parties to the Suit in which the pleading is

delivered. This has been held in Ramabai Shriniwas Nadgir (Supra).

101. I am of the considered view that, the Majority Award has

read Clause 7 of the subject Agreement in isolation by holding that

since the Appellants failed to issue notice in terms of Clause 7 of the

subject Agreement in case of default of the Respondents in making

payment of the installments on the due dates, no breach has been

committed by the Respondents. A cumulative reading of other clauses

1-arast-93127-2020.doc

including Clauses 52 and 53 of the subject Agreement would reveal

that the time was of the essence of the subject Agreement. Merely,

because the Appellants had not objected to the payment of the first to

sixth installment on time under the subject Agreement, that does not

result in the Appellants being estopped from raising the contention

that the payment under the subsequent installments had not been

adhered to by the Respondents.

102. Clause 52 of the subject Agreement is non-obstante and

would have an overriding effect, notwithstanding Clause 7 of the

subject Agreement. Further, under Clauses 52 and 53, it is provided

that a part payment of the installment shall constitute a default and

in case if there is a default in payment of any installment on the due

date, the subject Agreement will come to an end along with the rights

of the parties.

103. In addition to the aforementioned findings, I am of the

view that there was lack of readiness and willingness on the part of

the Respondents to perform their part of the subject Agreement

which has been overlooked in the Majority Award. None of the

installments were paid on the due date as per the subject Agreement.

1-arast-93127-2020.doc

Further, the Respondents had attached a condition on making

payment of last installment viz. to execute necessary documents to

complete the transactions. This was not as per the terms of the

contract and hence impermissible. The Respondents have thus not

been ready and willing to perform their part of the subject

Agreement. Further, the Respondents in the Statement of claim had

pleaded that they were ready and willing to pay entire balance in one

stroke, if the Appellants were agreeable to execute and register a

Deed of Conveyance of the Appellants property. This also displays

lack of readiness and willingness on the part of the Respondents to

perform the subject Agreement according to its terms. Further, the

Respondents have denied their liability to pay additional

consideration which they were obliged to pay. The Respondents have

also failed to display their readiness and willingness to meet the pre-

conditions for conveyance of the property.

104. Mr. Jain has also made submissions on the application

for additional award which was dismissed the Majority Tribunal on

the merits as well as rejection of prayer for condonation of delay i.e.

on limitation. Given the aforementioned findings with regard to the

Majority Award being patently illegal and perverse, it is not necessary

1-arast-93127-2020.doc

to render a finding on the submissions with regard to the additional

Award.

105. Mr. Jain has made independent submissions on the

learned District Judge failing to consider the ground of challenge in

the Appellants Section 34 Petition. Having held the Majority Award

to be patently illegal and suffering from perversity, I am inclined to

accept the submissions of Mr. Jain that the learned District Judge

ought to have considered the grounds in the Section 34 in light of the

aforementioned findings, particularly where the Majority Tribunal

had exceeded its scope of jurisdiction by awarding claims beyond the

subject Agreement. The Majority Award is thus, patently illegal as it

strikes at the root of the subject Agreement and shocks the conscious

of the Court. Thus, I find that the impugned order passed by the

learned District Judge is amenable to set aside in view of it not

interfering with the Majority Award which suffers from patent

illegality and perversity.

106. Mr. Godbole has cited several judgments on the power of

the Court under Section 37 of the Arbitration Act and where this

Court as well as the Supreme Court has held that the Court under

1-arast-93127-2020.doc

Section 37 of the Arbitration Act cannot enter into the merits of the

Claim. I am mindful of the law laid down by the Supreme Court and

this Court whilst arriving at the aforementioned findings, particularly

given the jurisdictional error on the part of the Majority Tribunal in

awarding the claim contrary to the terms of the subject Agreement.

107. Thus, the power exercised by this Court is within the

parameters of the Section 37 of the Arbitration Act and hence the

Majority Award is being set aside in exercise of such powers.

108. Accordingly, the impugned order of the learned District

Judge, the Majority Award as well as the order rejecting the

Application for Additional Award of the Tribunal impugned in the

above Arbitration Appeal, being Arbitration Appeal (St.) No.93127 of

2020 are required to be quashed and set aside.

109. In that view of the matter, submissions of Mr. Godbole in

support of the Arbitration Appeal (St.) No.5662 of 2020 seeking

severance of part of the Majority Award and modification of that part

which awards additional amount to be paid to the Applicants by the

Respondents is not required to be considered.

1-arast-93127-2020.doc

110. The Arbitration Appeal (St.) No.5662 of 2020 is

accordingly disposed of.

111. The Arbitration Appeal (St.) No.93127 of 2020 is made

absolute and impugned order dated 25th January, 2020 with

Majority Award dated 10th December, 2011 and additional Award

dated 18th February, 2012 are set aside.

112. The Arbitration Appeal (St.) No.93127 of 2020 is

accordingly disposed of.

[ R.I. CHAGLA J. ]

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter