Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Maharashtra Power Generation ... vs Knowledge Infrastructure ...
2023 Latest Caselaw 11492 Bom

Citation : 2023 Latest Caselaw 11492 Bom
Judgement Date : 8 November, 2023

Bombay High Court
Maharashtra Power Generation ... vs Knowledge Infrastructure ... on 8 November, 2023
Bench: R. I. Chagla
2023:BHC-OS:13555

                                                                                CARBPL.18419.21.doc



                             IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                 ORDINARY ORIGINAL CIVIL JURISDICTION
                                     IN ITS COMMERCIAL DIVISION

                    COMMERCIAL ARBITRATION PETITION (L) NO. 18419 OF 2021


              Maharashtra Power Generation Company Ltd.        ...        Petitioner

                         Versus

              Knowledge Infrastructure Systems Pvt. Ltd.       ...        Respondent


                                          WITH
                         INTERIM APPLICATION (L) NO. 7961 OF 2022
                                            IN
                    COMMERCIAL ARBITRATION PETITION (L) NO. 18419 OF 2021


              Knowledge Infrastructure Systems Pvt. Ltd.       ...        Applicant/Orig.
                                                                        Respondent

              In the matter between

              Maharashtra Power Generation Company Ltd.        ...        Petitioner

                         Versus

              Knowledge Infrastructure Systems Pvt. Ltd.       ...        Respondent



              Mr. Pankaj Sawant, Senior Advocate a/w Abhijeet Desai, Karan Gajra i/b
              Desai Legal for the Petitioner.
              Ms. Pratibha Chavan Mali, Deputy Law Officer, present.
              Mr. Vikram Nankani, Senior Advocate, Mr. Chetan Kapadia, Senior
              Advocate, Mr. Yuvaraj Singh, Mr. H.K. Sudhakara, Ms. Aishwarya
              Kantawala, Ms. Diya Jayan i/b M/s. HKS Legal for the Respondent.




              Waghmare                           1/48



                 ::: Uploaded on - 10/11/2023              ::: Downloaded on - 10/11/2023 21:52:45 :::
                                                                     CARBPL.18419.21.doc



                                      CORAM        : R.I. CHAGLA, J.
                             RESERVED ON           : 29th AUGUST, 2023.
                             PRONOUNCED ON : 8th November, 2023.


JUDGMENT :

1 By this Commercial Arbitration Petition, the Petitioner has

sought the setting aside of the impugned award dated 21.04.2021

together with impugned order dated 20.07.2020 (deciding preliminary

issue against the Petitioner) passed by the Arbitral Tribunal.

2 The Arbitral Tribunal by the impugned award has awarded to

the Respondent/Claimant an amount of Rs.22,06,47,321/- payable by the

Petitioner herein together with interest at the rate of 7.25 % from the date

of the Award till final payment and/or realization.

3 Further by the impugned order dated 20.07.2020 the Arbitral

Tribunal has decided preliminary issue "whether the dispute involves

allegations of serious fraud by the Claimant thereby rendered the dispute

non-arbitrable?" against the Petitioner herein. Thus, the Arbitral Tribunal

held that at the higher the allegation in the statement of Defence is a case

of simple fraud and not a case of serious allegations of fraud thus held

that the claims are arbitrable.

Waghmare                                    2/48




                                                                          CARBPL.18419.21.doc



4                 By an order dated 01.01.2022 passed by this Court in the

above Commercial Arbitration Petition, this Court was of the opinion that

the Commercial Arbitration Petition can be heard and disposed of at the

admission stage. This was whilst considering the application of the

Respondent herein for withdrawal of the awarded amount deposited by

the Petitioner in this Court pursuant to the order dated 16.12.2021.

Accordingly, directions were issued to the Counsel for the parties for

placing on record brief written notes of arguments and compilation of

judgments if any, within a period of four weeks from the date of the said

order. Thereafter a further extension had been sought for filing written

notes of arguments by the Counsel for the Respondent on 22.06.2023 and

which extension of time was granted and thereupon the written notes of

arguments have been filed on behalf of the Petitioner as well as the

Respondent.

5 It is necessary to advert the brief facts which were before the

Arbitral Tribunal and considered in passing of the impugned award as

under :

(i) The Petitioner has various Thermal Power Stations (TPS) in

the State of Maharashtra. The Petitioner requires to utilize foreign coal

alongwith domestic coal in certain proportions as per the guidelines

Waghmare 3/48

CARBPL.18419.21.doc

issued from time to time. Accordingly, the Petitioner places orders for

specific quantities of coal to be supplied to each of its TPS according to

the specific requirement of that particular TPS.

(ii) The Respondent/Claimant is in the business of importing,

dealing in and selling coal for industrial purpose.

(iii) Notifications were issued by the Government of India which

determined the Basic Customs Duty ("BCD") and Countervailing Duty

("CVD") for procurement of coal including steam coal imported from

Indonesia. The said notifications are as under :

a) On 01.06.2011 - Notification No.46/2011-Cus was issued

whereunder BCD was 0% and CVD was 6% for procurement of coal

from ASEAN countries, including for steam coal imported from

Indonesia.

b) On 17.03.2012 - General Notification No.12/2012 was issued

whereunder steam coal attracted BCD at 2% and CVD at 2%.

c) On 31.12.2012 - Notification No.64/2012 was issued

amending Notification No.46/2011-Cus w.e.f. 01.01.2013 to

provide 'Nil' BCD and 6% CVD on coal exported from Indonesia to

India.

Waghmare                                           4/48




                                                                          CARBPL.18419.21.doc



iv)                The Petitioner issued Letter of Award (LoA) on 30.07.2013 in

Respondent's favour for awarding the tender for supply of 1.148 MMT of

Coal to Bhusawal Thermal Power Station (TPS). The Respondent has

tendered as per the LoA Performance Bank Guarantee (PBG) of Rs.59.33

crores of Standard Chartered Bank for the Bhusawal TPS on 06.08.2013

v) A Contract for supply of 11,48,000 MT to Bhusawal TPS was

executed on 30.08.2013 whereunder the contract period began on

30.07.2013.

vi) The Petitioner issued LoA on 23.09.2013 in the Respondent's

favour for awarding the tender for supply of 0.96 MMT of coal to

Chandrapur TPS.

vii) The Respondent submitted PBG of Rs.46.62 crores of Yes

Bank for the Chandrapur TPS on 30.09.2013.

viii) A Circular No.41/2013 was issued on 21.10.2013 by which

importers of coal from ASEAN countries could pay for the first time a total

duty of 2% i.e. 0% BCD + 2% CVD (instead of 6% CVD).

ix) The Contract for supply of 9,56,500 MT to Chandrapur TPS

was executed on 25.10.2013 whereunder Contract period began on

13.09.2013.

Waghmare                                  5/48




                                                                CARBPL.18419.21.doc



x)          The Petitioner released on 04.12.2013 the 1st payment (90%

through LC) for invoice submitted by the Respondent for Bhusawal TPS.

The payment included the BCD component.

xi) The Petitioner released the 1st payment (90% through LC) for

invoice submitted by the Respondent for Chandrapur TPS on 31.12.2013.

This payment included the BCD component.

xii) The Petitioner addressed a letter on 01.03.2014 to the

Respondent raising the issue of availing concessional BCD. By this time,

approximately 47.44% of the final quantity was supplied to Bhusawal TPS

and 38% of the final quantity was supplied to Chandrapur TPS.

xiii) The Respondent replied to the Petitioner's letter dated

01.03.2014 by their letter dated 14.03.2014 disputing the contents

thereof and on the grounds that (a) the contracts prevailing customs duty

was 2%, which was in fact paid by the Respondent to the authorities,

(b) No new concession became available post contract and (c) the

contracts record that no concessional customs duty is applicable on coal.

xiv) The Petitioner addressed letter dated 19.03.2014 stating that

the Respondent had not responded to letter dated 01.03.2014. It was

stated that the BCD on coal was 0% and the Petitioner was entitled to

Waghmare 6/48

CARBPL.18419.21.doc

avail the benefit. Accordingly, the Petitioner will recover/deduct BCD

amounts from Respondent's outstanding payments.

xv) On 09.07.2014, the Petitioner issued an amendment to the

Contract for Chandrapur TPS directing the Respondent to divert quantity

of 80,000 MT from Chandrapur TPS to Khaparkheda TPS. It is noted that

the old Khaparkheda Contract for supply of coal to Khaparkheda TPS was

for the period from 01.11.2012 to 31.05.2013 and which was entered into

on 03.12.2012.

xvi) The Respondent completed the supply Contract of Bhusawal

TPS on 15.07.2014. The last rake of coal was supplied to Chandrapur

TPS.

xvii) On 31.07.2014 the Respondent completed the supply

Contract of Chandrapur TPS. As per the amendment dated 09.07.2014 of

Chandrapur TPS Contract, the last rake under this contract was supplied

to Khaparkheda TPS. The Respondent had addressed an e-mail calling

upon the Petitioner to issue Material Information Receipt ('MIR') for full

quantity delivered under the contract.

xviii) The Respondent addressed letter on 05.08.2014 to the

Petitioner for closure of the Chandrapur TPS Contract.

Waghmare                                  7/48




                                                                  CARBPL.18419.21.doc



xix)         The Respondent addressed reminder letters on 07.08.2014

and 12.08.2014 to the Petitioner for issuance of MIR for the last rake after

considering the quantity variation in the contract.

xx) The Petitioner amended the MIR issued for the last rake on

02.09.2014 indicating the total quantity delivered. However, the MIR

stated that the excess quantity will not be considered for billing.

xxi) The Respondent addressed letters on 18.09.2014, 19.09.2014

and 24.09.2014 calling upon the Petitioner to accept the full quantity

received and re-issue the MIR and corrected quality report for last rake

without restriction on billing for the same.

xxii) The Petitioner addressed a letter to the Respondent on

09.10.2014 informing the Respondent about its refusal to take into

consideration the full quantity received at Chandrapur TPS for the last

rake.

xxiii) This was responded to by the Respondent vide letter dated

13.10.2014 protesting against the decision taken by the Petitioner in letter

dated 09.10.2014. The Respondent issued final invoice for the full MIR

quantity.



xxiv)        The PBG for Bhusawal TPS was discharged on 31.10.2014


Waghmare                                    8/48




                                                                         CARBPL.18419.21.doc



and the PBG for Chandrapur TPS was discharged on 01.11.2014.

xxv) The Petitioner addressed a letter to the Respondent on

28.11.2014 alleging that the tolerance/variation of +/- 2% was

applicable separately for supplies made to Chandrapur TPS and

Khaparkheda TPS.

xxvi) The Respondent addressed several letters to the Petitioner for

releasing balance payments which were outstanding against the contracts.

xxvii) The Respondent addressed a letter to the Petitioner on 22.01.2015

requesting it to accept the quantity tolerance for supplies made under the

Chandrapur Contract TPS and accept the final invoice.

xxviii) On 31.03.2015, the Petitioner made part payment of

Rs.34,31,00,903/- to the Respondent after delay of more than 12 months

from due date of payment.

xxix) The Respondent by letter dated 08.05.2015 requested the

Petitioner for the deductions towards BCD to be released.

xxx) The Respondent addressed another letter dated 30.06.2015

to the Petitioner requesting for the deductions towards BCD to be

released.

Waghmare                                 9/48




                                                                 CARBPL.18419.21.doc



xxxi)       The Petitioner by its letter dated 10.09.2015 relied on its

previous letter dated 09.10.2014 and rejected the claim of the Respondent

for the invoice towards full MIR quantity to be paid.

xxxii) Thereafter the Petitioner made further part payment on

09.10.2015 of a sum of Rs.16,92,61,241/- and on 23.10.2015 made

further part payment of Rs.16,80,27,750/- and on 09.11.2015 made

further part payment of Rs.84,15,983/-.

xxxiii) The Petitioner by letter dated 24.07.2015 replied to the

Respondent by stating that any concession applicable during the

contractual period should be passed by seller to the purchaser and that

the contracts entitled the Petitioner to deduct/recover amounts towards

liquidated damages from amounts payable to the Respondent.

xxxiv) The Petitioner by its letter dated 05.03.2016 informed the

Respondent that it had deducted Rs.4,10,74,481/- as recovery towards

BCD against a separate and unrelated contract No.2619 dated 03.12.2012

for supply to Khaparkheda TPS.

xxxv) The Respondent replied to the Petitioner on 30.03.2016

stating that the said deduction of Rs.4.10 crores was illegal, arbitrary and

contrary to the provisions of the contract.

Waghmare                                    10/48




                                                                                CARBPL.18419.21.doc



xxxvi)           The Respondent through its Advocate's Notice dated

31.08.2017 invoked arbitration.


xxxvii)          In view of the Petitioner having failed to appoint its nominee

arbitrator, the Respondent filed application u/s.11 of the Arbitration Act

being Commercial Arbitration Application No.178 of 2008 on 10.11.2017.

xxxviii) This Court by order passed on 30.10.2018 in the

Respondent's Section 11 application appointed the Arbitral Tribunal for

adjudicating the dispute. It is relevant to note the contention of the

Petitioner that by this Court observing in the said order that the

Respondent is restricting its claim to 2% BCD this was to overcome the

condition precedent of first referring the disputes to the Chief Engineer

and therefore, all other claims (except the claim for 2% BCD) are beyond

the scope of reference.

xxxix) The Respondent moved an application on 14.12.2018 before

this Court for modifying/altering the statement about restricting its claim

to 2% BCD only. This application was rejected by this Court on

17.12.2018.

xl) The Directorate of Revenue Intelligence (DRI) had

investigated the supply of coal by the Claimant to the Respondent/

Waghmare 11/48

CARBPL.18419.21.doc

Petitioner herein and the DRI had found that the Claimant has

perpetrated fraud and misrepresentation in importing and supplying the

said coal. The Order of DRI was set aside by CESTAT. The Appeal from

the said order by CESTAT was thereafter dismissed by this Court.

xli) The impugned order dated 20.07.2020 was passed dismissing

the preliminary objection raised of disputes being non-arbitrable on

account of serious fraud allegedly committed by the Respondent.

xlii) The impugned Award was passed on 21.04.2021 directing the

Petitioner to pay the Respondent a sum of Rs.22,06,47,321/- alongwith

interest @7.25% p.a. from the Award date till payment.

xliii) On 20.08.2021, the present Commercial Arbitration Petition was

filed.

xliv) The Civil Appeal against this Court's Order on DRI findings in

the Supreme Court was withdrawn on 24.01.2023

6 Mr. Pankaj Sawant, learned Senior Counsel appearing for the

Petitioner has made submissions on the Issue No.1 which is with regard to

the recoveries of 2% BDC. He has submitted that the Arbitral Tribunal

has erroneously held that reliance on the Circular issued on 21.10.2013

is misplaced as it is merely clarificatory in nature and that too with regard

Waghmare 12/48

CARBPL.18419.21.doc

to CVD which is not covered by Clause 5.2 of the contract. He has

submitted that the Arbitral Tribunal ought to have considered that Clause

5.2 is squarely attracted in the present case on the basis of the Circular

dated 21.10.2013 issued by the Government of India. The Petitioner has

submitted that prior to the Circular dated 21.10.2013, the importers of

coal had two options viz.



           Particulars             Imports Generally            Benefit of ASEAN
                                                                     Treaty
               BCD                       2%                               0%
               CVD                       2%                               6%
              Total                      4%                               6%




Therefore, the Price Scheduled in the Contract correctly proceeded on the

basis of 2% BCD and 2% CVD because even though imports from ASEAN

countries were supposed to be at a concession, in reality, they attracted a

higher duty of 6% (compared to a duty of 4% otherwise). He has

submitted that it was otherwise not practical to claim 0% BCD as it was

always coupled with 6% CVD.

7 Mr. Sawant has submitted that the effect of Circular

No.41/2013 dated 21.10.2013 was :

Waghmare                                  13/48




                                                                     CARBPL.18419.21.doc




           Particulars             Benefit of ASEAN Treaty
              BCD                                0%
              CVD                                2%          (Instead of 6%)
             Total                               2%




Thus, the reliance on the 2013 Circular is not misplaced as it was only

after this Circular that the concession of 0% BCD was no longer coupled

with 6% CVD and hence, became applicable at a practical level.

8 Mr. Sawant has submitted that the Arbitral Tribunal has erred

in rejecting the arguments of the Petitioner by dismissing off the said

Circular as being merely a clarification and relating only to CVD and not

to BCD. The facts remains that it was only after the said Circular that for

the first time the concession of 0% BCD with regards to imports from

ASEAN countries became applicable at a practical level as it was no longer

coupled with the 6% CVD and is hence very much applicable in the

present case.

9 Mr. Sawant has submitted that the Claimant's argument that

it could not be asked to obtain Form A-1 after supplies have already

begun, this contradicts its own interpretation of the contract. He has

submitted that the Claimant must avail of any concession that becomes

available after the contract has come into force. In the event, the

Waghmare 14/48

CARBPL.18419.21.doc

Claimant's argument is accepted, it would lead to an absurd situation

where the Claimant agreed not to avail of a duty concession that was

available in law. Moreover, there is no evidence to suggest that obtaining

Forms A-1 would have cost more than 2% BCD exemption that was not

claimed.

10 Mr. Sawant has submitted that as per Clause 10 of Annexure

III of the ASEAN Notification, an AIFTA certificate of origin could even be

obtained retroactively in exceptional cases and no longer than 12 months

from the date of shipment. He has submitted that the Claimant could

have availed the benefit of this provision by making an application for the

AIFTA certificate for the remaining goods to be shipped after the

enforcement of the Notification No.41/2013.

11 Mr. Sawant has submitted that the Claimant did not produce

any evidence to suggest that they had ever applied for the AIFTA

certificate of origin. Therefore, this clearly indicates the approach of the

Claimant, thereby, causing further loss of public money.

12 Mr. Sawant has submitted that the Arbitral Tribunal ought to

have taken into consideration the fact that a concession of BCD having

become available (in practical terms), then it was an obligation on the

part of the Claimant under Clause 5.2 to avail of such concession, which

Waghmare 15/48

CARBPL.18419.21.doc

the Claimant failed to do so. He has submitted that on the basis of these

submissions, the Claim No.1 pertaining to deduction of 2% BCD ought to

have been granted in favour of the Petitioner.

13 Mr. Sawant has submitted that the Arbitral Tribunal has

erroneously interpreted Clause 5.2 of the contract. This they have done

on the premise that the contract must be interpreted firstly as per its plain

language and only in the event that there is ambiguity that recourse can

be taken to various interpretations.

14 Mr. Sawant has submitted that the correct interpretation of

clause 5.2 in a contract is that it applies to all concessions in force during

the contractual period and it was the Claimant's duty to take advantage of

all such benefits and pass on the benefit of the exemption or concession to

the Petitioner. This interpretation is in line with the 'common sense

approach' and the purpose of the clause. He has submitted that the

Supreme Court through several judgments has held that contracts should

be interpreted in a manner that gives effect to the contract and makes

good commercial sense. The law does not concentrate too much on

individual words and looks at the commercial purpose and factual

background of the contract. He has submitted that mercantile contracts

must be construed in a business fashion and in a manner that would make

Waghmare 16/48

CARBPL.18419.21.doc

good commercial sense.

15 Mr. Sawant has relied upon the decision of the Supreme

Court in Union of India vs. D.N. Revri & Co. 1 wherein the Supreme Court

held that the contract being a commercial document between the parties,

it must be interpreted in such a manner as to give efficacy to the contract

rather than to invalidate it. The meaning of such a contract must be

gathered by adopting the common sense approach and it must not be

allowed to be thwarted by a narrow, pedantic and legalistic interpretation.

He has also placed reliance on the decision of the Supreme Court in

MTNL vs. Canara Bank2 wherein the Supreme Court has held that the

meaning of a contract must be gathered by adopting a common sense

approach and must not be allowed to be thwarted by a pedantic and

legalistic interpretation.

16 Mr. Sawant has also placed reliance upon the decision of the

Supreme Court in Pawan Alloys & Casting (P) Ltd. vs. U.P. SEB 3 at page

284 wherein the Supreme Court has quoted with approval from Chitty on

Contracts that the law does not approach the task of construction with too

nice a concentration on individual words. The mercantile contract should

be construed in a business fashion and in a manner that would make good

1 1976 (4) SCC 147 2 (2020) 12 SCC 767 3 (1997) 7 SCC 251

Waghmare 17/48

CARBPL.18419.21.doc

commercial sense. He has placed reliance upon Chitty on Contracts, 27 th

Edn., Vol. I 1994, and in particular paragraph 45 regarding contracts in

standard form and paragraph 12.013 regarding onerous or unusual terms.

He has also referred to paragraph 12.040 regarding intention of parties

wherein the Author has commented that one must consider the meaning

of the words used, not what one may guess to be the intention of parties.

Further, the law does not approach the task of construction with too nice

a concentration on individual words with regard to dealing with

mercantile Contracts, the author has stated that the commercial

documents 'must be constructed in a business fashion' and 'there must be

ascribed to the words a meaning that would make good commercial

sense'.

17 Mr. Sawant has also placed reliance upon the decision of the

Supreme Court in Rajasthan State Industrial Development and

Investment Corporation vs. Diamond and Gem Development Corporation

Ltd.4 wherein the Supreme Court has relied upon its prior decision in DLF

Universal Ltd. vs. Town and Country Planning Development 5 wherein it

was held that it is a settled principle in law that a contract is interpreted

according to its purpose. The purpose of a contract is the interests,

objectives, values, policy that the contract is designated to actualize.

4    2013 (5) SCC 470
5    (2010) 14 SCC 1

Waghmare                                       18/48




                                                                        CARBPL.18419.21.doc



Consistent with the character of purposive interpretation, the Court is

required to determine the ultimate purpose of a contract primarily by the

joint intent of the parties at the time the contract so formed.

18 Mr. Sawant has also relied upon the decision of the Supreme

Court in Southern Electricity Supply Co. of Orissa Ltd. vs. Seetaram Rice

Mill6 wherein the Supreme Court has held that the contractual documents

must be interpreted by Judges on the common sense principle.

19 Mr. Sawant has thereafter made submissions on the

Petitioner's entitled to recover dues under the previous contract. This

claim related to the recoveries made by the Petitioner relating to supplies

under an earlier contract i.e. Old Khaperkheda Contract from the amounts

payable under the present Chandrapur TPS Contract. He has submitted

that the Arbitral Tribunal has erroneously held that without a notice of

demand and/or notice to set off and/or notice to set off and/or in the

absence of pleading, the Petitioner is not permitted to set off the amount

under the present Chandrapur Contract. Mr. Sawant has placed reliance

upon clause 34.0 of the contract wherein it is stated that 'The Purchaser

shall have the right to set off any amounts owed by the Seller to the

Purchaser, against amounts owed by Purchaser to the Seller ...."

(emphasis added). He has submitted that the language of the Clause 34 6 (2012) 2 SCC 108

Waghmare 19/48

CARBPL.18419.21.doc

i.e. "any amounts" is very wide and will include amounts under an earlier

contract. He has submitted that the amount is certain and crystallized

and hence the Petitioner is entitled to recover the same. In this

connection Mr. Sawant has relied upon the following Supreme Court

Judgments:

i) Union of India v. Raman Iron Foundry, (2 Judges);

ii) H.M. Kamaluddin Ansari & Co. v. Union of India,

(3 Judges) over-ruling Raman Iron Foundry - paras 21,

24, 27, 28, 31;

iii) Gangotri Enterprises Ltd. v. Union of India, (2

Judges) follows Raman Iron Foundry - without noticing

that it has been over-ruled by a 3-Judge Bench in H.M.

Kamaluddin Ansari; and

iv) State of Gujarat v. Amber Builders, (2 Judges)

paras 19 to 21 - holds that Gangotri Enterprises is per

incuriam because it relies upon Raman Iron Foundry

which has been specifically over-ruled by a 3-Judge

Bench in H.M. Kamaluddin Ansari.

20 Mr. Sawant has submitted that the Petitioner being a Public

Sector Undertaking is considered a State according to Article 12 of the

Waghmare 20/48

CARBPL.18419.21.doc

Constitution of India. As the funds involved in the contracts in question

are public money, the terms of the contracts have been designated to

protect the public interest and ensure that the work is carried out with

care and diligence.

21 Mr. Sawant has thereafter made submissions with regard

issues Nos.2 to 5 being beyond the scope of reference. He has submitted

that the Claimant's entitlement is limited to Claim No.1, as per the High

Court's order dated 30.10.2018. Moreover, the Counsel representing the

Claimant made a clear statement that the Claimant's claim is restricted to

the 2% difference that had been deducted by the Petitioner. He has

referred to the statement made by the Counsel on behalf of the Claimant's

recorded in the said order. He has submitted that the statement was

made by the Claimant's Counsel to overcome the Respondent's objection

about non-compliance with the condition precedent of first referring the

disputes to the Chief Engineer. He has referred to the findings of this

Court in paragraph 8 on that issue.

22 Mr. Sawant has submitted that the Claimant's communication

dated 14.03.2014 to the Chief Engineer and his reply dated 19.03.2014

are only in respect of the 2% claim for BCD i.e. Claim No.1 in the

Arbitration and this Court has on that basis held that the pre-condition

Waghmare 21/48

CARBPL.18419.21.doc

(which is otherwise required to be strictly followed) has been met. He

has submitted that the praecipe was filed by the Claimant for speaking to

the minutes of the said order to modify the statement made by its

Counsel, which has also been rejected by this Court. He has accordingly

submitted that Issue Nos.2 to 5 have been erroneously held by the Arbitral

Tribunal in the affirmative and the same needs to be set aside.

23 Mr. Sawant has thereafter made submissions with regard to

Issue No.2 pertaining to deduction of excess quantity supplied at

Chandrapur TPS in claimant. He has submitted that the Arbitral Tribunal

has erroneously held Issue No.2 pertaining to deduction of excess quantity

supplied at Chandrapur TPS in favour of the Respondent/Original

Claimant. He has placed reliance upon clauses 8.7 and 8.11 of Schedule-

A of the Chandrapur Contract, which were incorporated into the

Khaparkheda Amendment Contract. These clauses state the Petitioner is

not liable to pay for excess quantity beyond the contractual quantity,

considering a tolerance of +2% delivered at the TPS. He has submitted

that it is crucial that the Claimant supplies coal in the required quantities

as specified in the contract to ensure proper electricity generation, as

stipulated in clause 2.0 (Scope of Work) of the contract.



24          Mr. Sawant has referred to the communications wherein he


Waghmare                                    22/48




                                                                       CARBPL.18419.21.doc



has submitted that the stance of the Petitioner is correct and in

accordance with the terms of the contract viz, communications dated

02.09.2014, 12.09.2014, 09.10.2014, 26.11.2014 and 10.09.2015. He

has submitted that Amendment No.4 clearly states that "The total

quantity for Chandrapur TPS after diversion of 80,000 MT quantity to

Khaperkheda TPS is 8,76,500 MT". He has submitted that the Arbitral

Tribunal ought to have considered the said clause 8.7 of Schedule-A while

deciding the Issue No.2, which states that "The seller shall note that if any

excess quantity beyond contractual quantity considering tolerance of +2%

is received at the TPS: the payment for such quantity shall not be made".

He has submitted that the Arbitral Tribunal ought to have considered that

clause 8.7 of Schedule-A is an express prohibition in the contract and that

if the claim is granted then the same will be contrary to the express

prohibition in the contract. He has submitted that on the same principles

of 'business-like interpretation', 'common sense interpretation' and

'purposive interpretation' of the contract (as per the supreme Court

decisions already quoted above), it is clear that the tolerance levels of +/-

2% is to be applied separately qua each TPS.

25 Mr. Sawant has submitted that if the Claimant's argument on

interpretation of clauses 8.7 and 8.11 is to be accepted, then it would lead

to an absurd situation viz. that the Claimant would be free to deliver the Waghmare 23/48

CARBPL.18419.21.doc

entire quantity at the original TPS location (and zero quantity at the new

TPS location) and still claim that there is no excess delivery at all. Such

hyper-technical interpretation not only renders clause 8.7 useless and

otiose, but it also flouts business common sense and militates against the

very purpose and intent of the clause. Despite a diversion of quantity as

contractually permissible, the Claimant will be free to deliver the entire

quantity at the original TPS location (and zero quantity at the new TPS

location). Therefore, on basis of this ground also, the award passed in

Issue No.2 needs to be set aside.

26 Mr. Sawant has submitted it is not disputed that the quanity

supplied by the Claimant at this TPS was in excess of the 2% tolerance

limit - if the Chandrapur TPS quantity is taken as the reduced quantity of

8,76,500 MT. Therefore, on the above mentioned grounds, the Arbitral

Tribunal ought not to have allowed the present claim in favour of the

Claimant.

27 Mr. Sawant has made submissions on issue No.3 - losses on

account of wrongful deduction on Liquidated Damages on account of

alleged short supply to Khaparkheda TPS (diverted quantity). He has

submitted that the Arbitral Tribunal has erroneously held that the

deduction is illegal as the Petitioner has not produced any proof of the

Waghmare 24/48

CARBPL.18419.21.doc

damages incurred on its part and the toleration limit of +/-2% should

have been calculated on the total quantity of 9,56,500 MTs as per the

Chandrapur Contract and not independently on the standalone basis of

the diverted quantity of 80,000 MTs. He has reiterated his submissions

on the interpretation of clauses 8.7 and 8.11 above. He has submitted

that the amount of Rs.1,12,16,141/- was correctly withheld as per the

terms of the contract. He has submitted under clause 15.3 of the Contract

it states that "The parties to the contract agree that the liquidated

damages payable as per clause 15 of this Section II are a fair and

reasonable pre-estimate of the damages likely to be suffered by the

Purchaser..."

28 Mr. Sawant has placed reliance upon the decision of the

Supreme Court in Kailash Nath Associates Vs. Delhi Development

Authority and Another.7 where the Supreme Court has placed reliance

upon its prior decision in ONGC Ltd. Vs. Saw Pipes Ltd.8, where it was

held that if compensation named in a contract for such breach is a

genuine pre-estimate of loss which the parties knew when they made

contract to be likely to result from the breach of it, there is no question of

proving such loss. He has submitted that the Arbitral Tribunal has erred in

7 (2015) 4 Supreme Court Cases 136 8 SCC pp.740-43 paras 64 & 67-68.

Waghmare                               25/48




                                                                CARBPL.18419.21.doc



holding that liquidated damages has not been proved by leading evidence.

29 Mr. Sawant has made submissions with regard to Issue No.4 -

short payment under Contract No.2041 dated 30.08.2023. He has

submitted that reconciliation proceedings are not yet concluded as the

Claimant have made various alterations in view of the disputed amount

which is yet to be identified. The Respondent denies that an amount of

Rs.21,76,555/- is due and payable under the Bhusawal Contract.

30 Mr. Sawant has in respect of Issue No.7 - Limitation,

submitted that the cause of action first arose on 19.03.2014, when the

Petitioner informed the Claimant that the Petitioner would be recovering

the said amounts from the payments against the Contract. Therefore, on

the basis of the same, the Arbitration reference commenced by arbitration

notice dated 31.08.2017 which is barred by Limitation and therefore on

this ground also all the claims of the Claimant needs to be set aside. He

has submitted that alternatively, all deductions/recoveries made three

years prior to the date when the arbitration notice dated 31.08.2017 was

received by the Respondent are clearly barred by limitation.

31 Mr. Sawant has accordingly submitted that the claims as

raised in the Statement of Claim were liable to be dismissed by the

Arbitral Tribunal being devoid of any merits, with compensatory costs.

Waghmare                                   26/48




                                                                       CARBPL.18419.21.doc



The Award passed by the Arbitral Tribunal not having done so, needs to

be set aside.

32 Mr. Vikram Nankani, learned Senior Counsel appearing for

the Respondent has made counter submissions. He has referred to certain

Clauses in the contract between the parties. In particular he has referred

to Clause 4.1 in Section 1 containing instructions to bidders which

contains provisions relating to the Bid Price under Bid Currency. He has

referred to the relevant clauses viz. Clauses 4.2, 4.4, 4.6 and 4.8 of the

contract. Thereafter, he has referred to Clauses 5.1, 5.2 and 5.3 of the

Contract. He has submitted that the Tender proceeded on the basis that

no concessional Customs Duty is applicable on coal, as provided in Clause

5.3 in Section II containing the general terms and conditions of the

Contract. He has thereafter referred to Clauses 8.1 and 8.12 of Section II,

Terms and Conditions of the Contracts. Under Clause 8.1, the

Respondent had to take responsibility of maintaining the delivery

schedule, if needed, by rescheduling deliveries through a different

discharge port. Further, under Clause 8.12 of the Contract the Respondent

reserved to itself the right to change the port of delivery at any time.

33 Mr. Nankani has thereafter referred to the payment terms in

Clause 12.1 of the Contract which provides that customs duty shall be

Waghmare 27/48

CARBPL.18419.21.doc

paid on actuals subject to proof of documentary evidence of payment by

the supplier (Respondent).

34 Mr. Nankani has submitted that having regard to the terms

and conditions of the Contract/Tender and in particular the Clauses

referred to above, the Petitioner while evaluating the bid made by the

Respondent, added 2% towards BCD in terms of Clause 20 of Section-1

containing the instruction to Bidders. Mr. Nankani has submitted that

consequently, when the Petitioner and the Respondent executed the

Contract, Schedule B thereof expressly provided for BCD calculated @2%

of the landed value (also the assessable value under the provisions of the

Customs Act, 1962) calculated @101% of the CIF (CIF + 1%). He has

referred to the relevant portion of Schedule-B in respect of the price break

up relating to 2% BCD.

35 Mr. Nankani has submitted that the Petitioner's challenge to

the impugned Award and interim order are based on the premise that the

Arbitral Tribunal had incorrectly interpreted the terms of the Supply

Contracts. He has submitted that there are a plethora of judgments which

have defined the limited contours or the restricted remit of a Court when

a Petition is adjudicated under Section 34 of the Arbitration and

Conciliation Act, 1996 (Arbitration Act). Regarding the question of

Waghmare 28/48

CARBPL.18419.21.doc

interpretation of contracts, it is settled law that the Arbitrator is

empowered to interpret the contract. This means that no Court can

interpret the contract for the Arbitrator. The interpretation and

construction of a contract is therefore primarily for the Arbitrator to

decide.

36 Mr. Nankani has submitted that there is no ground made out

by the Petitioner of patent illegality. The Award is not against public

policy. The Award is also not perverse. The Award is a reasoned speaking

award. He has submitted that the Arbitral Tribunal is a sole master of the

quality and quantity of evidence and the view taken by the Arbitral

Tribunal is the correct view. He has submitted that where there are two

views possible, if the view preferred by the Arbitral Tribunal is possible,

no interference can be called for under Section 34 of the Arbitration Act

and it is not for the Court to substitute its view. He has placed reliance

upon the judgments of the Supreme Court in Ssangyong Engineering &

Construction Co. Ltd. vs. National Highways Authority of India 9; Delhi

Airport Metro Express Pvt. Ltd. vs. Delhi Metro Rail Corporation Ltd. 10 and

UHL Power Company Ltd. vs. State of Himachal Pradesh11.



37               Mr. Nankani has thereafter made submissions on the

9 (2019) 15 SCC 131
10 (2022) 1 SCC 131
11 (2022) 4 SCC 116

Waghmare                               29/48




                                                                              CARBPL.18419.21.doc



aforementioned issues which the Petitioner has addressed in challenging

the impugned Award. On the issue of BCD concessions not being availed

by the Respondent, he has submitted that the Arbitral Tribunal has

correctly interpreted Clause 5.2 of the Contract that it applies only to BCD

concession and not CVD concession. He has submitted that a plain

reading of Clause 5.1 shows that the parties distinguished between BCD

and CVD. This distinction has also been made by the Supreme Court in

Hyderabad Industries Limited vs. Union of India12 where the Supreme

Court has held that CVD or additional duty is levied under Section 3(1) of

the Customs Tariff Act, 1975 and Section 12 of the Customs Act, 1962 is

not the charging section therefor.

38 Mr. Nankani has submitted that Clause 5.2 of the Contract

refers only to BCD and does not apply to CVD. This is made further clear

by reference to 'Basic Concessional Customs Duty' meaning thereby that

Clause 5.2 applies only to changes in BCD after entering into the contract.

Consequently, it follows that, no change in any other taxes including CVD,

covered by Clause 5.1 would be covered by Clause 5.2.

39 Mr. Nankani has submitted that the Circular dated

03.10.2013 is a mere clarification and that too, with regard to the

position in relation to CVD. The Circular may have been issued during 12 (1999) 5 SCC 15

Waghmare 30/48

CARBPL.18419.21.doc

the contractual period, but since Clause 5.2 does not apply to or cover

CVD, the same is of no relevance. He has submitted that Section 151A of

the Customs Act provides for the Central Board of Excise & Customs (now

known as 'Central Board of Indirect Taxes & Customs') may issue a

Circular to bring about uniformity in matters of classification and levy of

duty. The Circular is executive and not legislative in nature. It has been

held in large number of cases including in Jayant Dalal vs.

Commissioner13 that the said Circular is binding only on the Department

and not on the Assessee. Being clarificatory in nature, the same only

confirms the law as it existed at the onset.

40 Mr. Nankani has submitted at the beginning of the

contractual period, coal attracted 3 rates of basic customs duty. 10% as

per Customs Tariff, 2% as per Notification 12/2013 Cus. and Nil as per

Notification 46/2011 as amended on 31.12.2012. There was no change

in the rate of BCD after the contractual period started to run. Hence,

Clause 5.2 of the Contract is not attracted. The parties chose to apply the

concessional rate of the basic customs duty @ 2%. There has been no

change in the rate of BCD during the contractual period. He has

submitted that the parties chose not to lead oral evidence. Having chosen

not to lead oral evidence, the Petitioner cannot reply upon or call back the

13 (1997) 10 SCC 402

Waghmare 31/48

CARBPL.18419.21.doc

said Circular dated 03.10.2013 which was not in existence on the date of

execution of the contract.

41 Mr. Nankani has submitted that the Petitioner has made

submissions on the contract requiring to be interpreted in a business-like,

purposive and common-sense manner. He has submitted that the Arbitral

Tribunal has correctly held that since there were no ambiguity or

absurdity in the literal language of Clause 5.2, there was no requirement

to do a purposive, business-like or common-sense interpretation of the

said Clause. The Arbitral Tribunal has interpreted Clause 5.2 of the

Contracts as per plain language and in holding that the intent of the

parties manifested from the plain language of Clause 5.2 itself, the plain

language of the said Clause could not be defeated by interpreting the

same in any other way. The Arbitral Tribunal has rightly opined that the

deduction towards BCD made by the Petitioner was illegal and wrongful

and that the Respondent was entitled to the same.

42 Mr. Nankani has submitted that there can be no question of

interpreting Clause 5.2 of the contract in a commercial sense as the

Respondent had submitted its bid and made arrangements to discharge its

duties under the contract on the basis of the terms of the documents.

Interpreting Clause 5.2 in such a manner would have meant for the

Waghmare 32/48

CARBPL.18419.21.doc

Respondent to midway change the arrangements put in place by the

Petitioner, for complying with its contractual obligations.

43 Mr. Nankani has thereafter addressed the issues involving

fraud causing the disputes to become non-arbitrable which Mr. Sawant

has in oral arguments not addressed though this was one of the issues

raised before the Arbitral Tribunal. He has submitted that a dispute being

arbitrable is within the domain of the Arbitral Tribunal to determine. The

Arbitral Tribunal has correctly determined this issue by considering that

the claim of non-arbitrability was on the ground of the issue involving

fraud had been based on the order of the Directorate of Revenue

Intelligence ("DRI"), which order was set aside by CESTAT and the Appeal

preferred to the High Court was also dismissed. Since the Appeal filed by

the Petitioner against the order of CESTAT was then referred to the

Supreme Court and was pending, the Arbitral Tribunal rightly did not

consider the DRI order.

44 Mr. Nankani has submitted that the Arbitral Tribunal had

correctly decided the issue of obtaining AIFTA Certificate (Form A-1) upon

a reading of Notification No.46/2011 and which provided that it has to be

obtained pre-shipment. Moreover, since the procedure and machinery as

per ASEAN Trade Rules for obtaining Form A-1 required the exporter to

Waghmare 33/48

CARBPL.18419.21.doc

apply for the Form A-1 pre-shipment, it was not possible to make this

happen midway.

45 Mr. Nankani has addressed the other issue raised by Mr.

Sawant during arguments and which relates to Claim Nos.2 to 5 being

beyond the scope of reference. He has submitted that the Arbitral Tribunal

has correctly interpreted that Section 11 of the Arbitration Act does not

require the Chief Justice or his designate to identify the disputes or refer

them to the Arbitral Tribunal for adjudication. Hence, the order dated

30.10.2018 passed in the Section 11 Application referring the disputes to

arbitration could not have restricted the Respondent from making its

claims as per its notice of invocation dated 31.08.2017. The operative

part of the said order dated 30th October, 2018 did not exclude any

claims. The Arbitral Tribunal has also appreciated that since the Chief

Engineer (FMC) had already rejected the Respondent's Claim Nos.2 and 3,

there could be no question of the Respondent again going to the same

authority for adjudication of these claims. With regard to Claim No.4, the

Arbitral Tribunal has found that there was no dispute as to the

reconciliation sheet jointly signed by the parties showing the amounts to

be due and payable. Insofar as Claim No.5 is concerned, the same was

not pressed by the Respondent.

Waghmare                                    34/48




                                                                         CARBPL.18419.21.doc



46               Mr. Nankani has submitted that the Arbitral Tribunal has

rightly held that these claims are not beyond the scope of reference and

jurisdiction of the Arbitral Tribunal. He has submitted that by the said

order dated 30.10.2018, this Court had kept all rights and contentions of

the parties open, except the question of jurisdiction of the Arbitrator. The

Petitioner's contention that these claims are beyond the scope of reference

overlooks paragraph 12 of the said order dated 30.10.2018 whereby 'all

disputes' between the parties have been referred to Arbitration by the

Arbitral Tribunal. He has submitted that the reliance placed by the

Petitioner on the praecipe filed by the Respondent for speaking to the

minutes of order is misplaced inasmuch as no orders were passed thereon.

This is in view of this Court having passed the said order dated

30.10.2018 wherein 'all disputes' have been referred to arbitration.

47 Mr. Nankani has thereafter addressed the issue of diverted

quantities from Chandrapur TPS to Khaparkheda TPS. He has submitted

that the Arbitral Tribunal has correctly appreciated Clause 8.7 of the

contract which uses the expression 'ordered quantity/contracted quantity'

which meant the tolerance of +/-2% against contracted quantity, if fully

ordered or against the ordered quantity. The Arbitral Tribunal has also

rightly considered that the amendment of the contract required the

parties to follow the procedure under Clause 35 of the Contract and no Waghmare 35/48

CARBPL.18419.21.doc

independent contract was entered into between the parties for the

purpose of diversion of quantity. The Arbitral Tribunal has accordingly

answered Issue No.2 in the affirmative and allowed the claim of the

Respondent in relation to the diverted quantities from Chandrapur TPS.

48 Mr. Nankani has submitted that the Petitioner had deducted

sum of Rs.1,12,16,141/- on the ground of alleged shortage in excess of -

2% at Khaparkheda. The Petitioner had directed the Respondent to divert

80,000 MTs from Chandrapur Contract to Khaparkheda. As against

80,000 MTs, the Respondent actually delivered 58,297 MTs. Applying

+/-2% tolerance limit under Clause 8.7 of the Chandrapur Contract to the

quantity of 80,000 MT (1600 MT), the Petitioner alleged that there was

shortage beyond 1600 MTs, and non-performance of the entire contract or

part thereof and that the Petitioner was entitled to deduct liquidated

damages under Clause 15.1 of the Chandrapur Contract. He has

submitted that this calculation of +/-2% with reference to 80,000 MT is

erroneous. The tolerance limit of +/-2% had to be calculated on the total

quantity of 9,56,500 as per the Chandrapur Contract. The tolerance limit

cannot independently or on stand-alone basis, be applied to diverted

quantity of 80,000 MT since it is part of the ordered quantity under the

Chandrapur Contract. There is undisputedly no separate contract for

80,000 MT diverted to Khaparkheda. He has accordingly submitted that Waghmare 36/48

CARBPL.18419.21.doc

there is no merit to the challenge of the Petitioner to the Arbitral Award

on this issue.

49 Mr. Nankani has thereafter addressed the issue of liquidated

damages. He has submitted that the Arbitral Tribunal has held that since

there was no shortfall more than permissible limits under the Supply

Contracts, the deductions effected by the Petitioner by way of Liquidated

Damages were impermissible. The Arbitral Tribunal had noted that it was

for the Petitioner to prove damages suffered. However no evidence was

produced in this regard. A finding was arrived at that damage/loss

caused is a sine qua non for the applicability of Section 74 of the Contract

Act and failure to prove damages would lead to the conclusion that the

Petitioner had not suffered any loss. He has submitted that without

prejudice to the submissions on their being no shortfall in quantity

supplied more than permissible limits under the Supply Contracts, the

deduction of Rs.1.12 crores by way of liquidated damages under Clause

15.1 of the Chandrapur Contract, has not been proved by leading any

evidence. It is settled law that the Petitioner needs to prove loss caused

by the alleged breach of short supply beyond the permissible limits of

Clause 8.7 of the Chandrapur Contract. He submitted that the decision of

the Supreme Court in Kailash Nath Associates vs. DDA (Supra) and MTNL

Waghmare 37/48

CARBPL.18419.21.doc

vs. Tata Communications Ltd.14 is in support of this view as it considers

Section 74 of the Contract Act in its correct perspective and not in the

manner contended by the Petitioner.

50 Mr. Nankani has submitted that the deduction of liquidated

damages was made from the payments due under the Chandrapur

Contract. The supplies to Khaparkheda TPS were diverted from

Chandrapur Contract as per the agreed terms and hence, the quantity

supplied to Chandrapur and Khaparkheda TPS ought to be taken together

when applying Clause 8.7 of the Supply Contracts. When taken together,

there was no short supply to Khaparkheda TPS as alleged by the

Petitioner. Accordingly, the Petitioner's contentions that they were

entitled to deduct liquidated damages for alleged short supply to

Khaparkheda TPS is misconceived.

51 Mr. Nankani has then made submissions on the issue of

Limitation. He has submitted that the Arbitral Tribunal had noted that

part payments were made by the Petitioner to the Respondent between

October and November, 2015 and thereafter, the Chief Engineer (FMC) of

the Petitioner had rejected the Respondent's claims vide letters dated

24.07.2015 and 10.09.2015. In the Arbitral Tribunal's view, the Petitioner

was not bound to make payment of the balance amount to the 14 (2019) 5 SCC 341

Waghmare 38/48

CARBPL.18419.21.doc

Respondent until the balance payments could have been sought only after

stipulated factors were determined and adjustments were carried out,

which happened only upon joint reconciliation of accounts which was

completed by the parties on 24.05.2017 in relation to Bhusawal Contract

and on 22.03.2017 in relation to Chandrapur Contract. Hence, the

Arbitral Tribunal has rightly held that the claims of the Respondent were

within limitation.

52 Mr. Nankani has submitted that the notice of arbitration is

dated 31.08.2017 and in view of part payments made by the Petitioner to

the Respondent between October and November, 2015, these factors have

been rightly taken into consideration by the Arbitral Tribunal including as

aforementioned the Joint Reconciliation of Accounts completed by the

parties on 24.05.2017 in case of Bhusawal Contract and on 22.03.2017 in

respect of the Chandrapur Contract in which the amounts deducted (and

now claimed) were also finalized and net amount post adjustments

payable to the Respondent have been mentioned. Further, the Petitioner

has accepted the Respondent's claim No.4 i.e. short payment under BTPS

Contract for Rs.21,76,555/- and paid the same to the Respondent on

26.08.2021. Hence, there is no merit in the challenge to the Arbitral

Award on the issue of limitation.

Waghmare                               39/48




                                                                  CARBPL.18419.21.doc



53          Mr. Nankani has accordingly submitted that there is no valid

ground of challenge under Section 34 of the Arbitration Act              in the

present Petition and accordingly the Petition be dismissed with costs.

54 Having considered the submissions, regarding issue No.1 viz.

BCD concession not having been availed of by the Respondent, the

Arbitral Tribunal has interpreted Clause 5.2 of the Contract as per its plain

language and upon such interpretation arrived at a finding that it is

apparent from the said Clause read with Clause 5.1 of the Contract that

the intent of the parties was to consider BCD distinct from CVD in the

Supply Contracts. The said Clause 5.2 is applicable only to BCD

concession and not to CVD concession. The Arbitral Tribunal has also

considered the notifications which were issued prior to the Supply

Contracts and found that no concessional Customs Duty applicable on

coal. Clause 5.2 of the Contract was made to cover import of coal under

Notification No.12/2012 and if concessions became available on BCD

during the period of the contract to such imports, they would be

applicable. The Petitioner had intentionally claimed the BCD of 2% under

Notification No.12/2012 as the CVD under the said Notification was also

2%. Thus, making the total duty of 4%. This against the Notification

No.46/2011 which was for ASEAN countries where BCD was 0% and the

corresponding CVD being 6% making a total duty of 6%. There was no Waghmare 40/48

CARBPL.18419.21.doc

scope for further concession in BCD under this notification. The price

schedule in the contract had also proceeded on the basis of 2% BCD and

2% CVD.

55 Further, the Circular dated 3rd October, 2013 relied upon by

the Petitioner has been held by the Arbitral Tribunal to be merely

clarificatory and that too with regard to the position in relation to CVD.

In view of the aforementioned interpretation of the Arbitral Tribunal on

Clause 5.2 and that CVD not being covered by the said Clause, it was

irrelevant as to when the said Circular had been issued i.e. prior to or

during the contractual period. In any event the Arbitral Tribunal had

noted that the parties chose not to lead oral evidence and having done so,

there was nothing on record to show as to when the said Circular dated

03.10.2013 was issued. There is much merit in the submission of the

Respondent that the Petitioner cannot now call back the Circular which

according to the Petitioner was not in existence on the date of the

execution of the contract.

56 It is settled law that the Arbitral Tribunal is empowered to

interpret the contract and the Court cannot interpret contracts for the

Arbitrator. The interpretation and construction of a contract is primarily

for the Arbitrator. The Arbitrator's view on the interpretation of the

Waghmare 41/48

CARBPL.18419.21.doc

Clauses of the contract, is a possible view and hence calls for no

interference under Section 34 of the Arbitration and Conciliation Act,

1996. Thus, in my view there is no merit in the challenge to the finding

of the Arbitral Tribunal with regard to issue No.1. The Arbitral Tribunal

having interpreted the aforementioned clauses which this Court finds is a

possible interpretation cannot be a ground of challenge under Section 34

of the Arbitration Act.

57 The decisions of the Supreme Court relied upon by the

Respondent namely Ssangyong Engineering & Construction Co. Ltd.

(supra); Delhi Airport Metro Express Pvt. Ltd. (supra) and UHL Power

Company Ltd. (supra) are apposite.

58 With regard to the Petitioner's contention of Issue Nos.2 to 5

being beyond this Court's reference and thus, not arbitrable, I do not find

any merit in this contention. This is in view of the order dated 30.10.2018

not placing any restriction upon the Respondent making its claims as per

Notice of Invocation dated 31.10.2017 and this is borne out from the

operative part of the said order. The Arbitral Tribunal has in my view

correctly interpreted Section 11 of the Arbitration and Conciliation Act,

1996, as not requiring the Chief Justice or his designate to identify the

disputes whilst referred them to the Arbitral Tribunal for adjudication.

Waghmare                                    42/48




                                                                          CARBPL.18419.21.doc



The Arbitral Tribunal has considered these Claim Nos.2 to 5 to be

arbitrable. The Arbitral Tribunal has appreciated that the Chief Engineer

(FMC) has already rejected the Respondent's Claim Nos.2 and 3 and

hence there could be no question of the Respondent again going to the

same Authority for adjudication of its claim. Further, with regard to

Claim No.4, there was no dispute as the reconciliation sheet was jointly

signed by the parties showing the amounts to be due and payable. Claim

No.5 was not pressed by the Respondent. Hence, I do not find any error

on the Arbitral Tribunal's part in adjudicating these claims. The

Respondent had also addressed these claims on merits and the Arbitral

Tribunal has after considering the Respondent's defence on these claims

arrived at the finding in the impugned award.

59 I shall now consider Issue No.2 - deduction of excess quantity

supplied at Chandrapur TPS decided by the Arbitral Tribunal in favour of

the Respondent. It is the Petitioner's submission that they had taken

action in view of Clauses 8.7 and 8.11 of Schedule A of the Chandrapur

Contract incorporated in the Khaparkheda Amendment Contract which

specifically stated that the Petitioner is not liable to pay for excess

quantity beyond the contractual quantity, considering the tolerance of +/-

2% delivered at TPS. It is the Petitioner's contention that the Respondent

had not supplied coal as per specific requirement at Khaparkheda TPS and Waghmare 43/48

CARBPL.18419.21.doc

hence, the Petitioner made deductions under Clause 8.7 of the

Chandrapur Contract.

60 The Arbitral Tribunal in considering this issue has interpreted

Clauses 8.7 to 8.11 of the Contract. The Arbitral Tribunal has considered

that Clause 8.11 of the Chandrapur Contract only permitted the Petitioner

to divert rakes from designated TPS to another TPS as per requirement.

The Respondent only had the right to have coal diverted to the

Khaperkheda TPS. The Arbitral Tribunal by interpreting Clause 8.7 has

considered the expression 'ordered quantity/contracted quantity' which

meant the tolerance of +/ -2% was against contracted quantity if fully

ordered or against the ordered quantity. The parties were required to

follow the procedure under Clause 35 of the Contract and no independent

contract was entered into between the parties for the purpose of diversion

of quantity.

61 The Arbitral Tribunal in my view has correctly accepted the

contention of the Respondent that the tolerance limit of +/- 2% under

Clause 8.7 of the contract cannot independently or on stand alone be

applied to the diverted quantity of 80,000 MT since it is a part of the

ordered quantity and the tolerance limit of +/-2% necessarily would have

to be calculated on the total quantity of coal supplied to the Chandrapur

Waghmare 44/48

CARBPL.18419.21.doc

TPS. There is no separate contract for 80,000 MT diverted to

Khaperkheda TPS. Thus, the Respondent had made the related deduction

under Clause 8.7 of the Chandrapur Contract on the basis that there was

no shortage of coal supplied to Khaperkheda TPS.

62 In any event the Arbitral Tribunal's interpretation of Clauses

8.7 and 8.11 of the Contract is a possible interpretation which calls for no

interference by this Court under Section 34 of the Arbitration Act. The

aforementioned decisions relied upon the Respondent are apposite in this

context as well.

63 Now coming to the issue of Liquidated Damages, the Arbitral

Tribunal has held that this issue will no longer arise in view of the finding

there was no shortfall of supply of coal more than permissible limits

under the supply contracts. Hence, the deduction effected by the

Petitioner by way of liquidated damages were impermissible. I find no

error in the Arbitral Tribunal holding that presuming that this issue was to

be considered the Petitioner has failed to prove damages suffered as no

evidence was produced in this regard. The deduction of Rs.1.12 crores by

way of liquidated damages is under Clause 15.1 of the Chandrapur

Contract. There is much merit in the contention on behalf of the

Respondent that the Petitioner needs to prove loss caused by alleged

Waghmare 45/48

CARBPL.18419.21.doc

breach of short supply beyond permissible limits of Clause 8.7 of the

Chandrapur Contract. No loss has been proved by the Petitioner. The

finding of the Arbitral Tribunal that damage/loss caused is a sine qua non

for the applicability of Section 74 of the Contract Act and in view of there

being no proof of any damage / loss, the Petitioner had not suffered any

loss cannot be faulted. Further, considering that there is no breach of the

Contract the decision relied upon by the Petitioner viz. Kailash Nath

(Supra) which relies upon ONGC (Supra) is in applicable. In any event

these decisions also consider Section 74 of the Contract Act and have held

that under this Section the expression"

"Whether or not actual damage or loss is proved to have been

caused thereby" means that where it is possible to prove actual damage or

loss, such proof is not dispensed with.

64 With regard to the issue of limitation, in my view the Arbitral

Tribunal has upon proper appreciation of the material on record rightly

held that the claims of the Respondent were within limitation. The

Arbitral Tribunal has considered there were part payments made by the

Petitioner to the Respondent between October and November, 2015.

Thereafter the Chief Engineer (FMC) of the Petitioner had rejected the

Respondent's claim vide letters dated 24.07.2015 and 10.09.2015. The

Waghmare 46/48

CARBPL.18419.21.doc

balance payment could have been sought only after joint reconciliation of

accounts which were completed by the parties on 24.05.2017 in relation

to the Bhusawal Contract and on 22.03.2017 in relation to the

Chandrapur Contract. The Notice invoking the arbitration has been issued

by the Respondent/Original Claimant on 31.08.2017. Hence I find no

merit in the challenge of the Petitioner to the findings of the Arbitral

Tribunal on the issue of limitation. This apart from the settled law that a

Court whilst considering a Petition filed under Section 34 of the

Arbitration Act cannot re-appreciate evidence.

65 Apart from these challenges to the impugned award which

have been raised in written and oral arguments on behalf of the

Petitioner, there are no other challenges raised to the impugned Award.

Further, I do not find any error in the impugned order dated 20.07.2020

by which the Arbitral Tribunal had rejected the submission of the

Petitioner that the dispute before the Arbitral Tribunal involves a case of

serious fraud and thus not arbitrable. The Arbitral Tribunal had upon

appreciation of the material on record arrived at a finding in the

impugned order dated 20th July, 2020 that the dispute is purely a

contractual dispute and the allegation in the defence taken at the highest

of simple fraud and not of serious allegation of fraud. The Arbitral

Tribunal has accordingly held that the case is arbitrable and such a Waghmare 47/48

CARBPL.18419.21.doc

finding cannot be faulted by this Court under Section 34 of the

Arbitration and Conciliation Act, 1996.

66 Accordingly I do not find any grounds raised in the

Arbitration Petition which fall within the acceptable grounds of challenge

to an award under Section 34 of the Arbitration and Conciliation Act,

1996.

67 The Arbitration Petition is devoid of any merit and is

accordingly dismissed. There shall be no order as to costs.



                                                   ( R.I. CHAGLA, J. )




Waghmare                                   48/48




 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter