Citation : 2023 Latest Caselaw 8969 Bom
Judgement Date : 31 August, 2023
2023:BHC-AS:25245-DB 23-aswp-2229-2022-J.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO. 2229 OF 2022
Bhiwandi Powerloom Co-operative Society Ltd.
(Formerly Known as Bhiwandi Co-operative
Spinning Mills Ltd.), having its office at 3,
Bengalpura, Bhiwandi, Thane-421 203
Through its Chairman Iqbal Ahmed Abdul Rauf
Punjabi. ... Petitioner
Versus
1. The State of Maharashtra, Through its
Principal Secretary, Revenue and Forest
Department, Mantralaya, Mumbai.
2. The Collector, Thane.
3. The Tahsildar (Revenue), Having its office
at Collector Office, Thane. ... Respondents
Mr. Raju D. Suryawanshi for Petitioner.
Ms. S. S. Bhende, AGP for Respondents-State.
CORAM K. R. SHRIRAM &
DR. N. K. GOKHALE, JJ.
DATED: 31st August 2023
JUDGMENT:- (PER Dr. N. K. Gokhale, J.)
1. Rule. Rule is made returnable forthwith. Heard finally by
consent of parties.
2. The Petitioner assails letter/order dated 29 th March 2019
issued by the Respondent No.3 directing the Petitioner to pay an
Gaikwad RD 23-aswp-2229-2022-J.doc
amount of Rs.87,04,480/- and for a declaration that the Petitioner is
not liable to pay the said amount towards extension of building
permission in respect of implementation of the project. The
Petitioner also seeks a declaration that the Government Resolution
("GR") dated 1st March 2019 is not applicable to it.
3. The Petitioner is a specified co-operative society registered
under the Maharashtra Co-operative Societies Act, 1960, with an
object of constructing spinning mills for the power loom sector in
Bhiwandi. The Respondents No.2 and 3 are the Collector, Thane
and Tahsildar (Revenue), Thane, respectively, of the Respondent
No.1-State of Maharashtra.
4. Shorn of unnecessary details, the brief facts are that by order
dated 9th September 1977, the Petitioner was allotted land
admeasuring approximately 10 acres and 5 gunthas of Survey No. 60
of Village Savande, Taluka Bhiwandi. In terms of the allotment, the
Petitioner was required to complete the construction of the building
and implement the project within three years from the date of
Gaikwad RD 23-aswp-2229-2022-J.doc
handing over the possession of the said land. The possession of the
land was handed over to the Society on 18th October 1977.
5. Accordingly, the Petitioner procured non-agricultural use
("NA") permission on 28th October 1983. By letter dated 31 st
January 1994, the Petitioner requested the collector to change the
NA permission and permit the use of land for power loom shed. By
letter dated 14th September 1994, the Collector issued a notice to the
Petitioner to show cause as to why the land should not be resumed
by the Government for non-compliance of the conditions of
allotment. The Petitioner replied to the notice, however, the land
came to be resumed by the State. An appeal preferred by the
Petitioner was dismissed by the Competent Authority, however, by
order dated 28th February 2002, the Revenue Minister of the State
set aside the resumption order in appeal.
6. It is the case of the Petitioner that he was unable to complete
the construction and implement the project within the stipulated
period on account of obstructions caused by various departments of
the State. By GR dated 11th January 2017, the State decided to grant
Gaikwad RD 23-aswp-2229-2022-J.doc
extension for a further period of three years to allottees such as the
Petitioner-Society on payment of 2% of the value of land as
published in the Ready reckoner. A subsequent GR dated 1 st March
2019 modified the amount to be paid for such extension of time.
The Petitioner made an application to the Collector for extension of
time on 8th March 2019. By letter dated 29 th March 2019, the
Tahsildar directed the Petitioner to deposit an amount of
Rs.87,04,182/- calculated as per applicable rate for grant of
extension of time. This is the communication that is impugned in
the Petition.
7. Mr. Suryawanshi, learned Counsel for the Petitioner draws
our attention to the letter of 29 th March 2019 addressed by the
Respondent No.3 to the Tahsildar of Bhiwandi by which the latter
has been directed to grant extension of time to the Petitioner-
Society as per its request subject to deposit of the aforesaid amount.
The said communication refers to the GRs dated 11 th January 2017
and 1st March 2019. He states that the Respondents failed to
appreciate the best efforts made by the Petitioner-Society to start
Gaikwad RD 23-aswp-2229-2022-J.doc
the project as it faced obstacles in seeking permission from various
government departments and it is only on 21 st February 2021 that
the Mumbai Metropolitan Regional Development Authority
("MMRDA"), the special planning authority, granted
Commencement Certificate for the construction. He has also put
forth a ground that 25th March 2020 onwards the Petitioner was
unable to move appropriate government departments on account of
the COVID-19 pandemic. He thus urges us to allow the Petition.
8. Ms Bhende, learned AGP points out a letter of 14 th August
2019 at Exhibit "G" (page 46) addressed by the Petitioner to the
Respondent No.2-Collector, clearly conveying that the Petitioner-
Society has abided by the directions of the Collector in respect of
deposit of an amount of Rs.15,63,702/- and furnishing a bank
guarantee of Rs.71,40,480/- issued by the Greater Bombay Co-
operative Bank Ltd., Thane. She also points to a government order
("GO") of 11th September 2019 at Exhibit "H" (page 47) granting
extension of time to the Petitioner-Society up to 1 st March 2021
upon the deposit of the aforesaid amount and furnishing of the
Gaikwad RD 23-aswp-2229-2022-J.doc
required bank guarantee. She thus submits that the Petitioner has
already complied with the conditions of the deposit of the charges
and furnishing of bank guarantee on the basis of which time for
implementation of project was extended and therefore, this Petition
is misconceived.
9. We have considered the submissions of both the parties and
have perused the documents on record. Undoubtedly, the
Petitioner was allotted the said land pursuant to GO dated 4 th
September 1977. The idea behind allotment of government land to
deserving persons, societies, corporate entities, etc. was to act as a
catalyst to promote economic growth and accelerate pace of
development. The order itself was passed by virtue of the powers
vested in the government under the provisions of the Maharashtra
Land Revenue (Disposal of Government land) Rules, 1971 ("Rules
1971"). Rule 41 of the Rules 1971 vests in the Collector the power
to annex additional conditions for the grant of land. It is in the
exercise of this power vested in the Collector by the statutory
Gaikwad RD 23-aswp-2229-2022-J.doc
provision as well as respective GRs, that the conditions have been
imposed on the Petitioner-Society.
10. Admittedly, the land was allotted to the Petitioner-Society on
9th September 1977 and possession was handed on 18th October 1977.
There was a specific condition No. (xiii) of the allotment order that
non-construction of building would lead to resumption of the said
land under the provisions of the Act and the Rules. As noticed
above, the Petitioner-Society failed to raise construction on the plot
and the land was resumed by the Collector. For the past 46 years,
the Petitioner-Society has failed to complete the construction and
implement the project, the purpose for which the land was allotted.
There is nothing on record to remotely indicate attempts made by
the Petitioner-Society to procure required permissions from
government department and obstacles allegedly created by such
departments to complete the project. On the contrary, the record
itself shows that the Collector has once already resumed the land in
the year 1995 itself for the Petitioner's failure to comply with the
conditions of allotment and it was only on the order of the Revenue
Gaikwad RD 23-aswp-2229-2022-J.doc
Minister as an appellate authority that the resumption order was set
aside and the Petitioner was afforded another opportunity to
complete the project. Despite this respite, the project has yet not
taken of and the object of allotting the said land has been frustrated
by the lackadaisical approach of the Petitioner-Society.
11. The record further shows that the Petitioner-Society has
availed the benefits of extension of time on payment of the extension
fee as prescribed and is now trying to assail the very same condition.
In our considered opinion, defaulting allottees of valuable plots
cannot be allowed to approbate and reprobate by first agreeing to
abide by the terms and conditions of allotment and enjoying the
benefits of extended period and later seek to deny their liability as
per the agreed terms. The impugned letter is nothing but a
communication between the competent authorities inter se directing
extension of period subject to payment of the required fee.
Similarly, the assailed GR is applicable to the case of the Petitioner
since it is by virtue of the government decisions itself that the land
came to be initially allotted to it. Having deposited the amount and
Gaikwad RD 23-aswp-2229-2022-J.doc
furnishing the bank guarantee, it is now the duty of the Petitioner-
Society to keep the bank guarantee alive as a condition to continued
enjoyment of the benefits of the land. It does not lie in its mouth to
assail at such a belated stage the applicability of the GR of 1 st March
2019 to it.
12. In view of the above discussion, the Writ Petition fails. Rule
is thus discharged. There will be no order as to costs.
(DR. N. K. GOKHALE, J.) (K. R. SHRIRAM, J.) Signed by: Raju D. Gaikwad Date: 01/09/2023 20:45:41 Gaikwad RD
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!