Citation : 2022 Latest Caselaw 2601 Bom
Judgement Date : 16 March, 2022
WP 5470-21 1 Judgment
IN THE HIGH COURT OF JUDICATURE AT BOMBAY,
NAGPUR BENCH, NAGPUR.
WRIT PETITION NO. 5470/2021
M/s Sainik Mining and Allied Services Limited,
A Public Limited Company, having its registered
Office at 129, Transport Centre, Rohtak Road,
Punjabi Bagh, New Delhi - 110035 and Corporate
Office at 7th Floor, Corporate Tower, Ambience Mall,
N.H. No.48, Gurugram-122001, herein represented
by Senior General Manager Omprakash Katare,
aged about 63 years, having its office at Sainik
Mining & Allied Service Limited, Qtr. No.B-92,
WCL Colony, Near Harihar Mandir, Umrer, Nagpur
(Maharashtra), Pin Code-441204, who has been duly
authorized vide letter dated 08/12/2021 read with
Board Resolution dated 23/07/2020. PETITIONER
.....VERSUS.....
1. M/s Western Coalfields Limited,
through its General Manager (CMC), WCL HQ,
Nagpur, Coal Estate, Civil Lines, Nagpur-440001.
2. M/s Western Coalfields Limited,
through its General Manager, Umrer Area,
PO Project, Dist. Nagpur-441204.
3. HDFC Bank, through Manager, having Branch
Office at E-13/29, Second Floor, Harsha Bhawan,
Middle Circle, Connaught Place New Delhi-110001. RESPONDENT S
Shri A.S. Jaiswal, Senior Advocate with Shri Gopal Sawal, counsel for the
petitioner.
Shri S.P. Dharmadhikari, Senior Advocate with Shri Kartik Shukul, counsel for
the respondent nos.1 and 2.
CORAM : A. S. CHANDURKAR AND SMT. M.S. JAWALKAR, JJ.
DATE ON WHICH ARGUMENTS WERE HEARD : 01ST MARCH, 2022. DATE ON WHICH JUDGMENT IS PRONOUNCED : 16TH MARCH, 2022.
JUDGMENT : (PER : A.S. CHANDURKAR, J.)
RULE. Rule made returnable forthwith and heard the learned
counsel for the parties.
WP 5470-21 2 Judgment
2. The challenge raised in this writ petition is to the order dated
08.12.2021 that has been issued by the Area General Manager, Umrer
Area of the Western Coalfields Limited by which the work order issued to
the petitioner pursuant to the tender notice dated 20.02.2016 has been
terminated and the performance security deposit furnished by the
petitioner has been forfeited. In addition, the petitioner has been
debarred from participating in future tenders of the Western Coalfields
Limited for a period of three years.
3. The facts giving rise to the present writ petition are that the
petitioner is a company incorporated under the Companies Act, 1956 and
is engaged in the business of excavation as well as mining of coal and
other allied services. On 20.02.2016, the Western Coalfields Limited
issued a tender notice inviting bids for three jobs with duration of 83
months. As per Clause 6.2 of the tender notice if there was failure on the
part of the Contractor to complete the work within the agreed time and
also to maintain the progress of that work, the Contractor was liable to
pay liquidated damages. As per Clause 6.4 there was a provision for
extending the date of completion for reasons stipulated therein including
a cause beyond the control of the Contractor. As per Clause 9, the
contract was liable to be cancelled in full or in part if the Contractor
defaulted in proceeding with the works with due diligence and the WP 5470-21 3 Judgment
Contractor continued to do so even after a notice in writing from the
Engineer In-charge. As per Clause 9(b) if there was failure to achieve
monthly agreed quantity of 75% or a period of six consecutive months or
a cumulative period of six months within a continuous period of eighteen
months then except on account of non-availability caused by a Force
Majeure event or an act of omission of company not occurring due to any
default of the Contractor, the Western Coalfields Limited was free to act
accordingly. Though there are other sub clauses to Clause 9 they are not
relevant for the present purpose. As per Clause 19 there is a provision for
payment of price variation and as per Clause 19.04.1 price variation on
account of diesel has been provided. In the formula stated in that clause
the diesel component expressed as percentage of total value of work was
0.30. The bid submitted by the petitioner was accordingly accepted by
issuing the letter of acceptance on 27.05.2016. Pursuant thereto the
petitioner was issued the work order dated 08.12.2016. In Clause 21 of
the said work order, the rate of diesel as on 15.03.2016 was indicated at
Rs.52.37 Ps. per litre. It was stated that the escalation/de-escalation
would be payable/recoverable as per the price variation clause of the
Special Terms and Conditions of the Tender Document.
4. It is the case of the petitioner that pursuant to aforesaid work
order the work commenced and the same was being done smoothly.
WP 5470-21 4 Judgment
However on account of setting in of the Covid-19 pandemic the petitioner
started facing difficulties. On 02.04.2020 a letter was issued by the
petitioner to the Area General Manager stating therein that for aforesaid
reason which was beyond the control of the petitioner the daily targets
could not be achieved. On 12.10.2021 the petitioner called upon the
Area General Manager that the price of diesel had increased and it was
higher than the basic price of contract for which reason the petitioner was
not in a position to clear the outstanding dues of the Indian Oil
Corporation Limited. This was likely to result in interruption of the
ongoing work. By a communication dated 10.08.2021 the petitioner
informed the Chairman and the Managing Director of the Western
Coalfields Limited, Nagpur all the difficulties faced on account of increase
in the price of diesel to Rs.97.09 Ps. per litre on 30.07.2021. The rates
thereafter increased to about Rs.103/- per litre as per communication
dated 27.10.2021. Considering the joint representations made by various
contractors to the Chairman of the Coal India Limited seeking
modification of the price variation clause, the General Manager, Coal
India Limited informed the Regional Managers of its various subsidiaries
that for future tenders an amendment was being made in Chapter 6 of the
Contract Management Manual of Coal India Limited. The same was to be
made applicable for future tenders including tenders in which the bid
submission had not been completed. On 02.11.2021 a show cause notice WP 5470-21 5 Judgment
was issued by the Are General Manager to the petitioner stating therein
that the site of the work had been handed over to the petitioner on
06.10.2016 and the work had been commenced on 25.11.2016. The
scheduled completion date of the work as per the work order was
24.10.2023. It was stated that the overburden removal and coal
production performance during April-2021 to September-2021 was
extremely poor. In addition there was deployment of insufficient numbers
of machines/equipments as per the agreement thus resulting in failure to
achieve the agreed quantity of coal and OB Evacuation. Various letters
had been issued for achieving the mutually agreed targets and despite
assurances by the petitioner there was no improvement in the
performance. It was stated that about 32 letters during the period 2017
to 2021 had been issued but the petitioner had not improved its
performance for achieving the targets. Reference was made to Clause 9
sub clauses (a) to (c) of the contract and the petitioner was called upon
to show cause as to why action as stated in Clause 9 may not be taken.
The petitioner on 12.11.2021 submitted its reply stating
therein that for a period of about 58 months 80% of removal of OB and
93% of evacuation of coal had been undertaken. The targets could not be
met during April-2021 to September-2021 on account of outbreak of
Covid-19 pandemic. It was further stated that on account of increase in WP 5470-21 6 Judgment
the price of diesel the cost of mining work had increased making it
difficult for the petitioner to run the machines with full capability.
5. The Area General Manager on 08.12.2021 after consideration
of the explanation of the petitioner and after grant of personal hearing
informed the petitioner about termination of the work order that was
issued on 27.05.2016, directed forfeiture of the performance security
deposit or 20% of the value of incomplete work whichever is higher and
also debarred the petitioner from further participation in future tenders of
the Western Coalfields Limited for a period of three years. It is this order
issued by the Area General Manager of the Western Coalfields Limited
that is the subject matter of challenge in this writ petition.
6. Shri A.S. Jaiswal, learned Senior Advocate for the petitioner
submitted that on account of global increase in the price of diesel it
became financially difficult for the petitioner to meet the targets with
regard to carrying out the work order under the contract. The diesel
component that was agreed was 0.30 when the price of diesel was
Rs.52.37 Ps. per litre as stated in the work order. The price of diesel had
risen to Rs.103/- per litre and for reasons beyond the control of the
petitioner it was difficult for the petitioner to achieve the targets as fixed.
The Western Coalfields Limited on realizing this material aspect had on its WP 5470-21 7 Judgment
own increased the diesel component from 0.30 to 0.56 on 17.11.2021.
However this variation was made applicable only to future contracts
without making the same applicable to existing and unfinished contracts
such as the present one. There was no valid reason on the part of the
Western Coalfields Limited to exclude the existing contracts like the one
in hand and the lower component of 0.30 was liable to be modified to the
component that was to operate for future contracts. Since the increase in
the price of diesel was for reasons beyond the control of the petitioner, it
was clear that the present situation was covered by the exception to
Clause 9(b) being a Force Majeure event. The Western Coalfields Limited
therefore was not justified in terminating the work order and further
forfeiting the performance security deposit and debarring the petitioner.
The learned Senior Advocate referred to the judgment of the Division
Bench in AG Enviro Infra Projects Private Limited Versus State of
Maharashtra & Others [2018(6) AIR BomR 698] and submitted that the
escalation in the price of diesel globally was a factor which required
alteration of the diesel component from 0.30. He also referred to another
judgment of the Division Bench in A2Z Infraservices Limited Versus
Union of India & Others [2018 (3) LLJ 363] and submitted that the ratio
thereof was clearly applicable to the case in hand. Therein the business
efficacy test was applied and it was submitted that on similar lines the
work order of the petitioner was liable to be restored. It was thus prayed WP 5470-21 8 Judgment
that the impugned action taken by the Western Coalfields Limited being
arbitrary in nature and violative of Article 14 of the Constitution of India
was liable to be set aside.
7. Per contra, Shri S.P. Dharmadhikari, learned Senior Advocate
for the respondent nos.1 and 2 opposed the aforesaid submissions.
According to him, the work order issued to the petitioner was terminated
in accordance with Clause 9 of the contract for bona fide reasons. The
order dated 08.12.2021 had clearly referred to Clauses 9(a) to 9(c) of the
contract. Contention urged by the petitioner could at the most relate to
Clause 9(b) of the contract but there was no escape from the fact that
there was a breach committed also with regard to Clause 9 (a) and 9(c)
thereof. On 17.11.2021, the Western Coalfields Limited had taken a
policy decision in the matter of consideration of joint representations of
various contractors and had amended Chapter 6 of the Contract
Management Manual which was to be made applicable for future tenders
including the tenders in which bid submission had not been completed.
The decision not to apply such amendment to existing contracts could not
be said to be arbitrary as the same would have resulted in the material
altering the contracts already entered. The decision to alter the
escalation clause was a matter of policy having financial implications and
hence the Coal India Limited did not act arbitrarily in making amendment WP 5470-21 9 Judgment
to operate prospectively. There was an escalation clause in the contract
entered into with the petitioner and the parties were bound by the same.
The petitioner was infact attempting to seek substitution of the escalation
clause in the contract but such prayer was not liable to be granted in
exercise of jurisdiction under Article 226 of the Constitution of India. It
was submitted that the period of the contract was 83 months and it was
for the petitioner as a prudent business firm to have considered future
possibilities while submitting its offer. The offer made by the petitioner
was to do business on the terms set out by the Western Coalfields Limited
and it was not permissible mid-way to seek alteration in the terms of the
contract. He submitted that in accordance with the escalation clause the
increase in the price of diesel was being paid to the petitioner but it was
only the petitioner who had defaulted in meeting the timeline for
completion of the work. The escalation clause in the contract was to
operate for the Contractor as well as the Principal and the same could not
be viewed only from the perspective of the Contractor. The rise in price of
diesel was hardly related to Article 14 of the Constitution of India. In the
writ petition there was no foundational pleadings as to the effect of the
pandemic situation on the petitioner. Further the petitioner did not
dispute the reasons contained while applying Clause 9(a) and 9(c) and
had only sought to rely upon Clause 9(b). The rise in global prices of
diesel could not be said to be a Force Majeure event as such rise was not WP 5470-21 10 Judgment
the act of God. Since there was no omission on the part of the Western
Coalfields Limited it was only the petitioner who was to blame for not
achieving the given targets.
The learned Senior Advocate sought to distinguish the
judgments relied upon by the learned Senior Advocate for the petitioner
by submitting that therein the Contractor as an agent of the Principal was
required to comply with statutory obligations under the Minimum Wages
Act, 1948. It was in that context that the price variation clause was
directed to be modified. In the case in hand there was no such statutory
obligation to be met either by the Western Coalfields Limited or by the
petitioner. Hence the business efficacy test was not applicable and the
price escalation clause was already provided. Moreover the policy
decision dated 17.11.2021 was not under challenge by the petitioner so
as to pray for that policy decision to be modified for being made
applicable even to existing contracts. It was then submitted that this
Court while issuing notice had directed that the bank guarantee furnished
by the petitioner was not to be encashed if the same had not been
encashed on the date of the order. Relying upon the decision in U.P.
Cooperative Federation Ltd. Versus Singh Consultants and Engineers (P)
Ltd. [(1988) 1 SCC 174] it was submitted that only if there was an
element of fraud on the part of the beneficiary that the encashment of the
bank guarantee could be refused by the bank. There was no such case WP 5470-21 11 Judgment
pleaded by the petitioner. It was thus submitted that no interference was
called for in the writ petition and the same was liable to be dismissed.
8. We have heard the learned counsel for the parties at length
and we have perused the documents placed on record. After giving due
consideration to the rival submissions, in our view the petitioner has not
made out any case for grant of relief under Article 226 of the Constitution
of India. In matters arising out of contractual disputes it is well settled
that the Court in exercise of jurisdiction under Article 226 of the
Constitution of India is merely concerned with the decision making
process rather than the decision itself. If the decision making process is
found to be fair and the decision has been taken after following all
procedural requirements and by granting due opportunity to the
concerned party the scope to interfere with the decision taken thereafter
would be limited. In the present case we find that the petitioner has not
raised a serious challenge to the decision making process of the Western
Coalfields Limited in terminating the work issued to the petitioner. The
challenge is principally to the decision of the Western Coalfields Limited
of terminating the work order issued to the petitioner. In other words,
the challenge is to the decision itself and not to the decision making
process. The issuance of show cause notice dated 02.11.2021 and the
fact of the petitioner giving reply thereto on 12.11.2021 is not in dispute.
WP 5470-21 12 Judgment
The termination of the work order on 08.12.2021 is in view of Clauses
9(a) to 9(c) of the Conditions of Contract. We may note that there was
also no serious challenge to the factual data mentioned in the show cause
notice that has been made the basis for termination of the work order.
The grievance of the petitioner is that on account of the global increase in
the prices of diesel, the diesel component in the work order which was
prescribed at 0.30% became financially non-viable. The Coal India
Limited on noticing such global increase in the prices of diesel unilaterally
on 17.11.2021 amended Chapter 6 of the Contract Management Manual
and revised the rates of diesel component. Such revision however was
made applicable only to future tenders and the tenders in which the bid
submission had not been completed. The petitioner contends that in the
light of the difficulties faced and with the onset of the pandemic such
amendment in the rate of diesel component ought to have been applied
even to the work orders in hand.
9. We find that the decision taken by the Coal India Limited
on 17.11.2021 of amending the Contract Management Manual is in
the nature of a policy decision which is not under challenge in the
writ petition. This policy decision has financial implications and it is
perhaps with said aspect in mind that it has been made applicable to
future tenders. It is however not necessary to go into the justification WP 5470-21 13 Judgment
on the part of Coal India Limited for not applying the revision in the
rate of diesel component to existing contracts. It is also not the case
of the petitioner that the benefit of such amendment was granted to a
work order already issued and that such benefit was denied to the
petitioner. The learned Senior Advocate for the respondents is justified
in submitting that in effect the petitioner seeks substitution of the price
escalation clause in the contract from what was agreed by the
petitioner. It would not be a sound exercise of discretion if the Court
were to alter certain terms of the contract as the parties would be
governed by the contract entered into between them. We also note that it
is the stand of the respondents that amongst various work orders in
operation it was only the petitioner who had defaulted in completion of
the work allotted to it and other contractors had continued with the
completion of contracts awarded to them. We therefore do not find
anything arbitrary on the part of the respondents in not applying the
amendments made to the Contract Management Manual to the contract
that was awarded to the petitioner on 08.12.2016. On perusal of the
show cause notice and the reply submitted by the petitioner we are
satisfied that the contract of the petitioner has been terminated in
accordance with the terms of the tender document itself by relying upon
Clauses 9(a) to 9(c) thereof.
WP 5470-21 14 Judgment
10. In support of the contention that the Western Coalfields
Limited ought to have applied the amendments made in Chapter 6 of
the Contract Management Manual even to tenders wherein the work
order was issued by taking a note of the increase in the price of diesel,
the learned Senior Advocate for the petitioner sought to rely upon the
decision in AG Enviro Infra Projects Private Limited (supra). The facts
of the aforesaid case indicate that one of the conditions of the tender
was to apply the notification issued by the State Government in the
matter of payment of minimum wages. During the period when the
contract was being worked out a notification increasing the minimum
wages was issued by the State Government. The Contractor by relying
upon such increase had sought the benefit of resolutions passed by
the General Body of the Municipal Corporation by which the Municipal
Corporation agreed to provide minimum wages to the contract labourers.
In that context it was held that it was the statutory obligation firstly of
the Municipal Corporation to implement the notification modifying the
rates of minimum wages. The Municipal Corporation as principal was
bound by such notification and therefore it was its duty to see that
the Contractor who was its agent was not put to any financial distress
while complying with such statutory obligation. The Court further found
that the benefit of the resolutions passed by the Municipal
Corporations was extended to similarly situated contractors and on WP 5470-21 15 Judgment
the basis of parity such benefit was liable to be extended to the
petitioner.
In A2Z Infraservices Limited (supra) there was an increase in
the rates of minimum wages with effect from 19.01.2017 when the
contract was being worked out. The Court again noticed that there was a
statutory obligation on the part of the Railway Department which was the
principal to comply with the notification increasing the rates of minimum
wages. The Contractor sought compensation for the increase in the cost
of labour pursuant to the notification dated 19.01.2017. It was held that
though the Railways applied the price variation clause till 18.01.2017 it
had not done so after issuance of the notification dated 19.01.2017. The
Court held that the Railways ought to neutralize the cost of labour by
acting under the price variation clause and further referred to the
principle of "business efficacy".
11. The facts of the aforesaid decisions clearly indicate that the
Contractor therein was obliged to comply with prescribed statutory
obligations under the Minimum Wages Act, 1948. Since it was the duty
of the principal to ensure such compliance and the work was being done
by its agent, the Court found it appropriate to direct the principal to
ensure that the Contractor was not put at a loss while complying with
such statutory obligations. However, we find that the facts of the case in
hand are distinct and the ratio of the aforesaid decisions cannot be made WP 5470-21 16 Judgment
applicable to the present case. The Coal India Limited took a policy
decision of amending the Contract Management Manual by increasing the
rate of diesel component and making it applicable to future tenders as
well as the tenders in which the bid submission had not been completed.
This policy decision amending Chapter 6 of the Manual has not been
challenged by the petitioner and it is also not the case of the petitioner
that the amendment as made have been applied either by Coal India
Limited or by Western Coalfields Limited to a work order that was already
issued and the work was in progress. Moreover, there is no statutory
obligation involved mandating the principal to abide by any variation in
the diesel component. It is merely a factor that is provided for under the
price variation clause and is in the mature of a business risk. Hence, the
ratio of the said judgments do not apply to the case in hand.
12. Another aspect that cannot be lost sight of is that the show
cause notice issued to the petitioner on 02.11.2021 has specifically
referred to Clause 9(a) to 9(c) of the conditions of contract while seeking
to terminate the contract. Clause 9(a) to 9(c) reads as under:
"Termination, Suspension, Cancellation & Foreclosure of Contract:
The company shall, in addition to other remedial steps to be taken as provided in the conditions of contract, be entitled to cancel the contract in full or in part, if the contractor, WP 5470-21 17 Judgment
a. makes default in proceeding with the works with due diligence and continues to do so even after a notice in writing from the Engineer-in-charge, then on the expiry of the period as specified in the notice Or b. fails to achieve a monthly agreed quantity of 75% (Seventy Five percent) for a period of 6(Six) consecutive months or for cumulative period of six months within any continuous period of 18(eighteen) months, save and except to the extent of non-availability caused by I) a Force Majeure event or ii) an act of omission of company, not occurring due to any default of the contractor.
Or
c. commits default/breach in complying with
any of the terms and conditions of the contract and does not remedy it or fails to take effective steps for the remedy to the satisfaction of the Engineer-in-charge, then on the expiry of the period as may be specified by the Engineer-in-charge in a notice in writing."
The impugned order dated 08.12.2021 has proceeded to terminate the
contract by relying upon Clause 9(a) to 9(c). Prior to issuance of
the show cause notice it has been stated that there were various
notices issued to the petitioner in which it was stated that the
monthly targets were not being achieved. It is not the case of the
petitioner that such notices were not issued to it. It is on that basis
that the Area General Manager has invoked Clause 9(a) to 9(c) thereof.
The thrust of the petitioner is on the global increase in the price of
diesel thereby rendering the diesel component of 0.30 to be financially
non-viable. The petitioner has sought to rely upon such increase to WP 5470-21 18 Judgment
be a Force Majeure event. Such contingency finds place in Clause 9(b)
of the conditions of contract. Before adverting to the same suffice it to
observe that there is no specific challenge raised to termination of
the contract under Clause 9(a) to 9(c) of the conditions of contract.
The show cause notice dated 02.11.2021 refers to the performance of
the petitioner in detail and further states that about 32 letters were
issued to the petitioner between 2017 to 2021. Despite that the
performance of the petitioner for achieving the daily minimum quantity
of OB removal and coal evacuation by deploying equipments as
per the terms and conditions of the contract had not improved.
Reply of the petitioner does not counter the aforesaid. We therefore
find that invocation of Clause 9(a) and 9(c) of the Conditions of
Contract for terminating the contract is supported by material that finds
place in the show cause notice as well as the order terminating the
contract.
13. Coming to the termination of the contract by relying upon
Clause 9(b) of the Conditions of Contract we find that if there is failure
to achieve monthly agreed quantity of 75% for a period of six
consecutive months or for a cumulative period of six months within
any any continuous period of eighteen months, the contract is liable
to be terminated. This contingency is saved only to the extent of WP 5470-21 19 Judgment
non-availability caused by a Force Majeure event. Increase in the
price of diesel cannot qualify as a Force Majeure event. Such increase
in the price of diesel would be in the nature of an expected or foreseen
phenomenon keeping in mind the duration of the contract which was
for a period of about seven years or 83 months to be precise. The
price escalation clause in the Conditions of Contract and especially
Clause 19.04.1 refers to such price variation on account of diesel.
The diesel component is provided at 0.30 as percentage of total value of
work. The petitioner having accepted the terms of the contract while
submitting its bid, the parties would be governed by this price
variation clause. That clause generally would operate to the benefit of
either party depending upon the increase/decrease in the price of
diesel. That would be a factor to be considered by a bidder while
submitting his bid. Seeking modification of the diesel component on the
basis of the amendment of those rates in the Contract Management
Manual would result in substituting one of the terms of the contract
with another which in our view would not be permissible since there is
no such scope provided for in the conditions of contract. The parties
would be governed by Clause 19.04.1. It would therefore not be
permissible for the petitioner to invoke the Force Majeure clause which is
not attracted at all.
WP 5470-21 20 Judgment
14. For aforesaid reasons therefore we do not find any case made
out to interfere in exercise of writ jurisdiction under Article 226 of the
Constitution of India. The writ petition therefore stands dismissed with
no order as to costs. Rule stands discharged.
(SMT. M.S. JAWALKAR, J.) (A.S. CHANDURKAR, J.) APTE
At this stage, the learned counsel for the petitioner seeks stay
of the judgment. He submits that the interim order operating be
continued for a period of four weeks. This request is opposed by the
learned counsel for the respondents.
We do not find any case made out to stay the encashment
of the bank guarantee. The respondents are free to encash the same.
The interim order making the work order subject to the outcome of the
writ petition shall continue to operate for a period of four weeks and shall
cease to operate automatically after that period.
(SMT. M.S. JAWALKAR, J.) (A.S. CHANDURKAR, J.)
APTE
Signed By: Digitally signed
byROHIT DATTATRAYA
APTE
Signing Date:16.03.2022 11:33
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!