Citation : 2022 Latest Caselaw 8036 Bom
Judgement Date : 19 August, 2022
1 wp7369.19 Judgment.docx
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
WRIT PETITION NO. 7369 OF 2019
Kiran S/o Chandrakant Maid,
Age: 50 years, Occ. : Business,
Proprietor M/S. Pushpachandra Reti
Contractor, Nashik
R/o Pushpendra Niwas, Godrejwadi, ...PETITIONER
Nashik Road, Nashik.
VERSUS
1. The State of Maharashtra
through the Principal Secretary,
Revenue Department,
Mantralaya, Mumbai-32.
2. The Hon'ble Minister,
Revenue Department
Government of Maharashtra
Mantralaya, Mumbai-32 .......(DELETED)
3. The Collector, Jalgaon.
4. The Tahsildar,
Tahsil Office, Amalner,
Tal.:Amalner, District: Jalgaon. ...RESPONDENTS
..........................................
Advocate for the petitioner : Mr. V.H. Dighe h/f Mr. S.S. Wagh
AGP for the Respondent Nos. 1, 3 & 4 : Mrs.M.A. Deshpande
.......................................
CORAM : MANGESH S. PATIL &
SANDEEP V. MARNE, JJ.
RESERVED DATE : 12.08.2022
PRONOUNCEMENT DATE : 19.08.2022
2 wp7369.19 Judgment.docx
JUDGMENT : [PER : SANDEEP V. MARNE, J.]
1. Rule.
2. Rule made returnable forthwith. With consent of the learned
Advocates for the respective parties, heard finally at the state of
admission.
3. The short issue involved in the present petition is about
entitlement of proportionate refund of amount paid for the extraction of
sand if the contractor is unable to extract the permissible quantality of
sand within the stipulated period. Also involved is the issue whether
flooding of river due to release of water from reservoir can be
considered as a 'natural calamity' for the purposes of grant of such
refund.
4. The facts of the case, as captured from pleadings filed
before us, stated are as under :
Petitioner claims to be a Civil Contractor who had
participated in e-tender process initiated by respondent No.3 and was
awarded the work order dated 18.01.2014 for extraction of sand from
the bed of river Tapi at Spot Nos. 3 and 4 of Gut No. 28, village Jallod,
Taluka Amalner. By work order, the Petitioner was permitted to extract
12862 brass sand by 30.09.2014. It is the case of the petitioner that by
30.09.2014, when the tenure of the work order ended, he was able to
3 wp7369.19 Judgment.docx
extract only 4291 brass sand. The Petitioner appears to have deposited
an amount of Rs. 1,08,99,999/- for extraction of 12862 brass sand. On
account of inability to extract remaining quantity, petitioner is claiming
proportionate refund of the amount paid by him to the Government.
5. The claim for refund is premised on two reasons cited by
petitioner for his inability to extract the permissible quantity of sand.
Firstly, on account of complaints made by the villagers, the Additional
Collector, Jalgaon had passed an order dated 24.06.2014 staying the
contract of the petitioner. The stay was lifted only on 11.07.2014. The
second reason, according to the petitioner, is the flooding of river Tapi
from 22.07.2014, on account of which, he was prevented from
extraction of sand till 18.09.2014. He claims to have sent an intimation
to the Tahsildar, Ahmednagar on 18.09.2014 stating that he had
stopped extraction activities on account of damage to the suction
pumps, approach roads etc. due to floods. He seeks to blame these two
reasons/factors for his inability to extract permissible quantity of sand.
6. The petitioner claims that he made several representations,
seeking extension of the contract period or alternatively proportionate
refund of the bid amount. Thereafter an appeal came to be filed before
the Minister, Revenue Department, on 21.11.2015, praying for the
extension of contract period or for proportionate refund of the bid
amount. A reminder appeal was filed on 07.05.2016. Crying non-
decision of appeals, he filed Writ Petition No. 9145 of 2016, which was
4 wp7369.19 Judgment.docx
disposed of with a direction to decide the appeal/representation. It
appears that the petitioner was required to file Contempt Petition No.
13 of 2017 on account of non decision of the appeal/representation. He
claims that after getting a wind of filing of Contempt Petition,
Respondent No. 1 hurriedly passed order on 30.01.2017 rejecting the
appeal/representation.
7. The petitioner thereafter, once again approached this Court
by filing Writ Petition No. 2947/2017, challenging the order dated
30.01.2017 which was disposed of by order dated 01.03.2018 setting
aside the order dated 30.01.2017 and directing re-consideration of
application filed by the petitioner for refund of proportionate amount by
considering the report given by the Tahsildar, after giving hearing to
the petitioner. Respondent No. 1 thereafter passed order dated
05.12.2018 partly accepting the claim of the petitioner for refund, in
respect of the period from 24.06.2014 to 11.07.2014 when there was
stay granted to the Collector. He is held to be entitled to proportionate
refund. However, his claim for refund on account of flood in the river
has been rejected by relying upon paragraph No. 'C'-(22) of the
Government Resolution darted 12.03.2013. It is this order dated
05.12.2018, which is the subject matter of the challenge before us in
the petition.
8. Appearing for the petitioner Mr. V.H. Dighe, has assailed the
order dated 05.12.2018 primarily on the ground that even though this
5 wp7369.19 Judgment.docx
Court directed consideration of the case in the light of paragraph 'C'-
(15) of the Government Resolution dated 12.03.2013, respondent No. 1
has ignored the said Clause and has once again rejected the prayer for
refund of appropriate amount by relying on paragraph 'C'-(22) of the
said Government Resolution. He further submits that despite this Court
directing respondent No. 1 to take into consideration the report of
Tahsildar, the same has not been considered while passing the
impugned order. He further submits that Clause 'C'-(22) does not deal
with the aspect of refund but deals only with the aspect of extension of
time. According to him, the provision for refund is to be found in
paragraph 'C'-(15) of the Government Resolution dated 12.03.2013. He
further submits that deposit of water in sand spot, though may not be a
valid ground for extension of contract or for replacement of sand spot
under Clause 'C'-(22), the same has been recognized in the provision
for refund under Clause 'C'-(15). Mr. Dighe, has laid great stress on the
report of the Tahsildar, as well as a tabular chart at Exh.-'E', showing
the details of release of water in river Tapi during July-2014 to
September-2014.
9. Mr. Dighe, has placed reliance on the judgment of this Court
in Shivaji J. Chavan Vs. The State of Maharashtra and Ors. -
Writ Petition No. 12089 of 2013 decided on 09.07.2015.
10. Per-contra, Mrs. M.A.Deshpande, the learned Additional
Government Pleader appearing for the State Government defends the
6 wp7369.19 Judgment.docx
impugned order by submitting that deposit of water in the sand spot or
flooding in the river, having been specifically excluded for either grant
of extension or for refund, Petitioner cannot claim refund under that
pretext. She refers to similar provision under Clause 26 of the Work
Order. She has further submitted that the petitioner was permitted to
use as many as four suction pumps on his request by the Collector, as
a special case so as to enable him to extract sand from deposited
water. She submits that the petitioner has to blame himself for his
inability to extract the permissible quantity of sand within the
permissible period.
11. Before we advert to the merits of the rival contentions, it is
necessary to clarify that even though the Petitioner had raised
alternate demands for extension or refund in his
appeals/representations, before us only the prayer for proportionate
refund has been made.
12. Having heard the learned Counsels for the parties at length,
we find that the entire issue revolves around the interpretation of
Clauses 'C'-(15) and 'C'-(22) of the Government Resolution darted
12.03.2013. Clause 'C'-(15) provides that the contractor cannot sue the
Government if the contract is terminated or he is prevented from
extraction of sand from the permitted area. The Clause further provides
that in the event of protest from villagers, Court orders, natural
calamities, opposition from administrative machinery, if the extraction
7 wp7369.19 Judgment.docx
or transportation is affected or if possession of sand spot is not handed
over, the proportionate refund of the bid amount is permissible in
respect of period during which the contract is suspended.
13. As against this, the paragraph 'C'-(22) essentially deals
with the tenure of contract and permissibility of extension thereof. It
provides that the period of contract is maximum of one year and would
ordinarily be between 1st October to 30th September. It further provides
that irrespective of the date of tender process, the contract would
come to an end on 30 th September. It further provides that it would be
the responsibility of the successful bidder to extract sand in permissible
quantity within the tenure of the contract. The Clause further provides
that the tenure of the contract shall not be extended, nor an alternate
sand spot would be provided for the reasons of non-availability of
expected quantity of sand, non availability of roads, deposit of water in
the sand spot or for the reason of any human or natural calamity.
14. Even though, one may say that Clauses 'C'-(15) and 'C'-
(22) operate in different spheres, both essentially relate to the
eventualities of non extraction of permissible quantity of sand. Clause
'C'-(22) imposes an absolute ban on extension of tenure of contract or
allotment of alternate sand spot for any reason whatsoever. Even for
the reason of deposit of water in the sand spot. As against this, Clause
'C'-(15) permits refund if the contract is terminated on account of
occurring of eventualities stated therein. Natural calamity is one such
8 wp7369.19 Judgment.docx
eventuality.
15. The petitioner has contended that his case for refund
cannot be governed by Clause 'C'-(22) and it ought to have been
considered in accordance with the provisions of Clause 'C'-(15). It is his
case that the flooding of river is covered by the eventuality of 'natural
calamity'. The claim for refund is thus premised on the alleged natural
calamity in the form of flooding of the river.
16. Accepting the Petitioner's contention that Clause 'C'-(15)
alone would govern his case, we proceed to examine his claim as per
the provisions of Clause C(15). On strict interpretation of Clause C(15),
refund is permissible only in respect of the period during which the
contract is terminated. The eventualities for which such contract might
be terminated have been enlisted in Clause 'C'-(15), which inter alia
includes natural calamities. However termination of contract appears to
be the sine qua non for entertaining claim for refund. On slight liberal
interpretation of the Clause, 'termination' might be construed to
include even 'suspension' of contract due to eventualities named
therein. However in the instant case, Petitioner's contract was neither
terminated nor suspended on account of alleged flooding of the river.
Hence, Petitioner's claim for refund falls outside clause C(15) and for
this reason alone the claim for proportionate refund is clearly
untenable.
9 wp7369.19 Judgment.docx
17. We find that the Respondents have correctly dealt with
Petitioner's case for refund under clause C(15). His claim for
proportionate refund in respect of the period from 24.06.2014 to
11.07.2014 when his contract was suspended, has been sanctioned.
This is because during that period, his contract was suspended and the
suspension was on account of one of the permissible eventualities viz.
stay by Collector. However, since his contract was never suspended on
account of alleged flooding in the river, there is no question of granting
the claim for proportionate refund.
18. Even if Clause 'C'-(15) was to be further liberally
interpreted by not applying the test of 'termination' or 'suspension' of
contract, in our opinion the case of the petitioner would not fall within
the eventuality of 'natural calamity'. Release of water from a reservoir
is a natural phenomenon occurring every monsoon and the contractors
bidding for sand extraction from river beds are expected to factor in
this eventuality while submitting the bid. A prudent contractor would
schedule the total available period for extraction in such a way that the
eventuality of release of water from reservoir is factored in. In the
present case, the contract was awarded to the petitioner on
18.01.2014 and the which was valid upto 30.09.2014. It is impossible
to believe that he expected that extraction would be possible on every
single day during the contract period or that water would not be
released from the reservoir.
10 wp7369.19 Judgment.docx
19. In this context, the conduct of the petitioner is also
relevant. The contract was roughly for nine months. The first
eventuality of stay occurred on 24.06.2014 i.e. after a period of five
long months from the date of award of contract. The stay was vacated
within 17 days on 11.07.2014. However, the petitioner was able to
extract only 4291 brass sand till then. He was expected to have
factored in the upcoming monsoon after June for arranging his schedule
of extraction during 9 months. The conditions for extraction during first
6 months were far suitable than the last 3 months. However during this
favorable period of 6 months he appears to have extracted only 1/3 rd of
the permissible quantity. It is unbelievable that he was expecting to
extract reamaining 2/3rd quantity in unfavorable monsoon period of 3
months.
20. Even though, paragraph 'C'-(22) does not deal with
entitlement to refund, same may be of some relevance for dealing with
this aspect. There is a specific stipulation in Clause 'C'-(22) that
irrespective of the date of award of contract, the tenure of the contract
must come to an end by 30th September. Therefore, contractors were
required to take into consideration the available tenure for extraction of
the permissible quantity of sand on the basis of the date of award of
the contract. Since the petitioner knew that he was being awarded the
contract in January, 2014, he must have submitted his bid considering
the fact that he was not getting the entire year for extraction of 12862
brass of sand.
11 wp7369.19 Judgment.docx 21. Paragraph 'C'-(22) further stipulates that it is the
responsibility of the contractor to extract permissible quantity of sand
within the permissible tenure. The petitioner, thus, knew that within a
period of less than nine months, he was expected to extract 12862
brass of sand and accordingly submitted his bid. Mrs. Deshpande has
submitted before us that the petitioner was permitted to use four
suction pumps for extraction of sand from the area where the water
was deposited as a special case. Despite this, he was grossly deficient
so far as quantity of extract was concerned. It therefore appears to us
that stay granted by Collector and release of water from reservoir came
as ready excuses for Petitioner to claim refund for unextracted quantity
which he was otherwise not in a position to extract. While he was found
entitled to get refund on the former pretext (as it was fitting into the
criteria of Clause C-15), the Government has rightly rejected the claim
on the latter pretext.
22. Mr. Dighe, has placed reliance on the judgment of this Court
in Shivaji Chavan (supra). However we find that the facts of that case
were entirely different. Petitioner therein was initially allotted a
particular sand spot and the allotment was cancelled by the District
Collector as there was threat of damage to a monument. Instead of
refunding the amount, he was allotted another sand spot for different
quantity of sand. Even in respect of alternate sand spot, there was
already a resolution of Gram Sabha objecting to allotment of said spot.
12 wp7369.19 Judgment.docx
It is in the light of these factual background that this Court held in
paragraph Nos.18 and 19 of the judgment as under :
"18. Thus, the scenario which emerges from the aforesaid discussion based on undisputed facts is that there was an error on the part of the Government of conducting an auction of Shevare spot No. 2, as later on, it was realized that excavation of sand at the spot will adversely affect an ancient monument. The auction of the said spot was therefore cancelled by the Collector when the petitioner had excavated quantity of only 840 brass out of the permitted quantity of 9600. Instead of refunding the amount of royalty paid by the petitioner on pro-rate basis, the Collector allotted another spot to him under order dated 11th May, 2011. In respect of the said spot allotted, the Gram Sabha had already raised an objection in January 2011 by passing a specific Resolution. As stated in the affidavit of Shri Dolas, the petitioner could excavate only 1614 brass of sand from the spot and the quantity of 7146 brass out of the permitted quantity could not be excavated. Shri Dolas has corrected the earlier statement made in the affidavit that the petitioner has excavated more than 8056 brass of land.
19. It is not even the case made out in both the affidavits or in the order dated 11 th May, 2011 that any effort was made to ascertain whether there was likelihood of resistance by the villagers as far as the spot No. 2 in village Chandaj is concerned. It is obvious that as there was no auction of the said spot allotted by the order darted 11th May, 2011, the procedure which is required to be followed under the G.R. dated 25 th October, 2010 was not followed. It is not the case of the State Government that before passing the order dated 11th May, 2011, any local inquiry was made to ascertain whether the petitioner will be able to excavate sand without any resistance. Perhaps, the allotment was made to avoid refund of the royalty amount."
Thus we find that the factual background in which the claim for
proportionate refund was granted by this Court was entirely different
than one involved in the present case. Therefore, the said decision is
clearly distinguishable.
13 wp7369.19 Judgment.docx
23. In the result, we do not find any merit in the petition and
the same is dismissed without any orders as to costs.
( SANDEEP V. MARNE ) ( MANGESH S. PATIL )
JUDGE JUDGE
mahajansb/
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!