Thursday, 14, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Shri. Umesh Vasant Dalal vs M/S. Omkar Buildcon
2022 Latest Caselaw 7927 Bom

Citation : 2022 Latest Caselaw 7927 Bom
Judgement Date : 17 August, 2022

Bombay High Court
Shri. Umesh Vasant Dalal vs M/S. Omkar Buildcon on 17 August, 2022
Bench: G. S. Kulkarni
         Digitally signed
         by VIDYA
VIDYA    SURESH AMIN
SURESH   Date:
         2022.08.17
AMIN     18:52:17
         +0530                                                 1                           33.ARA26_2018.doc

     Vidya Amin
                               IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                       CIVIL APPELLATE JURISDICTION

                                       ARBITRATION APPEAL NO. 26 OF 2018
                                                      WITH
                                        CIVIL APPLICATION NO. 29 OF 2018
                                                      A/W.
                                      ARBITRATION PETITION NO. 3 OF 2019

                Umesh Vasant Dalal                                       .. Appellant/Petitioner
                           Vs.
                M/s. Omkar Buildcon                                      .. Respondent

                Mr. A.M. Kulkarni for the appellant/applicant.
                Mr. Vishal C. Ghosalkar for the respondent.

                                                  CORAM :          G.S. KULKARNI, J.
                                                  DATE :           AUGUST 17, 2022.
                P.C.:


                1.          This Appeal is filed against the judgment and order dated 6

                December, 2017 passed by the learned Principal District Judge, Thane

                whereby an application filed by the appellant under section 9 of the

                Arbitration and Conciliation Act stood rejected.



                2.          This Court (G.S. Patel, J.) had heard the proceedings on 8

                January, 2020, when the following order has been passed:

                             "1. Parties agree that the Petitioner will first take inspection of the
                             seven fats that have been kept available unencumbered for him in
                             the project at Ambernath. This process will be complete within one
                             week from today. Mr Ghosalkar for the Respondent agrees that he
                             will share a copy of the original Occupation Certificate with Mr
                             Kulkarni for the Petitioner.

                             2. Subject to all these inspections, it is in principle agreed that
                             upon the Petitioner being put in possession of the seven fats, the
                             entire dispute between the parties can be treated as resolved. Both
                                          2                          33.ARA26_2018.doc

       sides are presently agreeable to this, but for now I will keep this as
       a non-binding, in-principle understanding subject to later
       confirmation.

       3. List the matter on 16th January 2020.


3.      Subsequently, on 15 July, 2022, this Court (R.I. Chagla, J.)

passed the following order:

       "1. Heard learned counsel for the parties.

       2. Mr. Vilas Kanade, partner of Respondent on behalf of the
       Respondent is present in Court and the Appellant is also present in
       Court.

       3. By an order dated 16th June 2022, this Court had recorded the
       Agreement of the parties that the Petitioner/ Appellant will take
       inspection of seven Flats that have been kept available
       unencumbered for him in the project at Ambernath. It was further
       recorded that it has been agreed in principle that upon the
       Petitioner/Appellant being put in possession of the seven flats the
       entire dispute between the parties can be treated as resolved. It
       was further submitted that the parties have agreed that the
       Petitioner/Appellant can take fresh inspection of the seven flats in
       the project at Ambernath on 17th June 2022. The other issues with
       regard to payment of property taxes and as to whose liability it is
       to pay the property taxes was reserved to the next date.

       4. Pursuant to order dated 16th June 2022, the
       Petitioner/Appellant has taken inspection of the seven flats at
       Ambernath on 17th June 2022. There are certain issues in respect
       of some of the flats. The Respondent has raised contentions with
       regard to the payment of society charges and that it is the
       Appellant's liability to pay society charges and electricity and other
       dues with regard to the subject flats. The Appellant has also raised
       the contention of delay in handling over of the subject flats to the
       Appellant and consideration payable in respect thereof. There are
       other issues with regard to the Respondents claim for payment due
       to the Appellant for not disclosing certain details with regard to
       access to the flat and as a result of which the Respondent had to
       settled with the adjacent society.

       5. Leaving these issues aside, to be determined at a later date, the
       parties are agreeable for the Appellant to take possession of the
       subject flats which are 001 and 002 on the ground floor; 101 on
       the first floor; 203 on the second floor; 304 on the third floor; 402
       on the fourth floor and 501 on the fifth floor of the subject
       building. The possession will be handed over by the Respondent
       tomorrow i.e. on 16th July 2022.
                                          3                          33.ARA26_2018.doc

        6. Place the Arbitration Appeal alongwith Arbitration Petition on
        4th August 2022, for determining the aforementioned issues.

        7. It is made clear that by the Respondent handing over the subject
        flats to the Appellant, the entire dispute between the parties have
        not been resolved. The parties are at liberty to file compilation of
        documents in support of their claims in order for adjudication of
        the claims on the next date."


4.    Considering the above orders, possession of 7 flats has already

been handed over by the respondent to the appellant. Learned counsel

for the respondent would rightly submit that in view of the said

developments as noted in the above orders, further adjudication of the

appeal is not called for, this more particularly that now the disputes

which have remained between the parties are monetary disputes namely

that the petitioner has a claim against the respondent as also the

respondent as counter claim against the petitioner. In fact the appellant

has already filed a Section 11 Petition (Arbitration Petition No. 3 of

2019) praying for appointment of an arbitral tribunal for adjudication of

such disputes. The said petition is also listed on today's cause-list.



5.    Learned counsel for the respondent would fairly state that insofar

as Section 11 proceedings are concerned, this Court may appoint an

arbitrator, as there is an arbitration agreement between the parties as

contained in the agreement in question.



6.    In view of the consensus between the parties for appointment of
                                         4                     33.ARA26_2018.doc

an arbitral tribunal for adjudication of the monetary claims of the

parties against each other, Section 11 proceedings can be disposed of by

appointing an arbitrator.



7.       Accordingly, both the proceedings are disposed of by the following

order:

                                        ORDER

(i) Arbitration Appeal No. 26 of 2018 stands disposed of as

infructuous;

(ii) Insofar as Arbitration Petition No. 3 of 2019 is concerned,

Mr. Sadashiv S. Deshmukh, Former District Judge is appointed as

a sole arbitrator to adjudicate the disputes between the parties

which have arisen under the Agreement in question.

(iii) The learned sole arbitrator, before entering the arbitration

reference, shall forward a statement of disclosure as per the

requirement of Section 11(8) read with Section 12(1) of the

Arbitration and Conciliation Act,1996, to the Prothonotary &

Senior Master of this Court, to be placed on record of this

application with a copy to be forwarded to both the parties;

(iv) Needless to observe that it would be permissible for the

respondent to file its counter claim.

         (v)     At the first instance, the parties shall appear before the
                                    5                        33.ARA26_2018.doc

prospective arbitrator within 10 days from today on a date which

may be mutually fixed by the learned sole arbitrator;

(vi) The fees payable to the arbitral tribunal shall be as

prescribed under the Bombay High Court (Fees Payable to

Arbitrators) Rules,2018.

(vii) All contentions of the parties are expressly kept open;

(viii) Office to forward a copy of this order to the learned

Arbitrator on the following address:

Mr. Sadashiv S. Deshmukh, Former District Judge 403, Jupiter, Building No.9, (Gavanndbaugh), Pokharan Road 2, Thane (W) 400610 Mob. 9820553525.

8. Disposed of in the above terms. No costs.

9. Civil Application would also not survive, it is accordingly disposed

of.

[G.S. KULKARNI, J.]

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter