Citation : 2021 Latest Caselaw 8038 Bom
Judgement Date : 18 June, 2021
carbpl.1246021..doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
IN ITS COMMERCIAL DIVISION
COMMERCIAL ARBITRATION PETITION (L) NO. 12460 OF 2021
Ecopark Developers LLP ..Petitioner/Orig.Claimant
Vs.
Ajay J. Mehra & Ors ..Respondents
Mr. Gaurav Joshi, Senior Counsel a/w Mr. Chirag Modi, Mr. Nikunj
Mehta, Parag Kabadi, Falguni Thakkar i/b DSK Legal, for the
Petitioner.
Dr. Birendra Saraf, Senior Counsel a/w Mr. Chirag Kamdar,
Jasmine Kachalia, Abinash Pradhan, Deepu Jojo, Viren Mandhle
i/b Wadia Ghandy & Co, for the Respondent.
CORAM:- B. P. COLABAWALLA,J.
DATE :- JUNE 18, 2021.
(THROUGH VIDEO CONFERENCING)
P. C.:
1. The present Petition is fled under Section 37 of the
Arbitration and Conciliation Act, 1996 (for short "the Arbitration
Act") seeking to assail the order dated 19 th April, 2021 (for short
the "impugned order") passed by the Arbitral Tribunal under
Section 17 of the Arbitration Act. By the impugned order, the
Tribunal dismissed the Petitioner's application dated 21st
September, 2019 fled under Section 17 of the Arbitration Act and
Aswale 1/35
carbpl.1246021..doc
allowed the Respondents' application dated 30th August, 2019 also
fled under Section 17 of the Arbitration Act.
2 The disputes in the present arbitration arise out of a
Development Agreement dated 19 th May, 2015 entered into
between the Petitioner and the Respondents. The Respondents
are co-owners of a piece and parcel of land bearing Survey No.
44/1, CTS No. 83 Village Vikhroli, District Mumbai Suburban
admeasuring 4853.3 square meters situate, lying and being at LBS
Marg, Vikhroli (W), Mumbai (for short the "said land") along with
one structure comprising of ground plus two foors standing
thereon. The said land is situated in the Industrial Zone. Along-
with the execution of the Development Agreement, the
Respondents also executed an irrevocable Power of Attorney in
favour of the partners of the Petitioner. As per Clause 3 and
Clause 4(i) of the Development Agreement, the Petitioner paid the
Respondents a sum of Rs. 9.63 Crores.
3 It is the case of the Petitioner that since access to the
said land was insuffcient for the development, on 19 th May, 2015,
the owner of the adjacent plot agreed to give a right of way. In
Aswale 2/35
carbpl.1246021..doc
these circumstances, simultaneously with the execution of the
Development Agreement, a Deed of Right of Way dated 19 th May,
2015 was executed between the owners of the adjacent plot, the
Petitioner and the Respondents respectively, for a consideration of
Rs. 1 Crore. The said consideration of Rs. 1 Crore has been paid by
the Petitioner to the owners of the said adjacent plot.
4 According to the Petitioner, it thereafter took various
steps in furtherance of the Development Agreement all the way up
to March 2017. According to the Respondents, since the Petitioner
did not undertake the development as per the terms of the
Development Agreement, the Respondents terminated the
Development Agreement on 30th May, 2019.
5 Since disputes arose between the parties in relation to
the Development Agreement, the Respondents fled Commercial
Arbitration Petition (L) No. 999 of 2019 under Section 9 of the
Arbitration Act wherein a without prejudice statement on behalf of
the Petitioner was recorded between the parties' advocates that
the Petitioner will not take any steps in furtherance of the
Development Agreement and the irrevocable Power of Attorney
Aswale 3/35
carbpl.1246021..doc
and it will maintain status-quo in respect of the said land for a
period of two weeks. This without prejudice arrangement
continued till 19th September, 2019 wherein an order came to be
passed directing the parties to maintain status-quo. Thereafter, on
24th September, 2019 with the consent of parties, the Arbitral
Tribunal was constituted and the Section 9 Petitions fled by the
Petitioner [Commercial Arbitration Petition (L) No. 1132 of 2019]
as well as the Respondents [Commercial Arbitration Petition (L)
No. 999 of 2019] were disposed of. Under this order, the Arbitral
Tribunal was constituted and a direction was given that the
aforesaid two Petitions be converted into applications under
Section 17 of the Arbitration Act to be adjudicated by the Arbitral
Tribunal. It further directed that the order of status-quo passed
by this Court on 19 th September, 2019 shall continue to remain in
operation till the disposal of the Section 17 applications (fled by
the Petitioner and the Respondents) and for a period of two weeks
thereafter.
6 The Arbitral Tribunal accordingly heard both the
applications and by the impugned order, the Interim Application
fled by the Petitioner was rejected and the Interim Application
Aswale 4/35
carbpl.1246021..doc
fled by the Respondents was allowed in terms of prayer clauses
(a), (b) and (c) thereof. As a consequence thereof, the Tribunal
directed the Petitioner to remove itself, their men, including
security guards, machinery etc from the said land within a period
of 21 days from the communication of the said order. Aggrieved
by the impugned order passed by the Tribunal, the Petitioner has
approached this Court under Section 37 of the Arbitration Act.
7 Mr. Joshi, the learned Senior Counsel appearing on
behalf of the Petitioner, submitted that the impugned order is
wholly perverse and contrary to the settled principles of law. He
submitted that by the impugned order, the Arbitral Tribunal has
granted a mandatory injunction dispossessing the Petitioner from
the said land. He submitted that such an interlocutory mandatory
injunction can only be granted in extremely special circumstances
and not as a matter of course. He submitted that it can hardly be
disputed that the Petitioner was in physical possession of the said
land considering that the Petitioner's security was exclusively and
at all times stationed on the said land since June 2017. He
submitted that the Arbitral Tribunal failed to appreciate the
conduct of the parties and the actual situation on the ground in
Aswale 5/35
carbpl.1246021..doc
order to ascertain as to which party was in possession of the said
land.
8 Mr. Joshi submitted that the relief of interlocutory
mandatory injunction is granted generally to preserve or restore
the status-quo of the last non-contested status which preceded the
pending controversy until the fnal hearing, when full relief may
be granted; or to compel the undoing of those acts that have been
illegally done; or the restoration of that which was wrongfully
taken from the party complaining. He submitted that in the
absence of special circumstances a mandatory injunction will
normally be not granted. To put it in a nutshell, Mr. Joshi
submitted that it is now well established that an interim
mandatory injunction is passed only in circumstances which are
clear and justify a fnding that the status-quo has been altered by
one of the parties to the litigation and the interest of justice
demanded that status-quo ante be restored by way of an interim
mandatory injunction. In support of this proposition, Mr. Joshi
relied upon a decision of the Supreme Court in the case of (i)
Samir Narain Bhojwani v/s aurora Properties and investments
and Anr. [ (2018) 17 SCC 203]; and (ii) Metro Marins and Anr v/s
Aswale 6/35
carbpl.1246021..doc
Bonus Watch Co (P) Ltd and Ors [(2004) 7 SCC 478].
9 Mr. Joshi submitted that the facts of the present case
clearly establish that the Petitioner was in possession of the said
land much prior to the disputes arising between the parties and
hence there was no question of the Tribunal granting an
interlocutory mandatory injunction dispossessing the Petitioner
from the said land. He submitted that on this ground alone the
impugned order ought to be interfered with.
10 Mr. Joshi then submitted that the fndings given by the
Tribunal that the Petitioner treated the subject project as
unviable, is contrary to the Petitioner's conduct and in any event
could not be decided at the interim stage. He submitted that this
fnding is totally contrary to the pleadings of the Petitioner and
contrary to the oral arguments canvassed and written
submissions fled before the Tribunal at the time it heard the
Section 17 applications. In other words, the aforesaid fnding of
the Tribunal was totally baseless, erroneous and contrary to the
record, was the submission. He submitted that these fndings are
illegal, perverse and suffer from a serious error of law. He
Aswale 7/35
carbpl.1246021..doc
submitted that the facts clearly establish that the Petitioner was
ready and willing to perform the Development Agreement and has
always been ready and willing to perform its obligations
thereunder and which is clear from all the steps taken by the
Petitioner for getting various permissions from the statutory
authorities. He submitted that the Tribunal, by relying upon the
statements in the Petitioner's advocate letter dated 12 th July,
2019, wrongly came to the conclusion that the project was
unviable or that the Petitioner was unable to and/or not ready and
willing to perform the terms of the Development Agreement.
11 Mr. Joshi lastly submitted that the impugned order
ought to be set aside also because it completely ignores the
relevant terms of the contract. Mr. Joshi submitted that under
Clause 12 of the Development Agreement, the Respondents were
obliged to issue a notice calling upon the Petitioner to rectify and
remedy the breach and/or called upon it to perform its
responsibilities under the Agreement. Once such a notice was
given, the Petitioner was supposed to cure such a breach and/or
perform such obligations within a period of 90 days. If the
Petitioner failed to cure such breach and/or perform within the
Aswale 8/35
carbpl.1246021..doc
aforesaid period of 90 days from receipt of the said notice, the
Respondents had the right and/or were entitled to rectify the
default and/or remedy the breach and/or step-in and perform the
roles and responsibilities and obligations of the Petitioner at the
cost of the Petitioner. Over and above this, Clause 12 provided
that in the event that the Petitioner was a defaulting party, then
the Respondents had a right to ascertain the market value of the
said land by appointing a valuer from either of the fve valuers
mentioned in the Clause and upon determining the market value,
call upon the Petitioner, by way of a written notice, to purchase the
rights of the Respondents at a valuation of 125% of the market
value, within a period of 30 days from such notice . It was only if
the Petitioner did not purchase the said land at 125% of the
market value that the Respondents had a right to terminate the
Development Agreement. To put it differently, Mr. Joshi
submitted that the termination of the Development Agreement
itself was illegal and if that be the case, there was no question of
granting any relief to the Respondents and against the Petitioner,
much less a drastic relief such as an interlocutory mandatory
injunction. For all the aforesaid reasons, Mr. Joshi submitted that
the impugned order is unsustainable and ought to be set aside by
Aswale 9/35
carbpl.1246021..doc
me under Section 37 of the Arbitration Act.
12 On the other hand, Dr. Saraf, the learned Senior
Counsel appearing on behalf of the Respondents, submitted that
there is no merit in the arguments canvassed by Mr. Joshi on
behalf of the Petitioner. He submitted that it is fallacious to
contend that the Tribunal has granted any interlocutory
mandatory injunction. Dr. Saraf submitted that the issue of
granting a mandatory injunction would arise only if the Petitioner
was in possession of the said land. Relying upon clause 2 (ii) and 2
(iii) of the Development Agreement, Mr. Joshi submitted that the
Petitioner was only granted a license to enter upon the said land
for the limited purpose of (a) soil testing; (b) construction of
access; and (c) to undertake survey of the said land; and for no
other purpose. He submitted that only upon obtaining the IOD and
Commencement Certifcate (CC) for development of the said land
that the Respondents were to handover quiet, vacant and peaceful
possession of the same to the Petitioner. Dr. Saraf submitted that
in the present case it is undisputed that the Petitioner has not
obtained any IOD or CC till date. In fact, this was one of the
reasons why the Respondents were constrained to terminate the
Aswale 10/35
carbpl.1246021..doc
Development Agreement due to the inordinate delay in developing
the said land. Dr. Saraf submitted that in addition to the aforesaid
clauses, there is correspondence on record to show that the
Petitioner was never in possession of the said land. In this regard,
he brought to my attention an email dated 9 th May, 2017 addressed
by the Petitioner to the Respondents wherein the Petitioner has
stated that they propose to enter the construction site so that they
can put their men and material on site and mobilize work for
making the access road and carrying out related jobs before
submitting the plan to the MCGM. In the said mail, the
Respondents were requested to confrm the same and inform the
security on site. In reply thereto, the Respondents on 30 th May,
2017 granted permission to the Petitioner to enter the said land
only for the limited purposes mentioned in the sub-clause (ii) of
clause 2 of the Development Agreement and for no other purpose.
In other words, permission was granted for (i) soil testing, (ii)
construction of access and (iii) to undertake survey of the said
land. He submitted that this clearly shows that even the
Petitioner understood that he was never in possession of the said
land and the same was to be handed over to him only when the IOD
and CC were issued. Over and above this, Dr. Saraf also brought to
Aswale 11/35
carbpl.1246021..doc
my attention a hand written letter dated 21 st September, 2019
wherein pursuant to this Court's order, the Petitioner had
removed 10 pumps from the said land on 20 th and 21st September,
2019 and that now the said land was fully cleared and had no
accessories. Dr. Saraf submitted that all this clearly goes to show
that the Petitioner was never in possession of the said land at any
point of time. This being the case, the Tribunal cannot be faulted
for directing the Petitioner to remove itself from the said land.
13 As far as the Petitioner's readiness and willingness to
perform the Development Agreement is concerned, Dr. Saraf
submitted that the Development Agreement was fnal and binding
between the parties and there was no question of further
negotiations or reworking the terms of the Development
Agreement. He submitted that as per the milestone chart at
Exhibit-B to the Development Agreement, the Petitioner was
required to obtain all permissions and complete construction on
the said property within 48 months from the date of fulfllment of
the "conditions subsequent" as more particularly set out in Clause
5 of the Development Agreement. Despite this, till date the
Petitioner has not even got the plans prepared for development,
Aswale 12/35
carbpl.1246021..doc
let alone, obtaining any permission by way of IOD or CC to
commence construction. He submitted that not only the
correspondence exchanged between the parties but even the
averments made in the application of the Petitioner (under
Section 17) clearly and unequivocally show that according to the
Petitioner, the project/development had become unviable in view
of the changes in statutory provisions with regard to the payment
of premium and providing additional amenity open space for
change of user from Industrial Zone to Residential Zone. He
submitted that the Petitioner had clearly expressed their non-
acceptance to bear the additional premium necessary to obtain the
necessary permissions which itself clearly establishes that the
Petitioner was unwilling to perform its obligation under the
Development Agreement. He submitted that under the
Development Agreement and more particularly Clause 6(xxii)
thereof, it was the duty of the developer to undertake the
development of the said land in accordance with the approvals and
the applicable law at the risk and cost entirely of the Petitioner.
He submitted that the said clause further clearly provided that
such cost shall include but is not limited to charges and / or fees,
premium (by any name called), including towards obtainment
Aswale 13/35
carbpl.1246021..doc
and / or deposits and / or fees, costs charges and/or expenses that
may, at any time, be payable to such authorities for carrying out
the work of constructing and / or completing the new buildings
and / or for applying and / or obtaining CC and/or completion
certifcate. By refusing and / or trying to negotiate with the
Respondents the question of payment of premium for conversion
of user of land from Industrial Zone to Residential Zone, and which
premium worked out to approximately Rs. 5.5 to 6 Cores, the
Petitioner clearly expressed and demonstrated their lack of
readiness and willingness to perform the said obligation under the
Development Agreement, was the submission of Dr. Saraf.
14 As far as wrongful termination is concerned, Dr Saraf
frstly submitted that this is a point that is canvassed and argued
for the frst time before this Court in Appeal and was never argued
before the Arbitral Tribunal. He submitted that detailed
submissions on behalf of the Petitioner have been recorded in the
impugned order. Despite this, there is no mention in the
arguments of the Petitioner that the termination was wrongful as
it was contrary to the terms of the Development Agreement and
more particularly clause 12 thereof. He submitted that by merely
Aswale 14/35
carbpl.1246021..doc
showing a stray-line in the affdavit in rejoinder fled by the
Petitioner in its Section 17 application that the termination of the
Development Agreement is totally illegal, bad in law and in total
derogation of the terms and conditions of the Development
Agreement, does not carry the case of the Petitioner any further.
He submitted that it would therefore be highly unfair to the
Arbitral Tribunal if I was to consider the aforesaid argument
(which was never canvassed before the Arbitral Tribunal) and on
that pretext set aside the impugned order.
15 Without prejudice to the aforesaid contention, Dr. Saraf
submitted that in any event termination of the Development
Agreement was not contrary to Clause 12 thereof. In this regard,
he took me through the said clause in great detail and pointed out
that what was set out in the said clause was "without prejudice to
other rights and remedies in law available to the non- defaulting
party". It can hardly be disputed that in law when there is a
breach, a party complaining of the breach is entitled to terminate
the agreement. Whether the termination was justifed or
otherwise, is something that the Court would decide. In the
present case, considering that the Petitioner had repeatedly
Aswale 15/35
carbpl.1246021..doc
defaulted in complying with its terms and obligations under the
Development Agreement, the Respondents, fnally in May 2019,
terminated the Development Agreement. He submitted that on a
proper reading of Clause 12, it is incorrect on the part of the
Petitioner to contend that the termination of the Development
Agreement was contrary to the terms and conditions thereof.
16 Dr. Saraf lastly submitted that the impugned order is
the detailed order recording all submissions of the parties and
giving proper and cogent reasons for its fndings and conclusions.
The view taken by the Tribunal is not only one which is correct but
is certainly a plausible view. Nothing in the impugned order can
be termed as perverse and/or patently illegal which would require
interference in Appeal under Section 37 of the Arbitration Act.
He, therefore, submitted that there was no merit in the above
Petition and the same be dismissed with cost.
17 I have heard the learned counsel for the parties at
length and have perused the papers and proceedings in the above
Petition. The frst issue that was canvassed by Mr. Joshi was that
the Tribunal was not justifed in granting an interlocutory
mandatory injunction. In this regard it would be apposite to refer
Aswale 16/35
carbpl.1246021..doc
to the reasons given by the Arbitral Tribunal. The Arbitral
Tribunal, after hearing the arguments of the parties, came to the
conclusion that merely because the Petitioner states that it had
entered upon said land, does not mean that any right has been
granted in favour of the Petitioner by the Respondents. The
Tribunal records that on a request being made by the Petitioner
for entering upon the said land, the Respondents have clearly
stated that the said entry was being given for the limited purpose
of widening the access way. The Tribunal noted that the terms of
the Development Agreement are also reasonably clear that
possession in its true sense would be given only after the
Petitioner obtained the IOD and CC. Admittedly, the IOD and CC
have not been obtained. The Tribunal was, therefore, of the view
that the balance of convenience was in favour of the Respondents
insofar as the question of possession is concerned. The Tribunal
also came to the conclusion that looking to the facts and
circumstances of the case, the balance of convenience was against
the Petitioner for grant of any interim reliefs. On going through
the reasoning of the Tribunal, I do not fnd anything that can be
stated to be objectionable. The terms of the Development
Agreement are explicit. Clause 2 (ii) and 2(iii) of the
Aswale 17/35
carbpl.1246021..doc
Development Agreement read thus:-
CLAUSE 2
(ii) Simultaneously with the execution hereof, the Owner have given license to the Developer to enter upon the said Property only to the limited purpose of (i) soil testing, (ii) construction of access and (iii) to undertake survey of the said Land, in pursuance to the Agreement and for no other purpose.
(iii) Upon obtainment of the IOD and commencement certificate for the development of the said Land (by utilization of the Project FSI), the Owners shall hand over quiet, vacant and peaceful possession of the said Land to the Developer for the purpose of performance of its obligations under this Agreement."
(emphasis supplied)
18 These Clauses make it abundantly clear that the
license was granted to the Petitioner to enter upon the said land
only for the limited purpose mentioned therein and for no other
purpose. Clause 2 (iii) in fact contemplates that the possession
would be given only once the IOD and CC is obtained. In the facts
of the present case, admittedly no IOD or CC is obtained. In these
circumstances, I am in agreement with the fndings given by the
Tribunal that the Petitioner was allowed to enter upon the land
only for a limited purpose and possession of the said land was not
given to the Petitioner. If this be the case, then, I do not fnd
anything so drastically wrong in the impugned order under which
the Petitioner is restrained from entering upon and/or remaining
upon the said land or any part or portion thereof. It is in light of
Aswale 18/35
carbpl.1246021..doc
this that the Tribunal directs the Petitioner to remove itself from
the said land. I do not think that the Tribunal has committed any
patent illegality or that the fndings in relation thereto are
perverse so as to interfere with the same under Section 37 of the
Arbitration Act.
19 As far as the two decisions relied upon by Mr. Joshi are
concerned, namely, Samir Narain Bhojwani v/s Aurora Properties
and Investments and Anr. [(2018) 17 SCC 203] and Metro Marins
and Anr v/s Bonus Watch Co (P) Ltd and Ors [(2004) 7 SCC 478], I
do not think there can be any dispute with the prepositions laid
down therein. However, it is equally well settled that the ratio of a
judgment has to be understood in the factual matrix before the
Court. The factual situation in the case of Samir Narain Bhojwani
(supra) was that Respondent 1-plaintiff was appointed by one
Andheri Kamgar Nagar Cooperative Housing Society Ltd. (for
short "the Society") under a Development Agreement dated 6-10-
1996 as a developer under the Slum Development/Rehabilitation
Scheme to develop the suit property in question, being a plot of
land situated at Versova Link Road, Taluka Andheri and bearing
Survey No. 139, City Survey No. 1319 (Part) admeasuring 8892 sq
Aswale 19/35
carbpl.1246021..doc
mts or thereabouts as per Indenture of Lease dated 31-3-1993 and
9402 sq mts as per city survey records. One part of the suit
property was for constructing tenements free of charge for
project-affected-persons and the balance property could be used to
develop and sell the balance FSI. Respondent 1 then executed an
Agreement for Sub-Development dated 22-9-1999 with
Respondent 2-Defendant 1, transferring the benefts of the
development rights in the suit property, with the consent of the
aforementioned Society, to Respondent 2 after keeping aside
15,000 sq ft for itself i.e. Respondent No.1. Subsequently,
Respondent 2 executed an Agreement for Development dated 10-
3-2003 with the appellant-Defendant 2, whereunder the appellant
would be entitled to 55% of the total area available for free sale
buildings and car parking in the suit property and Respondent 2
retained 45% of the total area available for construction of free
sale buildings and car-parking by utilising FSI which may be
available on the suit property as per the Slum Rehabilitation
Scheme. This agreement was entered into without the consent of
Respondent 1 and hence, all three parties executed a Tripartite
Agreement dated 11-9-2009, referencing the previous agreements
of 6-10-1996 and 22-9-1999 wherein Respondent 1 was entitled to
Aswale 20/35
carbpl.1246021..doc
an area of 22,500 sq ft, an increase from its earlier agreed upon
15,000 sq ft, which would be allocated out of the 45% share due to
Respondent 2. Disputes arose between the parties and several
proceedings were fled enumerated in the judgment after which
the Single Judge directed the appellant, by a mandatory order, to
hand over keys and possession of 8 fats to Respondent No.1 along
with 16 parking spaces, recording that he had moulded the reliefs
originally sought by Respondent No.1 in the changed
circumstances of the case and in order to shorten the litigation
and do complete justice. This order of the learned Single Judge
was upheld by the Division Bench of High court which was
challenged before the Supreme Court. It was in this context that
the Supreme Court has laid down the proposition set out therein in
paragraph 24 on-wards and has then opined that in the factual
scenario before it the mandatory order which was passed against
the appellant was in excess of jurisdiction. The factual situation
before me is totally different. In the facts of the present case, the
Tribunal has come to a prima facie fnding that the Petitioner was
never in possession of the said land. He was granted permission to
enter upon it only for a limited purpose of (a) soil testing; (b)
construction of access; and (c) to undertake survey of the said
Aswale 21/35
carbpl.1246021..doc
land; and for no other purpose. In fact, as correctly submitted by
Dr. Saraf, by their letter dated 21 st September, 2019, the
Petitioners themselves informed the Respondents that they have
removed their pumps from the said land and the same is now
vacant with no accessories. All this material would prima facie go
to show that the Petitioner was never in possession of the said
land, and therefore, the directions passed by the Tribunal in this
regard cannot be faulted. This being the case, the aforesaid
decision is of no assistance to the Petitioner.
20 Similarly, even the judgment of the Supreme Court in
the case of Metro Marins and Anr. (supra) is of no assistance to
the Petitioner. The facts of this case would reveal that the
Respondent has fled a suit for possession alleging the appellant to
be a licensee and the period of licence having expired he was
entitled to a decree for Khas possession of the suit property as also
for certain other ancillary reliefs. In the said suit, he fled an
interlocutory application, frstly praying for a judgment on
admission and in the alternative, for an injunction directing the
appellant to immediately hand over vacant and peaceful
possession of the suit property to the Respondent-Plaintiff. The
learned Single Judge declined the aforesaid reliefs. In Appeal, the
Aswale 22/35
carbpl.1246021..doc
Appellate Bench came to the conclusion that prima facie the
relationship between the parties is that of a licensor and a licensee
and it also came to the conclusion that at one time the appellants
were willing to voluntarily surrender possession but did not do so
because the Respondent did not agree to repay the security
amount. Accordingly, the Appellate Bench appointed an Interim
Receiver to take symbolic possession of the suit property and put
the Respondent/plaintiff in possession thereof subject to the fnal
adjudication in the suit. It is in this background that in paragraph
9, the Supreme Court observed that an interim mandatory
injunction can be granted only in exceptional cases coming within
the exceptions noticed in the judgment of the Supreme Court in
the case of Dorab Cawasji Warden v/s Coomi Sorab Warden (1992
SSC 117). The Supreme Court observed that once the possession
of the appellant either directly or through his agent is admitted,
then the fact that the appellant is not using the said property for
commercial purpose, or not using the same for any benefcial
purpose, or the appellant has to pay a huge amount by way of
damages in the event of him losing the case, or the fact that the
litigation between the parties is a luxury litigation, are all facts
which are irrelevant for changing the status-quo with regard to
Aswale 23/35
carbpl.1246021..doc
possession during the pendency of the suit. I fnd that the facts of
this case are totally different from the factual matrix before me.
The facts before me, prima facie, indicate that the Petitioner was
never in possession. In fact, even the permission sought for by the
Petitioner to enter upon the said land was for a limited purpose
and only for such limited purpose permission was granted by the
Respondent. This being the case, I fnd that the reliance placed on
above decision is also of no assistance to the Petitioner.
21 The next argument that was canvassed by Mr. Joshi
was regarding the readiness and willingness of the Petitioner to
perform the Development Agreement. The fndings of the
Tribunal in relation thereto can be found from paragraphs 25 to
27 of the impugned order. Though in the impugned order the
Tribunal wrongly records that the Development Agreement was to
be completed within a period of 48 months from the date of the
Development Agreement, namely 19 th May, 2019, I fnd that the
same makes little difference to the outcome of the case. The
Tribunal clearly notices that several obligations that were to be
performed by the Petitioner have taken time due to the fact that
permissions/NOCs were to be obtained from Governmental or
Aswale 24/35
carbpl.1246021..doc
statutory authorities. However, all this appears to be done by or
around the year mid-2017. The Tribunal then records that
thereafter there appears to be a clear reluctance on the part of the
Petitioner to take the requisite steps to perform its obligation
under the said Development Agreement. The Tribunal noticed
that the Petitioner appears to have found that on account of
change in the Governmental policy for conversion of user of the
land from Industrial to Residential, the constructional area will
reduce. This would obviously result in a reduction in the
proportionate area that would come to the share of the Petitioner
and therefore a reduction in its profts. The Tribunal further
noticed that the Petitioner had additionally found that a premium
of approximately 20% of the ready reckoner value of the land
amounting to around Rs. 5.5. to 6 Crores has become payable,
which the Petitioner had not anticipated at the time of entering
into the said Development Agreement. On account of these
changes, the Petitioner has clearly accepted and treated the terms
of the said Development Agreement as they exist to be unviable as
having become unfavourable to the Petitioner.
22 The Tribunal noticed that if the Petitioner seeks
specifc performance, it must be ready and willing to perform the
Aswale 25/35
carbpl.1246021..doc
terms and conditions of the Development Agreement as they exist.
The Tribunal noticed that the Petitioner has set out various
reasons, which the Respondents term as excuses, to justify non-
performance of the terms of the Development Agreement. In this
regard, the Tribunal takes note of the correspondence and in
particular the Petitioner's advocate's letter dated 12 th July, 2019
and especially the contents of paragraphs 5, 6, 10, 12 (xi) and 13
which, according to the Respondents, indicate that there is a lack
of readiness and willingness on the part of the Petitioner to
perform the Development Agreement in its present form. The
Tribunal also noticed that the parties have held meetings and the
Petitioner has desired re-negotiation of the terms between them.
However, as matters stand, there has been no variation to the
terms of the said Development Agreement nor has any
supplementary agreement been arrived at between the parties.
The Tribunal therefore holds that prima facie the Petitioner is not
ready and willing to perform the Development Agreement in its
current form and hence not entitled to any equitable relief under
Section 17 of the Arbitration Act.
23 After carefully going through these fndings, I can
Aswale 26/35
carbpl.1246021..doc
hardly term them as perverse or suffering from any patent
illegality. The Petitioner's advocate's letter dated 12 th July, 2019
can be found at page no. 423 of the paper book. On a holistic
reading of this letter, I do not fnd that the interpretation given by
the Tribunal in relation thereto can in any event be termed as
perverse. In this letter, the advocate for the Petitioner alleged that
the Respondents were initially attempting to foist these burdens
and costs on the Petitioner by resorting to the clauses of the
Development Agreement when in fact there are subsequent
developments and that involve substantially large costs in terms
of premium as well as reduction in development potential, which
was not acceptable to the Petitioner. The letter further records
that the new 2034 DCPR was due to be published and therefore
the parties had mutually agreed to wait for the same in order to
take advantage of any benefts offered, including exploiting any
additional FSI that may become available under the same and
thereafter proceed for development after reassessing and
reworking the commercials under the changed scenario. The
letter further states that on account of unpredictable
circumstances enumerated therein, there is a huge increase in
project cost (estimated 4 years ago) and the real estate market
Aswale 27/35
carbpl.1246021..doc
has seen an unprecedented recession. The letter states that it was
in these circumstances that the parties had mutually arrived at an
acceptable solution to proceed with the Development and in this
context, the Petitioner proposed certain offers to the Respondents
and also indicated their revised offer under 33 (19) of the DCPR
2034 wherein the Petitioner offered to provide commercial area of
50,000 sq. ft. carpet area that was more than what was offered in
the Development Agreement. In paragraph 12 (xi), the
Petitioner's advocate clearly states that the Petitioner had always
been ready and willing and are still ready and willing to proceed
with the Development Agreement but under the changed scenario
and circumstances require a reworking of the commercial terms
and conditions as may be mutually agreeable to both parties.
Thereafter, paragraph 13 of this letter clearly records that though
the Petitioner is ready and willing to perform their obligations
under the Development Agreement but the present circumstances
created by the delays and lapses on the part of the Respondents,
and which, for all practicable purposes, has derailed the entire
project making it unviable in the present form.
24 After going through this letter (dated 12 th July, 2019),
Aswale 28/35
carbpl.1246021..doc
and parts of which has been referred to by me, I do not fnd that
the fndings of the Tribunal in relation to the lack of readiness and
willingness of the Petitioner to perform the Development
Agreement in its present form, can in any way be faulted or
termed as perverse or patently illegal. In fact, there is a mail
dated 21st October, 2016 even prior to this letter whereby due to
the heavy premium to be paid for change of user, the Petitioner
writes to the Respondents to fnd an amicable solution in relation
thereto so that they could go ahead with the project. In other
words, though the Development Agreement clearly stipulated that
all premiums were to be paid by the Petitioner, they were not
agreeable to do so and wanted to fnd another via media so that
the burden on them could be reduced. In these circumstances, I
do not fnd that Mr. Joshi, the learned Senior Counsel appearing
on behalf of the Petitioner, is justifed in assailing the impugned
order by contending that the fndings given by the Tribunal in
regard to the lack of readiness and willingness of the Petitioner to
perform the Development Agreement in its present form are
either perverse or that it suffers from any patent illegality.
Consequently, this argument of Mr. Joshi is also to be rejected.
Aswale 29/35
carbpl.1246021..doc
25 The last argument canvassed by Mr. Joshi was that the
termination was itself bad as it was not consonance with Clause 12
of the Development Agreement. As far as this aspect is concerned,
from the record, I am unable to fnd whether this argument was
ever canvassed before the Arbitral Tribunal. This argument does
not fnd place in the impugned order though detailed arguments of
the Petitioner are duly recorded by the Arbitral Tribunal.
According to the Petitioner, this is a very important argument.
Despite this, and when they came across the impugned order, they
have made no application to the Tribunal stating that the aforesaid
argument was specifcally canvassed and not considered by the
Tribunal. In fact, even in the Petition, nowhere is it stated that the
aforesaid point was specifcally argued before the Tribunal and the
same was not considered by it. I would therefore be fully justifed
in not entertaining this argument at this stage as it would not be
fair to the Tribunal to set aside its order on a point that was never
canvassed before it.
26 Be that as it may, I have carefully gone through Clause
12 of the Development Agreement. For the sake of convenience
the same is reproduced hereunder:-
Aswale 30/35
carbpl.1246021..doc
"12.DEFAULT
(i) If any Party (Defaulting Party) commits a breach of
this Agreement or commits a default in performance of its roles, obligations and covenants under this Agreement, then in such a case without prejudice to the other rights and remedies, in law available to the other Party ("Non- Defaulting Party"), the Non-Defaulting Party shall issue a notice ("Remedy Notice) to the Defaulting Party and call upon the Defaulting Party to rectify and remedy the breach and/or perform its roles, responsibilities and covenants,
(ii) In the event the Defaulting Party falls to rectify or remedy the breach and/or perform the roles, responsibilities and obligations of the Defaulting Party, at its own cost, within a period of 90(ninety) days from receipt of the Remedy Notice, then the Non-Defaulting Party shall have a right and be entitled (but shall not be obligated) to rectify the default and/or and remedy the breach and/or step-in and perform the roles, responsibilities and obligations of the Defaulting Party, at the costs of Defaulting Party. The Defaulting Party shall forthwith bear the estimated costs of performance by the Non-Defaulting Party along with interest thereon at the rate of 18% (eighteen percent) per annum, from the date of the expiry of the Remedy Notice till the actual repayment thereof ("Default Costs"). Till such payment of the Default Costs, the same shall constitute a charge on Premises of the Defaulting Party and the Non-Defaulting Party shall be entitled to recover the same from the proceeds of the Premises of the Defaulting Party.
(iii) Notwithstanding what is stated in sub-clause (ii) above, if the Defaulting Party is the Developer, without prejudice to the rights and remedies available in law, the Owners shall also have the following rights and remedies:
(a) The right to ascertain the market value of all right, titile and interest of the Owners in the said Property
Aswale 31/35
carbpl.1246021..doc
including the Owners Premises ("Right of Owners"). The Owners shall appoint a valuer from either of big five valuers i.e. Knight Frank, Colier, JLL, CBRE and Cushman & Wakefield to determine the market value of the Right of Owners ("Market Value") within a period of 30(thirty) days from such appointment.
(b) Upon determination of the Market Value, the Owners shall call upon, by a written notice to the Developer to purchase the Right of the Owners at a valuation of 125% of the Market Value of the Right of the Owners, within a period of 30 (thirty) days from such notice to the Developer.
(c) In the event the Developer falls to pay and purchase the Right of the Owners at 125% of the Market Value within a period of 30(thirty) days of notice of the Owners thereof, the Owners shall have the right to terminate this Development Agreement and the Power of Attorney without any reference or recourse to the Defaulting Party. Upon such termination, the following acts shall be undertaken simultaneously:-
i. The Developer shall not longer be permitted to enter upon the said Land. The Owners shall continue to be in exclusive possession of the said Land;
ii. The Developer shall have no right, title or interest in the said Land and/or the Project FSI and/or the Developers Premises;
iii. In case the Developer has (i) dealt with the Developer's Premises (or any part thereof) in any manner (including Marketed the same) and/ or received any advance, loan, deposit or other consideration in respect of the Developer's Premises or any part thereof and/or created an encumbrance whatsoever with respect to the
Aswale 32/35
carbpl.1246021..doc
Developer's FSI and/or the Developer's Premises (or any part thereof), then in such a case Developer shall at its own cost and expense, repay/refund the same and settle any and all claims to the Developer's FSI and/or Developer's Premises and/or the said Land and every part thereof and shall also cause the cancellation/surrender of all such rights, claims and/or liabilities in respect thereof to the satisfaction of the Owners.
iv. The Owners shall be entitled to deal with and/or dispose of and/or develop the said Land and all improvements as may have been made by the Developer thereto, in the manner it deems fit and proper;
v. The Owners shall be entitled to the Developer's Premises and shall be entitled to receive all the receivables from the Developers Premises.
vi. The Monetary Consideration paid to the Owners till then by the Developer shall stand forfeited by the Owners, without any reference or recourse to the Developer."
(emphasis supplied)
27 Clause 12 (1) clearly stipulates that if any party
(Defaulting Party) commits a breach of this Agreement or
commits a default in performance of its roles, obligations and
covenants under this Agreement, then in such a case, without
prejudice to the other rights and remedies, in law available to the
other Party ("Non-Defaulting Party"), the Non-Defaulting Party
shall issue a notice ("Remedy Notice") to the Defaulting Party and
call upon the Defaulting Party to rectify and remedy the breach
Aswale 33/35
carbpl.1246021..doc
and/or perform its roles, responsibilities and covenants. On
reading the aforesaid clause, prima facie, it does not appear that
the non-defaulting party has to frst issue a notice before it can
terminate the agreement. I say this because the clause clearly
stipulates "......without prejudice to other rights and remedies, in
law available to the other Party ("Non-Defaulting Party")......" .
Similarly, Clause 12 (iii) stipulates that notwithstanding what is
stated in sub-clause (ii) above, if the Defaulting Party is the
Developer, without prejudice to the rights and remedies available
in law, the Owners shall also have additional rights and remedies
more particularly set out in Clause 12 (iii). At least prima facie,
these clauses do not mean that the Respondents could not
terminate the agreement without frst issuing a remedy notice or
without frst offering the said land to the developer for purchase at
125% of the market value. I, therefore, do not fnd, at least prima
facie, that the termination is contrary to the terms of the
Development Agreement. Having said this, I may hasten to add
that this is only a prima facie fnding and shall not be binding on
the Tribunal when it hears the matter fully and fnally.
28 In view of the foregoing discussion, I fnd no merit in
the aforesaid Petition and it is accordingly dismissed. However,
Aswale 34/35
carbpl.1246021..doc
there shall be no order as to costs.
29 At this stage, the learned counsel appearing on
behalf of the Petitioner prays that the status-quo order that was
passed earlier and continued till today, be continued for a
period of four weeks from today. This request is vehemently
opposed by Dr. Saraf, the learned Senior Counsel appearing on
behalf of the Respondents.
30 Having heard both sides on this aspect, to enable the
Petitioner to challenge this order before the Supreme Court, I
am inclined to accept the request of the learned advocate
appearing on behalf of the Petitioner. Under these
circumstances, the status-quo order which was operating till
today shall continue for a period of four weeks.
31 All parties to act on an authenticated copy of this order
duly signed by the Personal Assistant/Private Secretary/Associate
of this Court.
( B. P. COLABAWALLA, J. )
Aswale 35/35
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!