Citation : 2021 Latest Caselaw 8805 Bom
Judgement Date : 6 July, 2021
CA-14691-2018, 14693-2018.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
CIVIL APPLICATION NO.14691 OF 2018
IN FAST/35221/2018
THE STATE OF MAHARASHTRA AND ORS
VERSUS
VISHNU PANDURANG JADHAV
WITH
CIVIL APPLICATION NO.14693 OF 2018
IN FAST/35226/2018
..........
Mr. B. V. Virdhe, AGP for applicants - State.
Mr. V. V. Ingle and Mr. P. B. Rakhunde, Advocates for respondent.
..........
CORAM : SMT. VIBHA KANKANWADI, J.
Reserved on : 19.06.2021 Pronounced on : 06.07.2021
ORDER :-
. Present civil applications have been filed for condoning the delay
of 2248 days in filing the first appeals.
2. Heard both sides. In order to cut short it can be said both of them
have made submissions in support of their respective contentions.
3. This Court by order dated 08.04.2021 had specifically observed
that the delay of 2248 days is definitely inordinate and there is no
explanation offered in the application for a huge delay of 5 ½ years to
make application for certified copy. It was also observed that this Court
CA-14691-2018, 14693-2018.odt
may consider imposition of heavy costs to be recovered from the erring
officer in view of the judgment of the Hon'ble Supreme Court in State of
Madhya Pradesh Vs. Bherulal, [(2020) 10 SCC 654], however, an
opportunity was given to the Government to explain the delay. The
applicant was asked to file affidavit in support of the application for
delay condonation. Pursuant to the said order, affidavit of Naib
Tahsildar, SDO Office, Omerga, Dist. Osmanabad, namely, Mohan
Dhondiram Panchal has been produced. In the affidavit, it is stated that
the judgment and award in the matter was passed by the reference
Court on 25.06.2012, thereafter, the Deputy Collector prepared appeal
proposal and had sent it to the Law and Judiciary Department in the
year 2013. The Law and Judiciary Department by letter number
829/2013 dated 13.03.2013 approved the proposal to file appeal before
this Court. After the proposal from Law and Judiciary Department was
received, the office of the Government Pleader of this Bench issued letter
dated 15.03.2013 and demanded the certified copies of the judgment
and order in three sets. Thereafter, the Government applied for the
copies of the judgment and order and it appears that it went through the
channel of communication from Government office to Deputy Collector
and then Deputy Collector contended that the said office has been
closed down by the Government. All those matters were then
CA-14691-2018, 14693-2018.odt
transferred to the Sub Divisional Officer, Omerga by letter dated
15.03.2016 and 22.04.2016. After scrutinizing the files, when it was
found that the certified copies were not applied or are not forming part
of the record, they had applied for the certified copies once again on
02.12.2017. On the same day, those copies were received and sent to
the Government Pleader's office of this Court on 09.04.2018.
Thereafter, the appeal was drafted along with the civil application for
condonation of delay. It has been tried to be submitted that in view of
the accompanying documents, the delay is not intentional and the
record itself was not traceable in view of lapse of about 10 years.
6. Learned Advocate appearing for the respondents has filed the
affidavit-in-reply denying all the said contentions. Learned Advocate for
respondents has submitted that whatever reasons those have been tried
to be assigned cannot be said to be sufficient much less reasonable to
condone the delay.
7. The reasons given by affiant Mohan Dhondiram Panchal, the Naib
Tahsildar, appears to be based on the documents those he could trace
out. However, it is to be noted that when he has used the words 'once
again applied for the certified copy' that presupposes that in the past
there was an attempt and in fact the certified copies of the judgment
and award were received by the Government. In fact, without going
CA-14691-2018, 14693-2018.odt
through the judgment and record how the Law and Judiciary
Department had given approval to file appeal itself is a question and
then why the copies of the judgment and award were not attached to
the order is a question. Again then the Assistant Government Pleader of
this office was required to make communication and demand the
documents. It appears that, that communication was not taken seriously.
There is total lethargy on the part of the Government servants dealing
with the case. By order dated 15.08.2013, the office of Deputy
Collector, Land Acquisition No.1, Osmanabad was closed down. The
copy of the said order has been produced which shows that the charge
was given to the Sub Divisional Officer, Bhoom and it was lay down by
the District Collector, Osmanabad as to who would be the authority who
would look after the remaining matters. But then after the said order
was passed on 14.08.2013 it appears that till 15.03.2016 no action was
taken on the communication dated 20.04.2013 by learned AGP, Nilanga
to Deputy Collector, Manjra Project, Osmanabad. Merely, by saying that
the office was closed down, the responsibility of the
persons/government servants will not end. In fact, it was then the
responsibility of the officers to whom the charge was given by order
dated 14.08.2013 to comply with the formalities in pursuant to the
sanction given for filing appeal. Therefore, the affidavit, which is now
CA-14691-2018, 14693-2018.odt
filed in pursuance to the order passed by this Court on 08.04.2021;
which in fact ought to have been filed along with the application itself,
does not explain the delay of 2248 days and, therefore, the application
deserves to be rejected.
8. This Court in State of Maharashtra and others Vs. Damu Manaji
Kokani, Civil Application No.15424 of 2017 and the group of matters
decided on 04.01.2018 had taken note of all the earlier decisions by this
Court as well as Hon'ble Supreme Court. Few of them can be referred
here. In Pundlik Jalam Patil (D) by LRs Vs. Executive Engineer Jalgaon
Medium Project and Another, [2008 (17) SCC 448], the Hon'ble
Supreme Court has held that "pursuing stale claims and multiplicity of
proceedings in no manner sub-surves public interest. These public
interest parameters ought to be kept in mind by the Courts while
exercising the discretion dealing with the application filed under Section
5 of the Limitation Act. Dragging the land losers to Courts of law years
after the termination of legal proceedings would not serve any public
interest. Settled rights cannot be lightly interfered with by condoning
inordinate delay without there being any proper explanation of such
delay on the ground of involvement of public revenue. It serves no
public interest. Though the State or its instrumentalites seeking
condonation of delay may be entitled to certain amount of latitude, but
CA-14691-2018, 14693-2018.odt
the law of limitation is same for citizen and for Governmental agencies."
Same ratio was laid down in Registrar of Companies Vs. Rajashree
Sugar and Chemicals Ltd. and Ors., [(2000) 6 SCC 133].
Further, in Basawaraj and Another Vs. The Special Land
Acqusition Officer, [2013 (14) SCC 81], Hon'ble Supreme Court
observed that "the law on the issue can be summarised to the effect that
where a case has been presented in the Court beyond limitation, the
applicant has to explain the Court as to what was the "sufficient cause"
which means an adequate and enough reason which prevented him to
approach the Court within limitation. In case a party is found to be a
negligent, or for want of bonafide on his part in the facts and
circumstances of the case, or found to have not acted diligently or
remain inactive, there cannot be a justified ground to condone the delay.
No Court could be justified in condoning such an inordinate delay by
imposing any condition whatsoever."
Further, in State of Maharashtra and Ors. Vs. Vithu Kalya Govari
and Ors., [2008 (6) Mh.L.J. 239], the Division Bench of this Court
observed that "the State is not expected to be in negligent or to take no
action for years and let the matters become time barred on account of
its negligence and inaction. The usual reason of "official hassle" or
"approval at different levels" is hardly sufficient to justify condonation
CA-14691-2018, 14693-2018.odt
of delay of about two years. In law, advantage has accrued to the non-
applicants claimants and the same cannot be withdrawn in a mechanical
manner and that too without any sufficient cause being shown to the
applicants. Despite, awards/judgments of the Courts which have
attained finality, the claimants are not permitted to receive
compensation in respect of their lands, which came to be compulsorily
acquired, is itself, sufficient prejudice to them. Therefore, before any
delay can be condoned and the claimants subjected to further prolonged
litigation, the onus to show sufficient cause lies upon the applicant -
State". Therefore, applying these principles, it can be said that no
sufficient cause has been shown to condone the delay.
9. As aforesaid, this Court have taken note of the decision in State of
Madhya Pradesh Vs. Bherulal (Supra) and it was observed that in case of
failure to give any proper explanation, this Court may consider
imposition of heavy costs. In the said decision, it has been held that
unless officer/officer(s) concerned have reasonable and acceptable
explanation for delay and there was bona fide effort, there is no need to
accept usual explanation that file was kept pending for several
months/years due to considerable degree of procedural red tape in
process. Thereafter, the Hon'ble Supreme Court sent a warning in such
cases of inordinate delay to the Government or the State authorities that
CA-14691-2018, 14693-2018.odt
they should pay for wastage of judicial time which has its own value and
such costs shall be recovered from the officers responsible. To apply this
ratio, the affidavit was called, though the affidavit is not giving a good
state of affairs, however, it can be definitely said that the present officer,
who has filed the affidavit, could not have been the person in-charge in
the year 2013. Further, when the office itself was closed down, yet, who
was required to carry out the further affairs in view of order dated
14.08.2013 will have to be inquired into, but certainly it is not at the
cost of the present officer and, therefore, that action of recovery of
wastage of judicial time is not warranted. Suffice it to say, as the
reasonable ground has not been shown to condone the delay, the
applications deserve to be rejected.
10. It will not be out of place to mention here that in view of the
order passed in stay applications i.e. Civil Application Nos.14692 of
2018 and 14694 of 2018 amount of Rs.17,92,708/- and Rs.26,01,614/-
has been deposited in this Court respectively. It deserves to be disbursed
as per the award to the respective respondents - original claimants.
Hence, the following order :-
ORDER
I) Civil Application Nos.14691 of 2018 and 14693 of 2018 stand
rejected.
CA-14691-2018, 14693-2018.odt
II) The amount of Rs.17,92,708/- and Rs.26,01,614/- deposited in
these matters be disbursed to the respective respondents - original
claimants as per the award.
[SMT. VIBHA KANKANWADI, J.] scm
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!