Saturday, 11, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Parinee Almog Buyers Welfare ... vs State Of Maharashtra And Ors
2021 Latest Caselaw 10165 Bom

Citation : 2021 Latest Caselaw 10165 Bom
Judgement Date : 3 August, 2021

Bombay High Court
Parinee Almog Buyers Welfare ... vs State Of Maharashtra And Ors on 3 August, 2021
Bench: K.K. Tated, P. K. Chavan
                                                                18-WP-3607-2021.doc


            Shailaja


                         IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                    CIVIL APPELLATE JURISDICTION
                                   WRIT PETITION NO.3607 OF 2021


            Parinee Almog Buyers Welfare            ]
            Association                             ]          .. Petitioner
                       Vs.
            State of Maharashtra and others.        ]          .. Respondents
                                                 .....
            Mr. Kunal Katariya a/w Tanuj Lodha, a/w Rachana Magdum & Ria
            Jain i/b Lodha & Lodha Advocates, for Petitioner.
                                                 .....
                                         CORAM : K.K. TATED &
                                                 PRITHVIRAJ K. CHAVAN, JJ.

                                         DATE   : 3 rd AUGUST, 2021.


            P.C.


            1.         Heard Mr. Katariya, learned Counsel for the petitioner.


            2.         By this petition under Article 226 of the Constitution of
            India, the petitioner is challenging the order dated 18 th October,
            2020 passed by respondent No.2- The Maharashtra Real Estate
            Regulatory           Authority,   Mumbai     in    Source         Complaint
            No.SC10001999 declining to take any action against the
            respondent-Developer on the ground that he is not registered
            under Real Estate (Regulation and Development) Act, 2016.




SHAILAJA   Digitally signed by
           SHAILAJA SHRIKANT
                                                                                 1 of 5
SHRIKANT   HALKUDE
           Date: 2021.08.07
HALKUDE    15:35:45 +0530
                                                18-WP-3607-2021.doc


3.    Mr. Katariya, learned Counsel appearing on behalf of the
petitioner submits that the reason given by the Authority is
contrary to law. He submits that neither the Authority directed the
respondent-Developer to refund the amount to the petitioner nor
directed to take any action against them. Hence, the petitioner
preferred the present writ petition.


4.    It is to be noted that the Maharashtra Real Estate Regulatory
Authority, Mumbai in it's order dated 18 th October, 2020 made
following observations in paragraphs No.7 and 8 which read thus;


      "7. Since the Respondent does not have valid
      approvals from the Competent Planning Authority,
      no directions can be issued to register the project,
      as on date. However, the Respondent is directed to
      apply for MahaRERA registration within 30 days
      of their obtaining the requisite approvals for the
      project. Further, he shall not advertise, market,
      book or create third party rights by offer for sale,
      enter into agreement for sale for any apartment in
      this proposed project, without registering the
      project with MahaRERA.

      8.    To the query of the learned counsel for the
      Complainants No.2 and 3, requesting for direction
      on their prayer to refund the consideration
      amount paid by the Complainant, it was explained
      that as stated in Para 86 of the judgment of
      Hon'ble Bombay High Court in Writ Petition
      No.2737/- U Neelkamal Realtors Vs. Union of
      India, RERA will apply after getting the project
      registered. Therefore, merits of the other
      grievances made by the Complainants have not


                                                                2 of 5
                                                 18-WP-3607-2021.doc


     been gone into. The Complainants have the liberty
     to raise the same in an appropriate forum".

5.   Authority also relied on paragraph 86 of the judgment of
this Court in case of Neelkamal Realtors vs. Union of India, 2018
(1) ABR, 558, which reads thus :-


     "86. On behalf of the petitioners it was submitted that
     registration of ongoing project under RERA would be
     contrary to the contractual rights established between the
     promoter and allottee under the agreement for sale
     executed prior to registration under RERA. In that sense,
     the provisions have retrospective or retroactive
     application. After assessing, we find that the projects
     already completed are not in any way affected and,
     therefore, no vested or accrued rights are getting affected
     by RERA. The RERA will apply after getting the project
     registered. In that sense, the application of RERA is
     prospective in nature. What the provisions envisage is
     that a promoter of a project which is not complete / sans
     completion certificate shall get the project registered
     under RERA, but, while getting project registered,
     promoter is entitled to prescribe a fresh time limit for
     getting the remaining development work completed.
     From the scheme of RERA and the subject case laws cited
     above, we do not find that first proviso to Section 3(1) is
     violative    of     Article 14 of Article 19 (1) (g) of the
     Constitution of India. The Parliament is competent to
     enact a law affecting the antecedent events. In the case of
     State of Bombay vs. Vishnu Ramchandra (Supra), the
     Apex Court observed that the fact that part of the
     requisites for operation of the statute were drawn from a
     time antecedent to its passing did not make the statute
     retrospective so long as the action was taken after the Act
     came into force. The consequences for breach of such
     obligations under RERA are prospective in operation. In
     case ongoing projects, of which completion certificates



                                                                 3 of 5
                                                 18-WP-3607-2021.doc


     were not obtained, were not to be covered under RERA,
     then there was likelihood of classifications in respect of
     undeveloped ongoing project and the new project to be
     commenced. In view of the material collected by the
     Standing Committee and the Select Committee and as
     discussed on the floor of the Parliament, it was thought
     fit that ongoing project shall also be made to be
     registered under RERA. The Parliament felt the need
     because it was noticed that all over the country in large
     number of projects the allottees did not get possession for
     years together. Huge sums of money of the allottees is
     locked in. Sizable section of allottees had invested their
     hard earned money, life savings, borrowed money, money
     obtained through loan from various financial institutions
     with a hope that sooner or later they would get
     possession of their apartment/flat/unit. There was no law
     regulating the real estate sector, development
     work/obligations of promoter and the allottee. Therefore,
     the Parliament considered it to pass a central law on the
     subject. During the course of hearing, it was brought to
     notice that in the State of Maharashtra a law i.e. MOFA on
     the     subject has been in operation. But MOFA
     provisions are not akin to regulatory provisions of RERA".



6.   As the respondents are not served, following order is passed;


                                  :ORDER:

(a) The petitioner is permitted to serve the respondents by private notice along with entire proceedings either by R.P.A.D or hand delivery and file affidavit of service on or before 27 th August, 2021;

4 of 5 18-WP-3607-2021.doc

(b) If affidavit of service is filed in time, the matter to appear on board on 31st August, 2021;

(c) If affidavit of service is not filed in time, the matter to appear on board as per C.I.S date.

[PRITHVIRAJ K. CHAVAN, J.] [K. K. TATED, J.]

5 of 5

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Media

 
 
Latestlaws Newsletter