Citation : 2018 Latest Caselaw 1247 Bom
Judgement Date : 9 March, 2018
arp.24.17.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
ARBITRATION PETITION NO.24 OF 2017
Coastal Marine Construction and
Engineering Limited ..Petitioner
Vs.
Garware-Wall Ropes Limited ..Respondent
Ms. Ridhi Nyati I/b Ashwin Shanker, for the Petitioner.
Mr.Ashish Kamat a/w Mr. Kunal Mehta, Ms Yasmin Godrej and
Ms. Priyanka Deshmukh I/b Crawford Bayley and Co, for the
Respondent.
CORAM :- B.P.COLABAWALLA, J.
RESERVED ON : FEBRUARY 5, 2018.
PRONOUNCED ON : MARCH 9, 2018.
JUDGMENT :- [ Per B. P. COLABAWALLA J ]
1. This Arbitration Petition has been filed under Section
11 of the Arbitration and Conciliation Act, 1996 seeking the
appointment of a sole Arbitrator to adjudicate upon the disputes
which have been arisen between the Petitioner and the
Aswale 1/31
arp.24.17.doc
Respondent under the sub-contract dated 14th June, 2013. There
is no dispute that this sub-contract contains an arbitration clause
which inter alia states that any and all claims, disputes, questions
or controversies involving the parties and arising in connection
with this Agreement or execution, interpretation, validity,
performance, termination and which cannot be finally resolved by
such parties through negotiations, shall be resolved by a final and
binding arbitration to be held in Pune. The Arbitration Clause
further provides that the disputes shall be referred to a Sole
Arbitrator to be appointed by the Petitioner and the Respondent
jointly. This matter was argued before me on 5th February, 2018
and the parties asked for time till 20th February, 2018 to file
written submissions. Accordingly, both parties have also filed
written submissions before me. Before I deal with the rival
contentions it would be appropriate to refer to a few facts, which
are really undisputed. They are as follows:-
(a) The Petitioner is a company registered under the
provisions of the Companies Act, 1956 and is inter alia
engaged in the business of marine engineering,
geophysical and geotechnical survey etc. The
Aswale 2/31
arp.24.17.doc
Respondent is also a company registered under the
provisions of Companies Act, 1956.
(b) The Executive Engineer, Aul Embankment Division,
Aul, District-Kendrapara floated a tender inviting bids
inter alia for the "installation of geo-textile tubes
embankment with toe mound' at village Pentha in
Odisha for protection against coastal erosion. The said
tender was awarded to the Respondent, who in turn,
further sub-contracted the work to the Petitioner
pursuant to an Agreement dated 14th June, 2013
(Exhibit-A to the Application). As per the terms of the
said sub-contract, the Petitioner procured two bank
guarantees in favour of the Respondent, both in the
sum of Rs.1,18,37,281/- each. The first guarantee was
a performance bank guarantee and second one was an
advance payment bank guarantee.
(c) It is the case of the Petitioner that vide their letter
dated 2nd January, 2015, the Respondent wrongly
terminated the sub-contract and proceeded to encash
Aswale 3/31
arp.24.17.doc
the aforementioned bank guarantees. In response
thereto, the Petitioner by their letter dated 8th
January, 2015 objected to the wrongful termination
and encashment and instead considered the said act by
the Respondent as a repudiatory breach. Thereafter,
by their letter dated 7th October, 2015, the Petitioner
called upon the Respondent to make good the losses
suffered by the Petitioner on account of the wrongful
termination of the sub-contract as well as the wrongful
encashment of the bank guarantees.
(d) As mentioned earlier, Annexure-III of the sub-contract
dated 14th June, 2013 ("Commercial Terms and
Conditions") inter alia stipulated for all disputes would
be settled by arbitration. The said clauses reads as
under:-
"Jurisdiction:-
Each Party irrevocably submits to the non exclusive Jurisdiction of the Court at Pune, Maharashtra State, India.
Arbitration Any and all claims, disputes, questions or controversies involving the parties and arising in connection with this Agreement or execution, interpretation, validity, performance, termination hereof which cannot be finally resolved by such parties negotiation shall be resolved by final and binding arbitration held
Aswale 4/31
arp.24.17.doc
in Pune. The disputes shall be referred to a sole arbitrator to be appointed by GWRL and COMACOE Jointly in agreement".
(e) It is the case of the Petitioner that since negotiations
failed the Petitioner addressed a letter dated 11th July,
2016 to the Respondent and expressed their desire to
proceed to commence arbitration. Thereafter, vide
their letter dated 20th July, 2016, the Petitioner inter
alia proposed the name of one Mr. Mihir Naniwadekar
(Advocate) as the Sole Arbitrator.
(f) The Respondent vide its letter dated 17th August, 2016
objected to the invocation of the arbitration and the
appointment of said Mr. Naniwadekar as the Sole
Arbitrator. It is in these circumstances that the
provisions of Section 11 of the Arbitration and
Conciliation Act, 1996 have been invoked for
appointment of a Sole Arbitrator to decide the disputes
and differences that have arisen between the
Petitioner and the Respondent under the sub-contract
dated 14th June, 2013 and which admittedly contains
an arbitration clause. It is also not in dispute before
Aswale 5/31
arp.24.17.doc
me that the arbitration clause has been invoked by the
Petitioner. Since the Respondent has failed to agree to
a Sole Arbitrator as suggested by the Petitioner, and
neither has the Respondent proposed the name of any
other arbitrator, the present Petition has been filed.
2. In this factual backdrop, Ms. Nyati, the learned
counsel appearing on behalf of the Petitioner, submitted that there
was no reason why this Court ought not to appoint an arbitrator as
contemplated under Section 11 of the Arbitration and Conciliation
Act, 1996. She submitted that in the facts of the present case,
admittedly there was an arbitration clause that was contained in
the sub-contract dated 14th June, 2013. Pursuant to this clause,
the Petitioner had invoked arbitration and had called upon the
Respondent to agree to the appointment of the Sole Arbitrator as
suggested by the Petitioner. As the Respondent had failed to do so,
the present application was filed. She therefore submitted that
there was no impediment on this Court in invoking the provisions
of Section 11 and referring the disputes and differences arising
out of the sub-contract dated 14th June, 2013 to a Sole Arbitrator
as contemplated under the contract.
Aswale 6/31
arp.24.17.doc
3. On the other hand, Mr. Kamat, the learned counsel
appearing on behalf of the Respondent, submitted that in the facts
of the present case, the relief of appointing the Arbitrator cannot
be granted on two grounds. They are:-
(i) the contract is undisputedly unstamped and by appointing an Arbitrator, this Court would be acting upon an unstamped document which would be in violation of the provisions of Sections 33 and 34 of the Maharashtra Stamp Act, 1958. He submitted that it is common ground that the present contract is a 'works contract' as defined by Article 63 of the Maharashtra Stamp Act, 1958 and as per Section 30 (f) (a) thereof, the obligation to pay stamp duty on works contract is on the person who has received the contract, namely the Petitioner in the present case; and
(ii) the invocation of arbitration in the present case is premature as the Petitioner has not followed the mandatory pre-arbitral agreed procedure prescribed by the arbitration agreement.
4. On the first issue (of stamping), Mr. Kamat submitted
that though an arbitration agreement, in law, is a separate
contract and is independent from the underlying contract, the
same required stamping before the parties could be referred to
Aswale 7/31
arp.24.17.doc
arbitration. In support of this proposition, Mr. Kamat relied upon
following decisions:-
(i) SMS Tea Estates Pvt Ltd v/s Chandmari Tea Company Pvt Ltd reported in (2011) 14 SCC.
(ii) Chenbasapa and Another v/s Lakshman Ramchandra reported in 18 Bom LR 370.
(iii) Yasodammal and Another v/s Janaki Ammal reported in 1967 (81) LW 2 (Madras High Court)
(iv) Sohan Lal Nihal Chand v Raghu Nath Singh and Others reported in AIR 1934 Lahor 606.
(v) Maung Po Chein v/s CRVVV Chettyar Firm reported in AIR 1935 Rangoon 282.
(vi) Deepak Corporation, Bombay v/s Puspha Prahlad Nanderjog reported in (1995) 1 Mh.L.J. 489.
(vii) Lakdawala Developers Pvt Ltd v/s Badal Mittal and Others; Appeal (L) No.272 of 2013 in Arbitration Petition No.221 of 2013 decided on 25th June, 2013.
5. As far as the second issue is concerned, namely that
the arbitration was premature and therefore the pre-arbitral
procedure of amicably settling the matter was not resorted to, Mr.
Kamat relied upon the decision of the Supreme Court in the case of
Iron and Steel Co Ltd v/s Tiwari Road Lines reported in
(2007) 5 SCC 703.
Aswale 8/31 arp.24.17.doc6. In rejoinder, Ms. Nyati, the learned counsel for the
Petitioner, submitted that the reliance placed by the Respondent
on the aforesaid decisions and more particularly in the case of
SMS Tea Estates Pvt Ltd (supra), was wholly misplaced. Ms.
Nyati was at pains to point that after all these decisions were
passed, the Arbitration and Conciliation Act, 1996 has been
amended and Section 11(6-A) has been inserted which
categorically contemplates that this Court, whilst appointing an
arbitrator, must confine itself to the examination of the existence
of an arbitration agreement. In the facts of the present case, she
submitted that the Respondent had not denied the existence of the
arbitration agreement and even assuming for the sake of
argument that the document required stamping, the same did not
affect the existence of the arbitration agreement or even the
agreement as a whole. She was at pains to point out that this
Court must not go into the issue of enforceability or validity of the
agreement after the amendment to Section 11 in 2015. She
submitted that the Legislature has consciously restricted judicial
intervention under Section 11 in the clearest words possible to
only the examination of the existence of the arbitration agreement
Aswale 9/31
arp.24.17.doc
and nothing more. She submitted that no case was made out to
expand the scope of judicial intervention under Section 11 (6-A)
to include the issue of validity, enforceability etc. According to
Ms. Nyati, this was further emphasized by virtue of Section 11
(13) which was inserted again by the 2015 amendment. In this
regard, she also placed reliance on the report of the Law
Commission of India (Report No. 246) which was for the
amendment to the Arbitration and Conciliation Act, 1996. She
laid great stress on paragraphs 28 to 33 of this report which deals
with the Scope and Nature of Pre-Arbitral Judicial Intervention to
point out all that the Court has to look at is whether there exists
an arbitration agreement between the parties and nothing more or
nothing less. All other issues are to be left to be decided by the
arbitrator, once appointed under Section 11. She therefore
submitted that the reliance placed by Mr. Kamat on the judgment
of the Supreme Court in the case of SMS Tea Estates Pvt Ltd
(supra), was wholly misplaced.
7. Without prejudice to the aforesaid argument, Ms.
Niyati submitted that in the facts of the present case the clause
titled as " Royalties, Licenses, Mining Permits and other statutory
Aswale 10/31
arp.24.17.doc
requirements etc" clearly envisages that it was the Respondent
who had to pay all the necessary levies / fees / taxes / duties /
royalties and hence the Respondent could not defeat the
arbitration agreement by taking a dishonest defence that the
document was insufficiently stamped, when the liability to pay the
stamp duty, if any, was clearly on the Respondent.
8. As far as invocation of the arbitration being premature
is concerned, Ms. Nyati submitted that the facts of the present
case would clearly establish that there was no scope for any
amicable settlement. According to her, both parties had taken a
rigid stand by making allegations and counter allegations as well
as raising counter claims against each other. This, according to
Ms. Nyati, was clear from a bare perusal of the letters dated 7th
October, 2015 (Exhibit-D) and 24th October, 2015 (Exhibit-E) to
the application. Over and above this, she submitted that
notwithstanding the above, after the dispute had arisen and the
contract was terminated, Mr. Vivek Bansal (the Petitioner's Group
CEO) addressed numerous requests between 24th March, 2015 to
11th May, 2015 to Mr. Tiru Kulkarni, (Respondent's Vice
President) to schedule a meeting for negotiation. Despite this,
there was no response forthcoming. In these circumstances, Ms.
Aswale 11/31
arp.24.17.doc
Nyati submitted that in any event the said requests are in
sufficient compliance with the Arbitration Clause and therefore it
was incorrect to contend that invocation of the arbitration was
premature. In support of this submission, Ms. Nyati relied upon a
decision of the Supreme Court in the case of Visa International
Limited v/s Continental Resources (USA) Ltd. reported in AIR
2009 SC 1366.
9. I have heard the learned counsel for the parties at
length and have perused the papers and proceedings in the
present matter. I shall first deal with the argument of the
Respondent that the invocation of the arbitration was premature.
In this regard, I find considerable force in the argument canvassed
by Ms. Nyati. The Arbitration Clause which has been invoked in
the facts of the present case (and which has been reproduced
above) states that any and all claims, disputes etc which cannot be
finally resolved by such parties through negotiation, shall be
resolved by a final and binding arbitration to be held in Pune. In
the affidavit in rejoinder filed on behalf of the Petitioner, in
paragraph 4, it is categorically denied that the Petitioner never
initiated any settlement, negotiation and/or resolution process. It
has been further stated that the Petitioner acting through Mr.
Aswale 12/31
arp.24.17.doc
Vivek Bansal, the Group-CEO, addressed numerous requests to Mr.
Tiru Kulkarni, Vice President of the Respondent to schedule a
meeting for negotiation. Despite these requests, the Respondent
was not forthcoming. To substantiate this contention, the
Petitioner has annexed at Exhibit A to the said affidavit, text
messages exchanged between the Petitioner and the Respondent
between 24th March, 2015 to 11th May, 2015. These messages
were sent on Whatsapp. On going through Exhibit-A and which
has not been denied by the Respondent, I find that the Petitioner
had made several requests for a meeting to resolve the matter
without any success. This being the case, I do not find any
substance in the argument on behalf of the Respondent that since
there was no negotiation between the parties before invoking the
arbitration, the same was premature. From these text messages
(sent on Whatsapp), it is quite clear that on several occasions, a
request was made for a meeting to which there was no positive
response. This being the case, I find that the Petitioner was fully
justified in invoking the arbitration clause as contained in
Annexure-III to the sub-contract dated 14th June, 2013 (the
commercial terms and conditions).
10. Having said this, I shall now turn my attention to the
Aswale 13/31
arp.24.17.doc
main issue, namely whether I can refer the parties to arbitration
on the basis of what the Respondent alleges is an unstamped
document. Section 11 of the Arbitration and Conciliation Act,
1996 deals with appointment of arbitrators. The entire procedure
has been laid down under the said section as to how the arbitrator
/ arbitrators are to be appointed by the Court when the parties fail
to agree on the appointment of the arbitrator / arbitrators. What
is really relevant for my purpose are the amendments that are
carried out to Section 11 by Act 3 of 2016 w.r.e.f. 23rd October,
2015 (amendment of 2015). By virtue of the amendment of 2015,
sub-section 6-A was inserted in Section 11 which reads thus:-
"(6-A) The Supreme Court or, as the case may be, the High Court, while considering any application under sub-section (4) or sub- section (5) or sub-section (6), shall, notwithstanding any judgment, decree or order of any court, confine to the examination of the existence of an arbitration agreement."
11. What can be seen from a plain reading of this sub-
section is that the Supreme Court or as the case may be the High
Court, while considering any application under sub-section (4) or
sub-section (5) or sub-section (6) of Section 11 shall,
notwithstanding any judgment, decree or order of any Court,
Aswale 14/31
arp.24.17.doc
confine itself to the examination of the existence of an arbitration
agreement. The purpose for bringing this provision into force can
be seen from the 246th Report of the Commission on 'Amendment
to the Arbitration and Conciliation Act, 1996'. Paragraphs 28
to 33 deal with 'scope and nature of pre-arbitral judicial
intervention.' After referring to certain decisions of the Supreme
Court and more particularly under Section 11 of the Act, the
Commission in paragraph 33 has stated thus:-
"33. It is in this context, the Commission has recommended amendments to sections 8 and 11 of the Arbitration and Conciliation Act, 1996. The scope of the judicial intervention is only restricted to situations where the Court/Judicial Authority finds that the arbitration agreement does not exist or is null and void. In so far as the nature of intervention is concerned, it is recommended that in the event the Court / Judicial Authority is prima facie satisfied against the argument challenging the arbitration agreement, it shall appoint the arbitrator and/or refer the parties to arbitration, as the case may be. The amendment envisages that the judicial authority shall not refer the parties to arbitration only if it finds that there does not exist an arbitration agreement or that it is null and void. If the judicial authority is of the opinion that prima facie the arbitration agreement exists, then it shall refer the dispute to arbitration, and leave the existence of the arbitration agreement to be finally determined by the arbitral tribunal. However, if the judicial authority concludes that the agreement does not exist, then the conclusion will be final and nor prima facie. The amendment also envisages that there shall be a conclusive determination as to whether the arbitration agreement is null and void. In the event that the judicial authority refers the dispute to arbitration and/or appoints an arbitrator, under sections 8 and 11 respectively, such a decision will be final and non-appealable. An appeal can be maintained under section 37 only in the event of refusal to refer parties to arbitration,
Aswale 15/31
arp.24.17.doc
or refusal to appoint an arbitrator."
(emphasis supplied)
12. What can be seen from this paragraph is that the scope
of judicial intervention is only restricted to situations where the
Court/Judicial Authority finds that the arbitration agreement
does not exist or is null and void. The only reason why I refer to
paragraph 33 is to ascertain the intention of the Legislature for
the purposes of inserting sub-section 6-A to Section 11 of the
Arbitration and Conciliation Act, 1996. Another important and
telling factor can also be found in the Statement of Objects and
Reasons. This clearly states that India has been ranked at 178 out
of 189 nations in the world in contract enforcement. It is therefore
high time that urgent steps are taken to facilitate quick
enforcement of contracts, easy recovery of monetary claims and
award of just compensation for damages suffered, and reduce the
pendency of cases in courts and hasten the process of dispute
resolution through arbitration, so as to encourage investment and
economic activity. It is in these circumstances that clause 6 of
the Amendment Bill states that sub-section 6-A is inserted to
provide that the Supreme Court or the High Court, while
considering the application under sub-sections 4 to 6, shall confine
Aswale 16/31
arp.24.17.doc
itself to the examination of the existence of the arbitration
agreement. When one looks at the intention of the Legislature for
bringing about this amendment, I find considerable force in the
argument of Ms Nyati that what has to be looked into is only about
the existence of the arbitration agreement and nothing more or
nothing less.
13. In the facts of the present case, and as rightly
submitted by Ms. Nyati, the existence of the arbitration agreement
is not disputed. Even assuming for the sake of argument that the
document is insufficiently stamped, that would not by itself affect
the existence of the arbitration agreement that was contained in
the sub-contract awarded by the Respondent to the Petitioner
dated 14th June, 2013. In fact, Mr. Kamat, the learned counsel
appearing for the Respondent, fairly conceded before me that
there was no dispute about the existence of the arbitration
agreement. This being the case, I find that the reliance placed by
Ms. Nyati on sub-section 6-A of Section 11 is clearly well founded.
In the view that I take, I am supported by a decision of the
Supreme Court in the case of Duro Felguera, S. A. v/s
Gangavaram Port Limited reported in (2017) 9 SCC 729. The
Aswale 17/31
arp.24.17.doc
Supreme Court after considering Section 11 prior to its
amendment and also after its amendment, at paragraph 19
observed thus:-
"19. The effect of the Arbitration and Conciliation (Amendment) Act, 2015 in Section 11 of the Act has been succinctly elucidated in the textbook "Law Relating to Arbitration and Conciliation" by Dr P.C. Markanda, which reads as under:
"The changes made by the amending Act are as follows:
1. The words 'Chief Justice or any person or institution designated by him' shall be substituted by the words 'the Supreme Court or, as the case may be, the High Court or any person or institution designated by such Court'. Thus, now it is not only the Chief Justice who can hear applications under Section 11, the power can be delegated to any Judge as well.
2. As per sub-section (6-A), the power of the Court has now been restricted only to examination of the existence of an arbitration agreement. Earlier, the Chief Justice had been given the power to examine other aspects as well i.e. limitation, whether the claims were referable for arbitration, etc. in terms of the judgments of the Supreme Court in SBP and Co. v. Patel Engg. Ltd. [SBP and Co. v. Patel Engg. Ltd., (2005) 8 SCC 618] and National Insurance Co. Ltd. v. Boghara Polyfab (P) Ltd. [National Insurance Co. Ltd. v. Boghara Polyfab (P) Ltd., (2009) 1 SCC 267 : (2009) 1 SCC (Civ) 117] Now all preliminary issues have been left for the Arbitral Tribunal to decide in terms of Section 16 of the Act.
3. The amending Act has categorically provided in sub- section (6-B) that designation of any person or institution by the Supreme Court or High Court would not be construed as delegation of judicial power. The order passed by a designated person or institution would continue to be regarded as a judicial order.
4. It has been provided in sub-section (7) that the order passed under this section shall not be appealable. This change means that finality is attached to the order passed under this section and it would not be subject to further examination by an appellate court.
5. Sub-section (8) has been amended to bring it in conformity with amended Section 12 with regard to ensuring independence and impartiality of the arbitrator. Before appointing any arbitrator, a disclosure in writing has to be obtained in terms of Section 12(1) of the Act. This is to ensure that the appointed
Aswale 18/31
arp.24.17.doc
arbitrator shall be independent and impartial and also harmonizes the provisions of Sections 11 and 12 of the Act.
6. The amending Act has introduced sub-section (13) which provides that the disposal of the application under this section has to be expeditious and endeavour shall be made to dispose of the application within a period of 60 days from the date of service of notice on the opposite party. This sub-section would ensure speedy disposal of applications under this section and all contentious issues have been left to be decided by the Arbitral Tribunal.
7. For determining the fee structure of the Arbitral Tribunal, it has been recommended that the High Courts may frame the necessary rules and for that purpose, a model fee structure has been provided in the Fourth Schedule of the amending Act. However, this sub-section would not be applicable for the fee structure in case of international commercial arbitrations and domestic arbitrations where the parties have agreed for determination of fee as per rules of an arbitral institution. This sub-section has been inserted to ensure a reasonable fee structure since the cost of arbitration has increased manifold due to high charges being levied on the parties by the Arbitral Tribunal and other incidental expenses."
[Reference: Law Relating to Arbitration and Conciliation by Dr P.C. Markanda; Lexis Nexis, 9th Edn., p. 460]"
14. Thereafter in paragraph 47, the Supreme Court has
discussed what is the effect of the change introduced by
Arbitration and Conciliation (Amendment Act), 2015 and with
particular reference to Section 11 (6) and the newly added Section
11 (6-A). In this regard at paragraphs 47 and 48 read as under:-
"47. What is the effect of the change introduced by the Arbitration and Conciliation (Amendment) Act, 2015 (hereinafter referred to as "the 2015 Amendment") with particular reference to Section 11(6) and the newly added Section 11(6-A) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as "the 1996 Act") is the crucial question arising for consideration in this case.
Aswale 19/31 arp.24.17.doc48. Section 11(6-A) added by the 2015 Amendment, reads as follows:
"11. (6-A) The Supreme Court or, as the case may be, the High Court, while considering any application under sub- section (4) or sub-section (5) or sub-section (6), shall, notwithstanding any judgment, decree or order of any court, confine to the examination of the existence of an arbitration agreement."
(emphasis supplied)
From a reading of Section 11(6-A), the intention of the legislature is crystal clear i.e. the court should and need only look into one aspect--the existence of an arbitration agreement. What are the factors for deciding as to whether there is an arbitration agreement is the next question. The resolution to that is simple--it needs to be seen if the agreement contains a clause which provides for arbitration pertaining to the disputes which have arisen between the parties to the agreement."
(emphasis supplied)
15. On a plain reading of this decision, it is ex-facie clear
that the Supreme Court has opined that the intention of the
Legislature is crystal clear i.e. the court should and need only look
into one aspect, namely the existence of an arbitration agreement.
What are the factors for deciding as to whether there is an
arbitration agreement, the Supreme Court has clearly stated that
it needs to be seen if the agreement contains a clause which
provides for arbitration pertaining to the disputes which have
arisen between the parties to the agreement. That would suffice.
Aswale 20/31 arp.24.17.doc16. In the facts of the present case, there is no dispute
with reference to the existence of the arbitration agreement. This
being the case, I find that Mr. Kamat is not correct in submitting
that the dispute cannot be referred to arbitration merely because
the sub-contract dated 14th June, 2013 (and in which the
arbitration clause is contained), is an unstamped document.
17. There is yet another reason for taking this view. It is
now well settled that the provisions of the Stamp Act are enacted
for the purposes of securing the revenue for the Government and
not to arm a dishonest litigant with a technical defence. If one
needs to refer to any decision on this aspect, the observations of
the Supreme Court in the case of Hindustan Steel Ltd v/s
Messrs Dilip Construction Company reported in (1969) 1 SCC
597 are apposite. The relevant paragraph reads thus:-
"7. The Stamp Act is a fiscal measure enacted to secure revenue for the State on certain classes of instruments: It is not enacted to arm a litigant with a weapon of technicality to meet the case of his opponent. The stringent provisions of the Act are conceived in the interest of the revenue once that object is secured according to law, the party staking his claim on the instrument will not be defeated on the ground of the initial defect in the instrument. Viewed in that light the scheme is clear. Section 35 of the Stamp Act operates as a bar to an unstamped instrument being admitted in evidence or being acted upon; Section 40 provides the procedure for instruments being impounded, sub-section (1) of Section 42 provides for certifying that an instrument is duly stamped,
Aswale 21/31
arp.24.17.doc
and sub-section (2) of Section 42 enacts the consequences resulting from such certification."
(emphasis supplied)
18. In view of the foregoing discussion and with specific
reference to section 11(6-A) of the Act, I am unable to agree with
the submission of Mr. Kamat that this Court cannot refer the
disputes to arbitration because the arbitration clause is contained
in an unstamped document. It is not as if once the Arbitrator is
appointed, the Respondent is precluded from raising the issue of
stamping before the Arbitrator. The Arbitrator, if found that the
document is insufficiently stamped, can always impound the same
and send it to the necessary authorities under the Maharashtra
Stamp Act, 1958 for adjudication. This view of mine would also be
in line with the decision of the Supreme Court in the case of
Hindustan Steel Ltd (supra), which would ensure that the
revenue is secured for the State and at the same time would not
arm the litigant with the weapon of technicality to meet the case of
the opponent. I do not think that by accepting this technical
defence, the Respondent can be allowed to frustrate and delay the
arbitration proceedings. This would clearly be contrary to the
objects and reasons for which the amendments were brought
about to Arbitration and Conciliation Act, 1996 in 2015.
Aswale 22/31 arp.24.17.doc19. Having said this, I shall now deal with the judgments
relied upon by Mr. Kamat. The first decision relied upon by Mr.
Kamat was in the case of SMS Tea Estates Private Limited
(supra). In this case, the facts would reveal that the Appellant
before the Supreme Court requested the Respondent therein to
grant a long term lease in respect of two tea estates. Accordingly,
a lease deed was executed under which the respondent granted a
lease to the Appellant for a term of 30 years. Clause 35 of the said
lease deed provided for settlement of disputes between the parties
by arbitration. As the dispute arose between the parties, as per
Clause 35 of the lease deed, the Appellant issued a notice calling
upon the Respondent to refer the matter to arbitration. This
application was opposed by the Respondent who contended that
the unregistered lease deed was invalid, unenforceable and not
binding upon the parties. The further contention was that the said
lease deed was not duly stamped and therefore invalid,
unenforceable and not binding, having regard to Section 35 of the
Stamp Act, 1899. In these facts, the matter went to the Supreme
Court. Before the Supreme Court, three questions were raised,
namely (i) Whether an arbitration agreement contained in an
Aswale 23/31
arp.24.17.doc
unregistered (but compulsorily registrable) instrument is valid
and enforceable? (ii) Whether an arbitration agreement is an
unregistered instrument which is not duly stamped, is valid and
enforceable? (iii) Whether there is an arbitration agreement
between the appellant and the respondent and whether an
arbitrator should be appointed?
20. Whilst answering the first question, the Supreme Court
inter alia held that when the contract contains an arbitration
agreement, it is a collateral term relating to the resolution of
disputes, unrelated to the performance of the contract. It is as if
two contracts; one in regard to the substantive terms of the main
contract and the other relating to resolution of disputes had been
rolled into one, for the purposes of convenience. The Supreme
Court held that therefore an arbitration clause is an agreement
independent of the other terms of the contract or the instrument.
Resultantly, even if the contract or its performance is terminated
or comes to an end on account of repudiation, frustration or
breach of contract, the arbitration agreement would survive for
the purpose of resolution of disputes arising under or in
connection with the contract. Similarly, when an instrument or
deed of transfer or a document affecting immovable property
Aswale 24/31
arp.24.17.doc
contains an arbitration agreement, it is a collateral term relating
to resolution of disputes, unrelated to the transfer or transaction
affecting the immovable property. It is as if two documents, one
affecting the immovable property requiring registration, and the
other relating to resolution of disputes which is not compulsorily
registrable, are rolled into a single instrument. Therefore, even if a
deed of transfer of immovable property is challenged as not valid
or unenforceable, the arbitration agreement would remain
unaffected for the purpose of resolution of disputes arising with
reference to the deed of transfer. The Supreme Court further went
on to hold that having regard to Section 35 of the Stamp Act,
unless the stamp duty and penalty due in respect of the
instrument is paid, the court cannot act upon the instrument,
which means that it cannot act upon the arbitration agreement
also which is part of the instrument. As far as the stamping issue
is concerned, I find that this decision does support Mr. Kamat's
contention. However, I find that this decision has lost its efficacy
after the amendment to Section 11 and more particularly Section
11 (6-A). What I must note is that SMS Tea Estates Private
Limited (supra) was decided on 20th July, 2011 whereas the
amendments to the Arbitration and Conciliation Act, 1996 came
Aswale 25/31
arp.24.17.doc
into effect from 23rd October, 2015. Now, after the amendment
and as held by the Supreme Court in the case of Duro Felguera, S.
A.(supra), under sub-section 6-A of Section 11 the power of the
Court has now been restricted only to examination of the
existence of the agreement and nothing more and nothing less. As
stated earlier, the existence of the arbitration agreement has
never been disputed, and in my view correctly so. This being the
case, I find that the reliance placed by Mr. Kamat on the decision
of the Supreme Court in the case of SMS Tea Estates Private
Limited (supra), is wholly misconceived. Whether the document
is properly stamped or not is an issue that can certainly be
decided by the arbitrator once the matter is referred to
arbitration. It is not as if the arbitrator is powerless to impound
the document if found insufficiently stamped and thereafter
forward to the appropriate authority for adjudication and
recovery of stamp duty. Taking into consideration the purpose for
which the amendments were brought about and especially the
finding given in the 246th report of the Law Commission of India
that India has been ranked at 178 out of 189 nations in the world
for enforcement of contracts, I think this is exactly what the
Legislature intended. In any event, the wording of Section 11(6-
Aswale 26/31 arp.24.17.docA) are clear and unambiguous and leave no real scope for judicial
interpretation.
21. All the other decisions relied upon by Mr. Kamat with
the exception of (Lakdawala Developers Pvt Ltd's case), were
under the Stamp Act and were not with reference to any of the
provisions of the Arbitration and Conciliation Act, 1996. I,
therefore, find that the reliance placed on these decisions is wholly
misconceived.
22. As far as the reliance placed by Mr. Kamat on a
Division Bench Judgment in the case of Lakdawala Developers
Pvt Ltd (supra) is concerned, I find that this judgment also was
passed on 25th June, 2013 which was much prior to the
amendment of the Arbitration and Conciliation Act, 1996 in 2015.
Furthermore, this judgment follows the decision of the Supreme
Court in the case of SMS Tea Estates Private Limited (supra).
What is also important to note is that this decision was not
rendered with reference to Section 11 of the Arbitration and
Conciliation Act, 1996 but was rendered under Section 9 of the
said Act. The facts of this case would reveal that the Respondent
before the Division Bench had filed an application under Section 9
Aswale 27/31
arp.24.17.doc
for certain interim reliefs. In that application, the appellant before
the Division Bench took up the contention that the MOU was
insufficiently stamped and that in consequence, the document
could not be acted upon unless the stamp duty and penalty, if any,
payable thereon was adjudicated upon. The learned Single Judge
held that whether the MOU was insufficiently stamped or not,
could be decided in the arbitral proceedings before the arbitrator
and the arbitration agreement could be delinked from the other
provisions of the MOU so as to enable the Court to grant interim
measures. It is in these circumstances that the Division Bench
held that the view taken by the learned Single Judge was prima
facie contrary to the decision of the Supreme Court in the case of
SMS Tea Estates Private Limited (supra). Apart from what I
have stated with reference to the decision in the case of SMS Tea
Estates Private Limited (supra), I find that this decision is
wholly distinguishable on facts as different considerations would
apply when a party applies for interim measures under section 9
and when it applies for appointment of the arbitrator under
Section 11 of the Arbitration and Conciliation Act, 1996. I,
therefore, find that the reliance placed on this decision also is
wholly misplaced.
Aswale 28/31 arp.24.17.doc23. Before parting, I must also mention that prima facie I
find the argument made by Ms. Nyati that the liability to pay
stamp duty was on the Respondent herein, well founded. The
clause which was relied upon by Ms. Nyati reads thus:-
"ROYALTIES / LICENSES/ MINING PERMITS / OTHER STATUTORY REQUIREMENTS ETC It will be GWRL responsibility to obtain all requisite statutory Licenses/Permits from various Government State/Local Bodies/Authorities (apart from MoEF, CRZ and state pollution control board permissions which are in scope of ICZMP, State Project Management Unit-Odisha being owner), and to pay necessary levies/fees/taxes/duties/royalties (if applicable to GWRL scope of work), costs thereof at their own cost. COMACOE's responsibility will be limited to labour license and maintenance of proper record of such payments and submit the royalty receipts along with each invoice to GWRL."
24. On going through this clause carefully, I am prima
facie satisfied that the liability to pay stamp duty was that of the
Respondent. If the stamp duty, if any, has not been paid by the
Respondent, the Respondent cannot take advantage of its own
wrong and frustrate the arbitration agreement between the
parties. If I was to do that, it would be only adding premium to
dishonesty. Having said this, I must make it clear that these
observations are only prima facie and if the arbitrator finds that
the document is in fact insufficiently stamped, and directs further
Aswale 29/31
arp.24.17.doc
action on the same, it will be for the appropriate authorities to
adjudicate the stamp duty as well as who is liable to pay the same.
For all the foregoing reasons, the following order is passed:-
(a) The Arbitration Petition is allowed. (b) Mr. Mihir Naniwadekar (Advocate) is appointedas a Sole Arbitrator under Section 11 of the
Arbitration and Conciliation Act, 1996 to
adjudicate upon the disputes which have been
arisen between the Petitioner and the
Respondent herein under or in relation to and/or
connected with the sub-contract dated 14th June,
2013.
(c) The Petitioner herein shall file the disclosures of
by the Sole Arbitrator in the Registry as
contemplated under Section 11 (8) r/w Section
12 (1) of the Arbitration and Conciliation Act,
1996 within a period of two weeks from today.
(d) The Sole Arbitrator shall give all further Aswale 30/31 arp.24.17.docdirections with reference to the fees of the
arbitrator and how they are to be paid. All
further directions regarding the filing of the
Statement of Claim and Statement of Defence
and /or counter claim shall be given by the
arbitrator.
The Arbitration Petition is disposed of in the aforesaid terms.
However, there shall be no order as to costs.
(B. P. COLABAWALLA, J.) Aswale 31/31
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!