Citation : 2018 Latest Caselaw 44 Bom
Judgement Date : 4 January, 2018
(1) 34-CA 15424 of 2017 & ors.
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
34 CIVIL APPLICATION NO.15424 OF 2017
IN FAST/39803/2017 WITH CA/15425/2017 IN FAST/39803/2017
1) The State of Maharashtra
Through Collector, Dhule.
2) The Special Land Acquisition Officer-I,
Dhule, Tal. & Dist.Dhule.
3) The Executive Engineer,
Medium Irrigation Project, Dhule ..Applicants
Versus
Onkar Manaji Kokani
Age: Major, Occu.: Agriculture,
R/o.Dapur, Tq.Sakri,
Dist.Dhule. ..Respondents
...
Advocate for Applicants : Mr.A.M.Phule
...
WITH
CA/15426/2017 IN FAST/39834/2017 WITH CA/15427/2017 IN
FAST/39834/2017
WITH
CA/15428/2017 IN FAST/39841/2017 WITH CA/15429/2017 IN
FAST/39841/2017
WITH
CA/15430/2017 IN FAST/39838/2017 WITH CA/15432/2017 IN
FAST/39838/2017
::: Uploaded on - 11/01/2018 ::: Downloaded on - 12/01/2018 00:54:27 :::
(2) 34-CA 15424 of 2017 & ors.
CORAM : M.S.SONAK, J.
DATE : 4.1.2018
ORAL JUDGMENT:-
1) Heard Mr.A.M.Phule, learned AGP for the applicants
in each of these applications.
2) By these Civil Applications, the applicants are
seeking condonation of delay of 1590 days in instituting
appeals against the Judgment and Award dated 4.5.2013
made by the Reference Court enhancing the compensation
awarded to the respondents/claimants.
3) Mr.Phule, learned AGP submits that since the
applicant is impersonal agency, the issue of condonation
of delay may be liberally considered. He submits that
decisions are required to be taken at different levels
and this necessarily resulted in 'some delay'. He
submits that the applicants have good case to succeed on
merits and discretion may be exercised to condone the
(3) 34-CA 15424 of 2017 & ors.
delay. He submits that the explanation furnished in the
Civil Applications constitutes sufficient cause and
therefore, delay may be condoned.
4) Mr.Phule, learned AGP submits that in such matters,
the length of delay is not relevant but what is relevant
is the explanation offered. He relied on the decisions
of the Supreme Court in the cases of N.Balakrishnan vs
M. Krishnamurthy, reported in [1998 (7) SCC 123], and
Collector Land Acquisition vs Mst. Katiji & Ors,
reported in [1987 (2) SCC 107]. For all these reasons,
Mr.Phule, learned AGP submits that this is a fit case for
condonation of delay.
5) In this case, certified copies of the impugned
Judgment and Award dated 4.5.2013 were applied on
4.8.2016 and the same were received on 11.8.2016. There
was absolutely no explanation as to why it took over
three years to apply for certified copy of the impugned
(4) 34-CA 15424 of 2017 & ors.
Judgment and Award, particularly, since it is the case of
the applicants that the Reference Court has enhanced the
compensation almost 17 times i.e. from Rs.750/- per Are
to Rs.13,200/- per Are. In such a situation the least
that was expected was that the certified copies could be
applied for within some reasonable time for examining
whether or not the Award needs to be appealed.
6) In the Civil Applications, there is no explanation
as to why it took three years to apply for certified
copies of the impugned Judgment and Award. After the
certified copies of the Judgment and Award were obtained,
the appeals alongwith condonation of delay have been
instituted only on 8.12.2017 i.e. after a period one year
from the date of receipt of certified copies. The
explanation for this delay is also entirely vague. All
that is stated is that legal opinion had to be obtained
from the Office of the Government Pleader and the
Secretary, Law and Judiciary Department. There are vague
(5) 34-CA 15424 of 2017 & ors.
statements about incomplete documents, non-availability
of typed copies and so on. All such explanations hardly
suffice to explain inordinate delay of almost five years
(1590 days) in instituting all appeals of this nature.
7) The interest of the respondents for getting proper
compensation, whose lands have been acquired cannot be
overlooked. At this point of time, the respondents are
entitled to have the compensation awarded to them left
undisturbed. There is no clarity as to whether till date
the amount determined by the Reference Court has been
paid or not. In all probabilities, such amount has yet
not been paid. It is therefore, possible that only
purpose of instituting these appeals is to seek some
justification for unreasonable delay in payment of
compensation to respondents/claimants. If this is so, it
cannot be said that the applications for seeking
condonation of delay have been made in good faith. In
any case, the cause shown can hardly be said to be
(6) 34-CA 15424 of 2017 & ors.
sufficient cause.
8) Even, applying a liberal standard prescribed in
N.Balakrishnan (supra) and Mst. Katiji (supra), it is not
possible to condone inordinate and unexplained delay
based upon the vague and unjustifiable grounds set out in
these applications. The decision in N. Balkrishnan
(supra) case requires the applicant to demonstrate good
faith before claiming exercise of discretion. The
decision, no doubt, states that the length of delay is
not decisive but the quality of explanation is the
determinative factor. In this case, quality of
explanation is too poor to constitute any sufficient
cause. Mst. Katiji (supra), no doubt, absolves
explanation of each day's delay. However, the
observation does not mean that delay of over five years
is to be condoned as a matter of routine in the absence
of any sufficient cause.
(7) 34-CA 15424 of 2017 & ors. 9) In Pundlik Jalam Patil (Dead) By Lrs. vs. Executive
Engineer, Jalgaon, Medium Project and anr ., reported in
[(2008) 17 SCC 448], the Hon'ble Supreme Court has held
that pursing stale claims and multiplicity of proceedings
in no manner subserves public interest. These public
interest parameters ought to be kept in mind by the
courts while exercising the discretion dealing with the
application filed under section 5 of the Limitation Act.
Dragging the land-losers to courts of law years after the
termination of legal proceedings would not serve any
public interest. Settled rights cannot be lightly
interfered with by condoning inordinate delay without
there being any proper explanation of such delay on the
ground of involvement of public revenue. This serves no
public interest. Though, the State or its
instrumentalities seeking condonation of delay may be
entitled to certain amount of latitude but the law of
limitation is same for citizens and for governmental
(8) 34-CA 15424 of 2017 & ors.
authorities. It would be a different matter where the
Government makes out a case where public interest was
shown to have suffered owing to acts of fraud or
collusion on the part of its officers or agents and where
the officers were clearly at cross purposes with it. In
a given case, if any, such facts are pleaded and proved
they cannot be excluded from consideration. In cases
with which we are concerned, no such facts have been
either pleaded or proved.
10) In Registrar of Companies vs. Rajshree Sugar &
Chemicals Ltd. and ors reported in ., [ 2(2000) 6 SCC 133],
the Hon'ble Supreme Court held that though some latitude
has to be shown to the Government in deciding the
question of delay, that does not give a licence to the
officers of the Government to shirk their responsibility
to act with reasonable expedition.
11) In Esha Bhattacharjee vs. Managing Committee of
(9) 34-CA 15424 of 2017 & ors.
Raghunathpur afar Academy & ors ., reported in 3(2013) 12 [
SCC 649], the Hon'ble Supreme Court has held that an
application for condonation of delay should be drafted
with careful concern and not in a haphazard manner
harbouring the notion that the courts are required to
condone delay on the bedrock of the principle that
adjudication of a lis on merits is seminal to justice
dispensation system. Further, the Hon'ble Supreme Court
has held that an application for condonation of delay
should not be dealt with in a routine manner on the basis
of individual philosophy which is basically subjective.
The increasing tendency to perceive delay as a non-
serious matter and, hence, lackadaisical propensity can
be exhibited in a nonchalant manner requires to be
curbed, of course, within legal parameters.
12) In Postmaster General and Ors. vs. Living Media
India Limited and anr. reported in , [ 4(2012) 3 SCC 563],
the Hon'ble Supreme Court declined to condone the delay
( 10 ) 34-CA 15424 of 2017 & ors.
of 427 days in filing the special leave petition by
observing that department cannot take advantage of
various earlier decisions where a very liberal approach
was adopted when it came to condone delay on the part of
Government agencies. The Hon'ble Supreme Court observed
that the claim on account of impersonal machinery and
inherited bureaucratic methodology of making several
notes cannot be accepted in view of the modern
technologies being used and available. The law of
limitation undoubtedly binds everybody including the
Government. It is the right time to inform all the
government bodies, their agencies and instrumentalities
that unless they have reasonable and acceptable
explanation for the delay and there was bonafide effort,
there is no need to accept the usual explanation that the
file was kept pending for several months/years due to
considerable degree of procedural red-tape in the
process. The government departments are under a special
obligation to ensure that they perform their duties with
( 11 ) 34-CA 15424 of 2017 & ors.
diligence and commitment. Condonation of delay is an
exception and should not be used as an anticipated
benefit for government department. The law shelters
everyone under the same light and should not be swirled
for the benefit of a few. Considering the fact that
there was no proper explanation offered by the Department
for the delay except mentioning of various dates, the
Hon'ble Supreme Court held that, the Department has
miserably failed to give any acceptable and cogent
reasons sufficient to condone such a huge delay.
13) In Basawaraj and anr. vs. Special Land Acquisition
(2013) 14 SCC 81] the Hon'ble Officer, reported in [
Supreme Court went on to observe that the law on the
issue can be summarised to the effect that where a case
has been presented in the court beyond limitation, the
applicant has to explain the court as to what was the
"sufficient cause" which means an adequate and enough
reason which prevented him to approach the court within
( 12 ) 34-CA 15424 of 2017 & ors.
limitation. In case a party is found to be negligent, or
for want of bona fide on his part in the facts and
circumstances of the case, or found to have not acted
diligently or remained inactive, there cannot be a
justified ground to condone the delay. No court could be
justified in condoning such an inordinate delay by
imposing any condition whatsoever. The application is to
be decided only within the parameters laid down by this
Court in regard to the condonation of delay. In case
there was no sufficient cause to prevent a litigant to
approach the court on time condoning the delay without
any justification, putting any condition whatsoever,
amounts to passing an order in violation of the statutory
provisions and it tantamounts to showing utter disregard
to the legislature.
14) The Division Bench of this Court in State of
Maharashtra and ors. vs. Vithu Kalya Govari and ors.,
reported in [ 2008(6) Mh.L.J.239] has observed that the
( 13 ) 34-CA 15424 of 2017 & ors.
State is not expected to be negligent or to take no
action for years and let the matters become time barred
on account of its negligence and inaction. The usual
reason of "official hassle" or "approval at different
levels" is hardly sufficient to justify condonation of
delay of about two years. In law, advantage has accrued
to the non-applicants claimants and the same cannot be
withdrawn in a mechanical manner and that too without any
sufficient cause being shown by the applicants. Despite,
awards/judgments of the Courts, which have attained
finality, the claimants are not permitted to receive
compensation in respect of their lands, which came to be
compulsorily acquired, is itself, sufficient prejudice to
them. Therefore, before any delay can be condoned and
the claimants subjected to further prolonged litigation,
the onus to show sufficient cause lies upon the
applicant-State.
15) Applying the aforesaid principles to the facts and
( 14 ) 34-CA 15424 of 2017 & ors.
circumstances of the present case, it is clear that no
sufficient cause has been shown for condonation of delay
of over four years i.e.1590 days in institution of the
appeals. The Civil Applications are therefore, liable to
be dismissed and are hereby dismissed. There shall be no
order as to costs. As a consequence of dismissal of the
Civil Applications, the Appeals and the Civil
Applications pending therein also stand disposed of.
[M.S.SONAK, J.]
SPT/34-CA 15424 of 2017 & ors.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!