Wednesday, 29, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Shakiloddin Sharfoddin Badgujar vs The State Of Maharashtra And ...
2017 Latest Caselaw 7683 Bom

Citation : 2017 Latest Caselaw 7683 Bom
Judgement Date : 28 September, 2017

Bombay High Court
Shakiloddin Sharfoddin Badgujar vs The State Of Maharashtra And ... on 28 September, 2017
Bench: S.V. Gangapurwala
                                1                                 wp 10573.16

      IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                 BENCH AT AURANGABAD



                    WRIT PETITION NO. 10573 OF 2016

          Shakiloddin Sharfoddin Badgujar,
          Age: 44 Years, Occu.: Agril.,
          R/o.: Mominpura, Kinwat, 
          Tal.: Kinwat, District: Nanded               ..    Petitioner

                   Versus

 1.       State of Maharashtra,
          Through Secretary,
          Urban Development Department,
          Mantralaya, Mumbai - 32

 2.       Director Textile Secretariat,
          Floor, New Central Building,
          Maharashtra State,
          Pune, Tal. and Dist.: Pune

 3.       Director,
          Town Planner, Town Planning Office,
          Pune, Tal. and Dist.: Pune

 4.       District Collector,
          Collector Office, Nanded

 5.       Assistant Director,
          Town Planner, Town Planning Office,
          Nanded, Dist.: Nanded

 6.       Special Land Acquisition officer,
          Land Acquisition Office,
          Nanded, Dist.: Nanded.




::: Uploaded on - 05/10/2017                  ::: Downloaded on - 07/10/2017 00:49:31 :::
                                    2                                  wp 10573.16

 7.       Agricultural Produce Market Committee,
          Kinwat, Tal.: Kinwat,
          District: Nanded,
          Through its President / Secretary

 8.       Municipal Council,
          Kinwat, Tal.: Kinwat, Dist.: Nanded,
          Through its Chief Executive Officer              ..  Respondents

 Shri V. J. Dixit, Senior Advocate h/f Shri L. V. Sangeet, Advocate
 for the Petitioner.
 Mrs. R. P. Gour, A. G. P. for Respondent Nos. 1 to 6.
 Shri Upendra B. Bilolikar, Advocate for Respondent No. 7.
 Ms.   Deepali   S.   Biyani   h/f   Shri   B.   A.   Darak,   Advocate   for
 Respondent No. 8.

                               CORAM  : S. V. GANGAPURWALA &
                                        MANGESH S. PATIL, JJ.
                               DATE      :  28    September, 2017
                                               th




 JUDGMENT (Per S. V. Gangapurwala, J.) :

1. Rule. Rule Returnable forthwith. With the consent of parties taken up for final hearing.

2. Mr. Dixit, learned Senior Advocate for the petitioner submits that petitioner is the owner and possessor of land Gut No. 4/1 to the extent of 40R situated at Kinwat, Taluka - Kinwat. The said land is reserved in the Development Plan sanctioned on 15.2.2002 for the purpose of Market Yard. As no steps were taken for 10 years the petitioner on 26.9.2014 issued a Purchase Notice U/Sec. 49 of the Maharashtra Regional and Town Planning Act, 1966 (hereinafter to be referred as "M.R.T.P.

3 wp 10573.16

Act) to the respondents. After hearing the parties the Purchase Notice was confirmed U/Sec. 49(4) of the M.R.T.P. Act by order dated 6.1.2015. Learned counsel submits that for 1 year thereafter no steps are taken for acquisition. The application is not filed by the Appropriate Authority nor the Planning Authority for acquisition of the said property, as such, in view of Section 49 (7) of the M.R.T.P. Act the acquisition stands lapsed. The petitioner is free to develop the said property.

3. Mr. Bilolikar, learned counsel for respondent No. 7 Agricultural Produce Market Committee submits that, respondent No. 7 requires the writ land for its market yard, there is no other land available. However, because of the weak financial condition of respondent no. 7 steps could not be taken for acquisition. The respondent No. 7 has moved the Government for sanction of grants and the same is being considered. The writ petition be dismissed.

4. We have heard the learned counsel for respondent No. 8 and the learned A. G. P.

5. The following facts are undisputed:

I] The Development Plan is sanctioned on 15.2.2002. II] The land of petitioner to the extent of 40R from Gut No. 4/1 at Kinwat is reserved for Market Yard in the Development Plan.

                                       4                                   wp 10573.16

          III]     Notice   U/Sec.   49   of   the   M.R.T.P.   Act   is   issued   on
          26.9.2014.
          IV]      The respondent No. 3 confirmed the Purchase Notice
          on 6.1.2015.
          V]       Till date no application is made by respondent Nos. 7

or 8 for acquisition of the said property.

6. Considering the aforesaid factual matrix and the fact that no application has been made for acquisition till this date, the provisions of Section 49(7) of the M.R.T.P. Act would come into operation. Section 49(7) of the M.R.T.P. Act reads as under:

"Section 49..............

(7) If within one year from the date of confirmation

of the notice, the Appropriate Authority fails to make

an application to acquire the land in respect of

which the purchase notice has been confirmed as

required under section 126, the reservation,

designation, allotment, indication or restriction on

development of the land shall be deemed to have

lapsed; and thereupon, the land shall be deemed to

be released from the reservation, designation, or, as

the case may be, allotment, indication or restriction

and shall become available to the owner for the

purpose of development otherwise permissible in the

case of adjacent land, under the relevant plan."

5 wp 10573.16

7. In view of the aforesaid provision the Appropriate Authority has failed to make an application to acquire the land within 1 year from the date of confirmation of the notice. The reservation or restriction on development of the land is deemed to have lapsed and the land is deemed to be released from reservation and shall become available to the owner for the purpose of development otherwise permissible in the case of adjacent land, under the plan.

8. In light of the above, Rule is made absolute in terms of prayer clause "A". No costs.

[MANGESH S. PATIL, J. ] [S. V. GANGAPURWALA, J. ]

marathe/sep.17

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter