Citation : 2015 Latest Caselaw 446 Bom
Judgement Date : 17 October, 2015
wp1726.13.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
WRIT PETITION NO.1726 OF 2013
Messrs Eminent Agencies and Another ..Petitioners
Vs.
Bank of Baroda and Others ..Respondents
Mr. Dinesh Purandare, Mr Rafeeq Peer Mohideen, Mr T. N.
Tripathi, Ms. Sapna Rachure, for the Petitioners.
Mr. Anant B. Shinde, for Respondent No.1.
CORAM :- S. C. DHARMADHIKARI,J. &
B. P. COLABAWALLA, J.
RESERVED ON :- October 9, 2015.
PRONOUNCED ON :- October 17, 2015.
JUDGMENT :- [Per B. P. Colabawalla, J]
1. This Writ Petition under Article 226 of the
Constitution of India challenges the order dated 28th June, 2013
passed by the Debts Recovery Appellate Tribunal (for short, the
"DRAT") in Miscellaneous Appeal No.184 of 2010. By the
impugned order, the Appeal filed by the Petitioners was dismissed
by the DRAT.
Aswale 1/14
wp1726.13.doc
2. The brief facts giving rise to the present controversy
are that, Respondent No.1 - Bank granted various facilities to
Petitioner No.1 in the year 1999. The credit facilities availed by
the Petitioners were secured by an equitable mortgage of three
properties situated at Andheri(E) and Vasai, District Thane.
These properties were owned by Mr. Jujee A. Poonawala, Mr. Moiz
A. Poonawala and Fatima M. Baxamusa, the guarantors of
Petitioner No.1.
3. In view of the fact that Petitioner No.1 failed to pay its
dues, the Respondent Bank filed an Original Application before the
Debt Recovery Tribunal (for short, the "DRT") being Original
Application No.389 of 2002. This Original Application was filed
against Petitioner No.1, its partners and the guarantors.
Petitioner Nos.1 and 2 herein contested the Original Application
while the guarantors and other partners of Petitioner No.1 did not
contest the same.
4. During the pendency of this Original Application, on 9th
June, 2006 Petitioner No.1 submitted a compromise/settlement
proposal in the sum of Rs.65.77 lacs. This proposal was duly
Aswale 2/14
wp1726.13.doc
accepted by the Respondent Bank on the terms and conditions set
out in its letter dated 26th June, 2006. Despite the Respondent
Bank giving several opportunities and extensions to settle their
entire dues for a sum of Rs.65.77 lacs, admittedly, the Petitioners
defaulted in adhering to the terms and conditions of the said
settlement proposal. In these circumstances, the Original
Application filed by the Respondent Bank was proceeded with, and
by an order dated 20th November, 2008 this Original Application
was allowed and the Petitioners were directed to pay to the
Respondent Bank a sum of Rs.87,48,616.06/- together with simple
interest @ 10% per annum from the date of filing of the Original
Application till payment. A Recovery Certificate was also issued
accordingly.
5. After the aforesaid Original Application was decreed in
favour of the Respondent Bank, the Petitioners once again, on 19th
December, 2008 approached the Respondent Bank and submitted
a proposal to settle the matter for a sum of Rs.75 Lacs. This
proposal was accepted by the Respondent Bank and the same was
duly communicated to the Petitioners by letter dated 16th
February, 2009. The terms and conditions of this settlement inter
Aswale 3/14
wp1726.13.doc
alia provided that (a) Rs.50 lacs would be payable within 10 days
of sanction and the documents in respect of one of the mortgaged
properties (in the name of Mr Abbasbhai Poonawala) would be
released; and (2) the balance amount of Rs.25 lacs would be
payable on or before 28th February, 2009 and thereafter, the
documents in respect of the mortgaged property in the names of
Mr Moiz A. Poonawala and Mr Jujer A. Poonawala would be
released.
6. Admittedly, the Petitioners could not adhere to the
time frame set out in the said letter. Despite this, vide its letter
dated 10th June, 2009 the Respondent Bank gave one more
opportunity to the Petitioners to pay the amount of Rs.75 lacs,
failing which the Petitioners were informed that it would take over
possession of the mortgaged properties and recover its dues.
Since the payment was not made, the Respondent Bank vide its
letter dated 25th June, 2009 informed the Petitioners that it had
withdrawn the compromise proposal as they have failed to abide
by the terms and conditions of the settlement.
7. In view of the fact that the Petitioners did not pay the
Aswale 4/14
wp1726.13.doc
settlement amount within the stipulated period, the Recovery
Officer proceeded to execute the Recovery Certificate issued in
favour of the Respondent Bank to recover the decretal amount.
Accordingly, the Recovery Officer on 30th April, 2010 published a
sale notice in the newspaper (Free Press Journal) fixing 31st May,
2010 as the date for conducting the sale of the mortgaged
properties. The auction sale was accordingly conducted on the said
date. It is not disputed that these mortgaged properties have been
sold in the public auction for an amount of Rs.52,00,000/- and
37,50,000/- respectively to the auction purchaser and the sale has
been confirmed in their favour.
8. In the meanwhile, the Petitioners on 24th May, 2010
filed Miscellaneous Application No.101 of 2010 under Section
19(25) of the Recovery of Debts Due to Banks and Financial
Institutions Act, 1993 (for short, "the RDDB Act, 1993") before
the DRT inter alia praying that the Respondent Bank be ordered
and directed to accept the balance OTS amount of Rs.64.50 lacs
together with interest at the rate of 10% p. a. from 16th February,
2009 or such other rate as the DRT deems fit. In other words, by
the said Miscellaneous Application, the Petitioners sought
Aswale 5/14
wp1726.13.doc
enforcement of the settlement proposal dated 19th December,
2008. This Miscellaneous Application was heard by the DRT-III,
Mumbai and by its detailed order dated 26th July, 2010 dismissed
the same.
9. Being aggrieved by the aforesaid dismissal, the
Petitioners preferred Miscellaneous Appeal No.184 of 2010 before
the DRAT, Mumbai. The DRAT also, by an elaborate and reasoned
order dated 28th June, 2013 dismissed the Petitioners' Appeal. It
is in these circumstances the Petitioners are before us questioning
the validity and legality of the order dated 28th June, 2013 passed
by the DRAT in Miscellaneous Appeal No.184 of 2010.
10. In this factual background, Mr Purandare, learned
counsel appearing on behalf of the Petitioners submitted that the
OTS proposal given by the Petitioners to the Respondent Bank was
a bonafide one and the Petitioners could not adhere to the time
schedule of the said OTS as there were genuine difficulties in
raising the money in time. He submitted a chart inter alia
indicating how the payments have been made, though belatedly,
and therefore as per the OTS, only an amount of Rs.99,690.08 was
Aswale 6/14
wp1726.13.doc
outstanding as on 9th October, 2015. The Petitioners, having
shown their willingness to pay interest for the delayed period, no
prejudice was likely to be caused to the Respondent Bank, was the
submission of Mr Purandare. In these circumstances, he
submitted that the DRT ought to have directed the Respondent
Bank to accept the OTS amount by extending the time and not
recover the amounts in terms of the judgment and order dated
20th November, 2008 passed in Original Application No.389 of
2002.
In light of the facts highlighted above, according to Mr
Purandare, the DRT and the DRAT, had both gone wrong in
dismissing the Miscellaneous Application as well as the Appeal of
the Petitioners which require our interference under Article 226
of the Constitution of India.
11. On the other hand, Mr Shinde, learned counsel for the
Respondent Bank, sought to support the impugned order on all
counts. He firstly submitted that the Petitioners are guilty of
suppression in as much as, the Petitioners in their Miscellaneous
Application filed before the DRT, did not disclose the first
settlement proposal submitted by them in the year 2006.
Admittedly, the Petitioners do not adhere to the aforesaid
Aswale 7/14
wp1726.13.doc
settlement proposal and it was in these circumstances, that the
Original Application filed by the Respondent Bank came to be
allowed and the Petitioners were directed to pay a sum of
Rs.87,48,616.06/- to the Respondent Bank with simple interest
calculated at the rate of 10% p. a. from the date of the Original
Application till payment. After the Original Application was
decreed in favour of the Respondent Bank, the Petitioners once
again approached the Respondent Bank for settling its dues and
submitted the Settlement Proposal dated 19th December, 2008. In
the said proposal, the Petitioners agreed to pay a sum of Rs.75
lacs. Even the time frame set out in this settlement proposal was
not adhered to by the Petitioners. It is in these circumstances,
that the Recovery Officer proceeded to execute the Recovery
Certificate and has in fact sold the mortgaged properties in favour
of the auction purchasers and recovered the amounts. According
to Mr Shinde, even after giving credit of all monies paid by the
Petitioners as well as the monies received from the sale of the
mortgaged properties, there is still an amount of
Rs.1,07,83,232.06/- outstanding as on 22nd August, 2013. In
these circumstances, Mr Shinde submitted that enough
indulgence has been shown to the Petitioners and it is too late in
Aswale 8/14
wp1726.13.doc
the day for them to contend that the Respondents be ordered and
directed to accept the amounts as per the settlement proposal
dated 19th December, 2008 together with interest at the rate of
10% p. a. from 16th February, 2009 till payment. He, therefore,
submitted that there was no merit in this Writ Petition and the
same ought to be dismissed with costs.
12. With the help of the learned counsel, we have perused
the papers and proceedings in this Writ Petition along with the
impugned order dated 28th June, 2013. At the out set, we must
mention that even though several authorities/decisions are
referred to in the Writ Petition, apart from the above argument, no
other argument was advanced on behalf of the Petitioners and
neither were any of these authorities/decisions cited before us. It
is in these circumstances, that we have not been called upon to
deal with the same.
13. Having said this, we shall now deal with the arguments
as canvassed by Mr Purandare. The facts of this case clearly
reveal that in the year 2006 (and while the Original Application
was pending) the Petitioners approached the Respondent Bank,
Aswale 9/14
wp1726.13.doc
with a settlement proposal to pay a sum of Rs.65.77 Lacs. This
proposal was accepted by the bank vide its letter dated 26th June,
2006 which envisaged that the Petitioners pay a sum of Rs.65.77
lacs towards full and final settlement of its dues on the terms and
conditions set out therein. The terms and conditions inter alia
stipulated that the settlement amount would be paid in the
following manner:- (a) 10% of the settlement amount on or before
28th June, 2006; (b) another 10% of the settlement amount on or
before 15th July, 2006; and (c) the balance 80% would be paid in
17 equal monthly installments of Rs.2.93 lacs and the 18th
installment would be of Rs.2.85 lacs. The first installment was due
on 15th August, 2006 and so on.
14. Admittedly, the Petitioners failed to deposit 10% of the
settlement amount on or before 28th June, 2006. The Petitioners
therefore approached the Respondent Bank and sought time to
deposit the amount up to 5th July, 2006 which was allowed by the
Respondent Bank. Even then, the Petitioners did not pay the
aforesaid amount. Thereafter, on 13th July, 2006 the Respondent
Bank addressed another letter to Petitioner No.1 calling upon
them to deposit the amount of Rs.13.15 lacs on or before 15th July,
Aswale 10/14
wp1726.13.doc
2006. It was informed to the Petitioners that in case they fail to
deposit the aforesaid amount, it would be treated as a default as
per the terms and conditions of the settlement proposal. It is not
in dispute that the Petitioners could not pay any amount despite
seeking extension of time from the bank. It was in these
circumstances that this settlement of 2006 was withdrawn and
the Original Application was proceeded with and a decree in the
sum of Rs.87,48,616.06/- came to be passed.
15. Be that as it may, we find that even the second
settlement proposal dated 19th December, 2008 (in the sum of
Rs.75 Lacs) has not been adhered to by the Petitioners. This
settlement proposal clearly stipulated that Rs. 50 lacs would be
paid within 10 days of sanction of the said proposal and the
balance 25 lacs would be paid on or before 28th February, 2009.
The only amount paid was a sum of Rs.10 lacs on 3rd June, 2009.
Despite this, the Respondent Bank, vide its letter dated 10th June,
2009 informed the Petitioners that they could pay the entire
settlement amount immediately without any further delay. It was
further informed that in case the Petitioners fail to pay the
settlement amount, the Respondent Bank would take over
Aswale 11/14
wp1726.13.doc
possession of the secured assets to recover its dues. Thereafter,
further extensions were granted by the Respondent Bank to
Petitioner No.1 to make the payments as per the settlement
proposal dated 19th December, 2008. Despite this, the payments
were not made as per the extensions granted. The details of these
extensions have been elaborately set out in paragraphs 28 and 29
of the impugned order and in view of the fact that what is stated
therein is undisputed, we did not think it necessary to reproduce
the same once again in this judgment.
16. Looking to the totality of the facts of this case and as
narrated above, it is clear that the Respondent Bank had taken a
very lenient view in the matter. Despite several extensions being
granted to the Petitioners, they failed to deposit/pay the
settlement amount to the Respondent Bank. In this view of the
matter, we do not think that the DRT or the DRAT can be faulted
in dismissing Miscellaneous Application No.101 of 2010 or
Miscellaneous Appeal No.184 of 2010 respectively. The DRT as
well as the DRAT have passed detailed reasoned orders
considering the arguments of the Petitioners including the
judgments/decisions on which reliance was placed. After
Aswale 12/14
wp1726.13.doc
considering all the arguments, the DRT and the DRAT dismissed
the Miscellaneous Application as well as the Appeal of the
Petitioners. On going through these orders, we do not think that
they suffer from any patent illegality and/or perversity that would
persuade us to interfere in our extraordinary, equitable and
discretionary jurisdiction under Article 226 of the Constitution of
India. We do not think that in the facts of the present case, justice
lies on the side of the Petitioners for us to interfere with the
impugned orders.
17. Before parting, we must mention here that we
seriously doubt whether the DRT had jurisdiction to entertain the
prayer sought for by the Petitioners in Miscellaneous Application
No.101 of 2010. In the said Application, the Petitioners, in effect
sought enforcement of the settlement proposal dated 19th
December, 2008. In view of the fact that the DRT had already
decreed the Original Application filed by the Respondent Bank, it
had become functus officio and therefore we seriously doubt that
at the instance of the debtor such a Misc Application seeking
enforcement of the settlement proposal dated 19th December,
2008 could have been entertained by the DRT under section
Aswale 13/14
wp1726.13.doc
19(25) of the RDDB Act, 1993. However, since this issue was
neither argued nor raised by the parties, we leave this point open
to be considered in an appropriate case.
18. In view of our discussion earlier, we find no merit in
this Writ Petition. It is accordingly, dismissed. However, in the
facts and circumstances of the case, we leave the parties to bear
their own costs.
( B. P. COLABAWALLA, J.) (S. C. DHARMADHIKARI, J.)
At this stage, Mr Tripathi prays that the ad-interim order passed
in this Petition be continued so as to enable the Petitioners to take
appropriate steps including challenging this order in a higher
court. This request is opposed by Mr. Shinde on behalf of the
Secured Creditor-Respondent No.1 - bank. After having heard
both sides on this point, we are of the view that taking into
account the conduct of the Petitioners in not abiding by all the
opportunities to compromise and settle the 1st Respondent's claim,
this request cannot be granted. The request is therefore refused.
( B. P. COLABAWALLA, J.) (S. C. DHARMADHIKARI, J.)
Aswale 14/14
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!