Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Housing Society Ltd. vs Maharashtra Airport Development ...
2013 Latest Caselaw 236 Bom

Citation : 2013 Latest Caselaw 236 Bom
Judgement Date : 29 November, 2013

Bombay High Court
Housing Society Ltd. vs Maharashtra Airport Development ... on 29 November, 2013
Bench: R.D. Dhanuka
                                            .. 1 ..                             ARBPL-1999/13


                                IN THE HIGH COURT OF JUDICATURE AT BOMBAY.




                                                                                     
                                       ORDINARY  ORIGINAL CIVIL JURISDICTION  
     




                                                             
                                    ARBITRATION PETITION (L)NO.1999 OF 2013
       
                            
    Chaurangi Builders & Developers




                                                            
    Pvt. Ltd. 
    Formerly known as Reatox Builders
    & Developers Pvt. Ltd.
    A company incorporated under the provisions 




                                               
    of the Companies Act, 1956, having its 
    registered office at 3/341, 1A, Rajiv Co-operative
                                 
    Housing Society Ltd., Bandra-Kurla Complex, 
    Bandra (East), Mumbai-400 051.                               ...  petitioner. 
                V/s.
                                
    Maharashtra Airport Development Company
    Ltd. (MADC) 
    A company incorporated under the provisions of 
    Companies Act 1956 and having its registered 
          


    office at 8th floor, World Trade Centre, Cuffe Parade,
    Mumbai 400 005.                                                  ... respondent. 
       



    Mr R. S. Apte, Senior Advocate a/w Ms Najakiyo i/b P.M.Havnur for petitioner. 
    Mr D. J. Khambatta, Senior Advocate a/w I. J. Nankani, H. S. Khokawala, 





    Rahul Totla i/b M/s Nankani & Associates for respondent. 

                                       CORAM :  R.D.DHANUKA  J.
                                       DATED  :  NOVEMBER 29, 2013. 





    JUDGMENT :                

By this petition filed under Section 37(2)(b) of the Arbitration and

Conciliation Act 1996 (hereinafter referred as "Arbitration Act" for short)

petitioner seeks to impugn the order dated 12th November 2013 passed by the

Asmita 1/53

.. 2 .. ARBPL-1999/13

learned arbitrator rejecting the application filed by the petitioner under Section

17 of the Arbitration Act. Some of the relevant facts which emerge from the

pleadings and documents filed by both the parties are summarized as under :

2. (a) On 24 June 2005, respondent published a tender notice in the

newspaper for development of a modern township of MIHAN and invited offers

from the experienced developers for development of a modern township to

meet housing requirement of MIHAN. Vide notification dated 29 th May 2007,

the Ministry of Commerce and Industries, Government of India notified

MIHAN as Special Economic Zone (SEZ) pursuant to the provisions of the SEZ

Act 2005.

(b) On 22 September 2005, M/s Reatox Builders and Developers

who had submitted their bid @ Rs.72 lacs per acre was selected as successful

bidder for development of the modern township. A letter of intent came to be

issued in favour of the said builder. On 6 January 2006 the respondent

specified the details of land to be allocated to the said builder. On 2 March

2006, the said builder paid the first installment towards land cost of

Rs.4,46,40,000/- for 31 acres of land to the respondent. On 17 April 2006 the

respondent issued No Objection Certificate (NOC) for development of the said

township subject to final approval of all plans and necessary permissions from

Asmita 2/53

.. 3 .. ARBPL-1999/13

the Planning Authority and all other approvals to be obtained from the

competent authorities. On 26 April 2006, M/s Reatox Builders and Developers

came to be incorporated as a private limited company viz., Reatox Builders &

Developers Pvt. Ltd. On 23 May 2006, respondent issued a Certificate of

Confirmation for allocation of 31 acres of land and confirmed the schedule of

the land. On 9 June 2006 Airport Authority of India (Airport Authority of

India) approved height up to 61 meters for the buildings in the modern

township. On 22 June 2006, respondent entered into development agreement

for development of the modern township with the appellant. Name of M/s

Reatox Builders and Developers Pvt. Ltd. was changed with the new name M/s

Chaurangi Builders and Developers Pvt. Ltd., the appellant herein. The

Terms and Conditions of the development agreement were recorded in the said

agreement entered into by and between the parties. It is the case of the

appellant that the appellant obtained financial assistance by way of working

capital limit of Rs.20 crores from bank/financial institute on 28 th December

2006 and created security interest in favour of the bank/financial institute

interalia over the said land of 31 acres. respondent gave counter guarantee

of Rs.20 crores in respect of the said land to be developed by the petitioner.

On 30 March 2007, respondent issued a commencement certificate for

construction of buildings up to 18 floors on the basis of approved height of

Asmita 3/53

.. 4 .. ARBPL-1999/13

61 meters sanctioned by Airport Authority of India. Appellant paid second

installment of Rs.4,46,40,000/- on 24 April 2007 to the respondent towards

land cost/development fee.

(c ) On 29 May 2007, Ministry of commerce & Industry,

Government of India issued a notification notifying MIHAN as Special

Economic Zone (SEZ) which undertook authorized operation to develop in

non-processing area of SEZ for the residential modern township projects

including the said land of 31 acres allotted to the petitioner in the SEZ

entailing compliance of SEZ norms for the development of the said land. On

24 August 2007 respondent executed Power of Attorney in favour of the

appellant to do various acts in connection with the said land including to sell,

dispose of, assign, transfer nominate and/or alienate in any manner

whatsoever, all and singular tenement/apartments, flats, parking spaces, shops

in the modern township. On 16 August 2007, Ministry of Commerce &

Industry, Department of Commerce granted approval to the petitioner in

respect of the multi product SEZ including construction of 2082 flats subject

to compliance of procedure in terms of SEZ Act 2005 and Rules of 2006.

Appellant paid third installment to the respondent on 26 December 2007 in the

sum of Rs.4,46,40,000/-.

    Asmita                                                                                            4/53





                                                .. 5 ..                              ARBPL-1999/13


(d) It is the case of the appellant that since the respondent did not

consider the proposed second runway in MIHAN, petitioner was requested to

obtain height clearance from Airport Authority of India on account of proposed

second runway. It was necessitated in view of the anticipated reduction of

height of the buildings. It is the case of the appellant that vide letter dated 4 th

March 2008, appellant informed the respondent that the appellant would not

be able to adhere to the time schedule stipulated in the development

agreement and requested for extension of time for completion of the project.

On 3 April 2008 respondent agreed to allocate additional land of 11.644 acres

to the petitioner @ Rs.80 lacs per acre. It is the case of the petitioner that the

petitioner was not compensated by the respondent in respect of the loss

suffered by the petitioner in view of the reduction of height but the said

allotment was at the prevailing market value. The petitioner agreed to

develop the additional land of 11.644 acres. On 29 April 2008, the petitioner

paid 4th installment to the respondent in the sum of Rs. 4,46,40,000/- for 31

acres of land.

(e) On 12 May 2008, the appellant and the respondent entered into

co-development agreement which entitled the petitioner to identify customers

and unit holders for occupying the units in the project. On 12 May 2008,

petitioner paid a sum of Rs.4,46,40,000/- towards land costs/development to

Asmita 5/53

.. 6 .. ARBPL-1999/13

the respondent in respect of the additional land of 11.644 acres. On 17 th June

2008, the petitioner paid Rs. 2.20 crores towards land costs/development in

respect of the additional land of 11.644 acres.

(f) On 27 October 2008 Airport Authority of India issued height

clearance only up to 43.3 meters thereby reducing the height by 17.7 meters.

On 13 February 2009, the respondent issued second Commencement

Certificate to the petitioner and granted development permission to construct

the buildings with 13 floors with built up area of 213303.560 sq. meters. On

18 November 2009, the petitioner submitted construction schedule for 36

months to the respondent. On 16 February 2010, the petitioner made a

request to the respondent for extension of time to complete the construction

and for adjustment of the balance amount payable by the petitioner towards

land costs/development fee in respect of the two lands against the

consideration/purchase price payable by the respondent to the petitioner in

respect of the Low Income Group (LIG) Units to be constructed by the

petitioner in view of the alleged loss of about Rs.80 crores suffered by the

petitioner owing to the height reduction by the Airport Authority of India. On

29 March 2010, the respondent entered into a development agreement and

further executed Power of Attorney in favour of the petitioner for development

of the additional land of 11.644 acres on the terms and conditions recorded

Asmita 6/53

.. 7 .. ARBPL-1999/13

therein. On 13 July 2010 in the 41 st meeting of Board of Approval on account

of objection from Department of Revenue about sale of residential units of the

township to general public, Board of Approval granted approval for transfer of

authorized portion in the non processing area in favour of co-developer

subject to the condition that condition of sale was removed from the

agreement between the developer and co-developer as well as from Power of

Attorney granted by the respondent.

(g) On 14 July 2010, the petitioner borrowed term loan of Rs.105

crores from the Vijaya Bank for completion of the modern township. The

sanction terms were further modified on 22 nd September and 3rd June 2011.

On 14 July 2010, the respondent executed a Letter of Guarantee (Counder

Guarantee) of Rs.105 crores in favour of Vijaya Bank and permitted the

petitioner to offer the said land of 31 acres and the additional land of 11.644

acres as security to the bank.

(h) On 22 July 2010, the Airport Authority of India revised the

approved height of the buildings in the modern township by increasing the

height from 43.3 meters to 54.3 meters. It is the case of the petitioner that in

the local newspapers at Nagpur an article was published defaming the project

and the petitioner. Objections were raised about the legality of the project by

the local media and such articles published till December 2011. On 24 July

Asmita 7/53

.. 8 .. ARBPL-1999/13

2010, the petitioner and the respondent executed fresh development

agreement for development of 31 acres of land. On 26 July 2010, the

development agreement dated 24 July 2010 was registered with the Sub

registrar of Assurances, Nagpur. On 4 August 2010, the Board of Approvalrd

of approval communicated its decision about removal of condition of sale,

which necessitated correction in the development agreement dated 24 July

2010 by way of replacement of term 'sale' with the term 'lease' which

correction came to be carried out by executing correction deed on 14 August

2010. The said correction deed and fresh Power of Attorney were duly

registered on 17 August 2010. On 23 August 2010 the petitioner obtained

confirmation from the respondent whether the petitioner can lease the flats in

the modern township to general public/persons outside SEZ area anywhere

around the world i.e. for leasing the flat, area/state/country was not restricted.

It is the case of the petitioner that on 30 September 2010 respondent sought to

cancel the allotment of additional land of 11.644 acres to the petitioner and

offered the refund of payment made by the petitioner with interest.

(i) On 27 October 2010, Guidelines came to be issued for

development of Special Economic Zone which restricted sale of units only to

persons related to SEZ. On 24 November 2010 the petitioner submitted

drawings for 16 floors as a result of height revision by Airport Authority of

Asmita 8/53

.. 9 .. ARBPL-1999/13

India as on 13 January 2011. Based on the progress report it is the case of the

petitioner that the petitioner completed the overall physical work of about 34%

in the First City Project.

(j) On 25 March 2011, Board of Approval directed the

Development Commissioner, MIHAN-SEZ to take strict action against the

petitioner for its proposal to sell flats to general public. On 7 April 2011, the

Development Commissioner issued a show cause notice to the respondent for

issuing letter dated 23 August 2010 to the petitioner allowing them to sell the

units to general public/persons outside SEZ. It is the case of the petitioner that

that on 6 June 2011, Vijaya Bank granted its approval for takeover of loan by

Indiabulls and assignment & transfer of the security interest in favour of the

Indiabulls. On 17 June 2011, Indiabulls issued sanction note for sanction of

loan of Rs.155 crores to the petitioner. On 18 June 2011, the petitioner

requested the respondent to give consent to the said takeover of the loan by

Indiabulls and to transfer the existing counter guarantee in favour of

Indiabulls. On 18 July 2011, the respondent addressed a letter to the Deputy

Commissioner, MIHAN-SEZ and confirmed that imposing the provisions of

guidelines on a project that was started much earlier, appeared to be unfair.

On 26 July 2011, Director, Ministry of Commerce & Industry issued a show

cause notice to the respondent for issuing letter dated 23 August 2010 to the

Asmita 9/53

.. 10 .. ARBPL-1999/13

petitioner and calling upon to explain in writing to Board of Approval as to

why the letter of approval granted to them for whole of the area established as

MIHAN-SEZ should not be suspended for a period of one year and why

administrator be not appointed to discharge the function of the Developer.

(k) On 18 August 2011 and 2nd September 2011, petitioner

requested the respondent for consent to Indiabulls and transfer of counter

guarantee of Rs.105 crores to Indiabulls. It is the case of the petitioner that on

13 September 2011 Vijaya Bank certified the construction value of the project

completed so far to be at Rs.213.44 crores. On 14 October 2011, the

repayment schedule of term loan of Vijaya Bank started. On 18 November

2011, petitioner once again requested the respondent to give consent to

Indiabulls for transfer of counter guarantee.

(l) On 2 January 2012, Vijaya Bank conveyed to the petitioner

about the term loan account of Rs.105 crores turning non performing asset

(NPA). On 21st February 2012, the Vijaya Bank issued a notice under Section

13(2) of Securitization and Reconstruction of Financial Assets and

Enforcement of Security Interest, 2002 calling upon the petitioner to pay the

amount due along with interest. On 21 February 2012, the said Vijaya Bank

freezed the account of the petitioner at Mumbai branch. In the month of

February 2012, the said Vijaya Bank invoked counter guarantee submitted by

Asmita 10/53

.. 11 .. ARBPL-1999/13

the respondent for encashment. It is the case of the respondent that the said

Vijaya Bank has frozen the Fixed Deposits of the respondent lying with the said

bank in the sum of Rs.157 crores. The said Vijaya Bank has also filed

proceedings before the Debt Recovery Tribunal against the petitioner and the

respondent in respect of said loan transaction. The petitioner requested the

bank to withdraw the notice vide letter dated 10 April 2012 and by another

letter of even date requested the respondent for giving consent to Indiabulls

and to transfer the counter guarantee. It is the case of the petitioner that on

12 April 2012, the Vijaya Bank granted its approval for takeover of loan by

Indiabulls and assignment and transfer of the security interest in favour of

Indiabulls. It is the case of the petitioner that vide letter dated 18 April 2012,

the Vice Chairman and Managing Director of the respondent forwarded the

proposal to its Chairman for sanction of consent to transfer the counter

guarantee from Vijaya Bank to M/s Indiabulls Financial Services Ltd. This

letter was not on record before the arbitral tribunal and is sought to be relied

upon by the petitioner in this proceedings.

(m) On 23 April 2012, Vijaya Bank issued possession notice to the

petitioner and obtained symbolic possession of the three plots which was

subject matter of the development agreement. On 28 April 2012, the

petitioner requested the Vijaya Bank to restrain from taking any further steps

Asmita 11/53

.. 12 .. ARBPL-1999/13

and to withdraw the notices. On 14 May 2012, respondent issued

termination notice to the petitioner calling upon the petitioner to deposit a

sum of Rs.121 crores with the respondent for payment to the bank within

seven days. On 17 May 2012, petitioner replied to the termination notice.

According to respondent, the petitioner did not give any reply on merits of the

termination notice and did not dispute the correctness of the reasons of

termination notice issued by the respondent. On 18 May 2012, petitioner filed

writ petition (L) No.1414 of 2012 in this Court impugning the termination

notice dated 14 May 2012. The petitioner obtained ex-parte status quo order

by making an application before the vacation Court on 21 May 2012. On 23

May 2012, Vijaya Bank freezed accounts of the petitioner at Nagpur branch.

On 1 June 2012 name of the petitioner was changed from Reatox Builders &

Developers Pvt. Ltd. to Chourangi Builders & Developers Pvt. Ltd.

(n) On 25 June 2012, Division Bench of this Court passed an order

in the writ petition filed by the petitioner that the order of status-quo shall not

prevent either of the parties from issuing notices. On 16 July 2012

respondent addressed two letters both dated 16 July 2012 and terminated

letter of intent dated 22 September 2005, agreement dated 22 June 2006,

Power of Attorney dated 24 August 2007, Agreement dated 24 July 2010,

Correction deed dated 14 August 2010 and Power of Attorney dated 14 August

Asmita 12/53

.. 13 .. ARBPL-1999/13

2010 in respect of 31 acres of land and called upon the petitioner to pay a sum

of Rs.5.96 crores and terminated agreement dated 29 March 2010 and Power

of Attorney dated 29 March 2010 in respect of additional land of 11.644 acres

and called upon the petitioner to pay Rs.3.65 crores. On 21 July 2012,

petitioner replied to two termination letters and denied the allegations. It is

the case of the petitioner that joint meeting was held between the petitioner,

officers of bank and the respondent in which the proposal to regularize term

loan of the bank was discussed.

(o) On 10 September 2012 petitioner submitted a fresh proposal to

Vijaya Bank to regularize the term loan of the bank and to issue fresh sanction

of Rs.155 crores. On 10 December 2012, Vijaya Bank rejected the said proposal

of the petitioner. On 6 May 2013, Division Bench of this Court dismissed writ

petition No.2850 of 2012 as withdrawn and granted liberty to the petitioner to

take recourse to Dispute Resolution Mechanism provided in Clause 19 of the

agreement dated 24 July 2010 and continued ad interim relief for a period of

six weeks from the said date to enable the petitioner to take the appropriate

steps. On 17 May 2013, petitioner filed arbitration petition (L) No.640 of

2013 under Section 9 of the Arbitration Act for interim measures. On 13 May

2013, petitioner invoked arbitration clause under two development agreements

and issued a letter to the learned arbitrator who was named under the

Asmita 13/53

.. 14 .. ARBPL-1999/13

development agreement who agreed to act as sole arbitrator and gave his

consent vide letter dated 15 May 2013. On 31 May 2013 petitioner filed a

statement of claim and application under Section 17 of the Arbitration Act

before the learned arbitrator. On 7 June 2013, learned arbitrator passed an ad

interim order in application filed under Section 17 for a period of six weeks

from 7 June 2013. By an order dated 7 June 2013, then learned arbitrator

recused himself from the arbitration proceedings. On 9 July 2013, this Court

passed an order in arbitration petition (L) No.640 of 2013 and appointed Shri

Justice S. P. Kurdukar, former Judge of Supreme Court as the substituted

arbitrator by consent of parties. Both the parties filed their pleadings before

the learned arbitrator. Learned arbitrator continued the order of status quo

till 19 August 2013. By an order dated 12 November 2013, learned arbitrator

passed a detailed order refusing to grant the interim measures in favour of the

petitioner and rejected the application filed under Section 17 of the Arbitration

Act. Learned arbitrator stayed the operation of said order dated 12 November

2013 till 25 November 2013 and directed the petitioner to issue 48 hours

notice to the respondent before moving this Court for ad interim order or

interim reliefs. Being aggrieved by the said order dated 12 November 2013,

petitioner has filed this appeal under Section 37 of the Arbitration Act.

    Asmita                                                                                         14/53





                                               .. 15 ..                              ARBPL-1999/13


(p) On 25 November 2013, the respondent through the learned

senior counsel made a statement that no further action would be taken

pursuant to the order passed by the learned arbitrator till 28 November 2013.

In view of the difficulties of the learned senior counsel appearing for the

petitioner on 28th November 2013, learned senior counsel for the respondent

extended the statement made by him till 29 November 2013. On 29 November

2013, this Court heard both the learned senior counsel appearing for parties at

length.

3. Mr R. S. Apte, learned senior counsel appearing on behalf of the

petitioner made following submissions :

(a) petitioner has submitted tender on the premise that the height

of the buildings which would be permitted to be constructed on the plots in

question was 61 meters. petitioner had submitted plans accordingly. Height

of a building was however reduced by the Airport Authority of India on 27

October 2008 from 61 meters to 43.3 meters and subsequently increased on 27

February 2010 to 54.3 meters. It is submitted that by virtue of reduction of

such height from 61 meters to 43.3 meters, the petitioner who had proposed to

construct the buildings consisting of 18 floors was required to construct

buildings consisting of 13 floors only. petitioner had entered into various

Asmita 15/53

.. 16 .. ARBPL-1999/13

agreements in respect of the flats proposed to be constructed beyond 13 floors

and had received various amounts from the flat purchasers. In view of the

reduction of height by the Airport Authority of India, several such flat

purchasers were required to be accommodated in the portions from the first

floor to 13th floor. Some of the flat purchasers had cancelled their bookings

which were required to be refunded by the petitioner the amounts paid by

them. It is submitted that the additional land allotted by the respondent to the

petitioner was at market price and not in lieu of the compensation demanded

by the petitioner due to reduction of height by the Airport Authority of India.

(b) It is submitted that there was no reference to SEZ in the first

agreement entered into between the parties. In view of the notification issued

by the SEZ subsequently imposing restriction on sale, their sale of flats

constructed and proposed to be constructed was seriously affected. The

petitioner was informed for the first time on 7 th April 2011 that such decision

was taken by SEZ as far back as on 8 August 2007. There was negative media

campaign against the petitioner during the period between 23 July 2010 and

18 December 2011 which seriously affected the project of the petitioner and

also financially. petitioner had already invested Rs.300 crores and had already

constructed 550 flats which comprise of 34% of the total work awarded. It is

submitted that petitioner was not responsible because of such notification

Asmita 16/53

.. 17 .. ARBPL-1999/13

issued by SEZ which was conveyed to the petitioner for the first time on 7

April 2011 that is much after making huge investments by the petitioner and

completion of about 34% work.

(c ) It is submitted that under the terms of the development

agreement, the respondent agreed to issue counter guarantee in favour of the

Vijaya Bank from whom the petitioner borrowed Rs.105 crores. In view of the

breaches committed by the respondent, petitioner could not complete the

construction and could not sell the flats and could not repay the loan amount

of the Vijaya Bank and as a result thereof the said account with Vijaya Bank

declared the account of the petitioner as NPA. Vijaya Bank also issued notice

under Section 13(2) of the Securitization Act against the petitioner and took

symbolic possession of the plots handed over to the petitioner/developer by

the respondent.

(d) Learned senior counsel then placed reliance on Clause 3.7 of

development agreement and submits that in view of such clause, respondent

could not have created any obstruction against the petitioner from performing

their obligation under development agreement and could not have terminated

the agreements. It is submitted that under clause 19.3 read with Clause 20.1

of the development agreement, no action for termination of development

agreements could be taken by the respondent at all. It is submitted that there

Asmita 17/53

.. 18 .. ARBPL-1999/13

is no provision for termination of development agreements under those

agreements. Claim for damages was not an adequate remedy. The learned

arbitrator has rejected the application under Section 17 contrary to the

provisions of the contract by wrong interpretation of the provisions. It is

submitted that respondent ought to have allowed the petitioner to perform

their part of contract and ought to have issued the counter guarantee in favour

of M/s Indiabulls. Reliance is placed on clause 3.7 which provides for

furnishing counter guarantee by the respondent. It is submitted that since no

counter guarantee was issued by the respondent in favour of Indiabulls though

Vijaya Bank had agreed for transfer of loan, Vijaya Bank took coercive steps

against the petitioner, freezed the accounts of the petitioner, declared the

account of the petitioner as NPA and took symbolic possession of the plots.

(e ) Learned senior counsel submits that in view of the violation of

SEZ norms committed by the respondent, SEZ has issued show cause notices to

the respondent. Learned senior counsel submits that the SEZ withdrew the

embargo only on 28 November 2011. It is submitted that the respondent has

committed fraud upon the petitioner by suppressing the notification issued by

SEZ much earlier and thus termination was bad and illegal on this ground

alone. Learned arbitrator has misunderstood the submissions of the petitioner

regarding allegations of fraud in the impugned order and has not considered

Asmita 18/53

.. 19 .. ARBPL-1999/13

those submissions.

(f) Learned senior counsel placed reliance on a letter/note dated

18 April 2012 annexed at page 907 of the appeal paper book signed by the

Vice Chairman and Managing Director of the respondent to the Chief

Minister/Chairman of the respondent recommending the proposal for

approval. Learned senior counsel submits that under the said proposal, the

Vice Chairman of the respondent agreed that it was worthwhile to consider the

proposal of the petitioner to issue counter guarantee to M/s Indiabulls

Financial Services Ltd., otherwise the respondent was unable to pay Rs.105

crores to Vijaya Bank which shall adversely affect the credibility of the

respondent in the market and would have repurcussion on the image of the

respondent as well as the Government. The learned senior counsel sought to

place reliance upon some of the paragraphs of the said note dated 18 April

2012 in support of his submission that the respondent has suppressed the said

writing though the learned arbitrator had directed the respondent to furnish

inspection of the documents. The said writing was relied upon to submit that

the respondent has committed fraud upon the petitioner. Based on this

writing, learned senior counsel submits that even according to respondent,

respondent would be unable to pay even Rs.105 crores to Vijaya Bank and

thus if petitioner succeeds in arbitration proceedings, petitioner would not be

Asmita 19/53

.. 20 .. ARBPL-1999/13

able to recover any amount from the respondent and thus learned arbitrator

ought to have stayed the termination. It is submitted that the petitioner thus

have good chances of succeeding in their claim for specific performance before

the learned arbitrator and for declaration that the termination effected by the

respondent is totally bad and illegal. Learned senior counsel submits that the

petitioner had applied for copy of the said writing under the provisions of

Right to Information Act and has obtained a copy thereof. Mr Khambatta,

learned senior counsel for the respondent strongly opposed the reliance placed

by the petitioner on this writing on the ground that this writing was not part of

the record before the learned arbitrator and thus cannot be relied upon by the

petitioner in this proceedings for the first time. It is also opposed on the

ground that the said writing is an opinion of the Vice Chairman and admittedly

the said opinion/proposal of the Vice Chairman of the respondent has not been

accepted or approved by the Chairman of the respondent.

(g) Mr Apte, learned senior counsel then submits that the arbitral

tribunal has not considered the entire matter in correct perspective and has

rejected the arbitration application filed by the petitioner without considering

all the relevant submissions made by the petitioner. Learned senior counsel

sought to tender additional affidavit affirmed on 25 November 2013 for

placing certain additional facts on record. Mr Khambatta learned senior

Asmita 20/53

.. 21 .. ARBPL-1999/13

counsel strongly opposes tendering of affidavit at this stage on the ground that

though the said affidavit was affirmed as far back as on 25 November 2013

and the matter was moved by the petitioner before this Court on 25 November

2013, copy thereof was not served upon the respondent which shows the

malafide intention of the petitioner to somehow delay the outcome of this

proceedings. Learned senior counsel objected to this affidavit on the ground

that no new facts can be brought on record in this appeal filed under Section

37 of Arbitration Act for the first time which was not part of the record before

the learned arbitrator.

4. Mr Khambatta learned Senior Counsel appearing for the respondent

made the following submissions :

(a) Letter of intent was issued in favour of the petitioner on

22.9.2005 for development of the modern Township. The petitioner was fully

aware of the notification issued by SEZ. My attention is invited to the Co-

Development Agreements entered into between the petitioner and the

respondent on 12.5.2008 and more particularly recital (f) which records that

the petitioner had been granted formal approval for setting up a multi product

SEZ township by the Ministry of Commerce and Industries, Government of

India vide letter dated 6.11.2006 and by the Government of India, Ministry of

Asmita 21/53

.. 22 .. ARBPL-1999/13

Commerce on 29.5.2007 pursuant to the provisions of Special Economic Zone

Act, 2005. The parties had agreed to develop the plots as per SEZ Act, 2005

and SEZ Rules 2006. Under clause 1.1.1 it was agreed that the said agreement

shall be Co-development agreement along with Annexures attached thereto

and shall include modifications, alterations, additions or deletion thereto made

in the agreement after the date of execution of the said agreement subject to

the provisions of SEZ Act 2005 and SEZ Rules,2006. Clause 2 provided that

the Co-Developer would be entitled to identity the customers for identifying

the plots put up in units which was as per the agreement and subject to

obtaining all necessary permissions required in the meeting of obligations of

the SEZ Act, 2005 and SEZ Rules, 2006. It is submitted that the petitioner was

thus fully aware about their obligations that the lands were covered by SEZ

areas and/or subject to notification issued by the government under the

provisions of SEZ Act and SEZ Rules.

(b) It is submitted that the Airport Authority of India had reduced

the height and thereafter further increased the height of the buildings. The

petitioner continued to work and did not terminate the agreements inspite of

reduction of height by AAI. My attention is invited to the letter dated 3.4.2008

addressed by the respondent to the petitioner allotting additional land which

worked down to11.644 acres to make good the area loss which had taken

Asmita 22/53

.. 23 .. ARBPL-1999/13

place due to change of height on various conditions recorded therein. The

petitioner accepted the allotment of the additional land admeasuring 11.644

acres and was satisfied with the said plot. It is submitted that the petitioner

was thus fully compensated in respect of the area loss due to change of height

by the Airport authority of India and thus could not make any grievance in

respect of reduction of height by the Airport Authority of India. The petitioner

also did not make any further claim nor referred the dispute in respect of the

compensation and accepted the additional plot of land and entered into a

separate agreement in respect thereof. It is submitted that the petitioner has

finally entered into a Final Development agreement in respect of the said

additional plot of land on 29.3.2010 and Final Development Agreement in

respect of 31 acres on 24.7.2010. It is submitted that the petitioner was fully

aware of the restrictions imposed by the SEZ on sale of the tenements when

co-development Agreement was entered into between the parties.

(c) Learned Senior Counsel placed reliance on clause 2.5.1 of the

Development Agreement and submits that the petitioner was obliged to

complete the construction within 24 months from the date of signing of the

power of attorney. It is submitted that even according to the petitioner, till the

month of January, 2011 the petitioner could complete only 34 % of the work.

Since January, 2011 the petitioner had stopped the work on the plot

Asmita 23/53

.. 24 .. ARBPL-1999/13

admeasuring 31 acres and has not commenced any work on the plot

admeasuring 11.644 acres. The learned senior counsel placed reliance on

clause 16 (i) (ii) (v) and (vi) which provides for some of the events of default.

It is submitted that the petitioner had not paid the entire development fee

and/or revenue share payable in accordance with the provisions of the

Agreement. The petitioner committed material breach of the provisions of the

agreement by repudiating the provisions by declaring themselves not to be

bound for enforcement and initiated measures to enforce the counter

guarantee furnished by the respondent and got freezed the fixed deposits of

the respondent lying with Vijaya Bank. The petitioner did not adhere to the

schedule of construction and did not furnish to the respondent the

implementation of plans and programmes which the petitioner was under an

obligation to furnish regularly from time to time. Since the petitioner did not

make any payment to Vijaya Bank the said bank initiated measures under

section 13 (4) of the Securitisation Act by taking possession of the two plots on

23.11.2012 and filed proceedings before the Debt Recovery Tribunal against

the respondent also. The learned senior counsel submits that the respondent

was thus, justified in terminating the Development agreement. The petitioner

did not give any reply controverting the reasons recorded in the termination

letter and gave a very vague and cryptic reply. My attention is invited to clause

Asmita 24/53

.. 25 .. ARBPL-1999/13

7.5 of the Development Agreement which records that the developer shall be

solely responsible for arranging of the funds and shall act in accordance with

the provisions of the Agreement and standards of reasonable and prudent

developer. It is submitted that the respondent was thus not liable to issue a

fresh counter guarantee in favour of Indiabulls.

(d) In so far as the submission of the petitioner that there is no

right of termination provided under the Development Agreement and thus the

termination was bad and illegal on that ground alone is concerned,

Mr.Khambatta learned senior Counsel submits that in view of the events of

default having taking place and since the petitioner did not rectify the

breaches, the respondent was justified in terminating the Development

Agreement. If according to the petitioner the respondent was responsible for

non-compliance of the terms of the contract, even the petitioner could have

terminated the Agreement. It is submitted that power to terminate the

Agreement in case of breach vests under the provisions of the contract Act and

even if there was no specific power in the Development Agreement,it did not

preclude either of the party to terminate the contract in the event of other

party committing breaches. It is submitted that the learned Arbitrator was

thus, right in rejecting the application filed by the petitioner.

    Asmita                                                                                       25/53





                                               .. 26 ..                              ARBPL-1999/13


(e) It is submitted by the learned senior counsel that the petitioner

had proposed that the respondent shall furnish the counter guarantee for 36

months. No work was re-started by the petitioner after January, 2011. The

petitioner was never ready and willing to carry out the work within the

stipulated period of time and even after November, 2011. My attention is

invited to the sanction note dated 17.6.2011 from M/s Indiabulls which

records that the said company had proposed to sanction loan in favour of the

petitioner up to 155 crores in two trenches, the first trench for not exceeding

36 months from the date of first disbursement of the said loan subject to

submission of corporate guarantee by the respondent and subject to mortgage

of the lands of the respondent on which the petitioner was required to carryout

the entire construction. My attention is drawn to the contract provisions which

provides that the petitioner to carry out the entire construction within 24

months from the date of issuance of power of attorney. It is submitted that

thus the respondent was not liable or obliged to issue fresh counter guarantee

on the terms proposed by the petitioner and M/s Indiabulls.

(f) Mr. Khambatta learned senior counsel invited my attention to

the application filed by the petitioner under section 17 of the Arbitration and

Conciliation Act,1996 before the learned Arbitrator and more particularly para

67 thereof. It is the case of the petitioner themselves that in order to

Asmita 26/53

.. 27 .. ARBPL-1999/13

successfully complete the modern township the respondent was obliged to do

various acts such as further extension of time for approval of the project,

renewal of technical approval of the petitioner and the validity for further 10

years, submission of counter guarantee, to afford loan to the project give

consent to transfer and to secure the investors. It is submitted that petitioner's

own pleadings filed before the learned Arbitrator demonstrates that the

petitioner was not ready and willing to comply with their part of the

obligations. The learned senior counsel also invited my attention to the Writ

petition filed in this Court (Writ Petition No.2850 of 2012) by the petitioner

and in particular para 4 in which it is averred by the petitioner that the

petitioner had prepared for all the arrangements for projects and required

various compliance from the respondent that is withdrawal of termination

orders forthwith, renewal of the Development Agreement in respect of 31 acres

and 11.644 acres for next 10 years to complete the project, renewal of fresh

technical approvals having validity up to 10 years, submission of counter

guarantee to the bank for its loan to the project,Execution of tripartite

Agreement etc. Even in the rejoinder filed before the learned Arbitrator the

petitioner contended that the petitioner would require 10 years extention for

completion of the project. Learned senior Counsel submitted that the

petitioner did not terminate the Development Agreement and was thus, bound

Asmita 27/53

.. 28 .. ARBPL-1999/13

to complete the construction as per the Development Agreement and was not

discharged with compliance of their obligations under those two agreements.

(g) The petitioner admittedly has no money and was not in a

position to arrange for any funds, when petitioner stopped construction.

Learned senior counsel submit that in the arbitration proceedings the

petitioner has already quantified the claim of damages in the sum of

Rs.68,69,67,9,188/-. It is submitted that the petitioner cannot seek specific

performance of these agreements. In any event if the petitioner succeeds in

the arbitration proceedings the petitioner would be compensated in terms of

money.

(h) Mr. Khambatta learned Senior Counsel appearing for the

respondent invited my attention to the ad interim order passed by this Court in

Writ Petition No.2850 of 2012 and submits that the said order was obtained by

the petitioner without issuing any notice to the respondent from the vacation

court. Status quo order passed by the vacation court continued from time to

time. He placed reliance on the order passed by this court in Arbitration

Petition (L) No.629 of 2013 between he same parties by which order this Court

has prima facie held that termination of the contract cannot be stayed by this

Court under section 9 of the Arbitration and Conciliation Act, 1996.

(i) The learned Senior counsel placed reliance on the Judgment of

Asmita 28/53

.. 29 .. ARBPL-1999/13

the Supreme Court in COX AND KINGS INDIA LIMITED VS INDIAN

RAILWAYS CATERING AND TOURISM CORPORATION LIMITED reported

in (2012) 7 Supreme Court Cases 587 and in particular para 26 in support of

his submissions that remedy of the petitioner would lie in an action for

damages. Para 26 of the said Judgment of the supreme court in case of COX

AND KINGS LIMITED reads thus :

" It is no doubt true that the petitioner has invested large sums of money in the project, but that cannot entitle it to pray for and obtain a mandatory order of inunction

to operate the train once the lease agreement arrangement had been terminated. We are also unable to accept Mr.Rohatgi's submission that the joint venture agreement was akin to a partnership. Such submission had been rightly rejected by the Division Bench. As rightly pointed out by the Division Bench of the High Court, the petitioner's remedy if

any, would lie in an action for damages against IRCTS for breach of any of the terms and conditions of the Joint venture agreement and the memorandum of understanding. "

(j) Mr Khambatta learned Senior Counsel appearing for the

respondent placed reliance on the Judgment of this Court in case of MAYTAS

INFRA LIMITED vs UTILITY ENERGYTECH AND ENGINEERS PVT.LTD &

ORS 2009 (4) Bom C.R.143 and in particular para 11 thereof in support of his

submissions that the Court cannot compel a party to continue with the

contract. It is difficult for the Court to supervise the performance of the

contract based upon such type of public project. Para 11 of the said Judgment

reads thus :

" The Court cannot compel the respondent to continue with the contract. It is difficult for the court even to supervise such performance of contract, based upon such type of public project,I see there is no material and reason to grant interim injunction as sought

Asmita 29/53

.. 30 .. ARBPL-1999/13

by invoking section 9 of the Act. "

(k) Learned Senior counsel then placed reliance on the Judgment

of this Court in the case of MILAN COMMERCIAL VS ASIAN HEALTHCARE

reported in (2010) 2 Bom.C.R. 295 and in particular paras 56 and 57 in support of

his submissions that in case of a commercial contract if parties had taken a

decision based on commercial wisdom and material available with them and

terminated the contract and enter into a fresh contract the Court cannot

compel such party to continue with the work/project only through the

debarred party. The facet and importance of completion of the project within

the stipulated time just cannot be overlooked. Paras 56 and 57 of the said

Judgment reads thus :

56. " Once in a commercial contract like this, if parties have taken decision based upon the commercial wisdom and material available with them, and terminated the contract and entered into fresh contract, the Court cannot compel such party to continue with the work/project only through the debarred party. The facet and importance of completion of the project within the stipulated time just cannot be

overlooked. The contract, as alleged, if terminated illegally and/or any breach of various clauses the aspect of compensation/damages subject to proof and the evidence need to be kept in mind while considering the case of the plaintiff or the supporting defendants. (Maytas Infra Limited vs Utility Energytech and Engineers Pvt.Ltd & ors) 2009 (4) Bom C.R. 143 (O.S.)

57. " Timely completion of the project was the object of the company and the JVA. The plaintiff just cannot defend/support company's defaults and financial unstability and breaches of the obligations, to claim injunction, interim relief in such fashion. All these factors, in my view goes against the plaintiff and other supporting defendants."

(l) On the issue whether the contract could be terminated though

Asmita 30/53

.. 31 .. ARBPL-1999/13

there was no specific clause under those agreements for termination is

concerned, Mr. Khambatta learned senior Counsel placed reliance on the

Judgment of the Delhi High Court in case of RAJASTHAN BREWERIES

LIMITED VS STROH BREWERY COMPANY reported in AIR 2000 DELHI

450 in para 20 in support of his submissions that even in the absence of

specific clauses the parties could terminate the agreement in the event of

happening of the events specified therein in the contract Para 20 of the said

Judgment reads thus :

20. " Even in the absence of specific clause authorising and enabling either party to

terminate the agreement in the event of happening of the events specified therein from the very nature of the agreement, which is private commercial transaction, the same could be terminated even without assigning any reason by serving a reasonable notice. At the most, in case ultimately it is found that termination was bad in law or contrary to the terms of the agreement or of any understanding between the parties or for any other

reason, the remedy of the appellants would be to seek compensation for wrongful termination but not a claim for specific performance of the agreements and for that view

of the matter learned single Judge was justified in coming to the conclusion that the appellant had sought for an injunction seeking specifically enforce the agreement. Such an injunction is statutorily prohibited with respect of a contract which is determinable in nature. The application being under the provisions of Section 9 (ii) (e) of the Arbitration and Conciliation Act, relief was not granted in view of Section 14 (I) (c) read with

Section 41 of the Specific Relief Act. It was rightly held that other clauses of Section 9 of the Act shall not apply to the contract, which is otherwise determinable in respect of which the prayer is made specifically to enforce the same. "

(m) Mr Khambatta learned senior Counsel for the respondent then

submitted that the petitioner ought to have shown readiness and willingness

all through out from the beginning till the end for seeking specific performance

of the agreement which the petitioner failed to demonstrate before the learned

Asmita 31/53

.. 32 .. ARBPL-1999/13

Arbitrator in these proceedings.

(n) In so far as the internal note dated 18.4.2012 annexed at

Exhibit-N to the Petition, is concerned, it is submitted that the said document

was not relied upon before the learned Arbitrator and cannot be considered by

this Court for the first time. It is submitted that in any event the respondent

did not take any action on the said opinion of the Vice-Chairman which was

for approval of the Chairman of the respondent. No action on the said note

was taken by the respondent. It is submitted that in any event since no decision

was taken and was not conveyed to the petitioner, no reliance on such internal

note can be placed by the petitioner. If the said document would have been

produced by the petitioner before the learned Arbitrator by filing an Affidavit,

respondent could have been given an opportunity to explain the said note.

The petitioner cannot be thus permitted to rely upon the said note which is in

the nature of opinion expressed by the Vice-Chairman of the respondent on

which no action is taken by the respondent. The said proposal given by the

Vice-Chairman does not give any right in favour of the petitioner.

(o) In so far as the proposal regarding counter guarantee in favour

of M/s Indiabulls is concerned, it is submitted by the learned Senior Counsel

that the said proposal had already been rejected by the respondent as far back

as in the month of May 2012.

    Asmita                                                                                        32/53





                                               .. 33 ..                               ARBPL-1999/13


                 (p)     it   is   submitted     that   the   respondent   is   proposing   to   file   a 




                                                                                          

counter claim against the petitioner before the learned Arbitrator. In view of

the defaults committed by the petitioner in not clearing the dues of Vijaya

Bank the said Vijaya Bank has filed proceedings against the petitioner as well

as the respondent before the Debt Recovery tribunal by taking possession of

the lands which was handed over to the petitioner by the respondent for

development. The fixed deposits of Rs.117 crores which was deposited by the

respondent with Vijaya Bank as and by way of security has been freezed by the

said Vijaya Bank. The petitioner thus cannot plead that the respondent did not

have funds to pay to the petitioner their alleged dues.

(q) In so far as the allegation of fraud made by the petitioner

against the respondent are concerned, it is submitted by Mr Khambatta learned

senior Counsel that the petitioner first filed a Writ petition in this Court and

thereafter withdrew the said Petition with liberty to file arbitration proceedings

and got the Arbitrator appointed. In the written arguments filed before the

learned arbitrator the petitioner pleaded fraud and submitted that in view of

such allegations of fraud involved, the matter was required to be referred to

the civil court. It is submitted that the petitioner thus deliberately delayed the

proceedings by raising all sorts of frivolous objections and got the status quo

order continued which is causing serious prejudice to the rights of the

Asmita 33/53

.. 34 .. ARBPL-1999/13

respondent. It is submitted that the learned Arbitrator has thus rejected the

plea of fraud raised by the petitioner.

(r) In so far as the affidavit filed on 25.11.2013 sought to be

tendered by Mr Apte learned senior counsel for the petitioner is concerned the

learned senior Counsel for the respondent strongly protested against tendering

of such an affidavit at this stage. Learned senior counsel pointed out that

though the said Affidavit was affirmed on 25.11.2013 when this matter was on

board, the petitioner deliberately did not serve copy thereof and seeks to

tender the affidavit today, after completion of substantial arguments, with a

view to further delay the outcome of these proceedings and with a view to get

the status quo order continued. It is submitted that in any event this Court

cannot permit the petitioner to rely upon the additional affidavit at this stage.

(s) It is lastly submitted by the learned senior counsel that the

learned Arbitrator has dealt with each and every issue at length and has taken

a prima facie view that the termination cannot be stayed and the order of the

learned Arbitrator being not perverse, this court shall not interfere with such

reasoned order passed by the learned Arbitrator. Mr Khambatta invited my

attention to the findings recorded by the learned Arbitrator in the impugned

order.

    Asmita                                                                                           34/53





                                              .. 35 ..                              ARBPL-1999/13


5. In the rejoinder, Mr Apte learned Senior Counsel appearing for

the petitioner submits that if the petitioner would not have been ready and

willing to comply with their part of the obligations the petitioner would not

have invested more than Rs.300 crores. Since the petitioner has already

invested more than 300 crores and 34 % of the work was already completed it

was not possible for the petitioner to terminate the contract and to come out of

the project. It is submitted that M/s Indiabulls is a registered financial

institution which had already sanctioned substantial amounts of loans but in

view of the respondent refusing to furnish bank guarantee in favour of M/s

Indiabulls the said transaction did not materialise. The counter guarantee

furnished by the respondent in favour of Vijaya Bank is without any time limit.

It is submitted that the respondent has not rejected the proposal of the

petitioner to submit the guarantee in favour of M/s Indiabulls on the ground

that the said company was seeking counter guarantee for a period of 36

months. It is submitted that the petitioner has not abandoned the work. The

meetings were held from time to time between the parties till September,

2012. It is submitted that even today, various investors are ready to purchase

the property and to lend various amounts and the petitioner is ready and

willing to recommence the project. It is submitted that the order thus passed

by the learned arbitrator deserves to be set aside and the status quo order shall

Asmita 35/53

.. 36 .. ARBPL-1999/13

continue till the disposal of the arbitration proceedings.

6. Mr R. S. Apte learned senior Counsel for the petitioner placed

reliance on the Judgment of the Supreme Court in the case of

S.P.CHENGALVARAYANAIDU VS. JAGANNATH reported in AIR 1994

SUPREME COURT 853 in support of his submissions that withholding vital

documents which are relevant to a litigation amounts to fraud on the Court. It

is submitted that since the respondent did not furnish the note submitted by

the Vice Chairman of the respondent which clearly demonstrates breach of the

respondent and their proposal to issue counter guarantee in favour of the M/s

Indiabulls, the said document being vital documents having been suppressed

by the respondent thus in view of such fraud committed by the respondent,

the impugned order be set aside and the learned arbitrator be directed to

consider the said documents of the respondent. In so far as the judgment

relied upon by Mr.Khambatta are concerned, Mr.Apte submitted that those

judgments are not applicable to the facts of this case and are not

impermissible.

7. I have given my anxious consideration to the rival submissions

made by both the learned Senior Counsel.

    Asmita                                                                                         36/53





                                                .. 37 ..                              ARBPL-1999/13


    REASONS AND CONCLUSIONS :




                                                                                          

8. A perusal of the Development Agreements, entered into between

the parties it is clear that the the respondent had proposed to construct a

modern township in order to meet housing requirements of MIHAN and was a

public project. The petitioner was issued a letter of intent. The petitioner was

required to develop the plots of land in accordance with the terms and

conditions recorded in the letter of intent and in the development agreement.

The petitioner was also under obligation to comply with all the provisions of

law and the conditions as may be imposed by the authorities. Airport authority

of India Ltd had approved the height up to 61 meters of the buildings in the

modern townships. Subsequently, the height was reduced by the Airport

Authority of India Ltd from 61 meters to 43.2 meters on 27.10.2008 and

subsequently increased on 27.2.2010 to 54.30ft. The petitioner had made a

claim for compensation in view of the area reduced due to reduction of height

originally permitted. The respondent had considered such representations and

claim of the petitioner. Vide letter dated 3.4.2008 the respondent informed the

petitioner that the respondent had agreed to make the good loss which had

taken place due to change of height on various conditions set out therein. The

petitioner was allotted exact area of land which worked out to 11.644 acres on

payment of Rs.80,00,000/- per acre. The petitioner accepted the said

Asmita 37/53

.. 38 .. ARBPL-1999/13

allotment made by the respondent and entered into the Development

Agreement in respect of that plot on the terms and conditions recorded

therein. The learned Arbitrator has considered this issue at length in para 13

to 15 of the impugned order. The petitioner was fully aware of the topography

of the project and were aware that as the said plot was adjacent to the Airport

at Nagpur, clearance from the Airport Authority of India Ltd was necessary.

9.

It is not in dispute that inspite of reduction of height, the

petitioner accepted the additional plot of land and chose to enter into final

development agreement on 24.7.2010 and second Development agreement on

29.3.2010. The learned Arbitrator has in my view, rightly rendered a prima

facie view that the petitioner could not attribute any delay to the respondent.

The petitioner had with open eyes and with full knowledge that certain

approvals and permissions would be necessary from the Airport Authority of

India Ltd had entered into a Development Agreement on 22.6.2006 as well as

Final Development Agreement dated 24.7.2010 and has thus rightly rejected

the submissions of the petitioner that the delay was attributable on the part of

the respondent due to change of height by the Airport Authority of India Ltd.

10. As far as the submission of Mr.Apte learned senior Counsel for the

Asmita 38/53

.. 39 .. ARBPL-1999/13

petitioner that in view of the restrictions of sale introduced by SEZ during the

execution of the project by the petitioner and in view of the negative media

campaign against the petitioner during the period from 23.7.2010 to

18.12.2011, the respondent not having informed about the notification to the

petitioner the project of the petitioner got effected resulting in financial

problem is concerned, it is not in dispute that the Notification was issued by

SEZ on 29.5.2007. A perusal of the co-development agreement dated

12.5.2008 entered into between the parties clearly indicates that the schedule

lands proposed to be developed operated and maintained by the Co-developer

was under process of SEZ for the township, the developer had been granted

formal approval for setting up of multi-project by the Ministry of Commerce

and Industry, Government of India vide letter dated 6.11.2006 and further

vide letter dated 29.5.2007 pursuant to the provisions of Special Economic

Zones, 2005 authorising the operations and known processing for residential

modern township project. The Co-developer had proposed that he should be

permitted to apply to the board of approval under section 3 (12) of the Special

Economic Zone, 2005. The Board had recognised the petitioner a Co-

Developer. The petitioner was described as the Co-Developer under the said

Co-development Agreement. The respondent was described as the developer.

Thus, it is clear that at least on the date of execution of the co-development

Asmita 39/53

.. 40 .. ARBPL-1999/13

agreement on 12.5.2008 the petitioner was fully aware of the notification

issued by the government.

11. I am inclined to accept the submissions made by Mr.Khambatta

learned senior Counsel for the respondent that the petitioner had knowledge

about the applicability of the provisions of SEZ Act and SEZ Rules and the

notification issued by the Government from time to time which was made

applicable to the agreements entered into between the parties. The petitioner

did not raise any such issue even when the petitioner entered into two final

development agreements on 29.3.2008 and 24.7.2010 in respect of the plots

admeasuring 11.644 acres and 31 acres respectively. The learned Arbitrator

has dealt with this issue in paras 16 to 18 of the impugned order. The learned

Arbitrator has prima facie held that it was made clear to the petitioner about

the status of the land and consequently of the project they had agreed to

complete the project within 24 months. The learned Arbitrator rightly rejected

the contentions of the petitioner that they were not knowing about the SEZ

Rules and such allegations were far from truth and an after thought attempt

and was accordingly rejected. In my prima facie view, the findings of the

learned Arbitrator is correct and no interference is warranted.

    Asmita                                                                                      40/53





                                             .. 41 ..                             ARBPL-1999/13


12. In so far as the submission of Mr.Apte learned senior Counsel for

the petitioner that it was obligation on the part of the respondent to issue a

counter guarantee in favour of the M/s Indiabulls in terms of clause 3.7 is

concerned, it is not in dispute that the respondent had furnished counter

guarantee in favour of Vijaya Bank to secure the loan of Rs.105 crores availed

of by the petitioner. The petitioner committed default in making repayment of

the loan to Vijaya Bank as a result whereof the said Vijaya bank declared the

accounts of the petitioner as non-performing assets and issued a notice under

section 13 (2) of the Securitisation Act. The said Vijaya Bank also invoked the

counter guarantee issued by the respondent in the sum of Rs.105 crores and

freezed fixed deposit of Rs.117 crores which was given as a security to the

Vijaya Bank by the respondent. It is not in dispute that the said Vijaya Bank

has already filed proceedings against the petitioner and the respondent before

the Debt Recovery Tribunal. On perusal of clause 3.7 of the Agreement dated

24.7.2010 it is clear that the counter guarantee required to be furnished by the

respondent was for loan as per approved DPR and approved by the respondent

and such a guarantee was to be valid till end of April 2012 unless further

extended. On a perusal of sanction letter of M/s Indiabulls, it is clear that M/s

Indiabulls had proposed to sanction loans to the petitioner on the condition

that the said loan was to be in two trenches first trench to be for a period of 36

Asmita 41/53

.. 42 .. ARBPL-1999/13

months. According to the said sanctioned note one of the conditions was that

the respondent shall furnish counter guarantee for the sum of the amounts

sanctioned.

13. In my view, Mr.Khambatta learned Senior Counsel appearing for

the respondent is right in his submission that the respondent was not bound to

furnish any counter guarantee on fresh terms and conditions not agreed under

the Development Agreement and also on the ground that the petitioner had

already committed default to Vijaya Bank as a result thereof counter guarantee

already submitted by the respondent was invoked and fixed deposits of Rs.117

crores lying with Vijaya Bank was freezed. On perusal of the pleading filed

before the learned Arbitrator by the petitioner and in the Writ Petition filed in

this Court which was forming part of the record before the learned Arbitrator

and in this court, it is clear that the petitioner wanted to seek various

directions against the respondent. It was averred by the petitioner that the

petitioner would be able to complete the project after various terms and

conditions proposed by the petitioner including the submission of counter

guarantee for a period of 10 years was complied by the respondent. In my

prima facie view, the respondent was right in rejecting the proposal of the

petitioner that the respondent shall submit the counter guarantee in favour of

Asmita 42/53

.. 43 .. ARBPL-1999/13

M/s Indiabulls on the terms and conditions of loan approved by M/s

Indiabulls.

14. A perusal of clause 7.1 of the Agreement indicates that the

petitioner was solely responsible for arranging the funds required for

development in accordance with the provisions of the agreement and in

accordance with the standard of a reasonable prudent developer. The learned

arbitrator has dealt with this issue at length in para 19 to 26 of the impugned

order. The learned arbitrator has taken a prima facie view that the respondent

was justified in exercising their discretion that no counter guarantee be given

afresh in favour of the financial company like M/s Indiabulls and the learned

arbitrator would thus not interfere with the discretion exercised by the

respondent. The learned arbitrator has interpreted clause 3.7 of the

agreement and also clause 7.1 and has rendered a prima facie finding that the

petitioner was responsible for arranging for the funds. The proposal of M/s

Indiabulls was for Rs.155 crores and extension of time for 36 months from the

date of sanction was inconsistent and not compatible with the terms and

conditions entered into between the parties. It is held that no fault could be

found with the respondent. It is held that respondent had committed no

default in carrying out their obligation under the contract. The respondent

Asmita 43/53

.. 44 .. ARBPL-1999/13

cannot be faulted on the ground that they have failed in their obligation under

clause 3.7 by not giving counter guarantee in favour of M/s Indiabulls. In my

view the learned arbitrator has rightly rejected the submissions of the

petitioner and has rightly not interfered with the exercise of discretion by the

respondent in view of the provisions of the Agreement entered into between

the parties. The respondent had already landed into trouble in view of the

petitioner not repaying the loans availed from Vijaya Bank. The respondent in

these circumstances were not expected to issue a fresh counter guarantee and

more particularly on the terms and conditions proposed by M/s Indiabulls and

were justified in rejecting the said proposals. In my prima facie view, the

prima facie findings of the learned Arbitrator is correct and no interference is

warranted with this finding.

15. Next submission of Mr.Apte learned senior counsel for the

petitioner is that the petitioner was discriminated by the respondent by giving

unfair treatment in comparison with other developers who were similarly

situated and who had not completed the work. The Agreement with the

petitioner came to be terminated whereas no action was taken against other

developers. It is not in dispute that the petitioner had already filed a Writ

Petition in this Court impugning the action on the part of the respondent

Asmita 44/53

.. 45 .. ARBPL-1999/13

which Petition was withdrawn by the petitioner with liberty to file arbitration

proceedings.

16. The learned Arbitrator has dealt with this issue in paras 27 to 29

of the impugned order and has rightly rejected this submission upon

considering the Judgment of the Supreme Court in case of INDIA OIL

CORPORATION vs. AMRITSAR GAS SERVICES reported in 1991 (1)

SUPREME COURT CASES 533. In my view, the agreement between the

parties was commercial and Article 14 of the Constitution of India would not

apply for consideration in a contractual matter and the same has to be decided

strictly in accordance with the terms and conditions of the agreement entered

into between the parties and also in accordance with the provisions of Specific

Relief Act, 1963 and Indian Contract Act. There is no merit in the submission

of Mr Apte learned Senior Counsel for the petitioner that action of the

respondent was discriminatory.

17. In so far as the submission of Mr Apte learned Senior counsel that

there was no provision under the agreement entered into for termination of the

agreement and thus the termination of the agreement by the respondent was

illegal and contrary to the provisions of terms of the agreement is concerned it

Asmita 45/53

.. 46 .. ARBPL-1999/13

is not in dispute that clause 16.1.1. of the agreement provides for events of

default. The petitioner did not pay the development fees, revenue share

payable to the respondent in accordance with the provisions of the agreement.

The petitioner had abandoned the work by themselves repudiating the

contract. No work has been carried out admittedly by the petitioner since

January 2011. The petitioner did not adhere to the schedule of construction

and did not furnish to the respondent implementation plan and progress

report. In view of the default of the petitioner in making repayment to Vijaya

Bank the counter guarantee furnished by the respondent came to be invoked

and fixed deposits of the respondent in the sum of Rs.117 crores lying with

Vijaya Bank came to be freezed. The project came to a standstill since January

2011. The petitioner has no funds in hand and could not get any other

arrangement. The petitioner was demanding fresh terms and conditions for

completing the project from the respondent.

18. In these circumstances, in my prima facie view, the respondent

was justified in terminating the contract. In my view, even though there is no

provision in the contract entered into between the parties permitting either

party to terminate the contract, since events of default on the part of one party

had already occurred, other party is entitled to terminate the contract under

Asmita 46/53

.. 47 .. ARBPL-1999/13

the provisions of the Indian Contract Act. If the submission of Mr.Apte

learned Senior Counsel is accepted, in the absence of specific clause permitting

either of the party to terminate the contract even if breaches are committed is

accepted, no contract can be terminated even if one party has committed

breach and the other party would have to continue his contractual rights. In

my view, in such a situation, the provisions of the Indian Contract Act would

be attracted. In my prima facie view, the respondent was thus justified in

terminating the contract. I am in agreement with the view expressed by the

Delhi High Court in case of Rajasthan Breveries Ltd. (supra).

19. The learned srbitrator has dealt with this issue in paras 30 and 31

of the impugned order and has rendered a prima facie finding that the

petitioner is neither ready nor willing to perform their part of the contract due

to financial difficulties and it was difficult to expect that the petitioner would

complete the project as per the Development Agreement and the respondent

has thus taken into account various circumstances relating to default on the

part of the petitioner and has rightly terminated the said agreements. In my

view, the learned Arbitrator has rightly come to such a prima facie conclusion

based on the documents placed on record and interpretations of the terms and

conditions. No infirmity can be found in the findings rendered by the learned

Asmita 47/53

.. 48 .. ARBPL-1999/13

arbitrator.

20. In paras 32 to 37 of the impugned order, the learned arbitrator has

considered the issue of readiness and willingness on the part of the petitioner

to perform the development agreement at length. The learned Arbitrator has

adverted to the judgment of the Supreme Court in case of His Holiness

Ganesh Acharya reported in 1996 (4) SCCs 5266 and judgment of COX AND

KINGS INDIA LIMITED VS. INDIAN RAILWAYS CATERING AND TOURISM

CORPORATION LIMITED reported in 2012 (7) Supreme Court Cases 587

and has rightly held that termination cannot be stayed. The learned Arbitrator

has followed the supreme court judgment in case of His Holiness Ganesh

Acharya (supra) in which it is held that readiness means capacity of a party to

perform a contract which includes his financial position to pay the purchase

price.

21. In my prima facie view, the petitioner was not ready and willing to

comply with their part of the obligation. The petitioner has not carried out any

work since January 2011. Even according to the petitioner they have

completed only 34 % work. The petitioner has no funds and their accounts

with Vijaya Bank are already freezed and Vijaya Bank has already taken

Asmita 48/53

.. 49 .. ARBPL-1999/13

symbolic possession of the lands on which the development was to be carried

out by the petitioner. In my prima facie view, the learned Arbitrator was right

in rejecting the Arbitration Application to stay the termination notice. No

infirmity can be found with the conclusions drawn by the learned Arbitrator.

I am in agreement with the view of the learned single Judge of this court in

case of Maytas Infra Ltd (supra) that court cannot compel a party to continue

with the contract.

22. In so far as the issue of fraud canvassed by Mr.Apte learned senior

Counsel for the petitioner is concerned, a perusal of the record indicates that

allegations are made in the rejoinder before the Arbitral Tribunal. In the

written arguments filed before the learned arbitrator, it was urged by the

petitioner that in view of the serious allegations of fraud, the matter is required

to be referred to a civil Court for adjudication. The petitioner sought liberty to

withdraw Writ Petition and to file arbitration proceedings. No such plea was

raised by the petitioner while obtaining leave to withdraw the Writ Petition.

After filing of the arbitration proceedings, the petitioner raised the issue of

fraud to be referred to the civil court. The learned arbitrator has dealt with

this issue at length in paras no. 41 to 44 of the impugned order. The learned

arbitrator in my view has rightly rejected the submission of the petitioner

Asmita 49/53

.. 50 .. ARBPL-1999/13

regarding allegation of fraud. No such plea could be raised for the first time in

rejoinder. The learned arbitrator also considered the fact that there was no

specific pleading relating to fraud and misrepresentation and cheating in the

statement of claim and thus could not be permitted. In my view the learned

Arbitrator is right in rejecting the plea of fraud and no infirmity can be found

with the impugned order on this issue. Conduct of the petitioner would

indicate that such a plea was raised out of frustration.

23. As far as internal note relied upon by the petitioner for the first

time is concerned it is not in dispute that the petitioner had not relied upon

any such document before the learned arbitrator. By such note submitted by

the Vice Chairman of the respondent to the Chairman expressing his opinion

and sought approval. Such a proposal has not been neither accepted by the

respondent nor any decision thereon was conveyed to the petitioner. In my

view, since no action was taken by the respondent on such note, no

cognizance could be taken of such opinion/note/proposal for seeking approval.

In my view, Mr Khambatta learned Senior counsel appearing for the

respondent is right in his submission that if the petitioner would have

produced such note before the learned arbitrator on an affidavit, the petitioner

would have opposed production of such a writing being taken on record or in

Asmita 50/53

.. 51 .. ARBPL-1999/13

any event would have explained the so called admission in such writing on the

part of the respondent before the learned arbitrator. In my view, this court

cannot take cognizance of such document in these proceedings for the first

time. In any event since no action was taken on such note by the respondent

or no action was conveyed to the petitioner no reliance thereon can be placed

by the petitioner.

24.

The Supreme Court in the case of COX AND KINGS LTD supra held

that though a party had invested a large sum of money in the project, but that

cannot entitle it to pray for a mandatory order to operate the contract once it is

noted that the remedy of the petitioner would be if any in action for damages

against the respondent for beach of any of the terms and conditions of the

Joint Venture agreement and MOU. Similar view has been taken by the

learned Single Judge of this Court in the case of MILAN COMMERCIAL PVT.

LTD VS ASIAN HEALTHCARE (supra). In my view, the arbitrator has rightly

not stayed the termination of the agreement effected by the respondent. A

perusal of the pleadings before the learned arbitrator and in the writ petition

which was on record before the learned arbitrator, it is clear that the petitioner

was pressing demand of the additional terms and conditions for completion of

the project. In my view, the readiness and willingness of a party has to be all

Asmita 51/53

.. 52 .. ARBPL-1999/13

throughout. The petitioner has not carried out any work since January 2011.

Neither the Court nor the learned arbitrator can rewrite the contract and direct

a party to withdraw the termination notice and enter into a fresh contract on

the terms and conditions proposed by another party.

25. In my prima facie view, in view of the status quo order passed by

this Court which has been continued form time to time the public project of

this magnitude has been stalled for no fault of the respondent and the learned

arbitrator was thus justified in refusing to continue such status quo order in

favour of the petitioner. In the event of the petitioner succeeding in the

arbitration proceedings and if termination of the agreement is found to be

illegal the petitioner can be compensated in terms of money.

26. In my view, termination of the Agreement thus cannot be stayed.

There is no infirmity found by this Court in the order passed by the Arbitral

Tribunal. The impugned order is a reasoned order and is passed after

considering the submissions of the parties at length, documentary evidence

and provisions of law and thus no interference is warranted by this court.

27. In my view, the Petition is devoid of merits and is accordingly

Asmita 52/53

.. 53 .. ARBPL-1999/13

rejected.

28. Mr. Apte learned senior Counsel appearing for the petitioner seeks

continuation of the statement made by Mr. Khambatta learned senior counsel

appearing for the respondent. Mr. Khambatta on instructions has opposed

such a request. Application made by Mr. Apte for continuation of the statement

is accordingly rejected.

30. No order as to costs.

                              
                                                                    (R.D.DHANUKA, J.) 
        
     






    Asmita                                                                                     53/53





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter