Citation : 2013 Latest Caselaw 361 Bom
Judgement Date : 17 December, 2013
1
IN THE HIGH COURT OF JUDICATURE AT BOMBAY,
NAGPUR BENCH : NAGPUR
First Appeal No. 328 of 2008
Appellant : M/s R. N. Tandon and Sons,
1, South Civil Lines, Jabalpur
versus
Respondent :
Union of India, through its Deputy Chief
Engineer, Central Railway, Nagpur
Mr R. R. Srivastava, Advocate for appellant
Mr N. P. Lambat, Advocate for respondent
Coram : A. P. Bhangale, J
Dated : 17th December 2013
Oral Judgment
1. This is appeal under Section 37 of the Arbitration and
Conciliation Act, 1996. The appellant is aggrieved by judgment and order
dated 18th December 2007 passed by learned District Judge, Nagpur when
he had set aside the Award of Arbitral Tribunal in respect of price
escalation awarded to the contractor in the sum of Rs. 7,36,469/- with
interest @ 8% per annum.
2. It is grievance of the appellant that respondent Union of India
had awarded the work of construction of bridges between CH. 3550 meters
to 8000 mtrs in Section III of Metpanjara-Kohli Section of Central Railway
which included Earth Work also for tender value in the sum of Rs.
57,21,132/- The work was to be completed within nine months from the
date of acceptance letter excluding monsoon period of four months from
15th June to 15th October and, therefore, total period for completion of
contract was 13 months. On issuance of acceptance letter dated 23.1.1991,
appellant undertook the aforesaid work. The contract agreement was
signed on 25.9.1991 by the appellant and it was sent for signature of
respondent at Mumbai, which was received back sometime in November
1991 - January 1991.
3. It is grievance of the appellant that some official of the
respondent scored off the price variation clause from the contract
unilaterally without knowledge and consent of the appellant and thus, the
mischief was committed by an endorsement made without consent of the
appellant. Despite correspondence by appellant with respondent the
mischief was subsisting. According to appellant, there was no justification
for respondent to deny benefit of price variation clause to the appellant
when the appellant was similarly placed at par with other contractors.
My attention is invited to the price variation clause in the contract which
appears struck off by pen with endorsement "escalation clause not
applicable". Who struck off the price variation clause and who made the
endorsement as above and whether appellant had consented or not
remains a mystery since oral evidence of signatory on the contract was not
obtained by Arbitral Tribunal.
4. Learned counsel for the appellant submitted that learned
District Judge failed to consider this aspect before setting aside the award
passed by the Arbiral Tribunal. Learned District Judge also erred to answer
in the negative a question as to whether escalation is available in the
agreement and whether interference is possible in the Award under Section
34 of the Act. Considering that three similar agreements were entered into
by respondent with other similarly circumstanced three contractors in
respect of adjoining Sections during the same contract period as that of the
appellant, the Arbitral Tribunal could have exposed malafide action if any
of the respondent by insisting upon evidence of the contracting persons
when price variation clause appeared scored off in the contract. The
dispute is, as to who scored off and who made the endorsement and
whether Appellant had consented to it. Oral evidence insisted upon could
have settled this vital controversy between the parties. That being so,
impugned order passed by learned District Judge must be set aside in
exercise of appellate jurisdiction.
5. In the result, impugned order is set aside. The proceeding is
remanded to learned Arbitral Tribunal to record evidence as may be
available regarding price variation clause which is a matter of dispute
between the parties. The Tribunal would decide the question as to who
made endorsement and who struck off price variation clause and what is its
effect and whether the price variation clause was scored off uniterally. The
Tribunal shall decide the question as early as possible preferably within six
months from the receipt of writ from this Court. If the members of Arbitral
Tribunal who decided the controversy are not available presently, new
Arbitral Tribunal shall be constituted by the General Manager, Central
Railways, Mumbai as per the procedure agreed between the parties. R & P
be sent back immediately. The Arbitral Tribunal be constituted
expeditiously and appellant would appear before it soon after the issuance
of notice by the Tribunal.
A. P. BHANGALE, J
joshi
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!