Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Krishna vs Dreekamp-5 D26605
2012 Latest Caselaw 86 Bom

Citation : 2012 Latest Caselaw 86 Bom
Judgement Date : 5 October, 2012

Bombay High Court
Krishna vs Dreekamp-5 D26605 on 5 October, 2012
Bench: R. M. Savant
                                                            wps-7804.09 & 7636.09


                 IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                          CIVIL APPELLATE JURISDICTION




                                                                            
                         WRIT PETITION NO.7804 OF 2009




                                                    
                                     WITH
                         WRIT PETITION NO.7636 OF 2009


    1      Enercon (India) Ltd.              ]




                                                   
           a company incorporated and        ]
           existing under the laws of        ]
           India and having its              ]
           registered office at Plot No.     ]




                                            
           33, Daman- Patalia,               ]
           Bhimpore, Daman-396 210
                              ig             ]
           India                             ]
                                             ]
    2      Yogesh J. Mehra                   ]
                            
           being Indian Inhabitant           ]
           residing at 101, Hare             ]
           Krishna, Residency Society,       ]
           J.V.P.D. Scheme, North            ]
             

           South Road No.8, Vile Parle (W)   ]
           Mumbai 400 049                    ]
          



                                             ]
    3      Ajay J. Mehra                     ]
           being Indian Inhabitant           ]
           residing at 101, Hare             ]





           Krishna, Residency Society,       ]
           J.V.P.D. Scheme, North            ]
           South Road No.8, Vile Parle (W)   ]
           Mumbai 400 049                    ]..... Petitioners.





                      Versus

    1      Enercon GmbH                      ]
           a company duly                    ]
           incorporated and existing         ]
           under the law of Germany          ]
           and having its registered         ]
           office at Dreekamp 5,             ]
           D26605, Aurich, Germany.          ]
                                             ]

    lgc                                                                          1 of 124


                                                    ::: Downloaded on - 09/06/2013 19:13:31 :::
                                                                           wps-7804.09 & 7636.09

    2      Wobben Properties GmbH                        ]
           a company duly                                ]
           incorporated and existing                     ]




                                                                                          
           under the laws of Germany                     ]
           and having its office at                      ]




                                                                  
           Dreekamp-5 D26605,                            ]
           Aurich, Germany.                              ]..... Respondents.

    Dr.Veerendra   Tulzapurkar,   Senior   Advocate,   with   Mr.Virag   Tulzapurkar, 
    Senior   Advocate,   with   Mr.Nikhil   Sakhardande,   Ms.Sonali   Mathur   &   Ms. 




                                                                 
    Swagata   Naik   i/by  M/s.   AZB  &   Partners  for  the Petitioners  in   both  the 
    Petitions.

    Mr. S.U.Kamdar, Senior Advocate with Mr. Zubin Behramkamdin, Ms.Naira 




                                                    
    Variava-Jejeebhoy, Mr.Rohan Cama, Mr. Vivek Vashi, Ms.Anusha Jegadeesh, 
    Ms.Devika Deshmukh, and Ms.Kanika Sharma i/by Bharucha & Partners 
                                  
    for the Respondents in Writ Petition No.7804 of 2009.

    Mr.   Navroze   Seervai,   Senior   Advocate   with   Mr.   Zubin   Behramkamdin, 
                                 
    Ms.Naira Variava-Jejeebhoy, Mr.Rohan Cama, Mr. Vivek Vashi, Ms.Anusha 
    Jegadeesh, Ms.Devika Deshmukh, and Ms.Kanika Sharma i/by Bharucha & 
    Partners for the Respondents in Writ Petition No.7636 of 2009.
             

                                       CORAM : R. M. SAVANT, J.

Judgment Reserved on :- 6th August 2012.

Judgment Pronounced on :- 5th October 2012.

JUDGMENT :-

1 The above Writ Petitions have been filed invoking the Writ

Jurisdiction of this Court under Article 227 of the Constitution of India

challenging the order dated 27th August 2009 passed by the learned District

Judge, Daman by which order the Appeals being Misc. Civil Appeal

Nos.1/2009, 2/2009, 3/2009 and 4/2009 came to be allowed and resultantly

the order passed by the Trial Court dated 9 th January 2009 came to be set

aside, resulting in the Application filed under Section 45 of the Arbitration and

lgc 2 of 124

wps-7804.09 & 7636.09

Conciliation Act, 1996 being allowed in terms of prayer clause 28(a) thereof,

and the Injunction Application of the Petitioners above-named, who are the

original Plaintiffs, came to be rejected.

2 The issue that arises in the above Petitions is therefore in two parts

viz. Whether the parties are to be referred to arbitration, and Whether the

Petitioners are entitled to an anti-suit injunction in the facts and circumstances

of the present case. The impugned order is therefore also in two parts; first

part deals with the aspect of whether the parties are to be referred to

arbitration, and second part is, whether the Petitioners are entitled to an anti-

suit injunction. Since both the Petitions involve common facts and are

interconnected, the same are, therefore, heard together.

For the sake of brevity the Arbitration and Conciliation Act, 1996

of India and, the Arbitration and Conciliation Act, 1996 of England would be

referred to as the "Indian Arbitration Act" and "English Arbitration Act".

FACTUAL MATRIX :-

3 The Petitioner No.1 herein carries on business of manufacturing

and marketing of the Wind Turbine Generators (WTG's) and components in

India, and is also in the business of setting up wind power projects on turnkey

lgc 3 of 124

wps-7804.09 & 7636.09

basis. The Petitioner Nos.2 and 3 herein are the Directors of the Petitioner

No.1 and are arrayed as the Plaintiff Nos.1 to 3 in the Suit in question. The

Respondent No.1-Enercon GmbH is a Company incorporated under the laws of

Germany and is having its registered office at Aurich, Germany. One Dr.Alloys

Wobben is a Director of the Respondent No.1. The Respondent No.2 - Wobben

Properties GmbH is a Company incorporated under the laws of Germany and is

also having its registered office at Aurich, Germany. The Respondent No.1 is

engaged in mechanical engineering and possesses technical knowledge and

equipment for manufacturing and marketing the Wind Turbine Generators and

components. The Respondent No.1 carries on the said business all over the

world. The Respondent Nos.1 and 2 are arrayed as the Defendant Nos.1 and 2

to the Suit in question. The Petitioners and the Respondents are running the

joint venture business through the Petitioner No.1-Company at Daman in India.

Accordingly the parties have entered into various Agreements in furtherance of

the said business. The Petitioner Nos.2 and 3, on 12/01/1994 entered into a

Shareholding Agreement. In terms of the said Agreement the Respondent No.1

was holding 51% shares of the Petitioner No.1-Company, and the Petitioner

Nos.2 and 3 were holding 49% shares. The said Shareholding Agreement was

subsequently amended by two Supplementary Shareholding Agreements dated

19/05/1998 and 19/05/2000. Pursuant to the said Supplementary

Shareholding Agreements, the Respondent No.1 became a 56% shareholder in

the Petitioner No.1-Company whilst the shareholding of the Petitioner Nos.2

lgc 4 of 124

wps-7804.09 & 7636.09

and 3 was reduced to 44%. On the same day i.e. on 12/01/1994, the

Petitioner No.1 and the Respondent No.1 entered into a Technical Know-How

Agreement by which the Respondent No.1 had agreed to transfer to the

Petitioner No.1 the right and the technology to use the technical know-how for

the manufacture of E-26 Wind Turbine Generators specified therein and their

components. A Supplementary Technical Know-How Agreement amending the

earlier Technical Know-How Agreement was executed on 19/05/2000 by

which a further licence to manufacture the E-30 and E-40 Wind Turbine

Generators was conferred by the Respondent No.1 to the Petitioners. Under the

terms of the Technical Know-How Agreement, the Respondent No.1 has to

continuously supply special components to the Petitioner No.1. In April 2004

the period of the Technical Know-How Agreement expired, however, the

Respondent No.1 continued to supply the Wind Turbine Generators and

components. The Respondent No.2 has the patent of the said windmill

technology; whereas the Respondent No.1 is a licensor to supply the said

windmill technology, and the Petitioners are the licensees to use the said

windmill technology. It appears that from the year 2000 onwards and till date

the Petitioners are manufacturing the said Wind Turbine Generators and

continue to use the patents that were licensed by these agreements. On

29/09/2006 the Petitioners and the Respondent No.1 entered into what is

known as the "Agreed Principles" for the use and supply of the windmill

technology. Under the said Agreed Principles the Petitioners and the

lgc 5 of 124

wps-7804.09 & 7636.09

Respondents agreed to enter into what is known as the Intellectual Property

License Agreement ("IPLA" for short), which is the subject matter of the Suit in

question. It is the case of the Petitioners that the Agreed Principles are the

binding principles agreed between the parties, and which records an

agreement that all definitive agreements between the parties that were to be

prepared and finally executed would be on the basis of the binding principles

agreed therein. One of the agreements contemplated by the said Agreed

Principles was the IPLA. The Petitioner Nos.2 and 3 are the parties to the IPLA.

It seems that the Petitioner No.2 has signed the IPLA on behalf of the Mehra

family. At the time of the signing of the IPLA the Petitioners were already

aware of the five models of the WTG's being E-26, E-30, E-40, E-48 and E-53.

It is the case of the Petitioners that the IPLA was merely a draft of the oral

terms and not a concluded contract between the parties. It was their case that

the said document was an unincorporated and inchoate document and was not

a concluded contract. It appears that one Mr.Ketwigg , the Managing Director

of Respondent No.1 in a letter dated 02/10/2006, addressed to Petitioner No.2

stated therein that all the necessary contracts between the parties should be

completed by 19/10/2006. Further in the e-mail dated 04/10/2006 Ms.Nicole

Fritsch of the Respondent No.1 stated that she would try her best to

prepare/adapt the agreements according to the Agreed Principles by

19/10/2006. It is the case of the Petitioners that to their utter shock and

surprise, on 18/10/2006 Ms. Nicole Fritsch of the Respondent No.1 totally

lgc 6 of 124

wps-7804.09 & 7636.09

turned around and addressed a letter to the Petitioner No.2 falsely alleging that

the draft IPLA which was signed on 29/09/2006 was a final document.

Thereafter correspondence ensued between the parties and a contentious issue

arose as to whether the IPLA can be called final or not. Thereafter spate of

litigation ensued between the parties. This was as a result of the Respondent

No.1 stopping supplies which resulted in the Petitioner Nos.2 and 3 filing a

derivative Suit on the Original Side of this Court being Short Cause Suit

No.2667 of 2007 seeking resumption of supplies. This Court has, by an interim

order dated 31/10/2007 without prejudice to the individual contentions of the

parties, directed resumption of supplies by the Respondent No.1 to the

Petitioner No.1 until further orders of this Court. In view of the fact that the

said order was not complied with by the Respondent No.1, there is a Contempt

Petition which has been filed by the Petitioners, which is pending.

4 The Respondent No.1 has also filed a Company Petition being

No.121 of 2007 against the Petitioners before the Company Law Board,

Principal Bench, New Delhi some time in August 2007. The said Petition has

been filed under Sections 397 and 398 of the Companies Act. The reliefs

sought in the said Company Petition inter alia included removal of the

Petitioner Nos.2 and 3 as Directors of Petitioner No.1, transfer of the Mehras

shareholding in the Petitioner No.1 as well as associate and subsidiary

companies of Petitioner No.1 to Respondent No.1, and investigation to

lgc 7 of 124

wps-7804.09 & 7636.09

ascertain the conduct of Mehras in dealing with properties, monies and

management of the Petitioner No.1. In view of the non-compliance of the

order passed by the Company Law Board, contempt proceedings have been

initiated by the Petitioners against Dr.Wobben and Mr.Ketwigg. The Mehras i.e.

the Petitioner Nos.2 and 3 filed Company Petition No.74 of 2008 against the

Respondent No.1, Dr.Wobben and Mr. H D Ketwigg alleging oppression and

mismanagement by the Respondents. The said Petition was also filed under

Sections 397 and 398 of the Companies Act.

5 The Respondent No.1 had filed a Petition against the Petitioner

No.1 and others alleging that Petitioner No.1 had been supplying Wind Turbine

Generators to third parties in Germany thereby infringing the trademarks

belonging to Respondent No.1. The same was filed in the Hamburg District

Court which Court had initially granted an ex-parte ad-interim order dated

17/09/2007 restraining the Petitioner No.1 from effecting supplies to such

third parties in Germany. The Hamburg District Court thereafter dismissed the

claim of the Respondent No.1 on the ground that there was no evidence to

suggest Petitioner No.1's involvement in the matter. The aforesaid facts

therefore disclose the diverse litigation in which the parties are involved.

6 The Respondent No.1 addressed a letter dated 13/03/2008 stating

therein that it was desirous of having all disputes relating to the IPLA settled,

lgc 8 of 124

wps-7804.09 & 7636.09

including whether there is a binding agreement between Petitioner No.1 and

Respondent Nos.1 and 2 in respect of the IPLA. The Respondents also

informed the Petitioners that it had appointed Mr. V. V. Veeder QC as its

nominee arbitrator and called upon the Petitioners including Petitioner Nos.2

and 3 to nominate their arbitrator in accordance with the IPLA, which

according to the Respondent Nos.1 and 2 was a concluded contract. The

Petitioner No.2, on behalf of the Petitioners, replied to the said letter by his

letter dated 31/03/2008 stating therein that since the IPLA was not a

concluded contract, there was no question of a valid Arbitration Agreement

between the parties and as such, there was no question of appointing any

arbitrator in the matter. It was further stated that in any event, the past

conduct and attitude of the Respondent No.1 established that it had waived the

Arbitration Agreement. The UK Solicitors of the Respondent Nos.1 and 2

addressed a letter to the Petitioners dated 02/04/2008 stating therein that in

the event the Petitioners did not nominate their arbitrator within seven days of

the receipt of the said letter, the Respondent Nos.1 and 2 shall proceed under

the English Arbitration Act, 1996 to appoint their nominee arbitrator Mr. V. V.

Veeder QC, as the sole arbitrator. The said letter was received by the Petitioner

No.1 in Daman on 03/04/2008, along with the said letter was annexed

`Arbitration Claim Form' dated 27/03/2008 issued by the Respondent Nos.1

and 2 seeking several declaratory reliefs from the English Court in relation to

the IPLA which according to the Respondent Nos.1 and 2 is a concluded

lgc 9 of 124

wps-7804.09 & 7636.09

contract. The said declaratory reliefs inter-alia include injunctive relief from

the English Court to restrain the Petitioner Nos.2 and 3 from continuing with

independent proceedings before this Court, i.e. the Suit which was already

filed by the Petitioner Nos.2 and 3 in a derivative capacity as shareholders of

the Petitioner No.1. The said 'Arbitration Claim Form', which had been filed

before the English Court, was also served upon the Petitioner No.1 in Daman

04/04/2008 and seems to have triggered off the filing of the Regular Civil Suit

No.9 of 2008 before the learned Civil Judge, Senior Division, Daman on

08/04/2008 inter-alia for the following reliefs viz. for a declaration that the

IPLA was not a concluded contract and correspondingly that there was no

Arbitration Agreement between the parties; for a declaration that the initiation

of proceedings before the English Court by the Respondents was void and

illegal; and for a permanent injunction restraining the Respondents from

continuing with the proceedings before the English Court. In the said Suit the

Petitioners moved an Application for temporary injunction and for other

interim reliefs. The Trial Court, it seems, passed a status quo order on

08/04/2008 directing the Respondents to maintain status quo as regards the

proceedings initiated before the English Court till their appearance in the Suit

and to show cause why an interim order should not be passed against them.

The Respondents appeared in the Suit and filed an Application under Section

45 of the Indian Arbitration Act contending therein that the Suit before the

Trial Court ought to be referred to arbitration pursuant to the arbitration clause

lgc 10 of 124

wps-7804.09 & 7636.09

contained in the IPLA. The Respondents also sought a vacation of the status

quo order. It appears that in the interregnum on 11/04/2008, the Petitioner

No.1 had appointed Mr. Justice B. P. Jeevan Reddy (Retd.) as its arbitrator.

This, according to it, was necessitated in view of the threats of the Respondents

that the arbitrator appointed by them could be nominated as a sole arbitrator

under the English Law, in the event the Petitioner No.1 failed to nominate its

arbitrator. It seems that the arbitrator appointed by the Petitioners by his letter

dated 24/04/2008 stated that there were inherent defects in the arbitration

clause contained in the IPLA and therefore the same was unworkable and

expressed the inability of the arbitrators to appoint a third arbitrator.

Thereafter a joint letter was addressed which is dated 05/08/2008 by both the

arbitrators i.e. Mr. V. V. Veeder QC and Mr. Justice B. P. Jeevan Reddy (Retd.)

asking the parties to take necessary steps as may be advised.

7 The Plaintiffs i.e. the Petitioners herein had moved an application

for temporary injunction ex-parte in the said suit, wherein the Trial Court

directed the parties to maintain status quo. The Trial Court had granted an

exparte injunction restraining the Defendants i.e. the Respondents herein from

proceeding with the proceedings they had filed in the English Court. The

Application for interim reliefs and the Application filed by the Respondents

under Section 45 of the said Act was heard by the Trial Court, and by the order

dated 09/01/2009, the learned Civil Judge, Senior Division, Daman, allowed

lgc 11 of 124

wps-7804.09 & 7636.09

the said Application for interim reliefs filed by the Petitioners, and rejected the

Application for referring the parties to arbitration filed under Section 45 of the

said Act by the Respondents, i.e. the Trial Court confirmed the ex-parte ad

interim order of status quo granted by it on 8/4/2008 till decision of the suit.

The Defendants i.e. the Respondents herein were restrained not to constrain

the Plaintiffs i.e. the Petitioners herein to go for arbitration till the final

decision of the suit by invoking the IPLA.

The gist of the reasoning of the Trial Court was to the effect that

the document in question i.e. the IPLA was not on a stamp paper and it does

not bear the signature and seal of the Public Office in authentication that the

document is enforceable in law; that the Plaintiff No.2 had signed the

document under the influence of Dr.Alloys Wobben. The Trial Court, on the

basis of the material on record, recorded a finding that the IPLA was not a

concluded contract for want of free consent, and was executed due to undue

influence, fraud, mis-representation and mistake, that the Plaintiffs would

suffer heavy economic loss if the arbitration is held at London. In so far as the

jurisdictional aspect is concerned, the Trial Court recorded a finding that the

Court at Daman would have jurisdiction as the Plaintiff No.1 was a joint

venture between the Plaintiff No.1 and the Defendants which had its factory at

Daman.

    lgc                                                                                           12 of 124



                                                                            wps-7804.09 & 7636.09




    9              Aggrieved   by   the   order   dated   09/01/2009   passed   by   the   Trial 




                                                                                           

Court, the Defendants i.e. the Respondents herein filed four Appeals which

were Civil Misc. Appeal Nos.1/2009, 2/2009, 3/2009 and 4/2009. The said

Appeals were filed by the Respondents covering two aspects as to the grant of

the anti Suit injunction, and as to the rejection of the Application filed by them

under Section 45 of the said Act. The said Appeals were heard by the learned

Principal District Judge, Daman, who by the order dated 27/08/2009 allowed

the said four Appeals, and consequently set aside the orders passed by the Trial

Court granting the anti Suit injunction, and referred the parties to arbitration

by allowing the Application filed under Section 45 of the said Act. However,

the Lower Appellate Court has directed the Trial Court to first decide the

jurisdiction point before proceeding with the Suit. The Lower Appellate Court

has inter alia considered the enforceability of the Arbitration Agreement, the

case of the Plaintiffs that the IPLA was not a concluded contract, which the

Plaintiffs had sought to support by both intrinsic as well as extrinsic material,

and also the case of the Plaintiffs that the said Clause-18.3 was unworkable in

view of the methodology mentioned therein for the appointment of the

arbitrators. The Lower Appellate Court as can be seen from its order has on

the basis of the fact that the IPLA was signed by the Plaintiff No.2, reached a

conclusion that there was an agreement between the parties to refer the

disputes to arbitration which intention of the parties, according to the Lower

lgc 13 of 124

wps-7804.09 & 7636.09

Appellate Court, was required to be given effect to. The Lower Appellate Court

held that assuming that there was some defect in the methodology for

appointment of the arbitrators, that would not come in the way of enforcement

of the Arbitration Agreement. The Lower Appellate Court held that since the

parties had agreed to London being the seat of arbitration, the Plaintiffs could

not make a grievance as regards the jurisdiction of the English Courts. The

Lower Appellate Court has by its order dated 27/08/2009, as indicated above,

has allowed the said four Appeals.

10 It is the order passed by the Lower Appellate Court in the said four

Appeals which is the subject matter of the above two Petitions. In so far as

Writ Petition No.7804 of 2009 is concerned, the same challenges the order to

the extent of referring the parties to arbitration; whereas Writ Petition No.7636

of 2009 concerns the challenge to the setting aside of the anti Suit injunction.

11 SUBMISSIONS ON BEHALF OF THE PETITIONERS BY THE LEARNED SENIOR COUNSEL DR. VEERENDRA TULZAPURKAR IN WRIT PETITION NO.7804 OF 2009:-

i] That the Lower Appellate Court failed to decide the important

issue, as to whether the IPLA was a concluded contract and that

there is a valid subsisting Arbitration Agreement.

    lgc                                                                                    14 of 124



                                                                   wps-7804.09 & 7636.09

    ii]     Since   the   Lower   Appellate   Court   has   failed   to   decide   the   very 

important jurisdictional fact, namely the existence of a concluded

contract before referring the parties to arbitration, the exercise of

the Writ Jurisdiction of this Court under Article 227 of the

Constitution of India is warranted. The learned Senior Counsel

relied upon the Judgments of the Apex Court reported in (2006)

3 SCC 312 in the matter of Kishore Kumar Khaitan and Anr.

V/s. Praveen Kumar Singh and; (2008) 14 SCC 58 in the matter

of Ramesh Chandra Sankala V/s. Vikram Cement.

iii] That the IPLA is not a concluded contract and is only a draft. The

learned Senior Counsel sought to buttress the said submission by

referring to the clauses mentioned in the IPLA, regarding the grant

of licences, finance, tenure of the IPLA;

iv] That the patents in respect of which the licences were to be given

to the Petitioners were not finalized, the tenure of the IPLA was

also indefinite, and since the royalty is to be paid on the patents,

and since the fixation of the royalty was also not finalized; the

IPLA could not be said to be a concluded contract.

    lgc                                                                               15 of 124



                                                                       wps-7804.09 & 7636.09

    v]       That assuming the IPLA is a concluded contract, the arbitration 

clause 18.1 is vague and is unimplementable in view of the fact

that the arbitrator of the licensor is to don two hats, two roles, one

being the arbitrator of the licensor and second being the presiding

arbitrator;

vi] That the arbitration clause is unworkable is borne out by the fact

that both the arbitrators i.e. Mr V V Veeder, QC and Mr.Justice B P

Jeevan Reddy (Retd.) have expressed that the arbitration clause as

it stands is unworkable and would require clarification.

vii] That no steps were taken for registration of the patents as required

by Section 69 of the Patents Act, as both the parties treated it as

not a concluded contract.

viii] That the IPLA cannot be said to be a concluded contract in view of

the fact that as per the Agreed Principles all the four agreements

mentioned therein were to be executed at one time and the IPLA

therefore could be said to be finalized only after the said four

documents which were inclusive of the IPLA were executed.



    ix]      The   extrinsic   evidence   which   is   in   the   nature   of   the 


    lgc                                                                                   16 of 124



                                                                  wps-7804.09 & 7636.09

correspondence exchanged between the parties shows that the

IPLA was not a concluded contract. The learned Senior Counsel

would rely upon the letters dated 11/3/2006, 10/4/2006, as also

the letters date 30/09/2006, 2/10/2006 and 24/11/2006 which

are post the signing of the IPLA on 29/09/2006 which according

to the learned Senior Counsel ex-facie point out that the IPLA was

not a concluded contract, and that it was only a draft;

x]

That since the main contract cannot be said to have come into

existence, therefore, the clause providing for arbitration has also

necessary to be held as not having come in existence. The learned

Senior Counsel would rely upon the judgment of the Apex Court

reported in (1960) 1 SCR 493 in the matter of Union of India

v/s. Kishorilal Gupta and Brothers and, two Division Bench

Judgments of this Court reported in 2010 (2) Company Law

Reporter 393 in the matter of Nasir Husain Films (P) Ltd. v/s

Saregama India Ltd and anr.; and 2008 (4) Arbitration Law

Reporter 179 in the matter of Oberoi Construction P. Ltd v/s

Worli Shivshahi Co-op Hsg. Society Ltd. ;

xi] That since the underlying contract has not come into existence, in

view thereof the arbitration clause in the contract is inoperative.

    lgc                                                                              17 of 124



                                                                 wps-7804.09 & 7636.09

The learned Senior Counsel would rely upon the judgment of the

Apex Court reported in (1996) 2 SCC 667 in the matter of U.P.

Rajkiya Nirman Nigam Ltd Vs. Indure Pvt. Ltd. & ors.

xii] That the IPLA is not a concluded contract, since the subject matter

being absent as the portfolio regarding the patents was not

finalized. The parties were also not ad-idem as regards

commencement of the IPLA and its duration. The IPLA is therefore

vague, ambiguous and uncertain, and is therefore, void under

Section 29 of the Indian Contract Act. The learned Senior Counsel

would place reliance on the judgment of a Division Bench of the

Karnataka High Court reported in AIR 1966 Mysore 118 in the

matter of Coffee Board, Bangalore v/s. Janab Dada Haji

Ibrahim Halari, the judgment of the Apex Court reported in

(1990) 3 SCC 1 in the matter of Mayawanti v/s. Kaushalya

Devi; reported in (2004) 1 SCC 252 in the matter of United Bank

of India v/s Ramdas Mahadeo Prashad & others; reported in

AIR 1949 Nagpur 286 in the matter of The Central Bank,

Yeotmal Ltd. V/s Vyankatesh Bapuji; and reported in (1976) 1

WLR 591 in the matter of Bushwall Properties Ltd v/s Vortex

Properties Ltd.

    lgc                                                                             18 of 124



                                                                     wps-7804.09 & 7636.09

Since there was uncertainty about the duration of the IPLA, the

said agreement was void on account of uncertainty. Since the

portfolio of the patents was not finalized, there was uncertainty as

regards the patents and their duration, and since the duration of

the IPLA was contingent upon, the expiry of the last patents the

duration of the IPLA was not certain. The learned Senior Counsel

in support of the said contention relied upon the judgment of the

Apex Court reported in (2008) 5 SCC 58 in the matter of Vimlesh

Kumari Kulshrestha v/s. Sambhajirao and anr.

xiii] That the extrinsic evidence which has been referred to in the

Application for temporary injunction proves that the said IPLA was

not a concluded contract. The reply filed by the Respondents to

the said Application for temporary injunction was contradictory to

their letter dated 24/11/2006 wherein they had agreed that there

was some uncertainty and that they would try to resolve it by

having a in-house meeting.

xiv] That there can be no arbitration if there is no concluded contract.

Since in the instant case the IPLA is not a concluded contract, the

parties therefore cannot be referred to arbitration. The learned

Senior Counsel, in support of the said submission, sought to rely

lgc 19 of 124

wps-7804.09 & 7636.09

upon the following judgments of the Apex Court reported in (1)

(2006) 1 SCC 751, Dresser Rand S.A. v/s. Bindal Agro Chem

Ltd and K. G. Khosla Compressors Ltd.; (2) (2010) 5 SCC 425,

Andhra Pradesh Tourism Development Corporation Ltd & Anr.

V/s. Pampa Hotels Ltd.; (3) AIR 1962 SC 378, Jawahar Lal

Burman Vs. Union of India and (4) (1999) 1 SCC 9 M/s.

Rickmers Verwaltung GmbH v/s. The Indian Oil Corporation

Ltd.

xv] That the judgment in Shin-Etsu Chemical Co. Ltd. v/s. Aksh

Optifibre Ltd and anr cannot be placed reliance upon as the

proposition laid down by Justice B.N.Srikrishna that the Court

under Section 45 of the Indian Arbitration Act has only to take a

prima facie view, cannot be said to be a majority view, in view of

the discordant note sounded by Justice D.M.Dharmadhikari in Para

112 of the said judgment.

xvi] That in the facts and circumstances of the case the exercise of writ

jurisdiction under Article 227 of the Constitution of India is

warranted.

    lgc                                                                               20 of 124



                                                                     wps-7804.09 & 7636.09

    12      SUBMISSIONS   ON   BEHALF   OF   THE   RESPONDENTS   BY   THE 

LEARNED SENIOR COUNSEL SHRI S U KAMDAR IN WRIT PETITION NO.7804 OF 2009 :-

[a] That exercise of the Writ Jurisdiction under Article 227 of the

Constitution of India is not warranted in the facts of the present

case; as the view taken by the Lower Appellate Court on the aspect

of the parties being referred to arbitration, cannot be said to be a

view which could not be taken in the facts and circumstances of

the case.

[b] That the Petitioners have not pointed out as to how there has been

a failure to exercise the jurisdiction or the Lower Appellate court

has exceeded its jurisdiction in passing the impugned order which

is a pre-requisite to warrant the exercise of the writ jurisdiction;

[c] That the Lower Appellate court has passed the impugned order

considering the relevant material on record, which the Trial Court

had failed to do, and therefore it cannot be said that the order

passed by the Lower Appellate Court directing the parties to

arbitration is perverse. In support of the said submission, the

learned Senior Counsel relied upon the judgments of the Apex

Court reported in (1) (2001) 8 SCC 97, Estralla Rubber v/s Dass

Estate (P) Ltd. (2) (2003) 6 SCC 641, State Through Special

lgc 21 of 124

wps-7804.09 & 7636.09

Cell, New Delhi v/s. Navjot Sandhu alias Afshan Guru and ors.

and (3) (2010) 9 SCC 385, Jai Singh and ors v/s. Municipal

Corporation of Delhi and ors.

In so far as aspect of perversity is concerned, the learned Senior

Counsel relied upon the judgment of the Apex Court reported in

(2009) 10 SCC 206 in the matter of Arulvelu and anr v/s. State

Represented by the Public Prosecutor and anr.

The said judgments inter alia lay down the scope of interference

under Article 227 of the Constitution of India. The said judgments

inter alia lay down that the power under Article 227 of the

Constitution of India is to be exercised to keep the inferior Courts

within their bounds. It is not in the nature of an appellate power

and cannot be exercised for correcting a mere error. The said

judgments lay down that if there is a failure to exercise

jurisdiction or jurisdiction is exercised in excess of the powers or

the findings recorded are so perverse that no reasonable man

could have arrived at such a finding that the exercise of the writ

jurisdiction under Article 227 of the Constitution of India is

warranted.

    lgc                                                                               22 of 124



                                                                   wps-7804.09 & 7636.09

    [d]      That the Court whilst considering the application under section 45 

has only to arrive at a prima facie view as regards the existence of

the Arbitration Agreement and the arbitrability of the dispute and

is not concerned with any dispute as regards the underlying

contract. The learned Senior Counsel for the said purpose relied

upon the judgment of the Apex Court reported in (2005) 7 SCC

234 in the matter of Shin-Etsu Chemical Co. Ltd. v/s. Aksh

Optifibre Ltd and anr.

[e] For the proposition that the Court has to only arrive at a prima

facie view as regards Arbitration Agreement and the arbitrability of

the dispute. The learned Senior Counsel for the Respondents,

s case apart from the judgment of the Apex Court in Shin-Etsu'

(supra) relied upon another judgment of the Apex Court reported

in (2009) 2 SCC 134 in the matter of Shakti Bhog Foods Limited

V/s Kola Shipping Limited and the Division Bench Judgment of

this Court reported in 2007(5) Bom.C.R. 227 in the matter of

Caribjet Inc v/s Air India Limited and the judgment of a learned

Single Judge of this Court reported in 2012(3) Bom. C.R. 36 in

the matter of Olive Healthcare v/s. Lannett Company Inc. & anr.

    lgc                                                                               23 of 124



                                                                       wps-7804.09 & 7636.09

    [f]     That the documents in question unmistakably lead to a conclusion 

that the IPLA was a concluded contract. The learned Senior

Counsel sought to rely upon the correspondence between the

parties prior to the agreement being executed on 26/9/2006. The

said correspondence starts with the e-mail dated 25/6/2006 and

the e-mail and letters exchanged thereafter;

[g] That the fact that IPLA is a concluded contract is borne out by the

fact that the parties have signed the same, and therefore, in terms

of the requirements as mentioned in Section 44 of the said Act, the

Lower Appellate Court was right in referring the parties to

arbitration.

[h] That all along it has been the stand of the Respondents that the

Petitioners have executed the IPLA which was not disputed by the

Petitioners herein. The dispute started on account of the payment

in respect of the equity shares which were to be purchased by the

Respondents. The said fact is borne out by the letter dated 3 rd

November 2006 of the Petitioners and it is only thereafter that the

Petitioners started raising a dispute as regards certain aspects of

the IPLA;

    lgc                                                                                   24 of 124



                                                                   wps-7804.09 & 7636.09

    [i]     That   the   aspect   of   the   main/underlying   contract   and   the 

Arbitration Agreement are separable. In a given case, even if the

main contract can be said to be suffering from some infirmity but

that would not have any effect on the Arbitration Agreement. The

Court has only to prima facie see whether there is a valid

Arbitration Agreement.

[j] That the conclusivity that is required to be seen is only as regards

the Arbitration Agreement. The requirement for which finds a

place in Section 44 of the Indian Arbitration Act. The requirement

being that the Arbitration Agreement has to be in writing and

signed by the parties. In the instant case both the conditions are

satisfied. The learned Senior Counsel for the Respondents in

support of the said submission relied upon the judgment of the

Apex Court reported in (2012) 2 SCC 93 in the matter of Reva

Electric Car Company Private Limited v/s. Green Mobil and

(2008) 14 SCC 240 in the matter of Great Offshore Limited v/s.

Iranian Offshore Engineering and Construction Company.

[k] That the facts in Kishorilal Gupta's case are clearly distinguishable

from the facts of the present case, as in Kishorilal Gupta's case the

contract itself was superseded and therefore in the said fact

lgc 25 of 124

wps-7804.09 & 7636.09

situation the Court held that no reliance could be placed on the

arbitration clause in the superseded contract. For the said

purpose, the learned Senior Counsel relied upon the judgment of

the Apex Court reported in (2009) 10 SCC 103 in the matter of

Branch Manager, Magma Leasing and Finance Limited and Anr.

v/s. Potluri Madhavilata and anr. wherein the judgment in

Kishorilal Gupta has been distinguished by the Apex Court.

[l]

That whilst considering the application under Section 45 of the

said Act there can only be a prima facie examination of the

material on record so as to arrive at a conclusion whether there is

an Arbitration Agreement between the parties. In so far as other

aspects are concerned, the issue can be raised before the Arbitral

Tribunal. In support of the said submission, the learned Senior

Counsel for the Respondents relied upon the judgment of the Apex

Court reported in (2007) 7 SCC 120 in the matter of Aurohill

Global Commodities Ltd. v/s. Maharashtra STC Ltd. and (2009)

2 SCC 134 in the matter of Shakti Bhog Foods Limited v/s. Kola

Shipping Limited.

[m] That the infirmity if any in the main contract would not impinge

upon the Arbitration Agreement encompassed in the said contract.

    lgc                                                                              26 of 124



                                                                    wps-7804.09 & 7636.09

The position in law in that respect in India as well as in England is

the same. Hence the contention of the learned Senior Counsel for

the Petitioners that in view of the fact that the annexure to the

IPLA or other grounds on which the Petitioners contend that the

IPLA was not a concluded contract would have no bearing on the

Arbitration Agreement as it is well settled that the Arbitration

Agreement stands apart from the main contract. In support of the

said submission the learned Senior Counsel relied upon the

English judgment reported in (2007) UKHL 40 in the matter of

th Premium Nafta Products Limited (20 Defendant) and others

th v/s. Fili Shipping Company Limited (14 Claimant) and others

and also relied upon the judgment of a learned Single Judge of

this Court reported in 2003 CLC 601 in the matter of GTC

Limited v/s Royal Consulting RV and anr.

[n] That merely because there is a challenge to the main underlying

contract, the said fact would not impinge upon the validity of the

Arbitration Agreement. The learned Senior Counsel for the

Respondents relied upon the judgment of the US Federal Court

reported in 546 US 440 in the matter of Buckeye Check Cashing

Inc. v. Cardegna. The said view of the US Federal Court has been

affirmed by the Apex Court in the judgment reported in (2009) 2

lgc 27 of 124

wps-7804.09 & 7636.09

SCC 494 in the matter of P. Manohar Reddy & Bros. v/s.

Maharashtra Krishna Valley Development Corporation and

others and para 28 thereof.

[o] That it is only when the main underlying contract is vitiated on

account of fraud, coercion, etc, that the Arbitration Agreement can

be said to be affected, such is not the case in the instant matter.

(p)

That it is well settled even if there is any uncertainty or ambiguity

in the underlying contract, it can be looked into and if necessary

corrected by relying on extrinsic evidence. The learned Senior

Counsel in support of the said contention sought to place reliance

on Paras 11-123, 12-117, 12-118 and 13-008 from the learned

Author Chitty on Contract.

[q] That there is no uncertainty as regards the terms of the underlying

contract. The date of execution of the IPLA is certain and is

referable to page 46. The date 17/09/2006 appearing on IPLA is

referable to the letter dated 17/09/2006 of Yogesh Mehra by

which he has communicated his inability to remain present in

Aurich-Germany on the said day;

    lgc                                                                                  28 of 124



                                                                    wps-7804.09 & 7636.09

    [r]     That   the   contention   of   the   learned   Senior   Counsel   for   the 

Petitioners that the agreement is not a concluded contract as it

does not contain the annexure in respect of the patents which have

been granted to the Petitioners is only a bogey raised on behalf of

the Petitioners, as the Petitioners are using the patents from 1994

to 2004 and two more patents were used since 2004, the Technical

Know-How Agreement and Supplemental Technical Know-How

Agreement spelt out which patents have been given to the

Petitioners.

[s] That all questions relating to the agreement in any event have to

be decided by the Arbitral Tribunal. That since the agreement has

been signed, the requirement under Section 7 of the Indian

Arbitration Act is satisfied. For the said purpose the learned

Senior Counsel relied upon the judgment of a learned Single Judge

of this Court reported in AIR 2000 Bombay 108 in the matter of

Keval Krishna Balakram Hitkari v/s Anil Keval Hitkari and

others and the judgment of the Apex court reported in (1995) 6

SCC 571 in the matter of J.K.Jain and others v/s. Delhi

Development Authority and others.

That in so far as the issue as to whether the contract is concluded

lgc 29 of 124

wps-7804.09 & 7636.09

or not, the signing of the contract is one of the defining aspects

which test is laid down by the Apex Court in the judgment

reported in (2010) 1 SCC 83 in the matter of Grasim Industries

Limited and Anr v/s. Agarwal Steel

[t] That the contention of the learned Senior Counsel for the

Petitioners that the judgment of the Lower Appellate Court is

bereft of any findings is not correct. Findings have been recorded

on the basis that the parties have signed the IPLA as also on the

basis of the correspondence entered into between the parties

which can be seen from the impugned order.

[u] That even if a part of the arbitration clause is unworkable, the

same is severable as in the instant case the grievance of the

Petitioners is only as regards the number of arbitrators who are to

be appointed. The said dispute can therefore be said to be a

dispute only as regards the machinery provision but not as regards

the agreement between the parties to go for arbitration.

[v] That even if part of the agreement is bad, the part which can be

sustained will have to be enforced. The learned Senior Counsel

relied upon the judgment of the Apex Court reported in AIR 1997

lgc 30 of 124

wps-7804.09 & 7636.09

SC 605 in the matter of M.M.T.C. Limited v/s. Sterlite Industries

(India) Ltd. which is followed in (2002) 3 SCC 572 in the matter

of Narayan Prasad Lohia v/s. Nikunj Kumar Lohia and others.

[w] That the letter of the arbitrator appointed by the Petitioners

cannot be conclusive of the fact that the Arbitration Agreement is

not workable. The correspondence preceding the said letter does

not indicate that the said Arbitration Agreement is unworkable.

[x] That the defining aspect as it were, is the intention of the parties

to go for arbitration which is clearly manifest. For the said purpose

the learned counsel relied upon the judgment of the Allahabad

High Court reported in AIR 1954 Allahabad 750 in the matter of

A H Bhiwindiwala and Co. v/s. R B Lakshman Dass Mohan Lal

and Sons Ltd and anr. , and the judgment of the Apex Court

reported in (2009) 4 SCC 495 in the matter of Nandan

Biomatrix Limited v/s. D 1 Oils limited.

(y) That there is no merit in the contention of the learned counsel for

the Petitioners that the second relief sought in the suit of

injunction cannot go to arbitration. That the said relief can only

said to be referable to the IPLA as it is the contention of the

lgc 31 of 124

wps-7804.09 & 7636.09

learned Senior Counsel that since the IPLA is not a concluded

contract, the Arbitration Agreement is not enforceable. The test

would therefore be whether the Arbitration Agreement as

contained in IPLA can be enforced. For the said purpose the

learned Senior Counsel relied upon the judgment of the Apex

Court reported in (2006) 7 SCC 275 in the matter of Rashtriya

Ispat Nigam Ltd v/s. Verma Transport Co as also the judgment

reported in (2008) 16 SCC 774 in the matter of Everest Holding

Limited v/s. Syam Kumar Shrivastava and others.

[z] The learned Senior Counsel sought to distinguish the judgments

cited by the learned Senior Counsel for the Petitioners in the

context of the facts of the present case. The learned Senior

Counsel for the Respondents would contend that in the context of

the facts of the cases in the judgments cited by the learned Senior

Counsel for the Petitioners that the Apex Court has held that the

parties were not ad-idem, and therefore, the contract was not

concluded, but the same is not the case in the instant matter.

CONSIDERATION - WRIT PETITION NO.7804 of 2009

13 Heard the learned counsel for the parties and also perused the

Written Submissions filed on behalf of the parties.

    lgc                                                                                     32 of 124



                                                                         wps-7804.09 & 7636.09




    14          Since clause (18) of the IPLA is at the fulcrum of the controversy 




                                                                                        

involved in both the Petitions, it would be apposite to reproduce sub-clauses

18.1 to 18.3 of clause 18 of the IPLA.

(18.1) All disputes, controversies or differences which may arise between the parties in respect of

this Agreement including without limitation to the validity, interpretation, construction, performance and enforcement of alleged breach of this Agreement, the parties shall, in the first instance

attempt to resolve such dispute, controversy or difference through mutual consultation. If the

dispute, controversy or difference is not resolved through mutual consultation within 30 days after commencement of discussions or such longer

period as the parties may agree in writing, any party may refer dispute(s) controversy(ies) or difference(s) for resolution to an arbitral tribunal to consist of three (3) arbitrators of whom one will

be appointed by each of the Licensor and the licensee and the arbitrator appointed by Licensor

shall also act aas the presiding arbitrator.

18.2) The arbitrators shall have powers to award and/or enforce specific performance. The award of

the arbitrators shall be final and binding on the parties. In order to preserve its rights and remedies, either party may seek preliminary injunctive relief or other temporary relief from any court of competent jurisdiction or from the arbitration

tribunal pending the final decision or award of the arbitrator(s). Any such application to a court of competent jurisdiction for the purposes of seeking injunctive relief shall not be deemed incompatible with this agreement to arbitrate or as a waiver of this Agreement to arbitrate.

18.3) All proceedings in such arbitration shall be conducted in English. The venue of the arbitration proceedings shall be London. The arbitrators may

lgc 33 of 124

wps-7804.09 & 7636.09

(but shall not be obliged to ) award costs and reasonable expenses (including reasonable fees of counsel) to the party(ies) that substantially prevail

on merit. The provisions of the Indian Arbitration and Conciliation Act, 1996 shall apply.

15 It would also be apposite to reproduce the relevant provisions of

the Indian Arbitration and Conciliation Act, 1996 namely Sections 7, 44 and 45

(7) Arbitration agreement - (1) in this part, "arbitration agreement" means an agreement by

the parties to submit to arbitration all or certain disputes which have arisen or which may arise

between them in respect of a defined legal relationship, whether contractual or not.

(2)An arbitration agreement may be in the form of

an arbitration clause in a contract or in the form of a separate agreement (3) An arbitration agreement shall be in writing. (4) An arbitration agreement is in writing if it is

contained in -

(a) a document signed by the parties;

(b) an exchange of letters, telex, telegrams or other means of telecommunication which provide a record of the agreement; or

(c) an exchange of statements of claim and defence

in which the existence of the agreement is alleged by one party and not denied by the other.

(5) The reference in a contract to a document containing an arbitration clause constitutes an arbitration agreement if the contract is in writing

and the reference is such as to make that arbitration clause part of the contract.

(44) Definition - In this Chapter, unless the context otherwise requires, "foreign award" means an arbitral award on differences between persons arising out of legal relationships, whether contractual or not, considered as commercial under the law in force in India, made on or after the 11th day of October, 1960 -

    lgc                                                                                    34 of 124



                                                                            wps-7804.09 & 7636.09

(a) in pursuance of an agreement in writing for arbitration to which the Convention set forth in the First Schedule applies, and

(b) in one of such territories as the Central Government, being satisfied that reciprocal

provisions have been made may, by notification in the Official Gazette, declare to be territories to which the said Convention applies.

(45) Power of Judicial authority to refer parties

to arbitration - Notwithstanding anything contained in Part I or in the Code of Civil Procedure, 1908 (5 of 1908) a judicial authority, when seized of an action in a matter in respect of

which the parties have made an agreement referred to in section 44, shall, at the request of

one of the parties or any person claiming through or under him, refer the parties to arbitration, unless it finds that the said agreement is null and

void, inoperative or incapable of being performed.

16 As can be seen, Section 45 provides that an application may be

made to a judicial authority to refer any proceeding before it to Arbitration,

where the parties have entered into an Arbitration Agreement as contemplated

under Section 44 of the said Act. It further provides that such reference must

be made by the Court unless it finds that the Agreement is null and void,

inoperative or incapable of being performed. The reference therefore in

Sections 44 and 45 is to an Arbitration Agreement. If the Arbitration

Agreement is in the form of a clause in the main contract, then reference in

Sections 44 and 45 would be to that clause which is an Arbitration Agreement

contained as and by way of a clause in the main contract.

    lgc                                                                                        35 of 124



                                                                           wps-7804.09 & 7636.09

    17             In so far as the scope of the inquiry under Section 45 of the Indian 

Arbitration Act is concerned, the same is well settled by the authoritative

pronouncement of the Apex Court in the Judgment reported in 2005(7) SCC

234 in the matter of Shin-Etsu Chemical Co. Ltd. & Ors. vs Aksh Optifibre

Ltd. Paragraph 72 to 75 of the said Judgment are material and are reproduced

herein under:

"72. True, that there is nothing in Section 45 which suggests that the finding as to the nature of

the arbitral agreement has to be ex facie or prima facie. In my view, however, this is an inescapable

inference from an ex visceribus interpretation of the statute. Sub-section (3) of Section 8 in Part I of the Act envisages that even in a situation

where an application to the court has been made under sub-section (1), the arbitration may commence, continue and even an arbitral award be made. This was obviously meant to cut down

delay in the conclusion of the arbitral proceedings. There is conspicuous absence of a

corresponding provision either in Section 45 or in the rest of the provisions in Part II. This legitimately gives rise to an inference that once the arbitral agreement has been subjected to

scrutiny before the court under Section 45 of the Act, conceivably, the arbitral proceedings could be stayed till the decision of the court on the nature of the arbitral agreement. If it were to be held that the finding of the court under Section 45

should be a final, determinative conclusion, then it is obvious that, until such a pronouncement is made, the arbitral proceedings would have to be in limbo. This evidently defeats the credo and ethos of the Act, which is to enable expeditious arbitration without avoidable intervention by judicial authorities.

73. The absence in Part II of the Act of a provision corresponding to Section 5 in Part I has

lgc 36 of 124

wps-7804.09 & 7636.09

been highlighted as supportive of the view that greater judicial intervention is contemplated in Part II of the Act. The question that has arisen

before the Court is not the presence or absence of judicial intervention; it is one with regard to the

manner in which the said judicial intervention should proceed whether on a final view or prima facie view of the factors enumerated in Section 45 of the Act.

74. There are distinct advantages in veering to the view that Section 45 does not require a final determinative finding by the Court. First, under the Rules of Arbitration of the International

Chamber of Commerce (as in force with effect from 1.1.1998), as in the present case, invariably

the arbitral tribunal is vested with the power to rule upon its own jurisdiction. Even if the court takes the view that the arbitral agreement is not

vitiated or that it is not invalid, inoperative or unenforceable, based upon purely a prima facie view, nothing prevents the arbitrator from trying the issue fully and rendering a final decision

thereupon. If the arbitrator finds the agreement valid, there is no problem as the arbitration will

proceed and the award will be made. However, if the arbitrator finds the agreement invalid, inoperative or void, this means that the party who wanted to proceed for arbitration was given an

opportunity of proceeding to arbitration, and the arbitrator after fully trying the issue has found that there no scope for arbitration. Since the arbitrator's finding would not be an enforceable award, there is no need to take recourse to the

judicial intercession available under Section 48(1)(a) of the Act.

75. The finding of the court that the arbitration agreement is valid, operative and enforceable, if in favour of the party setting up the arbitration agreement, is not appealable under Section 50 as a matter of legislative policy. Refusing to refer parties to arbitration under Section 45, is however, made appealable under Section 50(1)

lgc 37 of 124

wps-7804.09 & 7636.09

(a) of the Act. Even after the court takes a prima facie view that the arbitration agreement is not vitiated on account of factors enumerated in

Section 45, and the arbitrator upon a full trial holds that there is no vitiating factor in the

arbitration agreement and makes an award, such an award can be challenged under Section 48(1)

(a). The award will be set aside if the party against whom it is invoked satisfies the court inter alia that the agreement was not valid under the

law to which the parties had subjected it or under the law of the country where the award was made. The two basic requirements, namely, expedition at the pre- reference stage, and a fair

opportunity to contest the award after full trial, would be fully satisfied by interpreting Section 45

as enabling the court to act on a prima facie view."

18 A useful reference could also be made to the judgment of a

Division Bench of this Court in Caribjet Inc v/s Air India Limited (supra).

Para 6 of the said judgment is material and is reproduced herein under :-

6. As rightly submitted by the learned Counsel for the appellant, the issue which is sought to be raised is no more res integra and has been well-settled by the decision of the Apex Court

in Shin-Etsu Chemical Company's case (supra). By a majority decision in the said case, the Apex Court has held that:

if on a prima facie examination of the documents and material on record including

the arbitration agreement on which request for reference is made by one of the parties, the judicial authority or the court decides to make a reference, it may merely mention the submissions and contentions of the parties and summarily decide the objection if any raised on the alleged nullity, voidness, inoperativeness or incapability of the arbitration agreement. In case, however, on a prima facie view of the matter, which is required to be objectively

lgc 38 of 124

wps-7804.09 & 7636.09

taken on the basis of material and evidence produced by the parties on the record of the case, the judicial authority including a regular

civil court, is inclined to reject the request for reference on the ground that the agreement is

"null and void" or "inoperative" or "incapable of being performed" within the meaning of Section 45 of the Act, the judicial authority or the court must afford full opportunities to the parties to lead whatever documentary or oral

evidence they want to lead and then decide the question like trial of a preliminary issue on jurisdiction or limitation in a regular civil suit and pass an elaborate reasoned order. Where a

judicial authority or the court refuses to make a reference on the grounds available under

Section 45 of the Act, it is necessary for the judicial authority or the court which is seized of the matter to pass a reasoned order as the

same is subject to appeal to the appellate court under Section 50(1)(a) of the Act and further appeal to this Court under Sub-section (2) of the said section."

19 The inquiry contemplated under Section 45 is therefore of a prima

facie nature of the existence of an Arbitration Agreement. If the Court comes to

a prima facie conclusion that there is an Arbitration Agreement and the same is

legal and valid the matter must be referred to the Arbitral Tribunal for further

consideration which can thereafter conclusively decide either way. If the Court

comes to the prima facie conclusion that there is either no Arbitration

Agreement or that the same is not valid in law, the Court must then proceed to

determine the same finally and conclusively.

    lgc                                                                                          39 of 124



                                                                               wps-7804.09 & 7636.09

    20              The   issue   which   requires   to   be   addressed   at   the   threshold   is 

whether the view expressed by Justice B.N.Shrikrishna in Shin-Etsu Chemical

Co. Ltd (supra) is the majority view. The said issue arises in view of the

submission of the Learned Senior Counsel for the Petitioners relying upon

paragraph 112 of the said Judgment of Shin Estu Chemical Co. Ltd. (Supra)

that Justice D.M.Dharmadhikari has not concurred with the view of Justice

B.N.Shrikrishna. In paragraph 111 of the said Judgment Justice

D.M.Dharmadhikari expressly concurs with the view of Justice Shrikrishna and

therefore there can be no dispute that the proposition laid down by Justice

Shrikrishna has been accepted by Justice D.M.Dharmadhikari, and is the

majority view in the said judgment. The said paragraph 111 is reproduced

herein under :-

"With utmost respect to both of them, I am inclined to

agree with the view expressed by learned Brother Srikrishna J. but only with a rider and a partly different reason which may I state below:-

The main issue is regarding the scope of power of any

judicial authority including a regular civil court under section 45 of the Act in making or refusing a reference of dispute arising from an international arbitration agreement governed by the provisions contained in Part III Chapter-I of the Act of 1996. I respectfully Agree

with learned Brother Srikrishna J only to the extent that if on prima facie examination of the documents and material on record, including the arbitration agreement on which request for reference is made by one of the parties, the judicial authority or the court decides to make a reference, it may merely mention the submissions and contentions of the parties and summarily decide the objection if any raised on the alleged nullity, voidness, inoperativeness or incapability of the arbitration agreement. In case, however, on a

lgc 40 of 124

wps-7804.09 & 7636.09

prima facie view of the matter, which is required to be objectively taken on the basis of material and evidence produced by the parties on the record of the case, the

judicial authority including a regular civil court, is inclined to reject the request for reference on the

ground that the agreement is 'null and void' or 'inoperative' or 'incapable of being performed' within the meaning of section 45 of the Act, the judicial authority or the court must afford full opportunities to the parties to lead whatever documentary or oral

evidence they want to lead and then decide the question like trial of a preliminary issue on jurisdiction or limitation in regular civil suit and pass an elaborate reasoned order. Where a judicial authority or the court

refuses to make a reference on the grounds available under section 45 of the Act, it is necessary for the

judicial authority or the court which is seized of the matter, to pass a reasoned order as the same is subject to appeal to the appellate court under section 50(1)(a)

of the Act and further appeal to this Court under sub- section (2) of the said section."

(emphasis supplied)

In so far as paragraph 112 which has been relied upon by the Learned Senior

Counsel, the same deals with a situation where the Award is passed in spite of/

and/or prior to the decision holding that such an Arbitration Agreement does

not exist. The Apex Court in the said case of Shin Estu Chemical Co. Ltd.

(supra) was not concerned with such a case, neither is this Court, in the

present Petition.

21 The Judgment in Shin Estu Chemical Co. Ltd (supra) has been

followed by the Apex Court in Shakti Bhog Foods Ltd, (supra) as also by a

Division Bench of this Court in Caribjet Inc. Vs. Air India Ltd. (supra), as also

lgc 41 of 124

wps-7804.09 & 7636.09

by a Learned Single Judge of this Court in Olive Healthcare Vs. Lannet

Company Inc. (supra). Hence, in the light of the aforesaid Judgments, the

Court for the purpose of determination of the existence or validity of an

agreement under Section 45 of the Indian Arbitration Act, has to restrict its

enquiry to the Arbitration Agreement and not the underlying contract. It is

required to be noted that there is a substantial change in law from the one that

existed under the Indian Arbitration Act 1940. In the 1940 Act under Section

33 thereof, the Court had the power and jurisdiction to determine the existence

or validity of Arbitration Agreement. However, under the provisions of the

Indian Arbitration Act, the said power of the Court has been taken away and is

now expressly vested with the Arbitral Tribunal under Section 16 of the Indian

Arbitration Act. Under Section 16, the Arbitral Tribunal can rule on its own

jurisdiction including ruling on any objection with respect to the existence or

validity of the Arbitration Agreement. Thus the power to determine finally and

conclusively the existence and validity of an Arbitration Agreement has been

conferred on the Arbitral Tribunal under Section 16 of the 1996 Act. It is the

Arbitral Tribunal therefore which will determine whether there is an

Arbitration Agreement or not for that purpose the Arbitration Agreement will

be a totally independent agreement dehors the other terms of the contract and

such an agreement would not ipso-jure become null and void or invalid even if

it has been held that the under lying contract is void. Another aspect which is

to be noted is that the severability and separability of the Arbitration

lgc 42 of 124

wps-7804.09 & 7636.09

Agreement though being a clause in the same contract, has now a recognition

not only under Section 16 of the 1996 Act but by a catena of the Judgments of

the Apex Court. A useful reference could be made to the Judgment reported in

2009(2)SCC 494 in the matter of P. Manohar Reddy & Bros. Vs.

Maharashtra Krishna Valley Dev. Corp. & ors., The Apex Court has

recognized that the Arbitration Agreement is separate and independent from

the main Agreement. It has been held that the Arbitration clause though being

a part of the contract is a collateral term which need not in all situations perish

with coming to an end of the underlying contract and it may survive the same.

Paragraphs 27 and 28 of the said Judgment are material and are reproduced

herein under :

"27. An arbitration clause, as is well known, is a

part of the contract. It being a collateral term need not, in all situations, perish with coming to an end

of the contract. It may survive. This concept of separability of the arbitration clause is now widely accepted. In line with this thinking, the UNCITRAL Model Law on International Commercial

Arbitration incorporates the doctrine of separability in Article 16(1). The Indian law - The Arbitration and Conciliation Act, 1996, which is based on the UNCITRAL Model Law, also explicitly adopts this approach in Article 16 (1)(b), which reads as

under:-

"16. Competence of arbitral tribunal to rule on its jurisdictional. - (1) The arbitral tribunal may rule on its own jurisdiction, including ruling on any objections with respect to the existence or validity of the arbitration agreement, and for that purpose,

(a) An arbitration clause which forms part of a contract shall be treated as an agreement

lgc 43 of 124

wps-7804.09 & 7636.09

independent of the other terms of the contract; and

(b) A decision by the arbitral tribunal that the

contract is null and void shall not entail ipso jure the invalidity of the arbitration clause.

(Emphasis supplied)

Modern laws on arbitration confirm the concept.

28. The United States Supreme Court in the

recent judgment in Buckeye Check Cashing, Inc. v. Cardegna 546 US 460 acknowledged that the separability rule permits a court "to enforce an arbitration agreement in a contract that the

arbitrator later finds to be void." The Court, referring to its earlier judgments in Prima Paint

Corporation v. Flood & Conklin Mfg. Co. 388 U. S. 395, and Southland Corporation v. Keating 465 U. S. 1, inter alia, held:

Prima Paint and Southland answer the question presented here by establishing three propositions. First, as a matter of substantive

federal arbitration law, an arbitration provision is severable from the remainder of the contract.

But this must be distinguished from the situation where the claim itself was to be raised during the subsistence of a contract so as to invoke

the arbitration agreement would not apply."

The said Judgment as can be seen approves the Judgments of

United States Supreme Court reported in 546 US 460 in the matter of

Buckeye Check Cashing Inc. Vs. Cardegana and, reported in 388 US 395 in

the matter of Prima Paint Corporation Vs. Floor and Conkling

Manufacturing Company

lgc 44 of 124

wps-7804.09 & 7636.09

22 A reference could also be made to the Judgment of the Apex Court

reported in 2009(10) SCC 103 in the matter of Branch Manager Magma

Leasing and Finance Ltd. & Anr. Vs. Potluri Madhavilata & Anr. The Apex

Court in the said Judgment has approved the proposition laid down in P.

Manohar Reddy's case (supra) and once again referred with approval the

judgment of the United States Supreme Court in Buckeye Check Cashing Inc.

The aforesaid Judgments of the Apex Court as well as the United States

Supreme Court, make it clear that the Arbitration Agreement would survive

even in case of invalidity of the main agreement or the underlying contract. It

is only in cases where the underlying contract is vitiated by fraud, coercion or

misrepresentation that the same would impact the Arbitration Agreement.

23 The principles of severability and separability of the Arbitration

Agreement is common both under the English Arbitration Act, 1996 and the

Indian Arbitration Act 1996, as evidenced by the following Judgments of the

Apex Court and the House of Lords reported in :-

1] 2003 CLC 601, GTC Ltd. Vs. Royal Consult R.V. & Anr.

2] 2009(2) SCC 134, Shakti Bhog Foods Ltd. Vs. Kola Shipping

Ltd.

3] Judgment of the House of Lords reported in 2007 UKHL 40,

Premium Nafta Products Ltd. & Ors. Vs. Fili Shipping Co. Ltd. &

Ors.

    lgc                                                                                     45 of 124



                                                                           wps-7804.09 & 7636.09




    24             It is in the context of the settled law as afore stated that the facts 




                                                                                          

of the present case would have to be seen. The Learned Senior Counsel for the

Petitioners laid much store on the correspondence post 29-9-2006 i.e. the date

when the IPLA was signed, to contend that the IPLA was not a concluded

contract. However, the correspondence prior thereto between the parties

indicates otherwise. If the said correspondence is seen, to which my attention

is drawn by the Learned Senior Counsel appearing for the Respondents, the

same discloses that it was on 27-6-2006 i.e. a good three months prior to its

execution, that the draft IPLA was sent to the Petitioners. The said IPLA had

already undergone changes on the basis of the suggestions of both the parties

and the final document was kept ready on 29-9-2006 as the Petitioner No.2

had shown his inability to come to Aurich on 17-9-2006 when it was to be

executed. The other three agreements namely the Successive Technological

Transfer Agreement, Name Use Licence Agreement and the Shareholders

Agreement were not executed on 29-9-2006 because they were not finalised as

certain issues were still required to be finalised. The most important letter if it

can be said so, is the letter dated 30-9-2006 which is addressed by the

Petitioner No.2 Yogesh Mehra in his own handwriting stating therein that he

has executed not one but more than one agreement on 29-9-2006. Pertinently

in paragraph 2 of the said letter, the Petitioner No.2 has in fact referred to the

patent of E-82 being the subject matter of the IPLA and not the Agreed

lgc 46 of 124

wps-7804.09 & 7636.09

Principles. The fact that the letter dated 30-9-2006 refers to the execution of

two agreements on 29-9-2006 and also refers to the E-82 patent, further

indicates that by the said letter dated 30-9-2006 the Petitioner No.2 admitted

to the execution of the IPLA. In so far as the email dated 4-10-2006 is

concerned, the said email refers to the preparation and adoption of the

agreements according to the "Agreed Principles". The said email refers to the

other three agreements. It seems that only after the claim for royalty was made

by the Respondents, that on 3-11-2006 the Petitioners purportedly

incorporated an indirect denial of the execution of the IPLA. In so far as the

email dated 24-11-2009 is concerned, the said email as can be seen from its

subject refers to the final IPLA the Shareholders Agreement and other

Successive Agreements. The email which dealt with the outstanding drafts of

the Agreements obviously did not refer to the final IPLA but refers to the other

Successive Agreements because as far as the IPLA was concerned, the same

itself stated that it was already a finalised agreement. The email therefore, did

not refer to any draft of the IPLA or the Shareholders Agreement and therefore

the said email does not in any manner aid the case of the Petitioners that the

IPLA was not a concluded contract. Further the email dated 15-12-2006 from

the Petitioners to the Respondents wherein also the Petitioners dealt with the

draft agreements but the subject of the said email as can be seen was the same

as that of the email dated 24-11-2006. Thereafter the email dated 10-1-2007

dealt with a further visit to Germany and revised "Drafts of Outstanding

lgc 47 of 124

wps-7804.09 & 7636.09

Contracts". Thereafter, the email dated 29-1-2007 sent by the Petitioners, in

fact mentions the amended version of the Shareholders Agreement which is

outstanding and not executed, Name Use Licence Agreement, and the

Successive Technological Transfer Agreement. The aforesaid material therefore

leaves no manner of doubt that the draft agreements referred to therein were

only the other three agreements and not the IPLA. Therefore, a perusal of the

documents on record discloses that not only is the Arbitration Agreement

contained in clause 18.1to the IPLA legally and validly executed, but it is in

writing and signed by the parties.

25 The contentions of the Learned Senior Counsel for the Petitioners

as regards the unenforceability of the Arbitration Agreement all revolve around

the alleged uncertainty and ambiguity in the underlying or the matrix contract.

It was contended that since the IPLA is vague, ambiguous and uncertain, the

same is void under Section 29 of the Indian Contract Act, 1872. Consequently

the Arbitration Agreement as contained in clause 18 of IPLA, is also void. The

contention therefore of ambiguity and uncertainty is as regards the underlying

contract and not in respect of the Arbitration Agreement. Assuming it to be so,

applying the principle of separability and severability of the Arbitration

Agreement from the main agreement, the submission of the learned Senior

Counsel for the Petitioners does not have merit and cannot impede the Court

from referring the parties to arbitration.

    lgc                                                                                    48 of 124



                                                                         wps-7804.09 & 7636.09




    26            Now coming to the contention of the Learned Senior Counsel for 




                                                                                        

the Petitioners that since on the IPLA three dates are appearing, the

commencement date and the duration of the IPLA is therefore uncertain and

therefore the IPLA is not a concluded contract on account of the said

uncertainty and ambiguity. In so far as the said three dates are concerned, the

first date i.e. 27-6-2006 is referable to the first email dated 27-6-2006 under

which the draft IPLA was forwarded to the Petitioner No.2. The Petitioner No.2

can therefore be said to be aware that 27-6-2006 is referable to the date on

which the draft was forwarded and therefore it could never be the date of

execution. The date 17-9-2006 appearing on the third page of the IPLA is the

date on which the IPLA was proposed to be executed. Since the Petitioner No.2

cancelled his visit to Aurich-Germany by its email dated 16-9-2006, the said

date 17-9-2006 remained to be cancelled /altered. The third date is 29-9-2006

which also appears on the first page of the IPLA. There is no dispute that the

signatures on the IPLA have been affixed by the parties on 29-9-2006. In the

light of the aforesaid and since it is not disputed by the Petitioners i.e. the IPLA

has been executed on 29-9-2006, the question of taking into consideration any

other date would not arise. In any event, the said dispute can only be relatable

to the underlying contract and can be raised before the Tribunal and if raised,

it is for the Arbitral Tribunal to adjudicate upon the same.

    lgc                                                                                     49 of 124



                                                                           wps-7804.09 & 7636.09

    27             Now coming to the judgments cited by the learned Senior Counsel 

for the Petitioners in support of his contention that since the underlying

contract cannot be said to have come into existence, therefore, the clause

providing for arbitration has also necessary to be held as not having come into

existence. In so far as Kishorilal Gupta's case (supra) is concerned, in the said

case, the contention was that even after supersession of an earlier contract, the

Arbitration Agreement contained in the superseded contract continues in spite

of the admitted position that under the new contract, there was no arbitration

clause. It is in the said fact situation that the Apex Court held that with the

supersession of the whole contract, the Arbitration Agreement also stood

superseded and does not survive. The said judgment has been distinguished by

the Apex Court in the case of Branch Manager, Magma Leasing and Finance

Ltd, by holding that the new contract entered into was a novation under

Section 62 of the Indian Contract Act and thus no reliance can be placed on the

Arbitration Agreement contained in such a superseded contract.

In the case of U.P. Rajkiya Nirman Nigam Ltd., (supra) the facts

were that the counter proposal was not signed at all and thus, no concluded

contract was arrived at between the parties. It was in the said context that the

Apex Court held that there was no concluded contract. Para 19 of the said

judgment is material and is reproduced herein under :-

"In view of the fact that Section 2 [a] of the Act envisages a written agreement for arbitration and

lgc 50 of 124

wps-7804.09 & 7636.09

that written agreement to submit the existing or future differences to arbitration is a pre-condition and further in view of the fact that the original contract

itself was not a concluded contract, there existed no arbitration agreement for reference to the arbitrators.

The High Court, therefore, committed a gross error of law in concluding that an agreement had emerged between the parties, from the correspondence and from submission of the tenders to the Board.

Accordingly it is declared that there existed no

arbitration agreement and that the reference to the arbitration, therefore, is clearly illegal. Consequently arbitrators cannot proceed further to arbiter the dispute, if any. The conclusion of the High Court is set

aside."

In the case of Nasir Husain Films (P) Ltd. (supra) the facts were

that reliance was placed on a draft document. The Division Bench of this Court

held that the major issues on which negotiations were still in progress were not

settled. The contract could not be said to be concluded.

In the case of Oberoi Const. Pvt. Ltd (supra) the facts were that

the General Body Resolution passed by the society did not accept the

concluded agreement and stated that the same will be subject to circulation of

the draft and finalization thereof. It was in the said context that the Division

Bench held that since the document was not accepted or signed or executed by

the society, there was no conclusivity of the contract.

However in the instant case, the IPLA has admittedly been

executed on 29/09/2006 by the parties signing on each page and also in the

lgc 51 of 124

wps-7804.09 & 7636.09

execution clause, therefore, the said judgments (supra) cited by the learned

Senior Counsel for the Petitioners would have no application.

In the case of United Bank of India (supra) the issue before the

Apex Court was centered around as to whether the MOU entered into between

the parties on 18-5-1994 and forwarded by letter dated 20-5-1994 has been

acted upon and complied with by the parties . One of the conditions for the

MOU to come into force was withdrawal of the suit by the Respondents filed by

them against the United Bank of India. Since the suit was not withdrawn, the

Apex Court held that the MOU cannot be said to have come into existence.

Para 7 of the said judgment is material and is reproduced herein under :-

"Undisputedly, the respondents did not withdraw the

suit filed by them against the United Bank of India, which is the condition precedent stipulated in clause (1)

of the MOU. The respondents also did not pay the guarantee liability of Rs. 2.33 lacs. No compromise petition was filed before an appropriate court. Therefore, by no stretch of imagination it can be said

that the terms and conditions stipulated in the MOU had been complied with and acted upon by the parties. Apart from what has been said, subsequent to the MOU there was also a lot of correspondence between the parties by exchanging letters giving offers and counter-

offers, as would be revealed in the letters dated 16.6.94,23.12.94,12.6.95,15.6.95 and 19.6.95. All these correspondence would go to show that the parties failed to arrive at a consensus even on what were the terms of the MOU. Thus, it is clear that there was no concluded contract nor was there any novation."

In the case of Vimlesh Kumar Kulshrestha (supra) the agreement

in question was held to be void for uncertainty as there was no proper

lgc 52 of 124

wps-7804.09 & 7636.09

description of the property given in the agreement by annexing a map, though

map was referred to in the agreement, nor the description was satisfactorily

proved in a suit for specific performance. It is the said context that the Apex

Court held that the agreement if read was uncertain. Para 24 of the said report

is material and is reproduced herein under :-

"Reference to the said legal maxim, in our opinion, is not apposite in the facts and circumstances of this case. By reference to the boundaries of the premises alone, the description of the properties agreed to be sold did

not become certain. For the purpose of finding out the correct description of the property, the entire agreement

was required to be read as a whole. So read, the agreement becomes uncertain."

In the case of Coffee Board, Bangalore (supra), the facts were

that the defendant had to specify the quantity of coffee which he intended to

purchase, those quantities were omitted to be specified and those portions

were left blank in the tender form. It is in the said context that the Division

Bench of the Karnataka High Court held that the offer was vague for

uncertainty and indefiniteness on the acceptance of which no contract is ever

born or comes into being. Paras 30 and 31 of the said report are material and

are reproduced herein under :-

"30 Now, in this case the defendant did only one of those two things. He stated the prices, but he did not state the quantities which he wanted. If a person is told that goods of more than one description are available for sale and he is asked to state what prices he would be willing to offer for those goods and which of those goods he would be willing to buy at those prices, and that person states only his prices but never indicates the

lgc 53 of 124

wps-7804.09 & 7636.09

goods required by him, it is, I think, Impossible for any one to suggest that there was any acceptable offer made by him. I do not find it possible to accede to the

argument that in a case in which a tenderer who had to submit his tender in the form Exhibit A-3 which was

sent in this case, does not fill in the blanks in the last paragraph of that tender, the necessary and inevitable inference is that he is willing to buy all the goods to which the tender form referred."

31 The fact that paragraph 3(a) of Exhibit A-1 required the tenderer to state the quantities and the fact that Exhibit A-3 contains separate columns for the price and the quantity, makes the position abundantly clear

that unless a tender like Ex. A-3 not only states the prices but also states the quantities, the tender is no

offer which in law can be accepted. In my opinion, the specification of the quantity required by the tenderer was an essential term of the offer, and if that term was

not to be found in the offer his offer was vague for uncertainty and indefiniteness, on the acceptance of which no contract is ever born or comes into being."

The aforesaid judgments were relied upon by the learned Senior

Counsel for the Petitioners to buttress his submission that the IPLA was void on

account of ambiguity and uncertainty.

Reading of the said judgments discloses that all the said judgments

are concerning the validity of the underlying contract and not the Arbitration

Agreement. In the said judgments the underlying contract has been held to be

void or has not come into existence on account of the reasons mentioned

therein. However, the instant case arises under Section 45 of the Indian

Arbitration Act, the infirmity, if any, in the underlying contract cannot therefore

lgc 54 of 124

wps-7804.09 & 7636.09

be looked into. It is well settled that even if there is any uncertainty or

ambiguity, it can be looked into and if necessary corrected by relying on

extrinsic evidence, as rightly contended by the learned Senior Counsel for the

Respondents, by placing reliance on the extracts from the learned Author

Chitty on Contract. Therefore the said judgments cannot aid the Petitioners to

further their case that the parties cannot be referred to arbitration.

28 In so far as the submission of the Learned Senior Counsel for the

Petitioners that all the agreements were to be executed simultaneously, the

same is not borne out by any document. The composite arrangement referred

to pertains only to the fact that the said arrangement will govern the

subsequent relationship of the parties in a composite manner and not that each

of the documents must be executed simultaneously.

The issue as to whether the IPLA is a concluded contract can also

be looked at from the angle of the same being signed by the parties. There is

no dispute that the Petitioner No.2 has signed the IPLA on 29-9-2006 by

affixing his signature on every page of the IPLA including the execution clause.

The presumption which arises on the execution of the documents is enunciated

by the Judgment of the Apex Court reported in 2010 (1) SCC 83 in the matter

of M/S. Grasim Industries Ltd. vs M/S. Agarwal Steel. Para 6 of the said

report is material and is reproduced herein under :

    lgc                                                                                            55 of 124



                                                                            wps-7804.09 & 7636.09

"In our opinion, when a person signs a document, there is a presumption, unless there is proof of force or fraud, that he has read the document property and understood

it and only then has has affixed his signatures thereon, otherwise no signature on a document can ever be

accepted. In particular, businessmen, being careful people (since their money is involved) would have ordinarily ready and understood a document before signing it. Hence the presumption would be even stronger in their case. There is no allegation of force or

fraud in this case. Hence it is difficult to accept the contention of the respondent while admitting that the document, Ext. D-8 bears his signatures that it was signed under some mistake. We cannot agree with the

view of the High Court on this question. On this ground alone, we allow this appeal, set aside the impugned

judgment of the High Court and remand the matter to the High Court for expeditious disposal in accordance with law."

In the said context the Judgment of a Learned Single Judge of this

Court is also relevant, which Judgment is reported in AIR 2000 BOM 108 in

the matter of Keval Krishna Balakram Hitkari v/s Anil Keval Hitkari. Para 8

of the said Judgment is relevant and is reproduced herein under :-

8. So far as the objections raised by respondent No. 1 that the agreement of arbitration was not signed on the day on which it is shown to have been signed and it was signed on the day on which the award was made is concerned in my opinion even if it is assumed that the

arbitration agreement was not signed in November, 1994 as claimed and that it was signed on 3rd April, 1995 the conduct of the parties of signing that agreement and accepting the award and executing further documents pursuant to that award has to be construed as existence of an arbitration agreement between the parties. The observations of the Supreme Court in para 6 of its judgment in the case of Vaidya Harishankar Laxmiram Rajyaguru of Rajkot are pertinent which reads as follows :

    lgc                                                                                        56 of 124



                                                                           wps-7804.09 & 7636.09

"6. The main objection to the award is that there was no written agreement signed by both the parties to refer the disputes to arbitration. It is clear from the narration

of facts that the parties had agreed to refer the dispute to arbitrator. The award signed by both the parties

about which there is no factual dispute reiterated the fact that the parties had agreed to refer the dispute to the arbitration of the said arbitrator and that he made an award. All these are in writing and signed by all the parties. This in our opinion in the light of the facts and

circumstances of the case can certainly be construed to be a proper arbitration agreement in terms of section 2(a) of the Act. In this connection reference may be made to the observations of this Court in Prasun Roy v.

Calcutta Metropolitan Development Authority, AIR 1988 SC 205 : (1987) 4 SCC 217 where all the relevant

authorities on this point have been discussed. See also in this connection the decision of the Judicial Committee in Chowdhri Murtaza Hossein v. Mst. Bibi

Bechunnissa, (1875-76) 3 IA 209, 220. The observations in the said decision were made in different context. But in the present context it is clear that the conduct of the parties that there was an arbitration agreement and by

signing two award it could be said that the parties had agreed to refer the disputes in writing to the arbitration

of the named arbitrator. This agreement was done twice firstly by signing an endorsement below the award and secondly by entering into an agreement in the form of a letter dated August 14, 1978 (Ex. 40)."

Hence there can be no escape for the Petitioners from the consequences

flowing from the signing of the IPLA; and the signing of the IPLA by the parties

is therefore a strong circumstance in arriving at a prima facie conclusion as

enunciated in Shin Etsu Chemical Co. Ltd's case for referring the parties to

arbitration.

    lgc                                                                                       57 of 124



                                                                              wps-7804.09 & 7636.09

    29             Now   coming   to   the   submission   of   the   Learned   Senior   Counsel 

appearing for the Petitioners that clause 18.1 of the IPLA itself is uncertain,

ambiguous and unworkable as according to the Learned Senior Counsel, out of

the two Arbitrators, one Arbitrator is also to don the hat of the Presiding

Arbitrator. For the said purpose clause 18 of the IPLA would have to be

revisited. A reading of the said clause 18.1 discloses that each of the licensors

have to appoint an Arbitrator and the licensee is to appoint one Arbitrator. In

terms of the IPLA, the Respondent No.2 has licenced the patents to the

Respondent No.1 who has then licenced them to the Petitioners, hence two

Arbitrators have to be appointed by each of the licensors and one has to be

appointed by the licensee making it in all three Arbitrators. Since at the time of

invocation of the arbitration clause, the Respondents in fairness agreed to

appoint the third arbitrator independently, the said fact cannot make the

Arbitration Agreement invalid, ambiguous and uncertain as contended by the

Learned Senior Counsel. In any event, the provision regarding the number of

arbitrators is merely a machinery provision and does not form part of the

Arbitration Agreement. Even if the machinery part is invalid, there is still an

Arbitration Agreement by and between the parties which can be enforced. A

useful reference could be made to the Judgments of the Apex Court which have

been relied upon by the learned Senior Counsel for the Respondents. The

relevant paragraphs thereof are reproduced herein under :-

    lgc                                                                                          58 of 124



                                                                             wps-7804.09 & 7636.09

     AIR 1997 SC 605    in the matter of   M.M.T.C. Limited vs Sterlite  Industries  

(India) Ltd. (supra) Paras 8, 9, 10 and 11 are relevant and are reproduced

herein under :-

"8. Sub-section (3) of Section 7 requires an arbitration agreement to be in writing and sub-section (4) describe the kind of that writing. There is nothings in Section 7 to

indicate the requirement of the number of arbitrators as a part of the arbitration agreement. Thus the validity of an arbitration agreement does not depend on the number of

arbitrators specified therein. The number of arbitrators is dealt with separately in Section

10 which is a part of machinery provision for the working of the arbitration agreement. It is, therefore clear that an arbitration

agreement specifying an even number of arbitrators cannot be a ground to render the arbitration agreement invalid under the New Act as contended by the learned Attorney

General.

                      9.            Section   10   deals   with     the   number   of 
                            arbitrators.   Sub-section   (1)     says   that   the 
                            parties   are   free   to   determine   the   number   of 

arbitrators, provided that such number shall

not be an even number. Sub-section (2) then says that failing the determination referred to in sub-section (1), the arbitral tribunal shall consist of a sole arbitrator. Section 11 provides for appointment of arbitrators. This is

how arbitral tribunal is constituted.

10. The arbitration clause provides that each party shall nominate one arbitrator and the two arbitrators shall then appoint an umpire before proceeding with the reference.

The arbitration agreement is valid as it satisfies the requirement of Section 7 of the New Act . Section 11 (3) requires the two arbitrators to appoint the third arbitrator or

lgc 59 of 124

wps-7804.09 & 7636.09

the umpire. There can be no doubt that the arbitration agreement in the present case accords with the implied condition contained

in para 2 of the First Schedule to the Arbitration Act, 1940 requiring the two

arbitrators, one each appointed by the two sides, to appoint. an umpire not later than one month from the latest date of their respective appointments.

11. The question is: whether there is anything in the New Act to make such an agreement unenforceable? We do not find any such indication in the New Act. There is no

dispute that the arbitral proceeding in the present case commenced after the New Act

came into force and, therefore, the New Act applies. In view of the term in the arbitration agreement that the two arbitrators would

appoint the umpire or the third arbitrator before proceeding with the reference, the requirement of Sub-section (1) of Section 10 is satisfied and sub-section (2) thereof hes no

application. As earlier stated the agreement satisfies the requirement of Section 7 of the

Act and therefore, is a valid arbitration agreement. The appointment of arbitrators must, therefore, be governed by Section 11 of the New Act.

(2002) 3 SCC 572 in the matter of Narayan Prasad Lohia v/s. Nikunj

Kumar Lohia and others . Para 17 is material and is reproduced herein

under:-

"We are also unable to accept Mr. Venugopal's argument that, as a matter of public policy, Section 10 should be held to be non-

derogable. Even though the said Act is now an integrated law on the subject of Arbitration, it cannot and does not provide for all contingencies. An arbitration being a creature

lgc 60 of 124

wps-7804.09 & 7636.09

of agreement between the parties, it would be impossible for the Legislature to cover all aspects. Just by way of example Section 10

permits the parties to determine the number of arbitrators, provided that such number is not

an even number. Section 11(2) permits parties to agree on a procedure for appointing the arbitrator or arbitrators. Section 11 then provides how arbitrators are to be appointed if the parties do not agree on a procedure or if

there is failure of the agreed procedure. A reading of Section 11 would show that it only provides for appointments in cases where there is only one arbitrator or three arbitrators. By

agreement parties may provide for appointment of 5 or 7 arbitrators. If they do

not provide for a procedure for their appointment or there is failure of the agreed procedure, then Section 11 does not contain

any provision for such a contingency. Can this be taken to mean that the Agreement of the parties is invalid. The answer obviously has to be in the negative. Undoubtedly the procedure

provided in Section 11 will mutatis mutandis apply for appointment of 5 or 7 or more

arbitrators. Similarly even if parties provide for appointment of only two arbitrators, that does not mean that the agreement becomes invalid.

Under Section 11(3) the two arbitrators should

then appoint a third arbitrator who shall act as the presiding arbitrator. Such an appointment should preferably be made at the beginning.

However, we see no reason, why the two arbitrators cannot appoint a third arbitrator at

a later stage i.e. if and when they differ. This would ensure that on a difference of opinion the arbitration proceedings are not frustrated. But if the two Arbitrators agree and give a common award there is no frustration of the proceedings. In such a case their common opinion would have prevailed, even if the third arbitrator, presuming there was one, had differed. Thus we do not see how there would be waste of time, money and expense if a party,

lgc 61 of 124

wps-7804.09 & 7636.09

with open eyes, agrees to go to Arbitration of two persons and then participates in the proceedings. On the contrary there would be

waste of time, money and energy if such a party is allowed to resile because the Award is

not of his liking. Allowing such a party to resile would not be in furtherance of any public policy and would be most inequitable."

The next contention of the learned Senior Counsel for the

Petitioners that since the Annexures 1 to 4 to the IPLA do not form part of the

finally executed IPLA, there is an uncertainty and ambiguity as regards the

Patent portfolio and the Marks which are licensed under the IPLA to the

Petitioners. Though in terms of the scope of inquiry contemplated under

Section 45 of the Indian Arbitration Act, the same is not necessary to be gone

into by this Court. In so far as the said contention is concerned, it is required to

be noted that the business relationship between the parties existed from the

year 1994. The Petitioners were already using the Patents right from 1994 and

to which Patents there were additions. Even the Marks have been used by the

Petitioners right from the year 1994, and therefore, the parties were aware of

the Patents and the marks in respect of which they have entered into a

contract. Therefore, prima facie, there doesn't seem to be any merit in the said

contention of the Petitioners. However, as indicated above, the issue as regards

the alleged infirmity in the underlying contract i.e. the IPLA is required to be

urged before the Arbitral Tribunal, and it will be for the Arbitral Tribunal to

consider the same.

    lgc                                                                                       62 of 124



                                                                          wps-7804.09 & 7636.09




                The   defining   aspect   is   the   intention     of   the   parties   to   go   for 




                                                                                         

arbitration which intention is clearly manifest in the IPLA. On the said aspect,

it would be gainful to refer to the judgment of the Apex Court reported in

Vs.

2009(4) SCC 495 in the matter of Nandan Biomatrix Limited D 1 Oils

Limited,. Paras 26, 27, 30, 32, 33 and 34 are material and are reproduced

herein under :-

"26 The disputed arbitration clause in the present case is clause 15.1, mentioned in the Supply

Agreement, which is reproduced as under:

"15.1 . Any dispute that arises between the parties shall

be resolved by submitting the same to the institutional arbitration in India under the provisions of arbitration and conciliation act, 1996."

"27 Arbitration agreement is defined under

Section 7 of the 1996 Act. It does not prescribe any particular form as such. In terms of the said provision,

arbitration agreement means:

"Section 7 - Arbitration agreement (1) In this Part, "arbitration agreement" means an agreement by the

parties to submit to arbitration all or certain disputes which have arisen or which may arise between them in respect of a defined legal relationship, whether contractual or not.

(2) An arbitration agreement may be in the form of an arbitration clause in a contract or in the form of a separate agreement.

(3) An arbitration agreement shall be in writing.

(4) An arbitration agreement is in writing if it is contained 13 in- (a) a document signed by the parties"

                "30            The Court is required, therefore, to decide 


    lgc                                                                                      63 of 124



                                                                      wps-7804.09 & 7636.09

whether the existence of an agreement to refer the dispute to arbitration can be clearly ascertained in the facts and circumstances of the case. This, in turn, may

depend upon the intention of the parties to be gathered from the correspondence exchanged between the

parties, the agreement in question and the surrounding circumstances. What is required is to gather the intention of the parties as to whether they have agreed for resolution of the disputes through arbitration. What is required to be decided in an application on Section 11

of the 1996 Act is : whether there is an arbitration agreement as defined in the said Act."

"32 I do not find any merit in the above

contentions raised on behalf of the non-applicant. The question which needs to be asked is : what did the

parties intend at the time of execution of the Supply Agreement dated 10.8.04? What did the parties intend when clause 15.1 came to be incorporated in the said

Supply Agreement? The answer to the said questions undoubtedly is that any dispute that may arise between the parties shall be resolved by submitting the same to the Institutional Arbitration in India under the

provisions of the 1996 Act. It may be mentioned that the name of a specific institution is not indicated in clause

15.1."

"33 The 1996 Act does not prescribe any form

for an arbitration agreement. The arbitration agreement is not required to be in any particular form.

[See : Bihar State Mineral Development Corporation & Another v. Encon Builders (I) (P) Ltd. - (2003) 7 SCC

418]. What is required is to gather the intention of the parties as to whether they have agreed for resolution of the disputes through arbitration."

34 In my view, in the present case, the parties unequivocally agreed for resolution of the disputes through Institutional Arbitration and not through an ad hoc arbitration. Therefore, in my view, there exists a valid arbitration agreement between the parties vide clause 15.1 in the Supply Agreement dated 10.8.04. The

lgc 64 of 124

wps-7804.09 & 7636.09

first issue is accordingly answered in favour of the applicant and against the non-applicant.

30 Now coming to the contention of the Learned Senior Counsel for

the Petitioners that the prayer in the suit pertaining to the anti suit injunction

can never be referred to arbitration in support of which contention reliance is

placed by the Learned Senior Counsel on the Judgment of the Apex Court in

Sukanya Holdings Pvt. Ltd. (supra). In so far as the said contention is

concerned, it is required to be noted that the Judgment in Sukanya Holdings

Pvt. Ltd (supra) has been distinguished by the Apex Court in the case of

Rashtriya Ispat Nigam Limited v/s Verma Transport Co. reported in (2006)

7 SCC 275. Paras 23, 45 and 47 of the said report are material and reproduced

herein under :-

"23 In the instant case, the existence of a valid

agreement stands admitted. There cannot also be any dispute that the matter relating to termination of the contract would be a dispute arising out of a contract and, thus, the arbitration agreement contained in clause

44 of the contract would be squarely attracted. Once the conditions precedent contained in the said proceedings are satisfied, the judicial authority is statutorily mandated to refer the matter to arbitration. What is necessary to be looked into therefor, inter alia,

would be as to whether the subject-matter of the dispute is covered by the arbitration agreement or not."

"45 Reliance placed by the learned counsel on Sukanya Holdings (P) Ltd. v. Jayesh H. Pandya and Another [(2003) 5 SCC 531 is misplaced.Therein, not only a suit for dissolution of the firm was filed, but a different cause of action had arisen in relation whereto apart from parties to the arbitration agreement, other parties had also been impleaded. In the aforementioned

lgc 65 of 124

wps-7804.09 & 7636.09

fact situation, this Court held :

"Secondly, there is no provision in the Act that when the

subject-matter of the suit includes subject-matter of the arbitration agreement as well as other disputes, the

matter is required to be referred to arbitration. There is also no provision for splitting the cause or parties and referring the subject-matter of the suit to the arbitrators."

"47 Such a question does not arise herein as the parties herein are parties to the arbitration agreement and the question in regard to the jurisdiction of the arbitrator, if any, can be determined by the arbitrator

himself in terms of Section 16 of the 1996 Act."

In my view, the Judgment in Sukanya Holdings Pvt. Ltd. (supra),

has no application even in the present case because the parties to the instant

proceedings are parties to the Arbitration Agreement and the cause of action

which is sought to be invoked is also covered by the Arbitration Agreement

between the parties and the said relief i.e. anti suit injunction is also claimed

on the basis of the dispute between the parties which are covered by the

Arbitration Agreement. It was held by the Apex Court in Everest Holding's case

(supra) that the Judgment in Sukanya Holdings Pvt.Ltd.'s case(supra) has

been distinguished in the case of Rashtriya Ispat Nigam Ltd. because in

Sukanya Holdings Pvt. Ltd.'s case two distinct and different causes of action

were merged in a suit and it required independent adjudication of the rights of

the flat purchasers who are not governed by the Arbitration Agreement and the

cause of action which is sought to be invoked is also covered by the Arbitration

Agreement between the parties.

    lgc                                                                                        66 of 124



                                                                         wps-7804.09 & 7636.09




    31            Now coming to the judgments relied upon by the learned Senior 




                                                                                        

Counsel for the Petitioners in support of his contention that there can be no

arbitration, if there is no concluded contract. The judgment in Dresser Rand

S.A. (supra) was a case where no contract had come into existence at all as

the contract was spelt out on the basis of a tender document and ultimately the

said tender document which was held to be merely an invitation to offer was

not accepted as a final contract. The terms and condition in the said case

contemplated for an agreement to come into existence only when the final

purchase order was placed, as there was no such purchase order placed, it was

held that there was no concluded contract. It is is well settled that the tender

or bid document is merely an invitation to offer, and therefore, the same by

itself cannot be treated as a contract between the parties.

In the case of Andhra Pradesh Tourism Development

Corporation Ltd & Anr. (supra), the facts were that even prior to the

incorporation and registration of a company, a contract was executed by its

purported Managing Director in the capacity of a Managing Director of the

company which was at the time not in existence. It was held that obviously

when the parties to an agreement do not exist, there could never be valid

parties to the agreement, and consequently, there can never be a valid

Arbitration Agreement between such parties.

    lgc                                                                                     67 of 124



                                                                             wps-7804.09 & 7636.09




In the case of Jawahar Lal Burman (supra) the contention was

that there was only a conditional acceptance of the tender and therefore there

was no concluded valid contract. On the basis of the facts of the said case the

Apex Court has held in Para 15 of the said report that there was a concluded

contract and the condition of security deposit was a condition subsequent and

not a condition precedent.

In the case of Rickmers Verwaltung GmbH (supra) the

correspondence between the parties were sought to be relied upon to spell out

a concluded contract. It is in the said context that the Apex Court examined

the said case and came to a conclusion that the correspondence in that case

does not spell out a concluded contract between the parties.

In my view, the said judgments do not further the case of the

Petitioners in any manner. As indicated above, the inquiry that this Court is

required to make under Section 45 of the Indian Arbitration Act is limited to

determine prima facie whether there is in existence an Arbitration Agreement

and if yes, refer the parties to arbitration unless it finds that the Arbitration

Agreement is invalid, inoperative, null, void and incapable of being performed.

Invalidity of the agreement could only be on the ground if the same is

questioned on the grounds of coercion, fraud, misrepresentation or that the

lgc 68 of 124

wps-7804.09 & 7636.09

said agreement has not been duly executed. It is pertinent to note that in the

instant case, the parties are not relying upon any correspondence for the

purposes of establishing the existence of the contract, because in the instant

case the IPLA is duly executed in writing and signed by the parties. The

correspondence that is sought to be relied upon by the parties is in support of

their respective assertions that the IPLA is not a concluded contract or that the

IPLA is a concluded contract. So far as the Respondents are concerned, the

said correspondence is relied upon to demonstrate that the parties had applied

their mind to the drafts of the IPLA, that were prepared before finally

executing the same on 29/09/2006. In my view, the Lower Appellate Court

was right in interfering with the order passed by the Trial Court. The view

taken by the Lower Appellate Court on the aspect of referring the parties to

arbitration on a prima facie view that there is in existence an Arbitration

Agreement cannot be faulted with in the facts and circumstances of the case.

CONCLUSION - WRIT PETITION NO.7804 OF 2009

32 In the light of the well settled position in law that the Court whilst

considering an Application under Section 45 of the Indian Arbitration Act has

only to arrive at a prima facie conclusion that there exist an Arbitration

Agreement, the submission of the learned Senior Counsel for the Petitioners

that since the Lower Appellate Court has referred the parties to arbitration

lgc 69 of 124

wps-7804.09 & 7636.09

without recording a finding that the IPLA is a concluded contract, is therefore

without merit. The scope of the jurisdiction under Article 227 of the

Constitution of India has been succinctly elucidated in the judgments which

have been cited on either side. It is well settled that the powers under Article

227 of the Constitution of India cannot be exercised "as a cloak of an Appeal in

disguise" and that the writ court cannot substitute its own conclusion for the

conclusion reached by the courts below. Interference is called for only if the

impugned order results in a mis-carriage of justice or the findings are so

perverse that no reasonable person could have arrived at such findings. In my

view, in the facts and circumstances of the present case, the conclusion arrived

at by the Lower Appellate Court whilst referring the parties to arbitration

cannot be said to be a conclusion which could not be arrived at in the facts

and circumstances of the case

33 In any event, since the findings of the Lower Appellate Court can

only be said to be prima facie in nature, the Petitioners would have an

opportunity to agitate the issue which they seek to agitate before the Arbitral

Tribunal. Hence in so far as the part of the impugned order, which relates to

the application filed by the Respondents under Section 45, is concerned, no

interference is called for in the writ jurisdiction of this Court under Article 227

of the Constitution of India. The Writ Petition No.7804 of 2009 is accordingly

dismissed. Rule discharged, with no order as to costs.

    lgc                                                                                        70 of 124



                                                                   wps-7804.09 & 7636.09


    34      SUBMISSIONS   ON   BEHALF   OF   THE   PETITIONERS   BY   THE 

LEARNED SENIOR COUNSEL DR.VEERENDRA TULZAPURKAR

IN WRIT PETITION NO.7636 OF 2009

(i) That assuming that the IPLA is a concluded contract in view of

Clause 18.3 wherein it has been specifically stated that the

"Arbitration and Conciliation Act, 1996" i.e. the Indian Arbitration

Act would be applicable, the said Act would therefore govern the

procedure as also a conduct of the proceedings and therefore the

English Courts would not have jurisdiction.

(ii) That since the arbitration is governed by the Indian Arbitration

Act, it is only the Indian Courts which would have jurisdiction,

and the Petitioners are therefore entitled to an injunction

restraining the Respondents from proceeding further with the

proceedings in the English Court;

(iii) That in view of an express choice of law i.e. the Indian Arbitration

Act, having been made by the parties as the law governing the

arbitration and the curial law, there is no question of determining

the seat of arbitration. For the said purpose the learned Senior

Counsel would place reliance on the following judgments reported

in :-

    lgc                                                                               71 of 124



                                                                    wps-7804.09 & 7636.09




            (1)    (2007)   5   SCC   692,   National   Agricultural   Co-op  




                                                                                   

Marketing Federation Indian Ltd v/s. Gains Trading Ltd. (2) (2009) 7 SCC 220, Citation Infowares Ltd. v/s. Equinox

Corporation ;

(3) (2008) 10 SCC 308, Indtel Technical Services Pvt. Ltd v/s.

W.S. Atkins;

(4) (2002) 4 SCC 105, Bhatia International v/s. Bulk Trading S.A. And Another;

(5) (1988) 1 Lloyds L.R. 116, Naviera Amazonica v/s Compania International;

(6) 2011(3) ARBL 350, Prima Buildwell v/s. Lost City; (7) (2008) E.W.H.C. 426, Breas of Doune v/s. Alfred Mc

Alpine,

(iv)

That in so far as arbitration proceedings are concerned, the

concept of venue is different from the concept of seat of

arbitration. The seat of arbitration would have the consequences

of fixing the jurisdiction. In the instant case, since the London is

only the "venue" and since the parties have chosen the application

of the Indian Arbitration Act, the parties would be governed by the

said Indian Law.

(v) That the determination of the seat of arbitration would come into

play only if the parties have not chosen the law which would be

applicable and it is only in the said context that the Court would

have to find out as to which curial law would apply to the

arbitration. Moreover, the curial law comes much later which is in

respect of the conduct of the proceedings. In the instant case, there

lgc 72 of 124

wps-7804.09 & 7636.09

is no need to find out the law applicable for which the seat of

arbitration can be an indicia, as the parties have by choice agreed

to the application of the Indian Arbitration Act. For the said

purpose the learned Senior Counsel relied upon two English

Judgments i.e. the judgment reported in (2008) EWHC 426 in the

matter of Braes of Doune Wind Farm (Scotland) Ltd. v. Alfred

Mcalpine Business Services Ltd. and (1988) Vol.1 Lloyd's Law

Reports 116 in the matter of Naviera Amazonica Peruana S.A.

v/s. Compania Internacional DE Seguros Del Peru.

(vi) That once the agreement contained a express term which in this

case is the Indian Arbitration Act, it is not open for the Court to

read into a contract a term on the basis of the venue which in the

instant case is the application of the English Law. The learned

Senior Counsel for the said purpose relied upon the judgments of

the Apex Court reported in (1968) 1 SCR 821 in the matter of

Nathati Jute Mills Ltd. v/s Khyaliram Jagannath.

(vii) That it is not permissible to interpret the said clause 18.3 in a

restricted manner so as to limit/confine the choice of law made by

the parties only to some parts of the Act. When the agreement in

clause 18.3 provides that the 'provisions of the Arbitration and

lgc 73 of 124

wps-7804.09 & 7636.09

Conciliation Act, 1996 shall apply', it is agreed between the parties

that the entire Act applies and not the select provisions. In

support of the said contention the learned Senior Counsel would

place reliance on the judgments of the Apex Court reported in

(1994) 4 SCC 104 in the matter of Assistant Excise

Commissioner v/s Isaac Peter, and 1968 (1) SCR 821 in the

matter of Naihiti Jute Mills Limited v/s. Khyalynam Jagannath.

(viii)

That once the parties have agreed that the Indian Arbitration Act

would apply, then any action contrary to the provisions of the

Indian Arbitration Act amounts to breach of contract, and if a

party commits breach of contract after expressly agreeing to the

application of the Indian Arbitration Act thereby to the exclusive

jurisdiction of the Indian Court, the Court ought to grant an

interim injunction preventing continuance of such breach.

(ix) That since the substantive prayer is as regards the injunction

sought by the Petitioners against the Respondents restraining them

from approaching the English Courts in view of the said

Arbitration Agreement, this Court would have to consider the

grant of the said relief as the said relief cannot be the subject

matter of arbitration. The learned Senior Counsel relied upon the

lgc 74 of 124

wps-7804.09 & 7636.09

judgment of the Apex Court in (2003) 5 SCC 531 in the matter of

Sukanya Holdings (P) Ltd. v/s. Jayesh H Pandya and anr.

(x) That it is well settled that where a party is put in an inextricable

situation by the proceedings filed in a foreign court, such a

situation would be oppressive to such a party. The Apex Court has

ruled that in such cases the Courts in India ought to exercise

jurisdiction and injunct parties from proceeding with the

proceedings in a foreign court. Reliance was placed on the

judgment of the Apex Court reported in (1987) 1 SCC 496 in the

matter of ONGC v/s. Western Company, North America.

(xi) That the learned Senior Counsel for the Petitioners in the

alternative submitted that even assuming the English Arbitration

Act, 1996 applies, since Section 18 which provides for

appointment of Arbitral Tribunal being non-mandatory, and in

view of the agreement between the parties that the Indian

Arbitration Act will apply, the application of the non-mandatory

provision of the English Arbitration Act is excluded by virtue of the

provisions of Section 4(2) of the English Arbitration Act, 1996.

The English Court therefore would have no jurisdiction to

entertain any application for appointment of Arbitral Tribunal.

    lgc                                                                                 75 of 124



                                                                      wps-7804.09 & 7636.09




    (xii)    That the issue of seat of arbitration would not arise in the present 




                                                                                     

case in view of the settled position in law as enunciated by the

Apex Court in the case of Bhatia International v/s Bulk Trading

SA and Another reported in (2002) 4 SCC 105 wherein the Apex

Court has held that in cases of international commercial

arbitrations held out of India provisions of Part I would apply

unless the parties by agreement, express or implied, exclude all or

any of its provisions.

(xiii) That the matter of appointment of Arbitral Tribunal is covered by

the law of Arbitration Agreement, and not the curial law or lex

arbitri. In support of the said submission the learned Senior

Counsel would place reliance on the judgment of the Apex Court

reported in (1998) 1 SCC 305 in the matter of Sumitomo Heavy

Industries v/s. ONGC, and (2012) 1 BCR 547 in the matter of

Sakuma Exports v/s Louis .

(xiv) That the curial law that would be applicable to the arbitration

proceeding cannot be approached from the choice of seat if the

parties have expressly chosen the application of a particular law.

The approach should therefore be to find out what is the law

lgc 76 of 124

wps-7804.09 & 7636.09

chosen by the parties rather than first finding out the seat and

then determine the law; that once the parties have made a choice

of the law applicable to Arbitration Agreement and the curial law,

then there is no need for finding out what the seat is and what

would be the law if a seat is in a particular country.

(xv) That the reference to the seat becomes relevant only in the

absence of choice of the curial law and this is borne out from the

passages of the very text books and the judgments relied upon by

the Respondents.

(xvi) That the choice of the parties as regards the proper law of

arbitration or the curial law is the determinative factor for

ascertaining the seat of arbitration. Only absent such choice, the

question of finding the seat of arbitration arises.

(xvii) That the judgments cited on behalf of the Respondents on the

aspect of seat being the determinative factor are not applicable in

the facts of the present case when the parties have expressly

chosen the application of the Indian Arbitration Act. In the cases

cited by the Respondents there was no choice of the proper law of

the Arbitration Agreement and/or the curial law and it is in the

lgc 77 of 124

wps-7804.09 & 7636.09

said circumstances that the choice of the seat became a

determinative factor.

(xviii) That the parties have agreed to the application of the Indian

Arbitration Act, 1996 to be the proper law of arbitration as well as

curial law is also indicative from the fact that in clause 18.3 the

expression "Presiding Arbitrator" is used which appears in the

Indian Arbitration Act, 1996 whereas the English Arbitration Act,

1996 the word "Umpire" appears.

(xix) If a party acts against the terms of the contract, it has the effect of

causing harm and injury to the other side. In the instant case, the

Respondents have invoked jurisdiction of the English Courts and

thereby dragging the Petitioners to a Court which does not have

jurisdiction in terms of the agreement. Reliance was placed on the

judgment of the Apex court in ONGC v/s. Western Company,

North America.(supra)

(xx) That the Petitioners are entitled to an anti suit injunction by the

reason of choice of the Indian Arbitration Act, by the parties as the

applicable law relating to the entire arbitration. It is only the

Indian Courts which would have jurisdiction, and the English

lgc 78 of 124

wps-7804.09 & 7636.09

Courts would have none. The Respondents having approached the

English Court thereby breaching the agreement as they have

wrongly invoked the jurisdiction of the English Court, the

Petitioners are therefore approaching the Civil Court to prevent

continuance of the breach by seeking an anti suit injunction.

(xxi) That the assets of the Respondents in the form of shares of

Petitioner No.1 and the dividend income arising thereform are in

Daman making the Respondents personally amenable to the

jurisdiction of the Daman Court as any order passed by the Daman

Court can be enforced against the assets of the Respondents in

Daman.

(xxii) That the Petitioner No.1 being a joint venture between the

Respondent No.1 and Mehra family. A joint venture is in the

nature of a partnership. The Respondent No.1 as partner of the

joint venture is carrying on business in Daman, and as such are

within the personal jurisdiction of the Daman Court. The learned

Senior Counsel in support of the said contention has relied upon

the judgment of the Apex Court reported in 1995(1) SCC 478 in

the matter of New Horizons Limited and Anr v/s Union of India,

and the judgments of this Court reported in AIR 1932 Nag 114 in

lgc 79 of 124

wps-7804.09 & 7636.09

the matter of Tarabai v/s Chogmal and in AIR 1971 Bom 362 in

the matter of Ex-parte-Girdharlal Shankar Dave which was

approved in the judgment reported in 1986 MLJ 325 in the

matter of Harshad V/s Ishardas.

(xxiii) That allowing the Respondents to proceed in the English Court

will result in allowing them to commit breach of and continue to

commit breach of the express agreement between the parties.

35 SUBMISSIONS ON BEHALF OF THE RESPONDENTS BY THE

LEARNED SENIOR COUNSEL SHRI NAVROZE SEERVAI IN WRIT PETITION NO.7636 OF 2009:-

[A] That the seat is a juristic concept and is not a linguistic concept,

as is sought to be contended by the learned counsel for the

Petitioners. The juristic concept of a seat is to be gathered from

the terms of the agreement, as it expresses the consensual intent

of the parties.

[B] That use of the expression "place", "venue" or directly referring to

the "city" where the arbitration is to take place, would mean that

all such words, phrases are used to indicate the seat of arbitration

and would not mean a geographical location.

    lgc                                                                                 80 of 124



                                                                    wps-7804.09 & 7636.09

    [C]     That since none of the  parties to the  IPLA are even located in 

London, it therefore clearly indicates that London was not

referred to for the sake of convenience but was designated as the

seat by the parties.

(D) That the parties having chosen the seat of arbitration as London

which is contained in Clause 18.3 of the agreement, it is not

proper for the Petitioners to resile from the said clause so as to

contend that London was chosen geographically as it was

convenient for the parties to meet in London.

(E) That the Petitioners approaching the Civil Court in Daman i.e. the

Indian Court are therefore acting in breach of the Arbitration

Agreement.

(F) The conjoint reading of Sections, 2, 4 and 5 of the English

Arbitration Act makes it clear that once the Arbitration Agreement

is in writing and the venue is London, the said agreement would

have to be given effect.

(G) That in terms of the English Arbitration Act both the mandatory

and non-mandatory provisions of the said Act would apply.

    lgc                                                                                81 of 124



                                                                    wps-7804.09 & 7636.09


    (H)     That in view of the fact that the seat of arbitration is London, the 




                                                                                   

applicability of the Arbitration and Conciliation Act, 1996 of India

would only govern the Arbitration Agreement but not the Lex

Arbitri.

(I) That the law of the country wherein the seat is situated would be

applicable in so far as the Lex Arbitri is concerned, the said

position is made clear from the commentaries of the learned

Authors Mustill & Boyd, Russell and Redfern & Hunter. The

learned Senior Counsel relied upon the following passages from

the commentaries of the three learned authors.

Mustill and Boyd - Chapter IV - The applicable law and the

jurisdiction of the court.

Russell - Paragraphs 2-087, 2-088, 2-090, 2-093, 2-094, 2-099, 2-

100 to 2-109.

Redfern and Hunter - Chapter 3 - Paragraphs 3.09 to 3.33 &

Paragraph 3.34 from the Chapter - The Law Governing the

Arbitration

[J] That the learned Authors have made it clear that in the absence of

an agreement as to the procedural law, the choice of seat

determines the procedural law of the arbitration. That where

lgc 82 of 124

wps-7804.09 & 7636.09

parties have failed to choose the law governing the arbitration

proceedings, those proceedings must be considered as being

governed by the law of the country in which the arbitration is

held on the ground that it is the country most closely connected

with the proceedings. In support of the said contention, the

learned Senior Counsel for the Respondents has relied upon the

following judgments. (1970) AC 583, James Miller & Partners

Ltd. v/s Whitworth Street Estate; (1984) 1 QB 291, Bank

Mellat v/s Helliniki Techniki SA; (1988) 1 Lloyd's Law Reports

116, Naviera v/s Compania; (2011) 6 SCC 179, Dozco India

Pvt. Ltd. v/s Doosan Infracore Company Ltd; (2011) 6 161,

Videocon Industries Ltd v/s. Union of India; (2011) 9 SCC 735

Yograj Infrastructure Ltd. v/s. Ssang Yong Engineering and

Construction Ltd; (2010) 3 Arb. L.R. 70, Bhushan Steel v/s

Singapore International Arbitration Centre; and (2011) 3 Arb.

L.R. 350, Prima Buildwell Private Ltd v/s. Lost City

Development LLC.

(K) That since the seat of arbitration being London, the English Law

would be applicable can be seen from Section 4 of the English

Arbitration and Conciliation Act, 1996. The said Act postulates

that unless there is clear and unequivocal intention to the contrary

lgc 83 of 124

wps-7804.09 & 7636.09

the law of the country wherein the seat of arbitration is situated

would govern the law of arbitration.

(L) That the seat of arbitration has got far reaching consequences in

the context of the application of the lex arbitri or the curial law,

the learned Senior Counsel in support of his contention that it

would be the English Arbitration Act that would be applicable

relied upon the following English judgments :-

[I] of C v D.

(2008) Vol. 1 Lloyd's Law Reporter page 239 in the matter

[II] (2007) Vol. 1 Lloyd's Law Reporter page 237 in the matter

of A v B [III] 2007 Vol. 1 Lloyd's Law Reporter page 358 in the matter of A v B (Costs) (No.2) [IV] (2009) Vol.2 Lloyd's Law Reporter page 376 in the matter

of Shashoua and others v Sharma [V] (2006)1 AC page 221 in the matter of Lesotho Highlands

Development Authority v/s Impregilo Spa and others. [VI] 1970 AC page 583 in the matter of James Miller & Partners Ltd, and Whitworth Street Estates (Manchester) Ltd. (Lord Hudson, J)

[VII] (1984) 1 QB page 291, in the matter of Bank Mellat v Helliniki Techniki S.A (Lord Waller, Lord Kerr and Lord Robert Goff L. JJ) [VIII] (1988) Vol 1 page 116, in the mater of Naviera Amazonica Peruana S.A. v. Compania Interacional De Serguros Del

Peru

[M] That the seat being London, the arbitration proceedings would be

governed by the English Arbitration Act, and therefore, there

would be exclusion of the Indian Arbitration Act, in so far as the

Lex Arbitri or the curial law is concerned, the natural corollary

lgc 84 of 124

wps-7804.09 & 7636.09

would be that the English Courts would have supervision over the

arbitration proceedings, therefore, the Respondents were entitled

to approach the English Court. In support of the said contention,

the learned Senior Counsel relied upon the following English

Judgments :-

[I] (2007) Vol.2 Lloyd's Law Reporter page 367 in the matter of C v D [II] (2008) Vol. 1 Lloyd's Law Reporter Appeal Court page 239 in the matter of C v D.

[III] (2007) Vol. 1 Lloyd's Law Reporter page 237 in the matter

of A v B [IV] 2007 Vol. 1 Lloyd's Law Reporter page 358 in the matter of A v B (No.2)

[IV] (2009) Vol.2 Lloyd's Law Reporter page 376 in the matter of Shashoua and others v Sharma

[N] That in so far as international commercial arbitration is

concerned, there are three potential systems of law applicable to

the arbitration viz, (1) The law governing the substantive

contract; (2) The law governing the agreement to arbitrate and

the performance of that agreement; and (3) The law governing

the conduct of the arbitration. In majority of cases all three will

be the same, but (1) will often be different from (2) and (3), and

occasionally, but rarely, (2) may also differ from (3).

[O] That the enquiry of the Court to ascertain the choice of seat in a

case where a place/venue/city has been mentioned/nominated by

lgc 85 of 124

wps-7804.09 & 7636.09

the parties, does not commence with a consideration of the

proper law of the contract/ arbitration, whilst ignoring the chosen

place/venue, as contended by the Petitioners. If the said

contention of the Petitioners is accepted, it would mean that once

the parties have chosen the law governing the Arbitration

Agreement, that law is both the law of the Arbitration Agreement

and the curial law and the parties's express choice of a curial law

by reference to a seat is to be completely ignored and rendered

otiose

[P] That the choice of law has to be a specific choice of curial law i.e.

the agreement must state that the law of a particular country as

the curial law. In the absence of any such specific agreement as to

curial law, the law of the country in which the seat of arbitration

is situate will apply.

[Q] That the non-mandatory provisions of the English Arbitration Act

can be excluded if there is an express agreement to the contrary

and such agreement is the one contemplated by Section 4(2) of

the English Arbitration Act and that in the absence of any such

agreement, the non mandatory provisions become mandatory and

that in view thereof, the provisions of Section 18 of the English

lgc 86 of 124

wps-7804.09 & 7636.09

Arbitration Act, which provides for machinery for appointment of

Arbitral Tribunal, is applicable and the Respondents cannot be

prevented from approaching the English Court for constitution of

the Arbitral Tribunal.

[R] That the curial law and the substantive law relating to Arbitration

Agreement are different and separate; whereas the substantive

law of arbitration governs the existence or validity of the

arbitration, the curial law governs the reference including the

appointment of Tribunal, and that the terms 'Constitution of the

Tribunal' refers to the composition or qualification of the

arbitrators and not its appointment.

[S] That the Petitioners being in breach of the agreement whereby

they have agreed to the exclusive jurisdiction of the English Court

having agreed to London as the seat are not entitled to any anti-

suit injunction.

[T] That the Respondents are not amenable to the jurisdiction of the

Courts in Daman and the Respondents cannot therefore be

injuncted from proceeding in a Court which has exclusive

jurisdiction.

    lgc                                                                              87 of 124



                                                                         wps-7804.09 & 7636.09




    [U]          That the Petitioners are not entitled to anti-suit injunction in view 




                                                                                        

of the well settled principles laid down in the judgment of the

Apex Court reported in (2003) 4 SCC 341 in the case of Modi

Entertainment Ltd. V/s. W.S.G. Cricket Pvt. Ltd.

[V] The learned Senior Counsel in the alternative submitted that

assuming the Indian Arbitration and Conciliation Act 1996 applies

on account of the choice of London as the venue, the English

Courts, if not having an exclusive jurisdiction, have concurrent

jurisdiction on account of Section 2(4) of the English Arbitration

Act.

[W] That since the parties have not specifically provided for as to what

is to happen in the event of a failure of the procedure for

appointment of the Arbitral Tribunal, and since Section 18 of the

English Act has not been excluded by the parties, the English

Courts have concurrent jurisdiction.

CONSIDERATION - WRIT PETITION NO.7636 OF 2009

36 Heard the learned counsel for the parties and also perused the

Written Submissions filed on behalf of the parties.

    lgc                                                                                     88 of 124



                                                                          wps-7804.09 & 7636.09




    37              This Court in Writ Petition No.7804 of 2009 has taken a  prima  




                                                                                         

facie view that there is in existence an Arbitration Agreement and therefore the

parties can be referred to arbitration. In so far as instant Petition i.e. Writ

Petition No.7636 of 2009 is concerned, the question is whether the Petitioners

are entitled to an anti suit injunction, and whether the English Courts have

jurisdiction.

The adjudication of the said aspect therefore revolves around the

interpretation of clause 18.3 of the IPLA. For the sake of convenience, the said

clause 18.3 is revisited herein under for the purposes of the present Petition.

"Clause 18.3---- All proceedings in such arbitration shall

be conducted in English. The venue of the arbitration proceedings shall be London. The arbitrators may (but

shall not be obliged to) award costs and reasonable expenses (including reasonable fees of counsel) to the Party(ies) that substantially prevail on merit. The provisions of the Indian Arbitration and Conciliation Act,

1996 shall apply"

39 The defining words therefore are that "The venue of the

arbitration proceedings shall be London", "The provisions of the Indian

Arbitration and Conciliation Act, 1996 shall apply". The learned Senior Counsel

for the Petitioners would contend, relying upon the said words that the parties

have made a choice of Lex Arbitri as well as curial law, and therefore, there is

no question of embarking upon an exercise of determining the seat so as to

lgc 89 of 124

wps-7804.09 & 7636.09

determine the curial law that would be applicable. In the said context, it would

be apposite to refer to the judgment in Bhatia International v/s Bulk Trading

S.A. & Another reported in (2002) 4 SCC 105; which covers the issue of the

application of Part-I of the Indian Arbitration Act. In the said case the

arbitration clause provided that the arbitration would as per the rule of the

International Chambers of Commerce. The arbitration was to be held in Paris.

Section 9 of the Arbitration Act, 1996 was invoked. The Additional District

Judge seating at Indore held that he had jurisdiction against the said order. A

writ was filed which was dismissed and the matter reached the Apex Court.

The Apex Court held that Part-I applies even when the arbitration was to be

held out of India unless parties agreed to exclude application of that part.

Para-32 of the said judgment is material and is reproduced herein under :-

"32. To conclude we hold that the provisions of Part I

would apply to all arbitrations and to all proceedings relating thereto. Where such arbitration is held in India the provisions of Part I would compulsory apply and parties are free to deviate only to the extent permitted

by the derogable provisions of Part I. In cases of international commercial arbitrations held out of India provisions of Part I would apply unless the parties by agreement, express or implied, exclude all or any of its provisions. In that case the laws or rules chosen by the

parties would prevail. Any provision, in Part I, which is contrary to or excluded by that law or rules will not apply."

40 In the said context, a reference could be made to the judgment

cited on behalf of the Petitioners viz. (2007) 5 SCC 692 in the matter of

National Agricultural Co-op Marketing Federation India Ltd. v/s Gains

lgc 90 of 124

wps-7804.09 & 7636.09

Trading Ltd. Paras 8 and 9 are material and are reproduced herein under :-

"8. Let me now examine whether the arbitration

procedure and appointment of arbitrator is governed by the Act, or by the laws in Hong Kong. This depends on the

interpretation of the arbitration clause in particular the following words : "the matter in dispute shall then be referred to and finally resolved by arbitration in Hong Kong in accordance with the provisions of the Arbitration and Conciliation Act, 1996." The respondent wants to read

this provision thus :

(i) the matter in dispute shall be referred to arbitration at Hong Kong;

(ii) the matter in dispute shall be finally resolved

by arbitration at Hong Kong; and

The respondent wants to ignore the words "in accordance

with the provisions of Arbitration and Conciliation Act, 1976 or any other statutory modification, enactment or amendment thereof for the time being in force" in clause 17 as a meaningless addition. The use of the words

'referred to and finally resolved by arbitration in Hong Kong', according to respondent, shows an intention that

the arbitration has to take place in Hong Kong in accordance with Hong Kong Laws.

9. The rules of interpretation require the clause to be

read in the ordinary and natural sense, except where that would lead to an absurdity. No part of a term or clause should be considered as a meaningless surplusage, when it is in consonance with the other parts of the clause and expresses the specific intention of parties. When read

normally, the arbitration clause makes it clear that the matter in dispute shall be referred to and finally resolved by arbitration in accordance with the provisions of the Arbitration and Conciliation Act, 1996 (or any statutory modification, enactment or amendment thereof) and the venue of arbitration shall be Hong Kong. This interpretation does not render any part of the arbitration clause, meaningless or redundant. Merely because the parties have agreed that the venue of arbitration shall be Hong Kong, it does not follow that Laws in force in Hong

lgc 91 of 124

wps-7804.09 & 7636.09

Kong will apply. The arbitration clause states that the Arbitration and Conciliation Act, 1996 (an Indian Statute) will apply. Therefore, the said Act will govern the

appointment of arbitrator, the reference of disputes and the entire process and procedure of arbitration from the

stage of appointment of arbitrator till the award is made and executed/given effect to."

(2009) 7 SCC 220 in the matter of Citation Infowares Limited v/s. Equinox

Corporation. Paras 9, 12, 16, 31 and 32 are material and are reproduced

herein under :-

"9. What is important is the agreement dated 25.01.2007

which has already been referred to. Under the said agreement clause 10.1 provided as under:

"10.1 Governing law- This agreement shall be

governed by and interpreted in accordance with the laws of California, USA and matters of dispute, if any, relating to this agreement or its subject matter shall be referred for arbitration to

a mutually agreed Arbitrator."

Thus, in between, first agreement dated 09.02.2004 and the subsequent agreement dated 25.01.2007 there was an essential difference that under the last agreement the governing law was to be that of California, USA. However,

that clause did provide for arbitration in case of disputes."

"12 So far so good. However, the question that has arisen is whether this Court would have the jurisdiction in the present factual scenario and on the backdrop of the

fact that the parties vide the aforementioned clause 10.1 had agreed that the governing law would be that of California, USA. According to the applicant, it is only this Court which would have the jurisdiction to appoint the Arbitrator, while according to the respondent this Court does not have the jurisdiction to appoint the Arbitrator as the provisions of the Arbitration Act would necessarily stand excluded in view of the specific language of clause 10.1 of the agreement wherein the governing law would be the law of California, USA."

    lgc                                                                                      92 of 124



                                                                         wps-7804.09 & 7636.09


"16. As against this, Shri Krishnan Venugopal, Learned Senior Counsel appearing on behalf of the respondent

urged from the language of the clause 10.1 that where the governing law is agreed between the parties, say foreign

law, then essentially, the question of appointment of arbitrator also falls in the realm of the said foreign law and not within the realm of Arbitration and Conciliation Act."

"31 It may be that the Arbitrator might be required to take into account the applicable laws which may be the foreign laws but that does not effect the jurisdiction under

Section 11 which falls in Part I which has been specifically held applicable in Bhatia International case. The learned

Judge, deciding Indtel Technical Services' case also has taken into consideration this aspect and has expressed in Paragraph 36 as follows: (SCC p.317)

"36...... The decisions cited by Mr. Tripathi and the views of the jurists referred to in NTPC case support such a proposition. What, however,

distinguishes the various decisions and views of the authorities in this case is the fact that in

Bhatia International this Court laid down the proposition that notwithstanding the provisions of Section 2(2) of the Arbitration and Conciliation Act, 1996 indicating that Part I of the said Act

would apply where the place of arbitration is in India, even in respect of international commercial agreements, which are to be governed by the laws of another country, the parties would be entitled to invoke the provisions of Part I of the aforesaid

Act and consequently the application made under Section 11 thereof would be maintainable.

The situation therefore is identical in the present matter."

"32 Shri Venugopal, however, contended that if the parties intended specifically in this case that the law governing the contract was Californian law, as expressed

lgc 93 of 124

wps-7804.09 & 7636.09

in Bhatia International as well as in Indtel Technical Services' case, an implied exclusion of Part I should be presumed. I am afraid it is not possible to read such an

implied exclusion. Seeing the striking similarity between Clause 10.1 in the instant case and Clauses 13.1 and 13.2

in Indtel case which have been quoted above and further the view expressed by learned Judge in Indtel Technical Services' case regarding the exclusion, it is only possible to read even distantly such an implied exclusion of Part I. It

cannot be forgotten that one of the contracting parties is the Indian party. The obligations under the contract were to be completed in India. Further considering the nature of the contract, it is difficult to read any such implied exclusion of Part I in the language of Clause 10.1. That

argument of learned senior counsel for the respondent therefore must be rejected."

(2008) 10 SCC 308 in the matter of Indtel Technical Services Private

Limited v/s. W.S. Atkins Rail Limited; Para 36 is relevant and is reproduced

herein under :-

"36 Although, the matter has been argued at great

length and Mr. Tripathi has tried to establish that the decision of this Court in Bhatia International case is not relevant for a decision in this case, I am unable to accept such contention in the facts and circumstances of the

present case. It is no doubt true that it is fairly well-

settled that when an arbitration agreement is silent as to the law and procedure to be followed in implementing the arbitration agreement, the law governing the said agreement would ordinarily be the same as the law

governing the contract itself. The decisions cited by Mr. Tripathi and the views of the jurists referred to in NTPC case support such a proposition. What, however, distinguishes the various decisions and views of the authorities in this case is the fact that in Bhatia International this Court laid down the proposition that notwithstanding the provisions of Section 2(2) of the Arbitration and Conciliation Act, 1996 indicating that Part I of the said Act would apply where the place of arbitration is in India, even in respect of international

lgc 94 of 124

wps-7804.09 & 7636.09

commercial agreements, which are to be governed by the laws of another country, the parties would be entitled to invoke the provisions of Part I of the

aforesaid Act and consequently the application made under Section 11 thereof would be maintainable."

(1988) 1 Lloyds L.R. 116 in the matter of Naviera Amazonica v/s Compania

International, In the said judgment the statement of law in Para (C) on page

119 is relevant and the same is reproduced herein under :-

"Where the parties have failed to choose the law

governing the arbitration proceedings, those proceedings must be considered, at any rate prima

facie, as being governed by the law of country in which the arbitration is held, on the ground that it is the country most closely connected with the proceeding."

Similar view has been expressed in the judgments reported in 2011(3) ARBL

350, in the matter of Prima Builders v/s. Lost City, and (2008) E.W.H.C.

426, in the matter of Breas of Doune v/s. Alfred . The proposition which is

laid down is that once an express choice is made by the parties, the parties

would be bound by the said choice.

41 It is a well settled position based on the commentaries of the

learned authors as also the judicial pronouncements, that the problems arising

out of an arbitration may call for the application of any one or more of the

following laws :-

    lgc                                                                                       95 of 124



                                                                         wps-7804.09 & 7636.09

[i] the proper law of the contract i.e. the law governing the contract which creates the substantive rights of the parties in respect of which dispute has arisen;

[ii] the proper law of arbitration agreement i.e. the law

governing the obligation of the parties to submit disputes to arbitration and to honour any award; and

[iii] the curial law i.e. the law governing the conduct of the

individual reference.

The learned authors Mustill & Boyd have classified them as

follows :-

[i] The proper law of arbitration agreement governs the validity of the arbitration agreement, the question whether a dispute lies within the scope of the arbitration agreement; the validity of the notice of

arbitration; the constitution of the tribunal; the question whether an award lies within the jurisdiction of the

arbitrator; the formal validity of the award; the question whether the parties have been discharged from any obligation to arbitrate future dispute.

[ii] The curial law governs : the manner in which the reference is to be conducted; the procedural powers and duties of the arbitrator; questions of evidence; the determination of the proper law of the contract.

[iii] The proper law of the reference governs: the question whether the parties have been discharged from the obligation to continue with the reference of the individual dispute.

The learned author Russell has classified in Chapter 5(c) as

follows:-

    lgc                                                                                     96 of 124



                                                                          wps-7804.09 & 7636.09

"That with the arbitration agreement itself it is also open to the parties to specify a procedural law for the arbitration which is different from the law governing

the arbitration agreement. In Para 2-101 it is made clear that in the absence of an agreement as to the

procedural law the choice of seat prescribes the procedural law of arbitration."

The learned authors Mustill & Boyd with reference to determination of the

curial law have stated as follows :-

"The choice of curial law may be made expressly, and

such a choice is effective, even though the law chosen is neither the proper law of the arbitration agreement nor

the law of the country where the arbitration is to take place. An express choice of curial law different from that of the proper law of the arbitration agreement is not

particularly unsual and does not give rise to any particular problems. An express choice of curial law different from the law of the country in which the arbitration is to be held is however almost unknown.

This is no doubt because of the formidable conceptual and practical problems which are likely to arise should

be necessary to invoke the powers of a court in relation to the reference.... In the absence of express agreement, there is a strong prima facie presumption that the parties intended the curial law to be the law of the `seat' of the

arbitration, i.e. the place at which the arbitration is to be conducted, on the ground that that is the country most closely connected with the proceedings. So in order to determine the curial law in the absence of an express choice by the parties it is first necessary to determine the

seat of the arbitration, by construing the agreement to arbitrate."

The learned Senior Counsel appearing for the Respondents

strenuously urged that in the instant case though London is the "venue" for the

arbitration meetings, it is in fact the seat of arbitration and not a convenient

lgc 97 of 124

wps-7804.09 & 7636.09

geographical location and therefore the English Arbitration Act would apply

and it would be the English Courts that would have jurisdiction. The learned

Senior Counsel for the Respondents in support of the said contention relied

upon a number of judgments which included well known English Judgments. It

would be apposite to consider them at this stage. 2007 2 Lloyd's Law Reports

367, C v D ; 2008 1 Lloyd's Law Reports 239, C v D; 2007 1 Lloyd's Law

Reports 237, A v B; 2007 1 Lloyd's Law Reports page 358, A v B; (2009) 2

Lloyds Law Reports 376, Shashoua v Sharma; 2006 1 AC 221, Lesotho

Highlands Development Authority Vs. Impergilo SpA; (2011) 6 SCC 179,

Dozco India Pvt.Ltd v Doosan Infracore Company Ltd; (2011) 6 161,

Videocon Industries Ltd v Union of India; 2011 9 SCC 735, Yograj

Infrastructure Vs Ssang Yong Engineering; 2010 (3) Arbitration Law

Reports 70, Bhushan Steel Ltd Vs Singapore International Arbitration

Centre; 2011 (3) Arbitration Law Reports 350, Prima Buildwell Pvt. Ltd

Vs. Lost City Development and the judgment of Justice EDER reported in

(2012) EWHC 689 (Comm) between Enercon GmbH and Anr. v/.s Enercon

(India) Ltd.

In C v. D, 2007 Lloyd's Law Reports 367 (supra) the relevant

clause was as follows :-

"Any dispute arising under this policy shall be finally and fully determined in London, England under the provisions of the English Arbitration Act of 1950 as amended"

    lgc                                                                                        98 of 124



                                                                              wps-7804.09 & 7636.09

It is in the said context the learned Judge has observed in Para 24 of the said

report as follows :-

"By agreeing to the 1996 Arbitration Act, the parties

thus, prima facie, accept the framework of the mandatory provisions and, absent other agreement, to the application of the non-mandatory provisions. Section 4(4) provides that "it is immaterial whether or not the law applicable to the parties' agreement is the

law of England and Wales. In the context this must mean the law applicable to the parties agreement to arbitrate."

Thereafter in Para 25 the learned Judge has observed as follows :-

"Thus, if the parties agree a curial law which is not the law of England and Wales, provisions of that are

effective to replace any non-mandatory provision in the 1996 Act, insofar as they make provision for such a matter."

The said judgment can therefore be said to be a judgment on the proposition

that the contract referred to in the provision of Section 2 of the English Act is

not the contract regarding proper law of the underlying contract but the

contract pertaining to the proper law of arbitration and, once such contract

exists, then, it is permissible for the parties to contract out of non-mandatory

provisions.

The second judgment in C v. D 2008 1 Lloyd's Law Reports 239

(supra) reiterates the said position. Para 19 of the said report is material

wherein it has been observed as follows :-

    lgc                                                                                          99 of 124



                                                                           wps-7804.09 & 7636.09

"That is reinforced by the terms of section 4(5) of the Act which refers not to a choice of law clause generally but to a choice of law as "the applicable law in respect

of a matter provided for by a non-mandatory provision of this part" of the Act. In other words there has to be a

choice of law with regard to the specific provision of the Act which the parties agree is not to apply."

In the case of A v. B, (2007) 1 Lloyd's Law Reports 237 (supra),

the choice of law of arbitration was Swiss law and the seat was Geneva. In the

said circumstances it was held that the Swiss law was applicable and,

therefore, the English Court had no jurisdiction. In the said case also reference

was made to the decision in Naviera Amazonica and a passage was quoted

from the said judgment in Para 111 thereof which is reproduced herein

under :-

"English law does not recognise the concept of a "de- localised" arbitration (see Dicey & Morris at pp 541,

542) or of "arbitral procedures floating in the transitional firmament, unconnected with any municipal system of law" (Blank Mellat v Helliniki Techniki SA [1984] QB 291 at p 301 (Court of Appeal). Accordingly,

every arbitration must have "seat" or locus arbitri or forum which subjects its procedural rules to the municipal law there in force... Prima facie, ie in the absence of some express and clear provision to the contrary, it must follow that an agreement that the

curial or procedural law of an arbitration is to be the law of X has the consequence that X is also the law of the "seat" of the arbitration. The Lex fori is then the law of X and, accordingly, X is the agreed forum of the arbitration. A further consequence is then that the courts which are competent to control or assist the arbitration are the courts exercising jurisdiction at X."

    lgc                                                                                      100 of 124



                                                                           wps-7804.09 & 7636.09

In the case of A v. B, 2007 1 Lloyd's Law Reports 358 (supra) in

view of the choice of law of arbitration being Swiss and the seat of arbitration

being Geneva, it was held that the part "A" had committed a breach of contract

to invoke the jurisdiction of the English courts.

In the case of Shashoua v. Sharma (supra) the relevant clause

was clause 14 which was the arbitration clause which provided for arbitration

to be in accordance with the Rules of Conciliation and Arbitration of the

International Chamber of Commerce, Paris. Clause 14.2 provided for

arbitration proceedings to be conducted in the English language and clause

14.4 provided that "the venue of arbitration shall be London, United Kingdom".

However, the matrix contract or the underlying contract was to be governed by

the laws of India, and therefore there was no choice of law of arbitration. It

was in the context of the said facts that it was stated that the English law was

applicable to arbitration. The contention of the Defendants that as the proper

law of the underlying contract was Indian law, the law relating to arbitration is

also Indian law, was negatived by the court on the ground that there was no

choice of the law of arbitration, and therefore, since the seat being in England,

the English law as applicable. It was held in the said judgment that the venue

was equivalent to the seat and the ICC Rules were not the law of arbitration as

the ICC Rules were not connected to any court. A reference was made to the

decision in the case of Braes and Doune. In the said fact situation it was held

lgc 101 of 124

wps-7804.09 & 7636.09

in the said case that English law was applicable as the seat was in England as

there was no choice of the law of arbitration.

In the case of Lesotho Highlands Development Authoritative v.

Impregilo SpA (supra) it has been expressly stated that the law of Lesotho

(that is the proper law of the underlying contract) is not an agreement to the

contrary in writing of the nature referred to in Section 4(2) and 4(5) of the

English Arbitration Act, 1996.

In the case of Dozco India Private Limited v. Doosan Infracore

Company Limited (supra), the seat was Seoul, Korea and it was held that the

same cannot be changed without a written agreement. In para 14 a passage

from Mustill and Boyd was referred to. However, what is required to be noted

is that in the said case also there was no choice of the law of arbitration. It is in

the said context, the seat assumes importance for determining the curial law or

lex arbitri. It is in the fact situation of the said case, it was held that Part-I of

the Indian Arbitration Act would not apply.

In the case of Videocon Industries Ltd. v. Union of India (Supra)

the question that arose in the said case can be found in paras 20 and 24 of the

said report viz. Kuala Lumpur was the designated seat or the seat of arbitration

and the same has been shifted to London, and the next issue was, whether the

lgc 102 of 124

wps-7804.09 & 7636.09

Delhi High Court could entertain a petition filed by the Respondents under

Section 9 of the Arbitration and Conciliation Act, 1996. There was no issue

before the Apex Court as to whether when there is a choice of proper law of

arbitration, the law of the country in which seat is situate will prevail over such

choice. In the said case there was no dispute that Kuala Lumpur was the seat

and the parties had initiated arbitration proceedings on the said basis. The

Apex Court in the said fact situation held that the Delhi High Court would have

no jurisdiction to entertain the Petition under Section 9 of the Indian

Arbitration Act. Notwithstanding the fact that the meetings of the arbitration

were held in London, though the seat of arbitration was in Kuala Lumpur.

In the case of Yograj Infrastructure v. Ssang Yong Engineering

(supra), as can be seen from reading of Para 54, the proper law of arbitration

was also the law of Singapore and the seat was also in Singapore. The law of

Singapore was incorporated in the rules and which rules were agreed to be

applicable by the parties in the contract.

In the case of Bhushan Steel Ltd v. Singapore International

Arbitration Centre (supra), it was held that Part-I of the Arbitration Act would

apply, if there is no agreement regarding the governing law of arbitration.

    lgc                                                                                   103 of 124



                                                                             wps-7804.09 & 7636.09

In the case of Prima Buildwell Pvt. Ltd v. Lost City Development

(supra) it has been held that in the absence of any other agreement to the

contrary, the law governing the Arbitration Agreement where the arbitration is

agreed to be held is the law of England and Wales.

42 Relying upon the said judgments it was the submission of the

learned Senior counsel for the Respondents that in the face of the express

choice of seat i.e. the place/venue of the arbitration proceedings, the Courts

have very rarely (and for exceptional reasons) disregarded the choice of seat of

the parties.

43 The next limb of the submissions of the learned Senior Counsel for

the Respondents was that in the absence of an express agreement as to the

procedural law, the choice of seat prescribes the procedural law of arbitration.

In support of which submission, the learned Senior Counsel for the

Respondents relied upon the judgment of the House of Lords in James Miller

& Partners Ltd. V/s Whitworth Street Estate, (supra). In the said judgment

a passage from Dicey and Morris has been quoted with approval which is

reproduced herein under :-

"Where the parties have failed to choose the law governing the arbitration proceedings, those proceedings must be considered, at any rate prima facie, as being governed by the law of the country in which the arbitration is held on the ground that it is the country most closely connected with the proceeding"

    lgc                                                                                        104 of 124



                                                                           wps-7804.09 & 7636.09




                                                                                          

The learned Senior Counsel in support of the aforesaid submission also relied

upon the judgment in the case of Bank Mellat V/s Helliniki Techniki SA,

(supra) wherein it is held that the curial law or the procedural law of the

forum of arbitration will apply in the absence of any contractual provision to

the contrary. The following excerpt on page 301 of the said judgment is

material and is reproduced herein under :-

"The fundamental principle in this connection is that

under our rules of private international law, in the absence of any contractual provision to the contrary, the procedural (or curial) law governing arbitrations is that

of the forum of the arbitration, whether this be England, Scotland or some foreign country, since this is the system of law with which the agreement to arbitrate in the particular forum will have its closest connections :

see Whitworth Street Estates (Manchester) Ltd. v. James Miller & Partners Ltd . [1970] A.C. 583"

In support of the aforesaid submission the learned Senior Counsel also relied

upon the judgment in the case of Naviera Amazonica V/s Compania

Internacional, (supra).

"Before considering the correct construction of this

particular contract on the question whether the "seat" (or whatever term one uses) of any arbitration thereunder was agreed to be London or Lima, or---- to put it colloquially--- whether this contract provided for arbitration in London or Lima, I must summarize the state of the jurisprudence on this topic and deal with the general submissions which were debated on this appeal. In that connection we were referred to Oppenheim & Co. v. Mahomed Haneef, [1922] 1 A.C.

482 at p.487; James Miller & Partners Ltd. v. Whitworth

lgc 105 of 124

wps-7804.09 & 7636.09

Street Estates (Manchester) Ltd, [1970] 1 Lloyd's Rep. 269; [1970] A.C. 583, in particular per Lord Wilberforce at pp.281 and 616, 617; Black Clawson International

Ltd. v. Paperwerke Waldhof-Aschaffenburg A.G., [1981] 2 Lloyd's Rep. 446 per Mr. Justice Mustill (as he then

was) at p.453; Dicey & Morris on The Conflict of Laws (11th ed.) vol.1, r. 58 at pp. 539 to 542; Mustill & Boyd on Commercial Arbitration, passim; D. Rhidian Thomas "The Curial Law of Arbitration Proceedings", Lloyd's Maritime and Commercial Law Quarterly (1984) p.491;

and Redfern and Hunter "The Law and Practice of International Commercial Arbitration" (1986) at pp. 52 to 70. In addition, among many other publications one should mention the two important earliest and most

recent discussions of this topic; first Dr. F. A. Mann's "Lex facit arbitrium" in 1967, reprinted in Arbitration

International, 1986, Vol. 2 p. 241 and now "The new lex mercatoria" by Lord Justice Mustill in Bos and Brownlies "Liber Amicorum for Lord Wilberforce"

(1987) at p. 149

Without analysing any of this material in detail, the conclusions which emerge from it can be

summarized as follows :

A. All contracts which provide for arbitration and contain a foreign element may involve three potentially relevant systems of law. (1) The law governing the substantive contract. (2) The law governing the

agreement to arbitrate and the performance of that agreement. (3) The law governing the conduct of the arbitration. In the majority of cases all three will be the same. But (1) will often be different from (2) and (3). And occasionally, but rarely, (2) may also differ from

(3).

In the present case there was no investigation of (1), the substantive law, because nothing turns on it, but I am content to assume that this was the law of Peru on the ground that this was the system with which this policy was most closely connected. On this appeal there was also ultimately no contest about law (2) which may be regarded as the substantive law of the agreement to arbitrate. The Judge rightly held that on the wording

lgc 106 of 124

wps-7804.09 & 7636.09

of the arbitration clause the parties had agreed expressly that their agreement to arbitrate should be subject to English law and that the leave granted under

O.11 to serve the insurers out of the jurisdiction had been correct on this ground. Accordingly, the entire

issued turned on law (3), the law governing the conduct of the arbitration. This is usually referred to as the curial or procedural law, or the lex fori.

B. English law does not recognize the concept of a

"de-localised" arbitration (see Dicey & Morris at pp. 541, 542) or of "arbitral procedures floating in the transnational firmament, unconnected with any municipal system of law" (Bank Mellat v. Helliniki

Techniki S.A., [1984] Q.B. 291 at p.301 (Court of Appeal)). Accordingly, every arbitration must have a

"seat" or locus arbitri or forum which subjects its procedural rules to the municipal law which is there in force. This is what I have termed law (3).

C. ... Where the parties have failed to choose the law governing the arbitration proceedings, those

proceedings must be considered, at any rate prima facie, as being governed by the law of the country in which

the arbitration is held, on the ground that it is the country most closely connected with the proceedings...

See Dicey & Morris Vol. 1 at p.539 and the references to

the approval of this classic statement by the House of Lords in Whitworth Stree Estate v. James Miller (sup). Or, to quote the words of Mr. Justice Mustill in the Black Clawson case (sup.) at p.453 where he characterized law (3) as "the law of the place where the reference is

conducted: the lext fori". Although Mr.Milligan contested this, I cannot see any reason for doubting that the converse is equally true. Prima facie, i.e. in the absence of some express and clear provision to the contrary, it must follow that an agreement that the curial or procedural law of an arbitration is to be the law of X has the consequence that X is also to be the "seat" of the arbitration. The lex fori is then the law of X, and accordingly X is the agreed forum of the arbitration. A further consequence is then that the

lgc 107 of 124

wps-7804.09 & 7636.09

Courts which are competent to control or assist the arbitration are the Courts exercising jurisdiction at X.

Prima facie, therefore, the forum of any arbitration which might arise under this policy was

London, since the arbitration clause provided, in effect, that the law in force in London was to be the curial or procedural law of any such arbitration.

D. In the light of some of the matters debated before

us it may be helpful to add that in my view, none of these principles is different in relation to "institutional" arbitrations, such as those conducted under the rules of the International Chamber of Commerce or the London

Court of International Arbitration. The relevant rules of such bodies are incorporated by reference into the

contract between the parties, and their binding contractual effect will be respected and enforced by the Courts of the forum, except in so far as they may

conflict with the public policy or any mandatory provisions of the lext fori."

A reading of the said judgments relied upon by the learned Senior Counsel for

the Respondents makes it clear that it is only in the absence of an agreement as

to the procedural law that the choice of seat assumes significance as in that

event the seat prescribes the procedural law.

In so far as the decision of Justice EDER rendered in the

proceedings between the Petitioners and the Respondents is concerned, it is

required to be noted that the learned Judge in Para 54 has himself observed as

follows :-

"Another reason why I have reached my conclusion somewhat reluctantly is that I would have reached the conclusion that the "seat" of the arbitration is London

lgc 108 of 124

wps-7804.09 & 7636.09

which is, of course, the conclusion which the claimants say Judge Purohit reached. Given my conclusion that these proceedings be stayed, my views on this issue are

obiter. However, this issue was addressed at some length and in the event that this matter goes further or

otherwise comes back before the court, it may be convenient to set out my brief reasons for such conclusion. It may also be of assistance to the BHC if an when it comes to hear the Writ Petitions although, as I say, my views are strictly obiter."

Further in Para 55, after referring to the issue which arises in the contest of the

question of "seat", the learned judge has observed as follows :-

"These are difficult issues. However, for present

purposes I propose to address the question of "seat" on assumption that it is to be determined on a balance of probability as a matter of English law by the court although I recognise that those assumptions are not

necessarily correct."

The said decision therefore can hardly be said to support the contention of the

Respondents as regards London being the "seat" of arbitration as the learned

Judge has himself observed that the views expressed by him were obiter.

44 The submission of the learned Senior Counsel for the Respondents

that the law governing the arbitration proceedings will be the English law and

that the parties have conferred exclusive jurisdiction on the English Court, and

thereby have excluded the jurisdiction of the Indian Court is made on the basis

that the seat being London, the English Arbitration and Conciliation Act, 1996

lgc 109 of 124

wps-7804.09 & 7636.09

applies, and therefore, the arbitration proceedings are to be governed by the

English Court, and therefore, the jurisdiction of the Indian Courts is ousted.

45 The issue which therefore arises is, as to whether in the instant

case enquiry as to determine the seat of arbitration is necessary so that the

same would result in determination of the curial law that would be applicable.

The legal position as can be seen that emerges from the judgments cited by the

learned Senior Counsel for the Petitioners is that the said enquiry is necessary

if the parties have failed to choose the curial law, as in the instant case it is not

disputed by the Respondents that the law relating to Arbitration Agreement is

the Indian Arbitration Act. In the context of the said issue it would be relevant

to revert to the excerpt of clause 18.3 of the IPLA which is as follows :-

"Clause 18.3---- All proceedings in such arbitration shall

be conducted in English. The venue of the arbitration proceedings shall be London. The arbitrators may (but shall not be obliged to) award costs and reasonable expenses (including reasonable fees of counsel) to the

Party(ies) that substantially prevail on merit. The provisions of the Indian Arbitration and Conciliation Act, 1996 shall apply"

As can be seen that after providing for award costs and reasonable expenses

(including reasonable fees of counsel) to the Party(ies) that substantially

prevail on merit. The said clause provides that the provisions of the Indian

Arbitration and Conciliation Act, 1996 shall apply. If the said clause is read in

the ordinary and natural sense, the placement of the words that "the Indian

lgc 110 of 124

wps-7804.09 & 7636.09

Arbitration and Conciliation Act shall apply" in the last clause 18.3 indicates

the specific intention of the parties to the application of the Indian Arbitration

Act, not only to the Arbitration Agreement but also that the curial law or the

Lex Arbitri would be the Indian Arbitration Act. The application of the Indian

Arbitration Act therefore can be said to permeate clause-18 so that in the

instant case laws (2) and (3) are same if the classification as made by the

learned authors is to be applied. The reference to the Indian Arbitration Act is

therefore not merely a clarification as to the proper law of the arbitration

agreement as is sought to be contended on behalf of the Respondents. It has to

be borne in mind that the parties are businessmen and would therefore not

include words without any intent or object behind them. It is in the said

context, probably that the parties have also used the word "venue" rather than

the word "seat" which is usually the phrase which is used in the clauses

encompassing an Arbitration Agreement. There is therefore a clear and

unequivocal indication that the parties have agreed to abide by the Indian

Arbitration Act at all the stages, and therefore, the logical consequence of the

same would be that in choosing London as the venue the parties have chosen it

only as a place of arbitration and not the seat of arbitration which is a juristic

concept.

46 The proposition that when a choice of a particular law is made,

the said choice cannot be restricted to only a part of the Act or the substantive

lgc 111 of 124

wps-7804.09 & 7636.09

provision of that Act only. The choice is in respect of all the substantive and

curial law provisions of the Act. The said proposition has been settled by

judicial pronouncements in the recent past. A useful reference could be made

to the judgment of a learned Single Judge of the Gujarat High Court reported

in XLVII Gujarat Law Reports 658 in the case of Hardy Oil and Gas Ltd. Vs

Hindustan Oil Exportation Co. Ltd.. Para 11.3 of the said judgment is relevant

is reproduced herein under :-

"However, their Lordships observed in Para 32 that in cases of international commercial arbitrations held out

of India provisions of Part-I would apply unless the parties by agreement, express or implied, exclude all or any of its provisions. In that case laws or rules chosen

by the parties would prevail. Any provision, in Part-I, which is contrary to or excluded by that law or rules would not apply. Thus, even as per the decision relied upon by learned Advocate for the appellant, if the

parties have agreed to be governed by any law other than Indian law in cases of international commercial

arbitration, same would prevail. In the case on hand, it is very clear even on plain reading of Clause 9.5.4 that the parties' intention was to be governed by English law in respect of arbitration. It is not possible to give a

narrow meaning to this clause as suggested by the Ld. Sr. Advocate, Mr. Thakore, that it would apply only in case of dispute of arbitration agreement. It can be interpreted to only to mean that in case of any dispute regarding arbitration, English law would apply. When

the clause deals with the place and language of arbitration with a specific provision that the law governing arbitration will be the English Law, such a narrow meaning cannot be given. No other view is possible in the light of exception carved out of clause 0.5.1 relating to arbitration. Term "Arbitration", in clause 9.5.4 cannot be taken to mean arbitration agreement. Entire arbitral proceedings have to be taken to be governed by English law"."

    lgc                                                                                           112 of 124



                                                                                wps-7804.09 & 7636.09

    47            The   argument   which   was   advanced   on   behalf   of   the   Petitioner 

therein who had invoked the Indian Arbitration Act to say that whereas the

choice pertained only to the existence and validity of the Arbitration

Agreement other matters were not covered by that choice and therefore an

application under Section 9 the Indian Arbitration Act was maintainable was

negatived by the learned Judge. The said view in Hardy Oil and Gas Ltd

(supra) has been approved by the Apex Court in Videocon Industries Ltd

(supra) and followed by a learned Single Judge of this Court in Sakuma

Export Ltd. v/s Louis Drefus Commodities reported in 2012 (1) Bom CR 547,

(Paras 35-38) are relevant and are reproduced herein under :-

35. There is yet another ground on which the aforesaid conclusion can be reached. It also arises out of the express agreement between the parties. As noted above,

the express agreement between the parties stipulates that Rules of the Refined Sugar Association, London

form part of the contract, if they are not inconsistent with the other provisions of the contract. The first clause relied upon by the Respondent from the Introduction/Preamble to the Rules of Refined Sugar

Association relating to Arbitration reads as under : "When the parties to a contract have incorporated a clause to the effect that any dispute arising out of it shall be referred to The Refined Sugar Association (sometimes referred to as the RSA) such dispute may be referred to the

Association for settlement in accordance with the Rules relating to Arbitration and the Arbitration Act, 1996."

36. From the above clause, it is clear that once the parties to the contract incorporate a clause to the effect that any dispute arising out of the contract shall be referred to the Refined Sugar Association, such dispute must be settled in accordance with the Rules relating to Arbitration and English Arbitration Act, 1996. Therefore even on this analysis it is clear that this Court does not

lgc 113 of 124

wps-7804.09 & 7636.09

have jurisdiction to entertain the present Petition under Section 34 of the Arbitration and Conciliation Act, 1996.

37. Again, the second clause relied upon by the

Respondent from the Introduction/Preamble to the Rules of Refined Sugar Association relating to

Arbitration reads as under :

"The Association's Rules and Arbitration procedures are conducted in accordance with English Law. However, where the parties have agreed a contract law other than

English, the Association may, with the parties' agreement, decide the dispute."

38. The above Clause clearly stipulates that the Association's Rules and Arbitration procedures are

conducted in accordance with English Law and it is only where the parties have agreed to a contract law other

than English, the association may, with the parties agreement decide the dispute. In the present case, the parties have not agreed to any contract law other than

English. In view of categorical assertion in the clause set out hereinabove that the Association Rules and Arbitration procedures are conducted in accordance with English law coupled with the fact that the parties

have expressly agreed to be governed by the Association's Rules relating to arbitration, there remains

no doubt in concluding that the parties have expressly agreed that the arbitration would be conducted in accordance with the English law. Again in Rule 8 it is clearly stated that "For the purpose of all proceedings in

arbitration, the contract shall be deemed to have been made in England, ........England shall be regarded as the place of performance, disputes shall be settled according to the law of England............. The seat of the arbitration shall be England and all proceedings shall take place in

England.........." In view thereof, nothing turns on the issue raised by the Petitioner that the Respondents have not exactly incorporated the recommended arbitration clause which include a condition that "such arbitration shall be conducted in accordance with English Law". As set out hereinabove, the introduction to the Association's Rules/Preambles provide that the arbitration proceedings are generally conducted in accordance with English Law except where the parties have agreed to a contract law other than English. In

lgc 114 of 124

wps-7804.09 & 7636.09

view thereof, though it is beyond any doubt from the aforestated decisions of the Hon'ble Supreme Court that the curial law does not govern the question pertaining

to the maintainability of the present Petitions u/s.34 of the Arbitration & Conciliation Act, 1996, it is established

that the parties herein have agreed to the Association's Rules and arbitration procedures being conducted in accordance with English law and Mr. Chinoy is not correct in his submission that the agreement contains no provision stipulating a choice of law governing the

arbitration procedure."

48 In the judgment reported in (2012) 2 BCR 168 in the matter of

Eitzen vs Ashapura what fell for consideration before a learned Single Judge

of this Court was the interpretation of the clause which stated that "English law

to apply". The said law was interpreted to mean that the same governed the

entire arbitration proceedings and the use of the expression "umpire" clearly

established that the parties chose the application of the English law as the said

expression "umpire" appears in the English law. The said judgment in Eitzen

(supra) has relevance to the present case as in the present case Clause 18.3 of

the IPLA uses the expression "Presiding Arbitrator" which expression finds

place in the Indian Arbitration Act and not in the English Arbitration Act. This

therefore is one more circumstance or indicia which shows that the choice of

law was the Indian Arbitration Act and such choice having been made by the

parties, the same governed the entire arbitration. The findings of the Lower

Appellate Court on the aspect of the law applicable which are drawn on the

basis of London being the "seat" of arbitration are therefore unsustainable.

    lgc                                                                                  115 of 124



                                                                              wps-7804.09 & 7636.09

    49             Though in terms of interpretation of Clause 18.3, this Court has 

reached a conclusion that the lex arbitri would be the Indian Arbitration Act.

The question would be, whether the Indian Courts would have exclusive

jurisdiction. The nexus between the "seat" or the "place" of arbitration vis-a-

vis the procedural law i.e. the lex arbitri is well settled by the judicial

pronouncements which have been referred to in the earlier part of this

judgment. A useful reference could also be made to the learned authors

Redfern and Hunter who have stated thus :-

"the place or seat of the arbitration is not merely a matter of geography. It is the territorial link between the arbitration itself and the law of the place in which that

arbitration is legally situated..."

The choice of seat also has the effect of conferring exclusive

jurisdiction to the Courts wherein the seat is situated. In the instant case, as

can be seen, there is no agreement between the parties as regards the "seat" of

arbitration as the parties have chosen London as only the venue for the

arbitration meetings. In view of London being the venue for the arbitration

meetings, the question that is posed is, whether the English Courts can exercise

jurisdiction in support of arbitration between the parties.

50 It is required to be noted that the instant case is a uncommon case

where there is no agreement between the parties as regards the seat of

arbitration, and the agreement between the parties is only as regards London

lgc 116 of 124

wps-7804.09 & 7636.09

being the venue for arbitration. The Arbitration Agreement in the instant case

also does not provide what is to happen in the event of a failure of the

procedure for appointment of the Arbitral Tribunal. Therefore in so far as

Section 18 of the English Act is concerned, which is a non-mandatory

provision, the application of the said provision has not been expressly excluded

by the parties, and therefore, the said provision is available for invocation by

the parties. In the context of London being only the venue and not the seat of

arbitration. It would be apposite to refer to Section 2(4) of the English

Arbitration Act which reads thus:-

"The Court may exercise a power conferred by any

provision of this Part not mentioned in subsection (2) or (3) for the purpose of supporting the arbitral process where

(a) no seat of the arbitration has been designated or determined, and

(b) by reason of a connection with England and Wales or Northern Ireland the court is satisfied that it is appropriate to do so."

Therefore in so far as Section 2(4) of the English Act is concerned,

the two requirements for exercising power under any of the provisions of the

English Arbitration Act, are that no seat of arbitration has been designated, and

that by reason of a connection with England and Wales or Northern Ireland the

court is satisfied that it is appropriate to do so. In the instant case, both the

conditions for the exercise of power under the said Part of the English Act are

satisfied, as no place other than London is mentioned in clause 18 of the IPLA,

lgc 117 of 124

wps-7804.09 & 7636.09

since London is not the seat, and therefore, no seat of arbitration has been

designated by the parties. Secondly since the meetings of the arbitration are to

take place in London, there is a strong connection between the arbitration and

the country wherein the arbitration meetings have to take place. As indicated

above Section 2(4) of the English Arbitration Act clamps itself in view of the

peculiar fact situation where the seat of arbitration has not been designated by

the parties.

Looked at from the said angle i.e. the territorial link between the

arbitration itself and the law of the place in which the arbitration meetings are

to be held, the conclusion that is is required to be drawn is that the English

Courts would have concurrent jurisdiction. The Lower Appellate Court has also

held that no exclusive jurisdiction has been given to the Indian Courts. Hence

the Respondents cannot be said to have committed a breach of the agreement

by invoking the jurisdiction of the English Court for constituting the Arbitral

Tribunal. The finding of the Lower Appellate Court to the said extent is

required to be sustained.

51 The contention of the learned Senior Counsel for the Respondents

that splitting up of the application of Indian Arbitration Act is permissible,

inasmuch as in respect of the Arbitration Agreement the Indian Arbitration Act

would apply but in so far as curial law is concerned, the provisions of the

lgc 118 of 124

wps-7804.09 & 7636.09

English Arbitration Act would have application. The said contention proceeds

on the basis that London is the seat of arbitration and therefore, the English

Arbitration Act would apply. The Indian Arbitration Act contains both the

procedural and the curial provisions, and therefore, when the parties have

agreed to the application of the Indian Arbitration Act, it has to apply as a

whole and not in parts. The submission of the learned Senior Counsel for the

Petitioners based on Sumitomo Heavy Industries (supra) that the appointment

of the Arbitral Tribunal precedes the reference and therefore the curial law is

not applicable is well founded. However for the reason that the parties have

chosen London as the place of arbitration, and since there is no agreement

between the parties as regards the seat of arbitration, Section 2(4) of the

English Act clamps itself as it were on the agreement; and therefore

notwithstanding the fact that in terms of the law laid down in Hardy Oil and

Gas Ltd (supra) and Sakuma Export Ltd (supra), the invocation of the

jurisdiction of the English Courts for taking such measures as are needed in

support of arbitration cannot be prevented as the English Courts can be said to

have concurrent jurisdiction.

52 As regards the submission of the learned Senior Counsel for the

Respondents based on Section 4(2) of the English Act is concerned, the same

has to be read with Section 4(5) of the English Act. The said Section provides

that if a choice of law other than the law of England and Wales or Northern

lgc 119 of 124

wps-7804.09 & 7636.09

Ireland as applicable law in respect of a matter provided for by a non-

mandatory provision of this part is equivalent to an agreement making

provision about that matter. Thus, as per the English Act, when a choice of law

other than law of England is made in respect of a non-mandatory matter

(appointment of Arbitral Tribunal governed by Section 18 of the Act) then such

a choice will constitute the agreement contemplated by Section 4 (2) of the

English Act so as to make the English Act in-applicable as regards non-

mandatory provision. In the present case, since there is no agreement between

the parties as regards the seat and, since the parties have agreed to hold the

arbitration meetings at London, the parties have expressly not excluded the

application of Section 18 of the English Arbitration Act, and is therefore

available for invocation by the parties. The parties would therefore be entitled

to approach the English Courts for constitution of the Arbitral Tribunal.

53 In so far as the relief of anti suit injunction is concerned, the

learned Senior Counsel for the Petitioners sought to rely upon the judgment of

the Apex Court reported in (1987) 1 SCC 496 in the matter of ONGC v/s.

Western Company, North America. The said anti suit injunction has been

sought by the Petitioners on the ground of breach of agreement by the

Respondents and on the ground of London being forum non-conveniens. The

learned Senior Counsel for the Petitioners contended that the Daman Court has

a personal jurisdiction over the Respondents. In support of the said contention

lgc 120 of 124

wps-7804.09 & 7636.09

he sought to rely upon the judgment of the Apex Court reported in (1995) 1

SCC 478 in the matter of New Horizons Ltd. v/s. Union of India, and the

judgments of this Court in Tarabai's case, Girdharlal Shankar Dave's case

and Ishardas's case (supra).

Per contra, in so far as the aspect of anti suit injunction is

concerned, the learned Senior Counsel for the Respondents relied upon the

judgment of the Apex Court reported in (2003) 4 SCC 341 in the matter of

Modi Entertainment v/s. W.S.G. Cricket Private Ltd. The principles spelt out

by the Apex Court in the said case whilst considering the application for anti

suit injunction can be seen from Para 24 of the said report which is reproduced

herein under :-

"From the above discussion the following principles

emerge :

(1) In exercising discretion to grant an anti-suit injunction the court must be satisfied of the following

aspects : -

(a) the defendant, against whom injunction is sought, is amenable to the personal jurisdiction of the court;

(b) if the injunction is declined the ends of justice will be defeated and injustice will be perpetuated; and

(c) the principle of comity - respect for the court in which the commencement or continuance of action/proceeding is sought to be restrained - must be borne in mind;

(2) in a case where more forums than one are available, the Court in exercise of its discretion to grant anti-suit injunction will examine as to which is the appropriate forum (forum conveniens) having regard to the convenience of the parties and may grant anti-suit

lgc 121 of 124

wps-7804.09 & 7636.09

injunction in regard to proceedings which are oppressive or vexatious or in a forum non-conveniens;

(3) Where jurisdiction of a court is invoked on the basis of jurisdiction clause in a contract, the recitals therein in

regard to exclusive or non-exclusive jurisdiction of the court of choice of the parties are not determinative but are relevant factors and when a question arises as to the nature of jurisdiction agreed to between the parties the court has to decide the same on a true interpretation of

the contract on the facts and in the circumstances of each case;

(4) a court of natural jurisdiction will not normally

grant anti-suit injunction against a defendant before it where parties have agreed to submit to the exclusive

jurisdiction of a court including a foreign court, a forum of their choice in regard to the commencement or continuance of proceedings in the court of choice, save

in an exceptional case for good and sufficient reasons, with a view to prevent injustice in circumstances such as which permit a contracting party to be relieved of the burden of the contract; or since the date of the contract

the circumstances or subsequent events have made it impossible for the party seeking injunction to prosecute

the case in the court of choice because the essence of the jurisdiction of the court does not exist or because of a vis major or force majeure and the like;

(5) where parties have agreed, under a non- exclusive jurisdiction clause, to approach a neutral foreign forum and be governed by the law applicable to it for the resolution of their disputes arising under the contract, ordinarily no anti-suit injunction will be granted in

regard to proceedings in such a forum conveniens and favoured forum as it shall be presumed that the parties have thought over their convenience and all other relevant factors before submitting to non-exclusive jurisdiction of the court of their choice which cannot be treated just an alternative forum;

(6) a party to the contract containing jurisdiction clause cannot normally be prevented from approaching the court of choice of the parties as it would amount to

lgc 122 of 124

wps-7804.09 & 7636.09

aiding breach of the contract; yet when one of the parties to the jurisdiction clause approaches the court of choice in which exclusive or non-exclusive jurisdiction is

created, the proceedings in that court cannot per se be treated as vexatious or oppressive nor can the court be

said to be forum non-conveniens; and

(7) the burden of establishing that the forum of choice is a forum non-conveniens or the proceedings therein are oppressive or vexatious would be on

the party so contending to aver and prove the same.

In view of the conclusion that this Court has reached, namely that the English

Courts would have concurrent jurisdiction to act in support of arbitration, the

case of the Petitioners for an anti suit injunction does not stand to scrutiny.

However, in so far as the aspect of forum non- conveniens is concerned, in my

view, since the Petitioners have agreed to London as the venue for arbitration,

they cannot be heard to complain that the Courts at London are forum non-

conveniens for them. The Petitioners have appeared before the said Courts,

and therefore, the case of forum non- conveniens is bereft of any merit.

54 For the reasons mentioned herein-above the finding (refer para 63

of the impugned judgment) of the Lower Appellate Court that London is the

seat of arbitration is required to be interfered with, the said finding is

accordingly set aside and it is held that London is only a geographically

convenient location which the parties have chosen as a venue to hold the

arbitration meetings.

    lgc                                                                                      123 of 124



                                                                             wps-7804.09 & 7636.09




CONCLUSIONS - WRIT PETITION NO.7636 OF 2009

55 On an interpretation of clause 18.3 of the IPLA this Court has

reached a conclusion that the curial law or Lex Arbitri would be the Indian

Arbitration Act. Though the Indian Arbitration Act would apply, however, in

view of the fact that the parties have chosen London as the venue for the

arbitration meetings, the English Courts would have concurrent jurisdiction

and therefore the jurisdiction of the English Courts can also be invoked by the

parties for taking such measures as are required in support of arbitration. The

judgment and order of the Lower Appellate Court on the aspect of anti suit

injunction is, therefore, sustained but on a different ground which is

mentioned in the body of this Judgment. The above Writ Petition No.7636 of

2009 is accordingly dismissed. Rule discharged, with no order as to costs.

                                                                          [R.M.SAVANT, J]






    lgc                                                                                       124 of 124



 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter