Tuesday, 21, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Angerlehner Structurals & ... vs Municipal Corporation Of Greater
2012 Latest Caselaw 47 Bom

Citation : 2012 Latest Caselaw 47 Bom
Judgement Date : 1 October, 2012

Bombay High Court
M/S. Angerlehner Structurals & ... vs Municipal Corporation Of Greater on 1 October, 2012
Bench: Anoop V.Mohta
     ssm                            1                               arbp162.09

              IN THE HIGH COURT OF JUDICATURE AT BOMBAY                           




                                                                     
               ORDINARY ORIGINAL CIVIL JURISDICTION




                                             
               ARBITRATION PETITION NO. 162 OF 2009

     M/s. Angerlehner Structurals & Civil
     Engineering Co., 2078 "B" Wing,




                                            
     2nd Floor, Oberoi Gardens, 
     Chandivali Studio Compound,
     Saki Vihar Road, Sakinaka, Andheri (East),
     Mumbai 400 072                                   .....Petitioners. 




                                 
                Vs.   
     Municipal Corporation of Greater
     Mumbai, constituted under the 
                     
     provisions of the Mumbai Municipal
     Corporation Act, 1888 having its
     office at 3rd Floor, Annexe Building,
     Municipal Head Office,
      


     Mahapalika Marg, Fort, Mumbai-400 001.           ....Respondents
   



     Mr. Z.T. Andhyarujina with Ms. Dohita Lewis, Mr. Javed Gaya 
     i/by Chamber of Javed Gaya for the Petitioners.
     Mr. Kevic Setalwad, Senior Counsel with Ms. Daisy Dubash and 





     Mr. H.C. Pimple for the Respondents.
                                     
                                  CORAM     :  ANOOP V. MOHTA, J.

JUDGMENT RESERVED ON : 27 AUGUST 2012.

JUDGMENT PRONOUNCED ON : 1 OCTOBER, 2012

JUDGMENT :-

This is a petition under Section 34 of the Arbitration and

ssm 2 arbp162.09

Conciliation Act, 1996 (for short, "the Arbitration Act"). The

majority award is under challenge.

Events:-

2 In the month of August, 1999 bids invited by the Mumbai

Municipal Corporation (for short "MMC"). On 12 September,

1999, the Petitioners submitted its bid. On 21 September 2000,

awarded them the Contract for Rehabilitation of sewer lines by

Lining/Coating method (Contract : SO/CA/02) for the price of

US$ 44,06,347.00 plus Indian Rupees 10,29,01,768.00. On 2

March 2001, an Agreement SO-CA-02 ("Contract") was

executed between the parties. The contract was initially for a

period of 24 months, but was extended on justifiable grounds to

nearly 29 months with the date of commencement as 11

January 2001 and the extended date of completion as 31 May

2003.

3 On 14 March 2001, letter from the Engineer (MMC) to the

Petitioners, informing them that M/s. TTI Consultants have

ssm 3 arbp162.09

been appointed as the "Consultants" under the Contract. On 11

April 2001, work order issued by the Engineer to the Petitioners,

pursuant to which they commenced their work under the

Contract. The work successfully completed within the time

stipulated in the Contract.

4 This works contract was partly financed by the World

Bank and in all such contracts there is a provisions for price

adjustment if the contract extends beyond 18 months.

Accordingly clause 70.3 of the COPA contained a price

adjustment formula that was to be applied to the payments

made under the contract. The Petitioners used to prepare and

raise its Bills (including price adjustment for local currency)

from time to time based on the agreed contractual formula.

However, the consultant rejected the Bills citing a discrepancy in

the contractual formula and unilaterally altered the same and

calculated the amounts that were due and payable to the

Petitioners and released the amounts to the Petitioners. On 14

February 2002, the Petitioners requested that this issue be

resolved. On 12 October 2002, Consultant's letter addressed to

ssm 4 arbp162.09

the Petitioners informing them that no extra claim was

permissible due to the Petitioners' misinterpretation of the

contractual formula. On 20 August 2003, the Petitioners' letter

submitted copies of the Statement of completion to the Engineer

and sought payment under the contract on the basis of the

Interim Payment Certificates (IPC's).

On 1 December 2003, Dy. Chief Engineer, MMC's letter to

the Petitioners that its claim for non-payment of certain dues on

account of formula of price adjustment had not been accepted

by them. The Petitioners were informed that the price

adjustment claim had been admitted as per the "corrected

formula recommended by the Consultant".

6 On 5 June 2004, the Petitioners' letter to the Engineer

informing him that they were going to approach the MMC for its

final opinion and scrutiny pursuant to clause 67 of the GC/COC.

7 On 24 June 2004, the Petitioners' letter to the DRE

informing him that his claim was wrongly rejected by both the

ssm 5 arbp162.09

Engineer and the MMC. On 23 September 2004, the DRE

recommended that the Petitioners have been paid correctly in

accordance with the changed formula.

8 On 21 October 2004, a Notice of Arbitration given by

Petitioners to the MMC, nominated Dr. Harald Wagner as its

Arbitrator. On 29 October 2004, a letter by the Respondents to

Mr. Sharad Upasni, Former Chief Secretary of the Government

of Maharashtra appointing him as their Arbitrator. On 15

December 2004, the reference was made to the President of

Institute of Engineers (India) to appoint a third and presiding

Arbitrator. On 11 July 2007, dissenting Award of Dr. Harald

Wagner in favour of the Petitioners. Majority Arbitral Award of

Mr. S. P. Upasani and Mr. S. L. Garg rejecting the Petitioners'

claim entirely.

9 On 10 October 2007, the Petitioners filed the present

Arbitration Petition. On 5 January 2012, the Respondents filed

reply. On 11 June 2012, the Petitioners filed rejoinder to the

reply filed by the Respondents. Annexed as Annexure I to this

ssm 6 arbp162.09

rejoinder is Award dated 18th April, 2012, passed in other

similarly placed matter (AJECT V. MCGM). This Award was, as

alleged, made on the legal principles in relation to the same

formula, as in the instant case, drafted by the same Consultant

(M/s. TTI Consultants) and a copy of this Award was issued by

the Arbitral Tribunal presided over by Mr. Ajit Pawar, a former

head of the PWD Dept. and two retired High Court Judges,

namely Mr. S. K. Shah and Mr. B. P. Saraf.

Submissions:-

10 The relevant portion of the submissions of the Petitioners

is as under:-

"5 Sub-Clause 70.1 and 70.3 of COPA provide for Price

Adjustment. According to these Sub-Clauses amounts payable

to the Claimant, in various currencies, are to be adjusted for rise

or fall in the cost of labour, equipment, plant, materials and

other inputs to the works, by applying to such amounts the

formula prescribed therein. It is further states that price

ssm 7 arbp162.09

adjustment shall be calculated for the local and foreign

components of the payment for work done as per formula given

in the contract data.

6 As per Sub-Clause 60.1, the Contractor is mandated to

submit monthly statements to the Engineer showing the

amounts the contractor considers himself to be entitled. The

statement is also to include amounts reflecting changes in cost

pursuant to Clause 70. As per Sub-Clause 60.2 the said

statement is to be approved or amended by the Engineer in such

a way that in its [Engineer's] opinion, it reflects the amounts in

various currencies due to the contractor in accordance with the

contract. The Engineer is mandated to determine amount due

to the Contractor and to issue an 'Interim Payment Certificate' to

the Employer certifying the amounts due to the Contractor.

7 The relevant forumla referred to in Sub-Clause 70.3 of the

contract are as under:-

           A.     R=RI+RF

           B.     Where 'R' is the total value of the work done 

during the month, 'RI' is the portion of 'R' as payable in foreign currency at fixed exchange rate.

      ssm                                 8                                arbp162.09

           C.     The   other   formula   governing   value   of   price 
                  adjustment of  various   components   of 




                                                                           
                  works are:-




                                                   
           i.     VI    =      Price Adjustment for labour component

                        =      0.85 x P 1/100 x R x [L1-Lo]/Lo




                                                  
           ii.    Vc    =      Price Adjustment for cement component

                        =      0.85 x P o/100 x R x [C1-Co]/Co




                                      
           iii.   Vs    =      Price Adjustment for steel component
                       
                        =      0.85 x P s/100 x R x [S1-So]/So

           iv.    Vb    =      Price Adjustment for increase or 
                      
                               decrease in cost of bitumen

                        =      0.85 x P b/100 x R x [B1-Bo]/Bo
      


           v.     Vr    =      Price Adjustment for increase or 
                               decrease in cost of POL
   



                        =      0.85 x P f/100 x R x [F1-Fo]/Fo





           vi.    Vm    =      Price Adjustment for increase or 
                               decrease in cost of local materials.

                        =      0.85 x P m/100 x R x [M1-Mo]/Mo





           vii.   Vp    =      Price Adjustment for increase or 

decrease in cost of plant and machinery

= 0.85 x P p/100 x R x [P1-Po]/Po

viii. VFc = Foreign Currency component

= 0.85 x RF x [Fe1-Feo]/ Feo

ssm 9 arbp162.09

8 It may be noted that all formula at Paragraph 7(c)(i) to

paragraph 7(c)(vii) above contain the term 'R' in them to be

used for calculating the value of price adjustment component

for various parts of the work."

     9      .....

     10     The Petitioner had made its Bid on the basis of whiat it 




                                          

read it was entitled to including the price adjustment formula

and that is demonstrated by Sub-Clause 70.2 of the Contract

"To the extent that full compensation for any rise or fall in costs

to the Contractor is not covered by the provisions of this or

other Clauses in the Contract, the unit rates and prices included

in the Contract shall be deemed to include amounts to cover the

contingency of such other rise or fall of costs" cautions the

prospective bidder that it needs to take into account the

provisions made in the price variation clauses while preparing

and quoting its price bid."

11 The learned Senior Counsel for the Respondents

submitted to maintain the award, by referring to the clauses and

the supporting majority Arbitrators' reasons, apart from the

ssm 10 arbp162.09

Judgments so relied.

12 The power of the Court to interfere with the interpretation

given by the Arbitral Tribunal is quite limited. The view if

possible and plausible then also scope is limited. (Jigar

Vikamsay Vs. Bombay Stock Exchange Limited) 1

The Petitioners have also in support of the challenge,

relied on Central Bank of India Ltd., Amritsar Vs. the

Hartford Fire Insurance Co. Ltd. 2 , State bank of India Vs.

Mula Sahakari Sakhar Karkhana Ltd. 3 Bishwanath Prasad

Singh Vs. Rajendra Prasad 4 and Haji Abdul Rahaman Vs. The

Bombay and Persia Steam Navigation Co. 5.

14 The learned counsel appearing for the Petitioners has also

relied on TN State Electricity Board Vs. Bridge Tunnel

Custom 6 The relevant portion of the same is as under:-

.

     1     2010(1) Bom. C.R. 908
     2     AIR 1965 SCC, 1288
     3     2006 6 SCC 293
     4     2006(4) SCC 432
     5     (1892) 16 Bom. 561
     6        AIR 1997 SC 1376





      ssm                                   11                                arbp162.09




                                                                              

"If he makes an award disregarding the Contract it would be a jurisdictional error beyond the scope of

the reference, he cannot clothes himeself to decide conclusively the dispute as it is an error of jurisdiction which ultimately requires to be decided by the Court."

15 There is nothing provided to deal with correction or

interpretation of agreed formula. The Respondents counsel has

relied upon the following judgments to support the award in

every aspects.

a) National highways Authority of India Vs. Unitech-

NCC Joint Venture, MANU/DE/0650/2010.

b) National highways Authority of India Vs. Unitech-

NCC Joint Venture, (2011) 178 DLT 496 (DB)

c) William Charles Binns Vs. W. & T. Avery Ltd., AIR

1934 Calcutta 778.

d) Dagdu Valad Jairam & Ors. Vs. Bhana Valad

Jairam & Ors., 28 B. 420(=6 Bom. L.R. 126)

e) Mumbai Metropolitan Region Development

ssm 12 arbp162.09

Authority Vs. Unity Infraproject Ltd. 2008(5)

Bom. C.R. 196.

16 It is relevant to note here the following clauses of the

contract and all the terms and conditions.

"Priority of Contract Documents-

5.2

The several documents forming the Contract are to be taken as mutually explanatory of one another, but in case of ambiguities or

discrepancies the same shall be explained and adjusted by the Engineer who shall thereupon issue to the Contractor instructions thereon and in such event, unless otherwise provided in the

Contract, the priority of the documents forming the Contract shall be as follows;-

                  1)      The   Contract   Agreement   (if  
                          completed);





                  2)      The Letter of Acceptance;

                  3)      The Tender;





                  4)      Part II of these Conditions;

                  5)      Part I of these conditions; and

                  6)      Any other document forming part of  
                          the Contract."





      ssm                                13                                arbp162.09

           "Sub-Clause 70.1 Price Adjustment




                                                                           

70.1 The amounts payable to the Contractor, in various currencies pursuant to Sub-Clause 60.1

shall be adjusted in respect of the rise or fall in the cost of labour, contractor's Equipment, Plant, materials, and other inputs to the Works, by applying to such amounts the

formulae prescribed in this clause."

"Sub-Clause 70.3 Adjustment Formulae

70.3 Contract price shall be adjusted for increase or

decrease in rates and price of labour, materials, fuels and lubricants in accordance with the following principles and procedures as per

formula given in the contract data, the amount certified in each payment certificate is adjusted by applying the respective prices adjustment factor to the payment amounts due in each

currency:

(a) Price adjustment shall apply only for work carried out within the stipulated time or extensions granted by the

Employer and shall not apply to work carried out beyond the stipulated time for reasons attributable to the Contractor, shall be paid in accordance with sub-clause 70.6;

(b) Price adjustment shall be calculated for the local and foreign components of the payment for work done as per formulae given in contract data; and

(c) Following expressions and meanings are assigned to the value of the work

ssm 14 arbp162.09

done during each quarter:

R= Total value of work done during the month. It would include the

value of materials on which secured advance has been granted, if any, during the month, less the value of materials in respect of

which the secured advance has been recovered, if any, during the month. This will exclude cost of work on items for which rates

were fixed under variations clause ig (51 and 52) for which the escalation will be regulated as mutually agreed at the time of fixation of rate.

RI= Portion of 'R' as payable in Indian Rupees.

RF= Portion of 'R' as payable in foreign

currency (at fixed exchange rates)

R= RI + RF

To the extend that full compensation for any rise or fall costs to the contractor is not covered by the provisions of this or other clauses in the contract, the unit rates and prices included in the contract shall be

deemed to include amounts to cover the contingency of such other rise or fall in costs."



     17    The   parties   having   once   agreed   and   acted   upon   the 





      ssm                                     15                                arbp162.09

clauses and accepted the formula, the heavy burden lies upon

the employer-Respondents to demonstrate that there was

mistake and it was never intended to act upon. The

Respondents, therefore, need to prove that the price escalation

was to be calculated currency-wise and not on the basis of R,

but R-1. The Respondents must prove that there is apparent

ambiguity in the document and in the formula, otherwise, it is

difficult to accept the submission that such unilateral

clarification and/or amendment to the agreed formula, is

permissible and so also its effect on the claim raised by the

Petitioners.

18 The Arbitral Tribunal and/or even the Court needs to

consider the nature of work/project and its technical aspects,

while considering the agreed clauses and conditions and the

formula. Admittedly, the contract was signed on 11 May 1999

which was in relation to micro-tunneling works at various

locations in Mumbai, which was partly the World Bank aided

works. There is no question of change of agreed formula

unilaterally. The parties, in fact, acted upon the same. The

ssm 16 arbp162.09

issues arose at later stage, in view of the doubt raised by the

experts. The terms and conditions and/or formula is clear and

there is no vagueness, the view if takes by the Arbitral Tribunal,

based upon the same, the interference of the Court, as recorded,

is limited. But, the things are otherwise. By

changing/amending the formula unilaterally the decision is

given. There is no question of such restriction on the power of

the Arbitral Tribunal and/or on the Court to interpret the

clauses read with the original formula.

No bar to look into the minority view:-

19 Two views based upon the same terms and conditions

including the questionable formula are on record. The learned

majority Arbitrators rejected the claim/ case of the Petitioners.

The learned dissenting Arbitrator, however, passed the order in

favour of the Petitioners. Under the Arbitration Act, majority

views prevailed for all the purposes. There is nothing under the

Arbitration Act not to read and refer the view expressed by the

dissenting Arbitrator. The Court under Section 34 of the

ssm 17 arbp162.09

Arbitration Act, even otherwise, considering the material placed

on record, may pass the order supporting and/or against the

majority views or independently take a particular view, which

may, in a given case, by accepting the view/opinion of the

dissenting Arbitrator. There is no bar that the Court cannot just

take into consideration both the views and pass appropriate

order based upon the material available on record.

Unilateral change in agreed formula not permissible:-

20 Admittedly, there is a dispute with regard to the agreed

formula and its applicability. Everyone concerned, bound by

the terms and conditions of the contract read with the agreed

formula. In such type of construction contract, the contractor

and/or such other person always take note of terms and

conditions and the basic formulas before executing or accepting

the contract/work. The Respondents and/or the employer also

bound to read, refer and rely the same for every purpose. In the

present case, we are concerned with the important element of

the formula "price adjustment". In the clauses and the formulas,

ssm 18 arbp162.09

there are various components like labour component, cement

component, steel component, increase and decrease in cost of

bitumen, POL, local materials, plant and machinery and foreign

currency component. There is no dispute that, as advertised

and as agreed, the contract was accordingly signed and the

parties proceeded, and in fact as recorded above, the Petitioners

completed the project also. The Petitioners, admittedly,

received part interim payment based upon the agreed formula.

21 It is settled law that out of two or three formulas available

under the construction contract and in case of vagueness and

ambiguity, the Arbitrator based upon the facts and

circumstances, as submitted by the concerned party, if preferred

one formula out of it, and passes the award, the Court may not

entertain the objections to such mode. (McDermott

International Inc. V. Burn Standard Co. Ltd.) 7 . If there is

some confusion and/or clarification is required to the formula,

as submitted by the learned Senior Counsel appearing for the

Respondents based upon the clauses of the contract, the

7 (2006) 11 SCC 181

ssm 19 arbp162.09

concerned officials and/or the Executive Engineer bound to

explain and/or clarify the ambiguity and/or discrepancy based

upon the documents on record. The power of clarification or

the discrepancy, even if any, so referred and mentioned in clause

5.2, in my view, cannot be read and permitted to be read that

the employer can amend and/or change the formula itself. It is

a commercial contract. The parties knowing fully the effect of

the clauses read with the formula so agreed, considering the

nature of construction executed the contract. Both the parties

acted upon accordingly, therefore, such agreed terms and

conditions and/or formula, in my view, just cannot be altered

and/or amended unilaterally and basically without consent of

the other party, in such fashion.

22 The submission raised by the learned Senior Counsel

appearing for the Respondents based upon the various

judgments cited and referred that the interpretation given by

the Arbitrator and/or experts and/or Engineers, just cannot be

interfered with, by the Court. The possible interpretation

and/or view expressed by the experts and/or Arbitrator and as

ssm 20 arbp162.09

settled, the Court normally reluctant to interfere with it. But, in

the present case, the Respondents/employer, unilaterally

changed the agreed formula without consent of the Petitioners

and refused the claim made by the Petitioners. The power of

clarification and/or removal of doubts or discrepancies of the

existing formula, cannot be equated with the power of

unilateral change and/or correction in the formula itself. It is

impermissible. It is clear breach of the contract.

23 First of all, there should be a clear case of removal of

ambiguity and/or vagueness in the formula. This contemplates

pre-existence of the agreed formula. In the present case, we

are not dealing with such situation. Admittedly, as recorded

above, the Respondents, on a foundation of "mutual mistake"

unilaterally, changed the clauses of the formula itself and

refused to grant the claim so made by the Petitioners. Sub-

clause 70.3 (i) to 70.3 (vii), the term "R" has been used by the

Respondents through out. The commercial understanding of

the word and its meaning as elaborated, remained unchallenged

till this date. There is nothing on record to show that the

ssm 21 arbp162.09

Respondents, at any point of time, sought clarification and/or

amendment to the formula, at earliest. Both the parties,

therefore, are bound to treat "R" as "R" throughout. Once each

and every items of formula and/or the clauses are defined since

the beginning, it cannot be changed. The payment/calculation

needs to be based upon unchanged formula. I am not inclined

to accept the submission of the learned counsel appearing for

the Respondents-Corporation that it can be changed and/or

interpreted at any point of time. The terms and conditions and

the clauses, so announced and agreed, unless altered by consent

of the parties, bind all, for all the purposes.

The binding effect on the monetary claim and the agreed formula:-

24 The another angle of the matter is, as submitted, that the

use of "R" and its meaning, if accepted as contemplated by the

Petitioners and/or the claimants, it would be contrary to the

spirit of the contract. Admittedly, this agreed formula and its

terms referring to price variation, play important role so far as

the monetary claim is concerned. The formula so announced

ssm 22 arbp162.09

and agreed was known and so also the nature of project and/or

the work. Therefore, the submission revolving around the

concept of "mutual mistake" is also unacceptable, as there is no

material whatsoever, brought on record by the Respondents-

employer to justify the same. There was opportunity available

with the Respondents either to amend the same at the earliest,

pending the execution of the work, and/or during the course of

Arbitration proceedings to lead evidence to support their case of

"mutual mistake". The submission and/or the averments of

mutual mistake, just cannot be accepted unless there is a clear

and apparent material and/or documents and/or evidence of

the parties to overwrite and to take away the written agreed

formula and its financial effect on the claim. All these things

are missing in the present case. There is no question of

unilateral rectification.

25 The parties, including the Arbitral Tribunal, in view of the

settled position of law, bound by the terms and conditions of the

contract, so also the agreed formula. This Court in Haji Abdul

Rahman Allarakhia and Anr. Vs. The Bombay and Persia

ssm 23 arbp162.09

Steam Navigation Company 8 , has observed as under:-

"A plaintiff seeking rectification must show that there was an actual concluded contract antecedent to the instrument sought to be rectified, and that such contract is inaccurately represented in the

instrument."

26 The Apex Court in D.C.M. Ltd. Vs. Municipal

Corporation of Delhi & Anr. 9 has observed as under-

13. The arbitrator was required to examine the narrow question whether the formula had been properly applied. It was not open to him to examine the correctness or otherwise of the

formula. He had to examine how the formula

had been worked. The formula had clearly set out the various factors to be taken into account.

"The arbitrator, therefore, was not right in distorting this formula by removing the factor of transmission and distribution losses from calculation of the units sold. The arbitrator's jurisdiction was confined to examining whether

the calculations were in accordance with the formula. Therefore, in effect, the arbitrator has acted beyond the scope of his reference in eliminating an important factor in calculation of the formula."

     8       (1892) 16 Bom 561
     9       (1997) 7 SCC 123





      ssm                                   24                                arbp162.09

The Similar contract and same formula, but different view by another Tribunal and its effect:-

27 It is relevant to note that, in the present case, an

application was moved by the Petitioners to bring on record

another award passed by the Arbitral Tribunal arising out of

similarly placed contract and the work, where the Respondents

were party. The same was rejected as it was placed on record

on 19 September 2006 at quite late stage of the Arbitration

proceeding. The submission of the learned counsel appearing

for the Respondents was accepted and the learned Tribunal not

permitted the Petitioners to place on record the said award and

the additional material on record, basically by observing that no

new evidence can be taken on record at the time of rejoinder.

The Petitioners have raised issue out of the same even in this

Section 34 Petition. The copy of the award was also placed on

record. Normally, there is no question of accepting the new

documents on record for the first time in Section 34 Petition.

The Presiding Arbitrator, as well as, one of the Arbitrator who

was the Arbitrator in the present matter, were fully aware of the

reasoned award so passed based upon the similar terms and

ssm 25 arbp162.09

conditions and the formulas, apart from similar nature of the

work.

The important documents placed at late stage:-

28 The Arbitrator, normally needs to follow the basic

principle of Civil Procedure Code (for short, CPC) and/or the

Evidence Act. But, at the same stroke, it is not binding for all

the purposes. The documents and/or material, though placed

at rejoinder stage, but goes to the root of the matter and in the

given case important for the final adjudication, pending before

them, in my view, just cannot be overlooked even by the Arbitral

Tribunal. The provisions of CPC and/or the Evidence Act are

not applicable, this itself also means in a given case, those

necessary restrictions also. If the case is made out, considering

the principle of natural justice, fair-play and equity, the Arbitral

tribunal can take note of all these evidence and/or documents,

as it goes to the root of the matter. There is no serious dispute

with regard to the award so passed in respect of M/s. Arabian

Jacking Enterprises for Contracting and Trading Company

ssm 26 arbp162.09

(AJECT) Vs. The Municipal Corporation of Greater Mumbai

(MCGM) dated 18 April 2012. The submission was made that

the facts and circumstances were different. But, after

considering the same formula and the submission, the same

Respondents have been directed to pay the amount with

interest. The similar submissions revolving around the right of

Respondents to change the formula unilaterally and/or by

mutual mistake and/or it was only with the interpretation of the

terms and conditions, were rejected.

The formula, cannot be changed unless consented at earliest:-

29 I am inclined to observe here that in such commercial

agreements and basically when both the parties agreed and

acted upon, just cannot be change any clause and/or clauses of

formula unilaterally, unless there is consent and/or the further

agreement and/or amendment recorded accordingly. The

concept of opportunity at relevant time is very relevant while

amending any clause of the agreement. In a given case, the

either party may provide justification and/or clarification

ssm 27 arbp162.09

and/or oppose the same at the relevant time itself, before

proceeding with the project. In the present case, immediately

after three bills, the dispute arose. The Petitioners referred and

objected to such amendment and/or modification of formula.

The experts of the Respondents gave their opinion. The

contractor, however, never accepted the same. The fact remains

that the formula so agreed initially sought to be amended

and/or changed by the Respondents pending the project and

thereby rejected the claim. The Petitioners, if not willing to give

consent and/or never agreed to change the agreed formula, it

was a matter of dispute at the relevant time itself. In my view,

this is not the case of discrepancy and not a case of clarification.

It is a clear case where, the Respondents want to unilaterally

amend the formula itself, which in my view, just not permissible

without giving full opportunity to the parties. The conclusion,

therefore, given by the majority Arbitrator in this matter, by

overlooking the similarly placed award. The party, one who

makes a positive statement referring to interpretation of the

clauses, if failed to prove the same and/or failed to support the

same, this destroy their own case. This supports the claimant's

ssm 28 arbp162.09

case that the agreed formula was intended for all the purposes.

The majority Arbitrator, therefore, in my view, committed an

error in rejecting the claim of the Petitioners.

30 Considering overall view of the matter and the award so

placed on record, "M/s. AJECT", the minority view required to

be maintained. But under the Arbitration Act the Court, under

Section 34, nowhere permitted to accept the minority view, in

such manner. The challenge under Section 34 Petition is always

to the majority award, therefore, to set aside the majority award

itself, in no way means acceptance of the minority award in the

present case. In such situation, the appropriate order will be to

remand the matter for re-consideration on all points.

31 I have already, based upon the Supreme Court Judgments,

observed in GWL Properties Ltd. Vs. James Mackintosh & Co.,

Arbitration Petition No. 272 of 2010 dated 16 March 2012,

referring to Jigar Vikamsey Vs. Bombay Stock Exchange

Limited, that-

     10    2010(1) Bom. C.R. 908





      ssm                                 29                                arbp162.09

(d) The jurisdiction of the Court to interfere with an Award made by an Arbitrator is limited, unless

there is an error apparent on the face of the Award and/or jurisdictional error and/or legal mis-

conduct. [Numaligarh Refinery Ltd. Vs. Daehim Industrial Co. Ltd. (2007(10) SCALE 577= (2007) 8 SCC 466] .

(e) The wrong point of law and apparent, improper and incorrect findings of facts which are demonstratable on the face of the material on record, may be treated as grave error and/or legal

misconduct.

32 I have already observed in Axios Navigation Co. Ltd. Vs.

Indian Oil Corporation Limited

"19 The Court even otherwise, is entitled and

empowered to express opinion on merits of the

matter if case is made out even by setting aside the majority view/opinion. It cannot be stated here that the Court ought not to have looked into the reasons given by dissenting Arbitrator's opinion. Any

opinion given by any of the Arbitrator whether by majority and/or by minority, if based upon the valid foundation of law and the record, just cannot be overlooked by the Court under Section 34 of the Arbitration Act, 1996. The Court's independent

reasonings irrespective of the reasons given by the majority and/or minority Arbitrator should prevail.

33 In view of above, the judgments so cited by the learned

senior counsel appearing for the Respondents, need no further

11 2012 Vol. 114 (1) Bom. L.R. 0392

ssm 30 arbp162.09

discussion. The facts are totally distinct and distinguishable. I

have already recorded that this is not the case of the

interpretation of the formula and the clauses. It is case of

unilateral amendment of the formula. The judgments,

therefore, so sited, in my view, nowhere sufficient to reject the

case and/or the submissions so made by the learned counsel

appearing for the Petitioners. The formula in question and the

unilateral change of the structure of the formula was not the

issue in the judgments so cited. This is not a case of mere

interpretation of the formula without changing its structure and

the items. The submission revolving around Section 28(3) of

the Arbitration Act is also of no assistance. It is not even a case

of rectification of term or formula or interpretation of agreed

formula. It is relevant to note and conclude by referring to

following paragraph of Dhulipudi Namayya Vs. The Union of

India

" Thus, the mere fact that a new and a collateral terms is annexed to an absolute acceptance would not affect the formation of the contract on the basis of the original offer which is unconditionally accepted. As observed in the case of Jainarain V. Surajmull, AIR 1949 FC 211 at p. 216 (B).

     12           AIR 1958 AP 533





      ssm                                    31                                 arbp162.09

If after a contract is concluded and its terms settled further negotiations are started with regard to

new matters, that would not prevent full effect being given to the contract already existing, unless it is

established as a fact that the contract was rescinded or varied with the consent of both the parties or that both parties treated it as incomplete and inconclusive. Once completed, the contract can be got

rid of only with the concurrence of both parties."

The remand is permissible mode to avoid further delay:-

Section 34 (4) of the Arbitration Act, permits the Court to

remand the matter for particular point and/or points and so

also the Civil Procedure Code (for short, "CPC"). I have already

observed in Angel Capital Angel Capital & Debt Market

Limited Vs. Mr. Sharad Munot, Arbitration Petition No. 972

of 2009, dated 31 August 2012, that if all issues and/or all

points are inter-linked and/or inter-connected, the limited

points and/or issues just cannot be remanded back for a fresh

adjudication. In the present case, the whole case revolving

around the formula in question, therefore, there is no question

of remanding back the matter on a particular point. I am

inclined to keep all points open and thereby granted

ssm 32 arbp162.09

opportunity to both the parties to make their submission afresh

before the Arbitral Tribunal. If the Arbitral Tribunal and/or its

members are not available, the parties are at liberty to take

appropriate steps to reconstitute the Tribunal. In the facts and

circumstances, just by quashing the award, I am not inclined to

delay the proceedings further, so far as the settlement of dispute

between the parties. The parties, by consent, subject to

permission of the Tribunal, may proceed based upon the same

material and/or evidence available on record, or even in a given

case may lead additional evidence by consent and/or by

obtaining appropriate permission from the Tribunal. The

requirement is an early disposal of the Arbitration proceeding.

No case to interfere with the cost so awarded.

     35     In the result following order:-

                                        ORDER





            a)     The impugned majority award dated 11 July 

2007 is quashed and set aside, except the

award of cost.

            b)     The   matter   is   remanded   back   for   re-





      ssm                              33                               arbp162.09

consideration, by giving opportunity to the

parties.

c) All points are kept open.

d) The hearing is expedited.

e) The parties to take steps accordingly.

f) The Petition is accordingly allowed partly.

g) There shall be no order as to costs.

(ANOOP V. MOHTA, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter