Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Union Of India vs M/S. C.M. Gandhi & Co
2012 Latest Caselaw 239 Bom

Citation : 2012 Latest Caselaw 239 Bom
Judgement Date : 20 October, 2012

Bombay High Court
The Union Of India vs M/S. C.M. Gandhi & Co on 20 October, 2012
Bench: Anoop V.Mohta
                                         1                                arbp215.03

              IN THE HIGH COURT OF JUDICATURE AT BOMBAY




                                                                           
                   ORDINARY ORIGINAL CIVIL JURISDICTION




                                                   
                   ARBITRATION PETITION NO. 215 OF 2003 

     The Union of India, through
     Director General, Naval Project (MB),




                                                  
     having their office at Accommodation
     Complex, Shahid Bhagat Singh,
     Road, Mumbai-400 023.                                  ..  Petitioner 




                                      
                  V/s.
                         
     M/s. C.M. Gandhi & Co.
     having their office at Aashirwad
     Building, 16, 4th Floor,
                        
     Plot No. 48-A, Next to Vithoba
     Temple, Sion (West),
     Mumbai-400 022.                                        ..  Respondent.
      


     Ms. S. V. Bharucha with Ms. Nisha Valani for the Petitioner.
     Mr. Simil Purohit with Mr. Rohan Cama, Mr. Gauraj Shah and 
   



     Mr. Namish Joshi i/by Vimadalal & Co. for the Respondent. 

                                        CORAM   :  ANOOP V. MOHTA, J.
                         RESERVED ON        : 17 SEPTEMBER 2012.
                         PRONOUNCED ON : 20 OCTOBER 2012.


     JUDGMENT :-





The Petitioner-Director General, Naval Project (MB),

through the Union of India has challenged award dated 24

December 2002, passed by the sole Arbitrator appointed under

2 arbp215.03

the Arbitration agreement between the parties. There is no

counter Petition/ challenge to the award by the Respondent

(Original Claimant).

2 The basic dates and events are as under.

On 9 June 1996, the Petitioner issued a Tender under

contract No. DGNP (MB)/04 of 97-98 for provision of Mast

Testing Facility at Naval Dockyard, Mumbai. On 23 September

1996, the Respondent submitted their tender for the said work.

On 6 May 1997, after obtaining some clarifications and due

negotiations, the Petitioner issued the work order for an amount

of Rs.1,04,56,327/- in favour of the Respondent. The date of

commencement of Phase-I as per work order No.1, 9 August

1997, was extended to 15 November 1997.

3 The date of commencement of Phase-II as per work order

No.1 was 9 August 1997, and the completion date was 8 August

1998 i.e. 12 months. This date was extended to 15 February

1999. On 18 December 1997, the Petitioner's by a letter issued

a Completion Certificate for Phase-I for having completed the

3 arbp215.03

same on 15 November 1997. On 15 February 1999, complied

the phase II. On 5 March 1999, the Petitioner by their letter

issued a Certificate of Completion stating therein that the work

has been completed satisfactorily. On 8 March 1999, pre-final

Bill and final bill submitted by the Respondent.

4 On 30 October 1999, a letter addressed by the Respondent

to the Petitioner raising claims on account of delays,

obstructions, hindrances and breach of contract committed by

the Petitioner. On 9 December 1999, letter addressed by the

Petitioner to the Respondent denying the aforesaid claims of the

Respondent. On 2 March 2000, notice addressed by Respondent

to the Petitioner invoking the Arbitration proceedings and

calling upon them to appoint a Sole Arbitrator as per condition

No. 70 of IAFW-2249 to settle the disputes/differences.

5 On 31 October 2001, Arbitration Application No. 197 of

2001 for an appointment of Arbitrator under Section 11 of the

Arbitration and Conciliation Act, 1996 (for short, the Arbitration

Act), preferred by the Respondent before this Court. On 15

4 arbp215.03

February 2002, by a reasoned order and after considering the

objections of the Petitioner, appointed an Arbitrator. On 8 May

2002, Government of India, Ministry of Defence appointed

Brigadier R.B. Singh, from the Union of India Panel of Learned

Arbitrator, as the sole Arbitrator.

6 On 9 July 2002, the statement of facts and claims filed by

the Respondent before the Sole Arbitrator. On 12 August 2002,

pleadings in defence of the Petitioner. On 17 August 2002,

Respondent statement of defence. On 29 August 2002, the

Petitioner's rejoinder in reply to the Respondent pleading in

defence. On 17 September 2002, the Respondent sur-rejoinder

in reply to counter claim raised by the Petitioner in its rejoinder.

On 24 December 2002, the learned Arbitrator passed the

detailed Arbitration Award for Rs. 22,21,476/-.

7 On 30 December 2002, the Respondent demanded the

claim amount from the Petitioner as per the Arbitration Award.

On 6 May 2003, the Execution Application No. 298 of 2003 filed

by the Respondent to implement Award dated 24 December

5 arbp215.03

2002. On 28 March 2003, the present Petition was filed by the

Petitioner. On 16 June 2003, it was dismissed for default. On

12 August 2003, the Petition restored subject to cost of

Rs.1000/-. On 25 September 2003, the Amendment Application

filed by the Petitioner was allowed. On 18 November 2003, the

Petition was admitted. The Petition listed for final hearing.

Heard accordingly.

8 The contract was for design and provision of Mast Testing

Facility at Naval Dockyard at Mumbai executed on 6 May 1997.

The period of completion of the contract was for 15 months

which was extended by consent. The Claimant-Respondent

submitted final bill on 8 March, 1999 as the Phase-I was

completed on 15 November 1997 and Phase-II was on 15

February 1999. There is no dispute that the contract governed

by the general conditions of contract. The relevant clauses are

conditions 11,65 and 70. As per condition 11 which deals with

time, delay and extension, it is specifically provided that "no

claim in respect of compensation or otherwise, howsoever

arising, as a result of extensions granted under condition (A)

6 arbp215.03

and (B) shall be admitted." There is nothing on record to show

that time was extended under the condition (A) and (B). There

is no dispute that time was the essence of contract. As per

clause 65, "no further claims shall be made by the contractor

after submission of the final bill and these shall be deemed to

have been waived and extinguished. The Arbitrator was under

obligation to pass award within 6 months and/or within the

extended time.

9 The Petitioner, therefore, challenged the grant of claim

Nos. 7(A) and (B) and 8. The full charges were also claimed of

Claim Nos. 1, 2, 4 and 5, as the same were partly allowed. No

evidence was led by the parties except the documents on record.

The final bill was submitted of 8 March 1999, the cheque was

sent on 1 February 2002, which was not accepted nor encashed.

The payment was admittedly not made within reasonable time,

though the demand was raised with supporting material.

10 The learned Arbitrator has awarded payment of final bill,

(Claim No.1), as the Petitioner agreed to pay final bill for

7 arbp215.03

amount of Rs. 3,26,213.52/-. For non payment of Star Rate

No.12., (Claim No. 2-A), the amount is awarded at Rs.

13,538.42/-. The Arbitrator has awarded Rs.2250/- for non-

payment of overhead, establishment (Claim No. 2-B). The

Arbitrator referring to the conditions that "the quantities of

various items as given in Schedule 'A' Part II are provisional and

may vary according to approved design and site conditions" and

therefore, has awarded Rs. 66,058.31 in view of admitted

increase cost of piling of depth beyond 16 meters. (Claim No. 2-

C). The Arbitrator has granted compensation for additional

bank guarantee, as the final bill could not paid by the Petitioner

in time. Therefore, claimed renewal charges of bank guarantee

from 5 November 1998 (Claim No.4). The learned Arbitrator

ultimately has granted bank charges from 9 September 1999

and partially granted Rs.42,000/-. The Contractor-Respondent

claimed compensation for delay in payment of Running Account

Receipts. (Claim No.5). The learned Arbitrator after holding

that there was delay of more than 37 months and therefore, has

granted only Rs.6,000/- though claim was of Rs. 1,35,649.57/-.

The learned Arbitrator, not granted any compensation for

8 arbp215.03

revision of rates for the work executed beyond the original

period of contract and also not granted for Deviation Order

(Claim Nos. 6 and 3).

11 The basic challenge raised by the Petitioner with regard to

the compensation for loss of idle staff and machinery and idle

labours and workers (Claim No. 7-A and 7-B) and compensation

towards loss of profits and overheads due to prolongation of

contract period (Claim No. 8). The supporting reasons are as

under:-

"33.9.5. The Union of India admitted that there was delay in

clearing site, giving decision for diversion of sewer and water

supply lines etc. They however argued that at all points of time,

contractor had some work in hand and he could continue with

other items of work. It was their contention that contract

carried a clause for payment of escalation which compensated

him for variation in prices of materials, fuel and wages of

labours. U.O.I. argued that contract provided for grant of

extension of time, which had been duly approved by the DGNP.

                                           9                                arbp215.03




                                                                            
     33.9.6        All   the   above   mentioned   reasons   have   had   a 




                                                    

contribution to make in causing this prolongation of 6 months 7

days. As the reasons unfold themselves, it is clearly evident that

majority of these were such that lied at the door-steps of DGNP.

The U.O.I. reference to certain letters, mentioned in paras

above, also revealed delays on the part of DGNP. These letters,

in no way, come to the rescue of their arguments. For whatever

be the compulsions with them, they could have eschewed the

delays and mitigated their consequential effects. Perusal of the

documentary evidence reveals that DGNP did not expedite on

many issues which did cause hindrance and delay in progressing

of activities connected with execution of this contract. The next

question to be decided is if all the reasons, as stated in para

above, fall under condition 11(A) and (B) of IAFW-2249 for

which consequential risks are that of the contractor under its

condition 11(C). My answer is clearly "No" as majority of these

reasons do not even remotely correspond to what is agreed

under the said Conditions 11(A) and (B). Therefore, the

immunity available to government would have to be limited to

10 arbp215.03

that portion of 6 months and 7 days delay the reasons for which

actually fell within the purview of conditions 11(A) and (B).

For this purpose, I have analysed the reasons and their time

effect on completion of contract. On doing so, I find that a

period of not more than three months (out of 6 months 7 days)

could be made to fall under condition 11(A) of IAFW-2249.

Balance 3 months delay is for reasons other than those listed in

condition 11(A) and therefore condition 11(C) of IAFW-2249 is

not attracted for this period of 3 months. The U.O.I. shall

therefore have to accept the liability for consequential effects of

this delay of 3 months caused at DGNP's hands. DGNP cannot

first be the cause for the delays and then argue to bail

themselves out proclaiming shelter under condition 11(C).

They cannot be the judge of their own actions. The facts have

to be unearthed and for this, one can only rely on material

evidence that emerges from the correspondence/letters between

the parties during the relevant period. I have done so. Having

decided on the proportion of responsibility for DGNP/U.O.I., the

next aspect is to decide on the measure of damage caused and

compensation therefore.

11 arbp215.03

33.9.7. For the hire charges claimed by contractor he had

furnished proof by way of paid vouchers and argued that this

was evidence of his machinery T & P and staff remained idle for

3 months. This part of his claim is therefore sustained to the

extent mentioned above and expenses for it works out to

Rs.1,70,700.00 for the effective period of 3 months.

33.9.8.

Second part of contractor's claim is for idle labour

and workers. Contractor has claimed labour component as 25%

of work done and amounting to Rs.28,15,901.20. He then

argued that this meant monthly labour cost as Rs.1,87,726.75

(i.e. Rs.28,15,901.00 divided by 15). contractor's case is that

he had deployed labour worth Rs.11,70,100.83 for additional

period of 6 months 7 days as a loss. U.O.I. denied the claim

arguing that there was no idle labour and that the labour

deployed by contractor was just sufficient for the work. I have

already concluded above that prolongation of contract was for

effective period of 3 months and was at the hands of DGNP.

Contractor's claim for idle labour and workers for this much

12 arbp215.03

period is justified and accordingly it is sustained for

Rs.5,63,180.00. I therefore award an amount of Rs.1,70,700.00

for Claim No. 7(A) and Rs.5,63,180.00 for Claim No. 7(B),

totalling to Rs.7,33,880.00."

And thereby awarded total sum of Rs.7,33,880/- for Claim

Nos. 7-A and 7-B.

So far as claim No. 8 is concerned, the following reasons

are given -

"33.10.1. I concluded period of prolongation as 3 months in

para 33.9.6 above. Contractor has claimed 17.5% as loss of

profit and overheads of his turnover. Contract value is

Rs.1,04,56,327.00 to be completed in 15 months. Monthly

turnover works out to Rs.6,97,088.46. Contractor's claim

towards loss of profit and overheads per month works out to

Rs.1,04,563.26 (Rs. 6,97,088.46x15%). Considering delay

period of prolongation as stated above for 3 months, I award

Rs.3,13,689.80 for Claim No.8."

The learned Arbitrator, thereby awarded a sum of

13 arbp215.03

Rs.313689.80. The reasons are well within the frame work of

law and the record for the following reasons and so also the

award.

13 The basic submission raised that the Arbitrator was

appointed on the application filed by the Respondent on 15

February 2002 and thereby directed the Arbitrator to proceed

expeditiously to resolve the dispute. The liberty was also

granted to the Respondent-claimant to raise the claims before

the Arbitrator and to the Petitioner to file counter-claim. The

parties accordingly filed their claims and the counter-claims.

Therefore, having once the parties filed the claim and counter-

claim, pursuant to the order passed by the Court to settle the

disputes, therefore, in the present facts and circumstances, the

claim so raised by the Respondent cannot be faulted with. The

Arbitrator, therefore, in view of the order, bound to adjudicate

the claims so raised by the parties.



     14    The Apex Court in  Ravindra Kumar Gupta and Co. Vs.  





                                            14                                 arbp215.03

Union of India 1 maintained the award as in that case also there

was delay attributable to the employer Union of India. The

similar clause was read and referred in the matter and also the

similar submissions referring to the grant of compensation

towards loss of profit, escalation overhead charges, on the

ground of employers delay, if any.

I have already in Union of India Vs. M/s. Suraj

Infrastructures Pvt. Ltd., 2 maintaining similar types of award of

compensation on the ground of delay on the part of employer

and observed as under:-

"26 The Apex Court in J.G. Engineers Private Limited Vs. Union of India & Anr. 3 , referring to Section 34 read with the provisions of Contract Act

observed as under:-

"Once it is held that the issues relating to who committed breach and who was responsible for delay were arbitrable, the findings of the

arbitrator that the contractor was not responsible for the delay and that the termination of contract is illegal are not open to challenge."

     1      (2010) 1 SCC 409
     2      Arbitration Petition No. 324 of 2009, dated 17 September 2012
     3      (2011) 5 SCC 758





                                          15                                arbp215.03


In the result, the escalation price so awarded on the

basis of delay and consequential termination of contract by the employer upheld.

16 The Arbitrator has power to award the interest unless

specifically agreed otherwise. There is no such clause pointed

out in the present case. The grant of interest, therefore, covered

by the provisions of Arbitration Act and the judgments.

17 The strong reliance is placed by the learned counsel

appearing for the Petitioner on Oil and Natural Gas

Commission Vs. Macqreqor-Navire Port Equipment and Ors. 4

referring to Section 74 of the Contract Act, 1872 read with the

provisions thereof and also the Interest Act, 1978.

18 So far as the counter-claim is concerned, there is no

material supplied and/or reasons given by the Petitioner to

claim the cost of reference. The cost of recovery for defects in

work was rejected for want of details and supporting material

and ultimately awarded Rs.9,902/- towards claim of defects in

4 2002(1) Bom. C.R. 278

16 arbp215.03

the work. I am inclined to grant 9% p.a. simple interest as not

awarded by the Arbitrator on the amount towards the counter

claim No.2, from the date of the award. The claim and counter

claim with interest, need to be adjusted accordingly.

19 So far as interest is concerned as mentioned in para

33.11.8, I am inclined to reduce the rate of simple interest from

12 % per annum to 9% per annum, in view of Krishna Bhagya

Jala Nigam Ltd. Vs. G. Harischandra Reddy & Anr. 5

20 So far as the future interest is concerned, I am restricting

the same also to 9% per annum simple interest, instead of 15 %

per annum as awarded. The aspect of pendency of present

Arbitration Petition for various reasons, is also relevant factor in

reducing the rate of interest. The future rate of interest, as the

award is of dated 24 December 2002 and the Petition was heard

for the facts referred above in the year 2012, the Petitioner

should not only be asked to suffer rate of interest because of

pendency of the litigation.

     5      2007 AIR SCW 527





                                             17                                arbp215.03




                                                                               
     21     The Respondent is entitled for the interest on the ground 




                                                       

of compensation/damages so awarded on the ground of delay

from the date of award only. So far as delay in payment is

concerned, the interest so awarded needs no interference. The

Arbitrator has awarded the compensation on the ground of

delay, loss of idle staff, machinery, labours and workers and loss

of profit and overhead due to prolongation of contract period.

Therefore, I am inclined to observe that the Respondent

claimant is entitled for the interest on the said amount from the

date of the award and not prior to that. There is no question of

interest on the assessed damage or compensation

retrospectively. It should only from the date of award.

22 Considering the scope and purpose of Section 34 of the

Arbitration Act, as there is no perversity and no illegality in the

reasons and the compensation so awarded is also reasonable

and just and fair based upon the record, the award needs no

interference, except the rate and date of the interest on all

stages as recorded above.

                                       18                                arbp215.03




                                                                         
     23   In the result, the following order:-




                                                 
                                  ORDER

          a)    The award is maintained, except the rate and 




                                                
                date   of   interest.     The   award   is   modified 

                accordingly. 




                                   
          b)    The Petition is accordingly disposed of in the 
                    
                above terms. 

          c)    There shall be no order as to costs. 
                   

                                   (ANOOP V. MOHTA, J.)
      
   







 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter