Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Deccan Chronicle Holdings ... vs Board Of Control For Cricket In ...
2012 Latest Caselaw 217 Bom

Citation : 2012 Latest Caselaw 217 Bom
Judgement Date : 18 October, 2012

Bombay High Court
Deccan Chronicle Holdings ... vs Board Of Control For Cricket In ... on 18 October, 2012
Bench: R.D. Dhanuka
hvn
                                              1
                                                                               ARBPL-1352.12



                 IN THE HIGH COURT OF JUDICATURE AT BOMBAY




                                                                                 
                      ORDINARY ORIGINAL CIVIL JURISDICTION




                                                         
                    ARBITRATION PETITION (L) NO. 1352 OF 2012

      Deccan Chronicle Holdings Limited having
      its registered office at 36, Sarojini Devi Road,




                                                        
      Secunderabad 500 003                                     ...        Petitioner

                                           Versus

      1. Board of Control for Cricket in India,




                                                 
      having its registered office at Holkar
      Stadium, Khel Prashal, Race Course Road,
                                
      Indore 452 003
      And
      Board of Control for Cricket in India,
                               
      Cricket Centre, Wankhede Stadium,
      "D" Road, Churchgate, Mumbai 400 020

      2. Kamla Landmarc Real Estate Holdings
             

      Pvt. Ltd. Having its office at Shanti Vimal,
      Ground Floor, Sir P.M. Raod, Vile Parle (East),
          



      Mumbai 400 057, Maharashtra                              ...        Respondents


      Mr. S.U. Kamdar, Sr. Counsel along with Mr. Zal Andhyarujina and Mr. Arcot





      Chandrashekar i/by M/s. Dave Girish & Co. for the Petitioner.

      Mr. Janak Dwarkadas, Sr. counsel with Mr. Nandkishore and Mr. Anjan
      Dasgupta for HSA Advocate for intervener Ratnakar Bank.

      Mr. Navroz Seerwai, Sr. Counsel, Mr. Rohan Cama, Mr. Ajay Vazirani, Mr.





      Amey Nabar, Mr. S.S. Ghosh, Mr. Anirudh Hariani, Ms. Deeksha Dadwal, Mr.
      Ameya Deosthale i/by M/s. Hariyani & Co. for respondent no. 2.

      Mr. T.N. Subramanium, Sr. Counsel along with Mr. P.R. Raman, Mr. Viraj
      Maniar, Ms. Akhila Kaushik, Ms. Misbah Dada and Mr. Nikhil Karnawat i/by
      M/s. Maniyar Srivastava Associates for respondent no. 1.

                                         CORAM : R.D. DHANUKA, J.

DATE : 18TH OCTOBER, 2012.

ORAL JUDGMENT:

1. By this Petition under section 9 of the Arbitration & Conciliation Act,

hvn

ARBPL-1352.12

1996 (hereinafter referred to as "Act"), the petitioner seeks stay of the

termination of Franchise agreement by letter dated 14 th September, 2012

and the subsequent decision of the Working Committee of the Board of

Control for Cricket in India (hereinafter referred to as "BCCI") dated 15 th

September, 2012 confirming the same. The Petitioner also seeks status

quo order against the parties and injunction against BCCI from acting upon

the tender notice issued on 14th October, 2012 and or providing any party

with the invitation to tender in respect of the franchise for the City of

Hyderabad.

2. The relevant facts in the matter are briefly set out hereunder :

In and around 2007, the BCCI conceptualised a tournament to be

called "Indian Premier League" which would involve competition between

various teams of Twenty-20 format of cricket. A sub committee of the

respondent known as Indian Premier League managed by a separate

governing council, was setup/established to oversee the operation of the

league, which in turn, ultimately reports to BCCI. The IPL/BCCI conceived

that private individuals/companies should establish and operate the teams as

franchisees in the league, as per the guidelines and regulations framed by

IPL/BCCI. The Deccan Chronicle Holdings Ltd. (hereinafter referred to as

"DCHL") was declared successful bidder for Hyderabad franchise of the

league and the franchise agreement dated 10th April, 2008 was thereafter

executed between DCHL and BCCI.

hvn

ARBPL-1352.12

3. On 14th September, 2012, BCCI terminated the franchise agreement

on various grounds. On 15th September, 2012, the DCHL filed Arbitration

Application (L) No. 1238 of 2012 in this court for seeking interim measures.

4. On 1st October, 2012, this court disposed of the said arbitration petition

by passing a detailed order. In Para 6 of the said order, it has been

observed that admittedly DCHL failed to make payments as agreed to its

players, support staff, associations and overseas cricket boards which

became due on and from 1st May, 2012. In Para 42 and 43 this court held

as under :

"42. In the above circumstances I am of the view that BCCI has at all

stages acted in some haste in terminating the Franchise Agreement

with DCHL. Though BCCI had after issuing the termination notice on

14th September 2012, granted time to DCHL to cure the defects upto

5.00 p.m. on 15th September 2012, it would have been prudent on the

part of BCCI to take the decision of confirmation of termination of the

Franchisee Agreement after considering all the letters received from

DCHL or its Bankers on 15th September 2012. Instead, BCCI has, on

the same day at 5.30 p.m., without considering the letters received by it

by 5.00 p.m. or a little thereafter, taken the decision to confirm its

decision dated 14th September 2012 to terminate the Franchise

Agreement executed by and between BCCI and DCHL. Despite the

above, I do not attribute any motives to BCCI at this stage and, as

stated hereinabove, I am proceeding on the basis that the haste on part

of BCCI was due to the fear and anxiety expressed by their Learned

hvn

ARBPL-1352.12

Senior Advocate namely that the failure on the part of DCHL to fulfill

their contractual commitments may tarnish their image in International

cricketing circles. However such hasty termination, if after a detailed

adjudication by the Arbitrator is found to be incorrect will cause grave

loss and prejudice not only to DCHL but also to the Banks and financial

institutions which are backing DCHL with financial support, resulting in

complete destruction of DCHL which cannot be compensated in terms

of money. At the same time the Court whilst granting protective reliefs in

the above petition to DCHL, as submitted by the learned Senior

Advocate appearing for the BCCI, will also have to keep in mind the

interest of BCCI, the game and its players more particularly the image

of BCCI in the International Cricketing World. I have inquired from the

Learned Advocate for DCHL whether his clients are willing to furnish an

irrevocable and unconditional Bank Guarantee to BCCI in the sum of

Rs. 100 crores as security for the IPL Series VI, within 10 days from

26th September 2012 , the Learned Advocate after taking instructions

has responded in the affirmative. Though I find that the balance of

convenience is more in favour of DCHL, I am of the view that the

following protective orders will take care of the interest of both the

parties.

(i) DCHL shall furnish an irrevocable and an unconditional Bank Guarantee

of a Nationalized Bank in the sum of Rs. 100 crores (Rupees One hundred

crores) to BCCI on or before 9th October, 2012 which should be in force for a

period of one year.

(ii) DCHL shall bear all the expenses for IPL Series6 i.e. make payments to

BCCI towards Franchise fee, player and support team costs and in addition

hvn

ARBPL-1352.12

also bear the cost of match conduction and other expenses. In the event of

any default on the part of DCHL, BCCI shall be entitled to invoke the Bank

Guarantee to the extent necessary.

(iii) The representative of YES Bank who is present in Court, undertakes to

make wire transfer to the respective foreign parties on or before 3 rd October

2012 and upon presenting proof of such wire transfer, BCCI shall return the

demand drafts drawn in favour of the foreign parties by YES Bank to the

authorised representative of the said Bank.

(iv) BCCI shall forthwith disburse the demand drafts aggregating to

Rs.8,95,38,750/to the beneficiaries named therein.

(v) Upon DCHL furnishing the said Bank Guarantee in the sum of Rs.100

crores to BCCI and DCHL through its Bankers effecting the aforestated wire

transfers to the foreign parties, BCCI shall deposit the amount already due

and payable by BCCI to DCHL and payable in future to DCHL with the

Prothonotary and Senior Master of this Court which the Prothonotary and

Senior Master shall invest in a fixed deposit of a Nationalised Bank from time

to time until further orders of the Court.

(vi) BCCI shall, pending the arbitration proceedings and making of an Award

by the learned Arbitrator and for a period of 7 days thereafter if the Award is

in their favour, not act on the termination of the Franchise Agreement.

However, it is clarified that this order shall immediately cease to be in effect

in the event DCHL fails to furnish a Bank Guarantee of Rs. 100 crores as

provided in clause (i) above on or before 9 th October, 2012.

(vii) DCHL undertakes to pay IFCI Ltd. the balance installments as agreed in

the consent terms on its due dates. The undertaking is accepted.

(viii) DCHL shall pay the undisputed outstanding dues of Hotels, transporters

hvn

ARBPL-1352.12

etc. as regards the IPL Series V on or before 31st October 2012.

(ix) This Order shall not preclude the BCCI from adding one more Franchisee

for IPL6 series and thereafter.

43. The above Arbitration Petition is accordingly disposed of with a

clarification that all the observations made herein are prima facie and the

Learned Arbitrator shall make his Award without being influenced by any of

the observations made herein."

5. On 9th October, 2012, the DCHL applied before this court for extension of

time to furnish bank guarantee as set out in para 42(i) of the order dated 1 st

October, 2012 upto 12th October, 2012, 5.00 p.m. The DCHL also applied for

permission to furnish a bank guarantee of ICICI Bank instead of a nationalized

bank. This court granted extension of time to furnish bank guarantee upto 12 th

October, 2012, 5.00 p.m. This court, however, directed the petitioner to take out

appropriate proceedings for seeking necessary modifications of the order dated 1 st

October, 2012 as sought by the petitioner. It is an admitted position that no such

application came to be made by the petitioner seeking substitution of bank

guarantee of nationalized Bank by ICICI Bank.

6. On 12th October, 2012 at 11.00 a.m., an oral application was made for

extension of time to furnish bank guarantee which has been admittedly declined.

The order passed by this court on 1st October, 2012 being self operative,

termination of the contract came into effect at 5.00 p.m., on 12 th October, 2012.

7. In the arbitration meeting held before the arbitral tribunal on 12 th October,

2012 which commenced at about 5.30 p.m., after directions were issued by the

arbitral tribunal, an application under section 17 of the Act came to be made for

hvn

ARBPL-1352.12

grant of status quo order passed by this court. The arbitral tribunal passed status

quo order on 12th October, 2012. The order passed by the arbitral tribunal granting

status quo has been set aside by this court by passing a separate order today. In

the meanwhile, BCCI issued a tender notice on 14 th October, 2012 inviting a new

premier league franchise. It is provided that bids must be submitted at 12.00 noon

of Thursday, 25th October, 2012. It is further provided that bids may be submitted

in respect of the cities such as Ahmedabad, Cuttack, Dharamsala, Indore,

Hyderabad, Kanpur, Kochi, Nagpur, Noida, Rajkot, Ranchi and Vizag.

8.

The Petitioners moved this petition under section 9 of the Act for seeking

stay of the termination of the franchise agreement by letter dated 14 th September,

2012 and confirmed by letter dated 15 th September, 2012 and for injunction against

the BCCI from acting upon the tender notice issued on 14 th October, 2012.

9. Mr. Kamdar, the learned senior counsel appearing for DCHL, Mr. N.A.

Seervai, the learned senior counsel for Kamla Landmarc Real Estate Holding Pvt.

Ltd. (respondent no. 2), and Mr. Janak Dwarkadas, learned senior counsel

appearing for Intervenor Ratnakar Bank, addressed this court in support of grant

of interim measures. The learned counsel made following submissions :

(a) IPL-6 would start in April, 2013. There are no existing liabilities of

DCHL towards BCCI. Ratnakar Bank one of the creditors is supporting

DCHL in applying for status quo of the termination order. DCHL has

already entered into agreements with players and the same are in

existence today. No prejudice would be caused to BCCI if DCHL is

permitted to go out of franchise and is allowed to sell its team to the

second respondent.

hvn

ARBPL-1352.12

(b) If termination is not stayed, several creditors including petitioners

would be seriously affected. The DCHL has invested about Rs. 600

Crores., which would be wasteful. There is no complaint made by any

players against DCHL regarding payments. DCHL has so far paid a

sum of Rs.237 Crores to BCCI. Whatever, fees is payable in future

under the Franchise Agreement would also be paid. After refusal of stay

by this court and stay of order passed by the arbitral tribunal in appeal,

there is change in circumstances which warrants grant of interim

measures by this court on this application under section 9 of the Act.

The learned counsel relied upon avermetns made in para 14 and 15 of

this petition which reads as under :

"14. The Petitioner states and submits that entering into MOU by the

Petitioner and the Respondent no.2 amounts to a significant change in

circumstance. The Petitioner states and submits that the said MOU was

arrived at on 11 th October, 2012 and has not been the subject matter of

any application made in the said Arbitration Petition.

15. The Petitioner states and submits that subject to the consent of

the Respondent No. 1 under the terms of the MOU, the Respondent No.

2 will perform all obligations in respect of the Deccan Chargers

Franchise for IPL-6. This is a marked contract to the position before the

Ld. Judge in the said Arbitration Petition and the basis of the

circumstances under which the Orders dated 1 st October, 2012 and 12th

October, 2012 came to be passed. The record clearly bares out that

these orders were passed on the basis that in fact the Petitioner would

hvn

ARBPL-1352.12

continue to run the Franchise and to meet all obligations of the Franchise

to the Respondent No. 1 and its players in IPL-6."

(c) MOU has been already entered into between DCHL and Kamla

Landmarc Real Estate Holdings Pvt. Ltd. (respondent no. 2), by which

DCHL has agreed to go out of the franchise and proposed to sell its

team to the 2nd respondent for consideration. All the liabilities of the

DCHL have been agreed to be taken over by the proposed purchaser.

My attention is invited to various provisions under the said MOU dated

11th October, 2012 including the financial terms recorded by and

between the parties thereto. It is submitted that in terms of Clause 10.1

of the Franchise agreement, DCHL has already applied for prior

consent of BCCI by letter dated 11 th October, 2012 enclosing copy of

MOU dated 11th October, 2012 to BCCI and the said permission is

awaited.

(d) BCCI instead of permitting DCHL to auction its team to an

outsider is adamant to sell its team with an intention to make huge profit

and put DCHL to tremendous loss which loss cannot be compensated in

terms of money. No prejudice would be caused if the termination is

stayed and an opportunity is given to DCHL by introducing a party who

is willing to purchase the team of DCHL and save DCHL from this

situation.

(e) This Court has made various observations in the order 1 st October,

2012 in favour of DCHL and against BCCI about conduct of BCCI in

terminating the contract.

hvn

ARBPL-1352.12

10. The learned senior counsel Mr. T.N. Subramanium on the other hand submits

that:

(a) the order passed by this court on 1 st October, 2012 staying the

termination on various conditions is self operative The conditions not

having been complied with, the termination came into effect at 5.00 p.m.,

on 12th October, 2012. Once the respondent's application for extension

of bank guarantee came to be rejected by this court at 11.00 a.m., on

12th October, 2012, an application was made without prior notice before

the arbitral tribunal for continuation of stay. It is submitted that this court

has rightly stayed the operation of status quo order granted by the

arbitral tribunal. It is submitted that once extension was refused by this

court and this court having stayed the operation of the status quo order

passed by the arbitral tribunal, this petition again seeking stay of

termination is not maintainable.

(b) The orders passed by this court on 1 st October, 2012, 12th

October, 2012 and 13th October, 2012 have not been challenged by

the respondents. All these orders are binding on the parties. It is

submitted that four winding up petitions filed against the petitioner

company were pending on the date of filing earlier petition under

section 9 of the Act. M/s. Tata Capital has filed recovery

proceedings against the petitioner wherein an injunction order has

been passed from selling assets of petitioner. The learned senior

counsel invited my attention to clause 2.1(b) of the Franchise

agreement which empowers the BCCI to grant to the franchise a

hvn

ARBPL-1352.12

right to be the only team in the league whose home stadium is

located in the territory during a period of not less than the first three

seasons.

(c) Under clause 10.1 of the franchisee agreement, the

franchise has no right to assign or delegate the performance of

any right or obligation under that agreement without prior written

consent of BCCI. It is submitted that in view of the DCHL not

having remedied the material breach pointed out by BCCI, the

BCCI was justified in terminating the contract. It is submitted

that the insolvency event as defined under clause 11.6 of the

Franchise agreement had occurred.

(d) The learned senior counsel also invited my attention to

various clauses in the MOU entered into between DCHL and the

second respondent. It is submitted that the application for prior

consent made by DCHL under clause 10.1 of the agreement is

under consideration of BCCI. The learned counsel invited my

attention to clause 2 of the MOU which provides that the net

realisation under the franchise would be INR 1250 Crores in

aggregate be discharged and payable in the manner set out

therein. It is proposed that the cash pay out of INR 350 Crores

payable by the purchaser in 10 years in equal installments payable

starting from the 30th day of December of the calender year

pertaining to the closing date more particularly set out in Annexure

hvn

ARBPL-1352.12

I. It is provided that the first pay out shall be made not later than

30 December, 2013. My attention is invited to clause 3 which

records various conditions precedent for consideration of

transaction of sale of the franchise in terms of the said MOU.

Clause 3(a)(c ) and (e) are relevant and are as under :

"(a) The seller shall procure and obtain all consents,

approvals, no objections, permissions of its Lenders, its

shareholders, BCCI and the High Court of Bombay including

any other authority for consummating the sale of the

Franchise to the purchaser free of any lien, charge and

encumbrance and for execution of the Definitive Agreements

and all other documents and writings as may be necessary to

give effect to the sale.

(c ) The Seller shall settle in full all the liabilities of the

Franchise up to the Closing date only (i.e. the date when the

Sale and Transfer of the Franchise shall be effected in favour

of the Purchaser and which shall be a date not later than 31

March, 2013 or a mutually extendable date) (including but not

limited to player amounts due for IPL 2010 season or any of

the previous seasons, amounts due to Cricket associations,

amounts due to each Bought-out player, amounts due to

BCCI, Support Staffs, etc.) and also undertake to take over

and keep the Purchaser harmless from all liabilities and claims

pertaining to the Franchise that have arisen upto the Closing

hvn

ARBPL-1352.12

date or arise (at any time thereafter) due to any event or

cause of action pertaining to or taken place on or prior to the

Closing Date.

(e) Execution and satisfactory delivery of Definitive

agreements between the Seller and the purchaser no later

than 31 March, 2012 or a mutually extendable date."

(e) It is submitted that if reliefs as claimed by the petitioner in

this petition

are granted, it would amount to setting aside the

termination under section 9 of the Arbitration and Conciliation Act,

1996 which is not permissible. It is submitted that the order passed

by this court on 1st October, 2012 was an equitable and protective

order considering the interest of both the parties. The petitioner

not having complied with the conditions imposed by this court in

that order, cannot once again apply for stay of termination.

(f) It is submitted that though this court had granted liberty to

apply on 9th October, 2012 for modification of the order dated 1st

October, 2012 and to furnish bank guarantee of ICICI bank in place

of Nationalized Bank with a rider that it would be considered on

merits, no such application was made. It is submitted that the draft

of the bank guarantee forwarded to BCCI by DCHL was not in

accordance with the interim order passed by this court on 1 st

October, 2012. It is submitted that the agreements entered into with

hvn

ARBPL-1352.12

players would come to an end on 31 st December, 2012. If the

agreement is not continued, the players would be free to act for

other teams and would be available for auction. It is submitted

that any stay as sought by DCHL would not be in the interest of

BCCI, players, in the interest of the game and may tarnish the

image of BCCI in international cricketing circle. It is submitted that

in recent past BCCI had granted an opportunity to DCHL to

auction its team. The auction was held on 13 th September, 2012.

Only one bid was received by DCHL and was not accepted by

DCHL.

11. From the backgrounds of the facts narrated aforesaid, it is clear that

the order passed by this court on 1 st October, 2012 was an equitable order

considering the interest of both the parties. In Para 42 of the said order, it

is recorded that this court had enquired from the learned counsel for DCHL

whether his clients were willing to furnish irrevocable and unconditional bank

guarantee to BCCI in the sum of Rs. 100 Crores as security for IPL series 6

within 10 days from 26th September, 2012. The learned counsel after

obtaining instructions from the client had responded in the affirmative. It was

therefore, recorded that balance of convenience though was in favour of

DCHL, protective orders came to be passed which would take care of

interest of both the parties. It was also observed that this court did not

attribute any motives to BCCI at this stage. It is observed that the court was

proceeding on the basis that the haste on the part of BCCI was due to fear

hvn

ARBPL-1352.12

and anxiety expressed by their learned senior counsel that the failure on

the part of DCHL to fulfill their obligation may tarnish their image in

international cricketing circles. In my view the order passed by this court on

1st October, 2012 being self operative order, termination of the contract

came into effect at 5.00 pm on 12 th October, 2012. The validity and legality

of the same would be the subject matter of arbitration before the arbitral

tribunal. This proceedings are not by way of an appeal against the order

passed by this court on 1st October, 2012. I can not sit in appeal on the order

passed by this court on 1st October, 2012 and 12th October, 2012.

12. In my view the petitioner having failed before this court, obtained an

order of status quo from the arbitral tribunal by filing application which was

not maintainable. The arbitral tribunal acted without jurisdiction and granted

status quo order which was stayed by this court by passing order on 13 th

October, 2012. In my view, filing of another application under section 9 of the

Act for staying termination of the impugned order is in the teeth of the order

passed by this Court on 1st October, 2012, 12th October, 2012 and 13th

October, 2012 and is a gross abuse of process of law.

13. It is clear that when the petitioner applied for extension of time to

furnish bank guarantee at 11.00 a.m., on 12 th; October, 2012, even

according to the petitioner, MOU was already entered into on 11 th October,

2012 itself between DCHL and second respondent. In this respect reference

to the pleadings filed by the BCCI in Civil Application in the appeal would be

hvn

ARBPL-1352.12

relevant. In Para 5 of the Civil Application dated 13 th October, 2012 in

Arbitration Appeal, it is averred by the BCCI that at around 11.00 a.m., on

12th October, 2012 this court expressly refused DCHL's request for further

extension of time to furnish bank guarantee which request has been made

on the ground that negotiations for the sale of Hyderabad Franchise were

in progress. DCHL has filed affidavit in reply to this Civil Application on 16 th

October, 2012. These averments made in Para 5 of the Civil Application are

not denied by the petitioner in the affidavit in reply. In any event on the

date of making of the application for extension of time to furnish bank

guarantee at 11.00 a.m., on 12th October, 2012, MOU which is now being

relied upon by DCHL was already in place. Inspite of the said fact, this

court had refused to extend time for furnishing the bank guarantee. In

my view thus there is no change in the circumstances which warrants

exercise of the powers of this court under section 9 in this application.

14. Even otherwise, perusal of the MOU entered into between DCHL and

the second respondent indicates that the said transaction is made subject to

execution and delivery of satisfactory definitive agreements containing

various conditions. It is subject to consent of Lenders, BCCI, High Court,

Bombay and such other approvals as may be required by the seller from any

other authority. Clause 3 provides for various conditions precedents required

to be complied with before any final agreement can be arrived at. It is

stated in clause 3(c) that the seller shall settle in full all the liabilities of the

Franchise upto the closing date which shall be the date not later than 31 st

hvn

ARBPL-1352.12

March, 2013 or a mutually extendable date. The financial obligation recorded

in the said MOU indicates that cash pay out of INR 350 Crores payable by

the purchaser i.e. respondent no. 2 in 10 years in equal installments

starting from 30th day of December of calender year and has to be not latter

than 30 December, 2013.

15. In my view, while exercising power under section 9 of the Act, this

court can not supervise compliance of any conditions agreed upon by

DCHL and second respondent. Various permissions, consents, approvals,

no objections are required to be obtained by DCHL from its lenders,

shareholders, BCCI and the High Court of Bombay, and other authority for

consummating the sale of the Franchise to the purchaser free of any lien,

charge and encumbrance and for execution of the Definitive Agreements and

other documents. It is not possible for this court to direct any of these

authorities to grant its consent, approval or no objection in favour of the

DCHL proposing to auction its team to the second respondent. In my prima

facie view, if reliefs as claimed by the petitioner are granted, this court will

have to first set aside the termination order dated 14 th September, 2012 and

then grant specific performance of the MOU entered into between DCHL

and second respondent and then to direct BCCI to accept such assignment.

In my view such recourse is not permissible under section 9 of the

Arbitration Act, 1996.

16. In my view, no case is made out for ad interim relief. The respondents

hvn

ARBPL-1352.12

are directed to file affidavit in reply on or before 1 st November, 2012.

Rejoinder, if any to be filed on or before 20 th November, 2012. The matter

tobe placed on board for final hearing on 29 th November, 2012. It is made

clear that this court has not expressed any views on the on the validity or

legality of the termination order.

(R.D. DHANUKA, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter