Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Board Of Control For Cricket In ... vs Mr. S.U. Kamdar
2012 Latest Caselaw 206 Bom

Citation : 2012 Latest Caselaw 206 Bom
Judgement Date : 18 October, 2012

Bombay High Court
Board Of Control For Cricket In ... vs Mr. S.U. Kamdar on 18 October, 2012
Bench: R.D. Dhanuka
hvn
                                                  1
                                                                                          ARA46.12



                  IN THE HIGH COURT OF JUDICATURE AT BOMBAY




                                                                                       
                              CIVIL APPELLATE JURISDICTION




                                                               
                           ARBITRATION APPEAL NO. 46 OF 2012

      1. Board of Control for Cricket in India,
      a society registered under the Tamil Nadu Societies




                                                              
      Registration Act, 1975 having its registered office at M.A.
      Chidambaram Stadium, 5, Victoria Hostel Road,
      Chepauk, Chennai 600 005 and its head office at
      Cricket Centre, Wankhede Stadium,
      "D" Road, Churchgate, Mumbai 400 020                     ...              Appellant




                                                     
                                    ig         Versus

      Deccan Chronicle Holdings Limited having
      its registered office at 36, Sarojini Devi Road,
                                  
      Secunderabad 500 003                                           ...        Petitioner

      Mr. T.N. Subramanian, Sr. Counsel along with Mr. P.R. Raman, Mrs. Viraj Maniar,
      Mrs. Akhila Premkumar, Mrs. Misab Daba, Mr. Nikhil Karnawat i/by M/s. Maniar
             

      Srivastava Associates for the applicant/appellant.
          



      Mr. S.U. Kamdar, Sr. counsel along with Mr. Zal Andhyarujina along with Mr.
      Arcot Chandrashekar i/by M/s. Dave & Girish & Co. for respondent.

                                            CORAM : R.D. DHANUKA, J.

DATE : 18TH OCTOBER, 2012.

ORAL JUDGMENT :

1. This appeal is filed under section 37 of the Arbitration & Conciliation Act,

1996 (hereinafter referred to as "Act") challenging the order dated 12th October, 2012

passed by the arbitral tribunal under section 17 of the Act continuing status quo order

passed by this court. Some of the relevant facts are :

2. On 10th April, 2008 the franchise agreement was entered into between the

parties whereby the respondent was granted a right to own and operate a team in the

hvn

ARA46.12

league subject to the terms and conditions set out therein. On 14 th September, 2012

the appellant terminated the said Franchise agreement. The respondent filed

Arbitration Petition (L) No. 1238 of 2012 in this court under section 9 of the Act for

interim measures. After hearing both the parties, this court passed an order on 1 st

October, 2012 disposing off the said Arbitration Petition (L) No. 1238 of 2012. The

said order was a conditional order granting stay of termination on respondent

complying with various conditions including the condition to submit bank guarantee

of Rs. 100 Crores of a nationalized Bank on or before 9 th October, 2012. Time to

submit bank guarantee was extended till 12th October, 2012.

3. On 12th October, 2012 at 11.00 a.m. the respondent applied for extension of

time to furnish bank guarantee. It is not in dispute that the said application made by

the respondent for extension of time to furnish the bank guarantee was declined by

this court. The arbitral tribunal issued a notice convening a meeting for issuing

directions on 12th October, 2012 at 5.00 p.m. It is not in dispute that the meeting

begun around 5.30 p.m. After directions were given by the arbitral tribunal the

respondent filed an application under section 17 of the Act for interim measures. The

respondent prayed that pending the hearing and final disposal of the arbitration

proceedings, the arbitral tribunal be pleased to stay the termination of the Franchise

agreement and maintain status quo as per order dated 1 st October 2012 passed by this

Court. By an order dated 12th October 2012, the arbitral tribunal after recording

submissions of both the parties, passed the following order :

"Status quo granted by the Hon'ble High Court and continued till to-day,

i.e. 12.10.2012 5.00 p.m. is ordered to continue. The application for

hvn

ARA46.12

interim relief will be heard by the Tribunal on 17.10.2012 at 11.30 a.m."

4. From the perusal of the order passed by the arbtiral tribunal, it is clear that the

prayer for continuation of status quo order prayed for by the respondent was

strongly objected by the appellant. The appellant pointed out that termination of

contract came into effect and grant of any status quo would virtually amount to grant

of mandatory relief. The arbitral tribunal however took a view that when the status

quo had been granted by this court and was operative till 5.00 p.m. of 12th October,

2012, it would be in the interest of justice if it was directed to be continued for some

time by giving an opportunity to the BCCI to file its response to the application

submitted by the respondent herein.

5. Being aggrieved by the said order dated 12th October, 2012, the appellant

filed this appeal under section 37 of the Act. In view of the extreme urgency the

matter was moved in Chambers on 13th October, 2012 when both the parties were

heard by this court. On 13th October, 2012 this court passed a detailed order granting

ad interim relief in terms of prayer clause (a) of the Civil Application and the

effect, implementation and operation of the impugned order dated 12 th October, 2012

passed by the arbitral tribunal came to be stayed. The respondents have not

challenged the said order dated 13th October, 2012 passed by this court granting ad

interim stay of the operation of the order order passed by the arbitral tribunal on 12 th

October, 2012.

6. The learned senior counsel Mr. T.N. Subramanian, appearing for the appellant,

hvn

ARA46.12

submits that the order passed by this court on 12th October, 2012 was a self

operative order. The termination was stayed till 5.00 p.m., of 12 th October, 2012 on a

condition that the respondent furnishes a bank guarantee of the nationalized bank in

the sum of Rs. 100 Crores on or before 5.00 pm. of 12 th October, 2012. Various

other conditions were directed to be complied with as per the said order passed by

this court on 1st October, 2012. It is submitted that on 12 th October, 2012 at 11.00

am., when the oral application came to be made by the respondents for continuation

of ad interim order passed by this court, it was declined by S.J. Kathawala,J. It is not

in dispute that such application was made and the same was rejected by this court. It

is submitted that the order passed by this court on 1 st October, 2012 was made

operative till the disposal of the arbitral proceedings provided the respondent

therein furnishes bank guarantee of Rs. 100 Crores of the nationalized bank on or

before 5.00 p.m., of 12th October, 2012. When the application under section 17

was moved before the arbtiral tribunal, admittedly the bank guarantee of the

nationalized bank in the sum of Rs. 100 Crore was not furnished. The order dated 1 st

October, 2012 passed by this court, being self operative, termination came into effect

at 5.00 p.m., of 12th October, 2012. The oral application for extension of time to

furnish bank guarantee was already rejected by this court at 11.00 a.m., on 12 th

October, 2012. The learned arbitrator therefore, could not have passed any orders

under section 17 of the Act when such application was already rejected by this court

under section 9 of the Act. The learned counsel further submitted that there was no

statement of claim filed by the respondent before the arbitral tribunal. Unless the

pleadings were filed before the arbitral tribunal claiming substantive relief, no

application under section 17 of the Act for interim measures could be entertained

hvn

ARA46.12

by the arbitral tribunal. It is submitted that in any event the application filed under

section 17 of the Act was not signed by the parties but was signed by the learned

counsel. It is submitted that the arbitral tribunal thus could not have entertained such

application which was not competent in the absence of the pleadings as well as

application not having been signed by the respondent. The learned counsel placed

reliance upon the judgment of the Supreme Court in the case of M.D. Army Welfare

Housing Organization Vs. Sumangal Services Pvt. Ltd. 1 in support of this

contention. It is submitted that the grant of status quo amounted to grant of

mandatory injunction. The relief which was rejected by this court has been granted

by the arbitral tribunal which is not permissible in law.

7. Mr. Kamdar, the learned senior counsel appearing for the respondent on the

other hand submits that filing of pleadings was not mandatory before entertaining

the application under section 17 of the Act. In any event, the application filed under

section 17 of the Act itself was a pleading and thus the arbitral tribunal was

justified in passing the order of status quo. In so far as application not having been

signed by the parties is concerned, it is submitted that the said application was signed

by the counsel under the authority of the clients and he had undertaken to replace

the same by another application duly signed by the respondent.

8. is submitted by Mr. Kamdar that once this court became functious officio on

rejecting the application of the respondent under section 9 of the Act at 5.00 p.m., of

12th October, 2012, the respondent was justified in making the application under

1 2004 (9) SCC 619

hvn

ARA46.12

section 17 of the Act before the Arbitral Tribunal. It is submitted that the powers of

the arbitral tribunal are independent and in addition to the powers of this court

under section 9 of the Act. It is submitted that the learned arbitral tribunal is ceased

of the matter and the matter has been directed to be placed for further hearing on 17 th

October, 2012, thus this court should not interfere with the status quo order passed by

the arbitral tribunal and the ad interim order passed by this court be vacated.

9. I have heard the learned counsel and have considered the rival submissions.

10. The records of this proceedings indicate that the order dated 1 st October, 2012

passed by this court disposing off the application under section 9 of the Act filed by

the respondent, is self operative. This court passed protecting order staying the

termination of the contract on various conditions including the condition that the

respondent furnishes bank guarantee of Rs. 100 Crores of a nationalized bank in this

court on or before 5.00 p.m., of 12th October, 2012. It is not in dispute that till 5.00

p.m., of 12th October, 2012 no such bank guarantee came to be furnished. It is also

not in dispute that at 11.00 a.m., on 12 th October, 2012 an oral application came to

be made by the respondent for extension of time for furnishing the bank guarantee

which was declined by this court. The arbitral tribunal had scheduled the arbitral

meeting at 5.00 p.m. on 12th October, 2012 for giving directions. The meeting

commenced at about 5.30 p.m. After directions were issued by the arbitral tribunal,

application under section 17 came to be filed by the respondent seeking interim

measures by applying status quo order. In view of the admitted fact that the bank

guarantee was not furnished by 5.00 p.m., of 12 th October, 2012 by the respondent,

hvn

ARA46.12

the termination order issued by the BCCI came into effect. The oral application for

extension of time to furnish bank guarantee was declined by this court. Once this

court has declined extension of time and the termination order having come into

effect, in my view the arbitral tribunal has acted beyond its jurisdiction to grant

status quo order. If the court had declined to grant the relief, the arbitral tribunal

cannot grant that relief. The powers of the arbitral tribunal are not superior to that of

the Court. The arbitral tribunal could not sit in appeal over the order passed by this

court. The perusal of the order passed by this court on 1 st October, 2012 indicates

that

no liberty was granted by this court to the respondent to make any such

application under section 17 of the Act before the arbitral tribunal for continuation of

the status quo. In absence of any such liberty, such application made by the

respondent under section 17 for continuation of status quo itself was not

maintainable.

11. I am not inclined to accept the submissions made by the learned senior

counsel Mr. Kamdar that at 5.00 p.m., of 12 th October, 2012 this court having become

functious officio, powers of the arbitral tribunal under section 17 of the Act could

be invoked independently. This is not a case where section 17 application was made

without there being any order of this court under section 9 of the Act. There may

be a situation where an application under section 9 is made before this court and

party have applied for liberty to treat the said application as an application under

section 17 of the Act and to pursue the same before the arbitral tribunal. If any leave

is granted by this court while permitting parties to apply under section 17 of the Act,

such powers can be exercised by the arbitral tribunal under section 17 of the Act for

hvn

ARA46.12

continuation, modification or varying the order. In my view, once application for

extension of time was rejected by this court and termination order had came into

effect, application under section 17 made by the respondent before the arbitral

tribunal for status quo was incompetent and not maintainable. The perusal of the

order passed by the arbitral tribunal indicates that the arbitral tribunal has exercised

appellate powers over the order passed by this Court which arbitral tribunal does

not have. For the reasons recorded aforesaid, I need not decide the issue that

arbitral tribunal could not have passed status quo order as there were no pleadings

filed before arbitral tribunal.

12. I am therefore, of the view that the learned arbitrator has acted without

jurisdiction and thus the impugned order passed by the arbitral tribunal on 12th

October, 2012 is quashed and set aside. The appeal is allowed. There shall be no

order as to costs.

(R.D. DHANUKA, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter