Citation : 2012 Latest Caselaw 177 Bom
Judgement Date : 12 October, 2012
1 ARBPL1164.12.odt
hvn
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
ARBITRATION PETITION (L) NO. 1164 OF 2012
Spice Digital Ltd.
A Company registered under the Companies Act,
1956 having its registered office at C-5, Sainik
Farms, New Delhi 110 062 and Corporate Office
at S. Global Knowledge Park, 19A and 19B
Sector 125, Noida 201301, U.P. ... Appellant
Versus
Vistaas Digital Media Pvt. Ltd.,
a company registered under the Companies Act,
1956, having its registered office at 415, Palm
Spring Road, Link Road, Malad (West),
Mumbai 400 064 ... Respondent
Mr. D.D. Madon, Sr. Advocate alongwith Sanaya Dadachanji alongwith Mr. Amit
Chavan along with Tanvi Dudeja and Ujwal Trivedi i/by M/s. Manilal Kher
Ambalal & Co. for the appellant.
Mr. Pradip Sancheti, Sr. Advocate alongwith Mr. Nirmay Dave along with Mr.
Mayur Agarwal i/by M/s. Bilawala & Co. for respondent.
CORAM : R.D. DHANUKA,J.
RESERVED ON : 26TH SEPTEMBER, 2012
PRONOUNCED ON : 12TH OCTOBER, 2012
JUDGMENT :
1. By this appeal filed under Section 37(2)(b) of Arbitration & Conciliation
Act, 1996 (for short Arbitration Act, 1996) though lodged as petition, the appellant
(original claimant/applicant before the arbitral tribunal) seeks to challenge the
order dated 16th August, 2012 passed by the learned arbitrator rejecting the
application for interim relief sought by the appellant under section 17 of the
Arbitration Act, 1996.
2 ARBPL1164.12.odt
Some of the relevant facts which emerge from the pleadings and
documents filed by both the parties are :
2. The company carries on business of telecom value added services. The
respondent is carrying on business of telecom content aggregation. It is the case
of the appellant that the respondent approached the appellant in the month of
September, 2009 with a proposal for providing "Live Aarti" feed from Shree
Shirdi Saibaba Shrine, Shree Siddhivinayak Temple, Mumbai and Shree
Kashivishwanath Temple, Varanasi and certain other shrines and sought the
appellant's support and assistance in developing the market for the said service.
The appellant accordingly entered into an agreement with the respondent for a
period of three months.
3. On 11th June, 2010 the parties entered into the Content Licence
Agreement effective from 1st January, 2010 initially for a period of 18 months.
Clause 6.2 of the said agreement provides that there shall be a lock-in period of
18 months for licensor from the effective date i.e. 1 st January, 2010. Clause 1.6
provided that Manokamana, a unique service developed by Licensee, which
will enable the End User to record his/her "Manokamna (wish)" (the
"Manokamna Feed") on Licensee's platform, which shall be played inside the
Temple Premises at "Shree Shirdi Saibaba, at Nashik through licensor respondent.
Scope of agreement was provided in clause 2 of the said agreement. The appellant
was granted exclusive licence and right to provide content and its related services
specified in Annexure A to the agreement, the rights to use the Content with
3 ARBPL1164.12.odt
mobile and/or landline devices of the End User. The respondent also agreed to
provide its expert services to the appellant for the Manokamna services as per the
instructions of the licensee for the consideration stated therein. Clause 12.1.(a)
and (b) provided that :
"12. TERMINATION :
12.1 Subject to clause 6.2, this agreement or any part thereof may be
terminated;
(a) By either party, upon giving at least thirty (30) days prior written
notice to the other without assigning any reason thereof; however both
the parties shall continue performing their respective obligations during
the notice period.
(b) Immediately, upon written notice by either party, if the other
breaches a performance, representation, warranty or material obligation
of this Agreement and fails to cure the breach within fourteen (14) days
from the receipt of a written request to cure from the non-breaching
Party; or ......"
Clause 12(2)(a) to (f) reads as under :
"12.2 Consequences of termination :
Withstanding any other rights and remedies provided elsewhere in the
Agreement, on termination of this Agreement :
(a) Neither party will represent the other Party in any of its dealings.
(b) Neither Party shall intentionally or otherwise commit any act(s)
4 ARBPL1164.12.odt
as would keep a third party to believe that the other Party is still
associated with the former party in terms of this Agreement.
(c ) Each Party shall immediately stop using the other Party's name,
trade, mark, intellectual property, etc. in any audio or visual form for
any activity whatsoever and return/destroy as directed by the other
Party, all intellectual property; information in relation to such
intellectual property of the other party in its possession and also the live
audio feed.
(d) Neither Party will be entitled to claim any amount of loss or
compensation for termination of Agreement.
(e) Each Party must, at the requisition of the other Party, either; (I)
return to the other Party the other Party's Confidential Information, or
(ii) destroy or delete the other Party's Confidential Information and
certify to the other Party in writing that it has done so.
(f) The expiry or termination of this Agreement for any reason shall
not affect any rights and/or obligations :
(i) accrued before the date of termination or expiry; or
(ii) expressed or intended to continue in force after and despite
expiry or termination."
Clause 14.6 of the agreement and 14.7 which provides for
Exclusivity and waiver respectively are as under :
"14.6 Exclusivity : it is hereby agreed and clarified that with effect
5 ARBPL1164.12.odt
from 16th June, 2010, the Agreement shall be on exclusive basis with
respect to the Content and its related services provided by the Licensor
to the Licensee and the Licensor also agrees not to enter into similar
agreement for the purpose as enumerated herein with any third party.
However, Licensee shall be entitled to enter into similar agreement
with any third party for the purpose as enumerated herein.
14.7 Waiver : No waiver of any breach of any provision of this
agreement constitutes a waiver of any prior, concurrent or subsequent
breach of the same or any other provisions, and will not be effective
unless made in writing and signed by an authorized representative of
the waiving Party."
Clause 14.11 of the agreement provides for arbitration.
4. On 1st June, 2011 both the parties entered into amendment agreement to
the principal agreement dated 11th June, 2010. Clause 2.1 of the said amended
agreement provides that the term of the principal agreement as defined in clause
6 of the principal agreement was extended for the period of four years from
1.7.2011 to 30th June, 2012 unless terminated earlier in accordance with the
provisions of the principal agreement. Clause 6.2 of the principal agreement is
amended and reconstituted by clause 2.2.1 of the amended agreement which reads
as under :
"2.2 Amendment :
2.2.1 Sub clause 6.2 of the Principal Agreement, be and is hereby
amended and substituted by the following new sub clause 6.2, as
6 ARBPL1164.12.odt
enumerated below :
"There shall be a lock-in period of 24 months for the Principal
Agreement for the Licensor from 1st July, 2011 to 30th June, 2013.
However, if the Principal agreement is terminated before the above
lock-in period by Licensor, then the Licensee shall have undisputed
right to withhold the payment of the licensee fee (as specified in
Annexure "B" of this Principal Agreement), if any due at the time of
such termination, along with the right to approach the Court of law for
appropriate remedies that the Licensee may be entitled to under the
law:. However, this sub clause shall not be applicable in the event there
is a material breach committed by the Licensee and in such an event the
Licensor shall have the right to terminate the Principal Agreement in
accordance with the provisions contained therein."
5. In Annexure A to the said amended agreement, the content listing and
delivery mode was provided and names of various religious places for which
respondent possess legal right is mentioned. It is agreed by the respondent that
during the term of the principal agreement, content from the three
temples/shrines namely (I) Shree Shirdi Saibaba, Shirdi, Dist. Nashik, (ii) Shree
Kashivishwanath Temple, Varanasi and (iii) Takht Shree Harmandir Sahib
Gurudwara, Patna shall be provided at all time without failure. However, for the
other temples/shrines as referred in annexure A, the respondent shall ensure to
get content replaced by any other new temple/shrine with prior consent from the
7 ARBPL1164.12.odt
appellant in case the same are not available due to any reason, thereby,
maintaining at all times the count of temples/shrines. Annexure B of the
principal agreement which provides for commercial terms, amended by clause
2.2.6 providing for consideration payable by the appellant to the respondent. It
was provided that consideration payable by the appellant to the respondent for the
period till 31st March, 2011 shall be payable based on MIS report for the content
shared by Licensee, which shall be paid by Licensee by 30 th June, 2011 subject to
receipt of the invoice and for the period from 1st April, 2011 to 30th June, 2011,
shall be payable based on the MIS report for the content shared by licensee by 15 th
August, 2011, which shall be paid by 15th September, 2011 subject to receipt of the
invoice. It is agreed that during the period from 1st July, 2011 to 30th June, 2012,
the appellant shall submit to the respondent reconciled MIS report for the content
within 45 days from the end of each quarter and the appellant shall pay the
respondent the license fee over and above the minimum guaranteed amount as
mentioned in the agreement within 10 days of such reconciliation, subject to
receipt of the invoice from the respondents. Similarly it was agreed that during
the period from 1st July, 2011 to 30th June, 2012, the appellant shall submit to the
respondent reconciled MIS report for the content within 45 days from the end of
each quarter and shall pay licence fees over and above minimum guaranteed
amount within 10 days of such reconciliation subject to receipt of invoice from
the licensor. In so far as Manokamna services are concerned it was agreed that
the appellant shall pay the respondent a fixed amount of Rs.3,50,000/- per month
or 45% of the gross earning from Manokamna services whichever was higher.
8 ARBPL1164.12.odt
Clause L of Annexure B provides that the respondent shall be entitled to verify
and examine all past and future MIS reports shared by the appellant in terms of
the principal agreement and in case of any discrepancy of more than 5%, the
appellant shall pay respondent the amount payable for such discrepancy on
demand by the respondent within seven days of raising of such demand. Clause
(M) provided that all amounts payable for present and future periods during the
term shall be paid as stipulated. It shall be considered as a material breach and
licensor shall be entitled to terminate the Principal agreement notwithstanding the
lock-in period, in accordance with the provisions of the principal agreement.
Clause (O) provided that no minimum guarantee amount shall be payable by the
licensee to the licensor if the said period for which the content is not made
available by the lincesor in cases of three temples namely Shree Shirdi
Saibaba, Nashik, Shreee Kashivishwanath Temple, Varanasi and Takht Shri
Harmindir Sahib Gurudwara, Patna for a period continuously exceeds 15 days
during the term. In case of temple Shree Kashivishwanath, it is provided that if
the content was not made available to the licensee continuously for any period
exceeding 15 days during the term, then only 85% of the minimum guarantee
amount shall be payable by the Licensee to the Licensor only for such period for
which the content is not made available.
6. Clause 3.1 provided that the amendment agreement shall form integral
part of the principal agreement and shall be read with the principal agreement.
9 ARBPL1164.12.odt
7. It is the case of the appellant that since 1 st December, 2011, the respondent
stopped providing live aarti feed from Kashivishwanath, Varanasi and only
provided the content from 12 temples/shrines. It is the case of the appellant that
respondent in the month of January, 2012 made a request to the appellant to
examine records of the appellant and to verify the MIS reports and field
inspection of all such documents was given to the respondent on 19 th January,
2012 and 20th January, 2012. Various correspondence was exchanged in this
regard between the parties. In the month of March, 2012, respondents offered to
the appellant as replacement ig for Kashi Vishwanath, live aarti feed from
Gurudwara Banglasahib. It is the case of the appellant that the live aarti from Shri
Bangla Saheb Gurudwara had already been borrowed by the appellant from
another service provider and as such was not interested in that content from the
respondent. It is the case of the appellant that on 10 th April, 2012, the respondent
vide email had given ultimatum to the appellant to (i) purchase 50% equity in
the Respondent (ii) increase the minimum guaranteed fees or (iii) cancel the
contract.
8. On 18th June, 2012 the respondent issued termination notice to the
appellant alleging material breaches and gave cure period of 14 days which
expired on 1st July, 2012.
9. On 28th June, 2012, the appellant gave reply to the notice of termination
denying any breach of the content licence and called upon the respondent to
10 ARBPL1164.12.odt
withdraw the notice of termination and to continue to comply with their
obligations under the content licence agreement and maintain 13 shrines at all
times for live audio streaming by the appellant. By the said letter, the appellant
invoked arbitration agreement and nominated Mr. Justice Bhimrao Naik, a former
Judge of this court as an Arbitrator and requested the respondent to concur with
his name.
10. The appellant thereafter filed a petition under section 9 of the Arbitration
Act, 1996 in this court (Arbitration Petition (L) No. 826 of 2012). On 29 th June,
2012 S.J. Kathawala,J. directed that the matter shall stand over to 16 th July, 2012
and in the meantime, the respondent shall not act on the basis of termination
notice dated 18th June, 2012. By an order dated 17 th July, 2012 passed by S.J.
Kathawala,J. the Arbitration Petition (L) No. 826 of 2012 as well as Arbitration
Application (L) No. 917 of 2012) filed under section 11 of the Act, came to be
disposed of by consent of both the parties. The disputes between the parties were
referred to sole arbitration of Mr. Justice F.I. Rebello (retired). It was directed that
the order passed by this court on 29 th June, 2012 shall continue for the period of
four weeks from the date of the said order dated 17 th July, 2012 and that the
learned Arbitrator shall decide the application under section 17 of the Act without
being influenced by ad interim order dated 29 th June, 2012 which was passed
without going into the merits of the case.
11. By an order dated 16th August, 2012 the learned Arbitrator dismissed the
11 ARBPL1164.12.odt
application under section 17 of the Arbitration Act, 1996 filed by the appellant
herein.
12. Mr. D.D. Madon, the learned senior counsel appearing for the appellant
submits as under :
(i) In the month of December, 2011, the respondent stopped giving feed to the
appellant for Kashi Vishwanath temple unilaterally. By letter dated 16 th April,
2012 from the respondent to the appellant, the respondent had given two options
to the appellant offering (i) 50% equity participation so as to revive business
understanding, demanded revised rates and if those conditions were not agreeable
to the appellant, asked to close the relations. It is submitted that this letter shows
that there was no dispute and or grievance in respect of any part of obligation on
the part of the appellant till the date of the said letter. The appellant could not
agree to the demand for royalty made by the respondent by letter dated 13 th
March, 2012 for Banglasahib Gurudwara, Delhi as the Appellant had separate
agreement with third party in respect thereof and no feed was given by the
respondent to the appellant.
(ii) The respondent could terminate the contract under clause 12.1(a) by
giving atleast 30 days notice only after lock-in period from 1 st July, 2011 to 20th
June, 2012 was over. It is however, fairly stated that the contract could be
terminated under clause 12.1.(b) even during the lock-in period if there was any
material breach of the contract defined under clause (m) of the amended
12 ARBPL1164.12.odt
agreement and if the appellant failed to cure the material breach within fourteen
days from the receipt of written notice from the respondent to cure the same.
Clause 12.2 provides for the consequences of termination as produced earlier.
(iii) Clause 12.2.(d) of the contract provide that neither party will be entitled to
claim any amount of loss or compensation for termination of agreement. The
learned arbitrator gave a finding that by notice dated 18 th June, 2012 the
respondent had called upon the appellant to pay outstanding minimum guaranteed
amount for the month of May and June, 2012 which was paid by the appellant
by forwarding two cheques along with advocate's notice dated 28 th June, 2012
i.e. within 14 days, which cheques were encashed by the respondents, thus cured
the breach within the time prescribed. The finding is given that there can be no
material breach in so far as these amounts was concerned, considering the
definition of material breach. In respect of Manokamna services, though they
were discontinued from 1st December, 2012, no demand has been made by the
respondent for payment of any amount on account of discontinuance of such
services. In view of the finding of the learned arbitrator that there was no material
breach committed by the appellant during the lock in period, termination of
agreement by notice dated 18 th June, 2012 was illegal and contrary to clause 12.2
of the agreement which warranted interference by the learned arbitrator under
section 17 of the Arbitration Act, 1996. It is submitted that on the one hand, the
leaned arbitrator has held hat the agreement by its very nature is determinable,
considering section 49(1)(c) of the Specific Relief Act and specific performance
13 ARBPL1164.12.odt
thus cannot be granted and on the other hand relying upon clause 12(2)(d) had
observed that neither party will be entitled to claim any amount of loss or
compensation for termination of contract. It is submitted that the party can not be
deprived of either of these reliefs..
(iv) The learned arbitrator could not have considered letter sent by e-mail on
11th June, 2012 by Mr. Shehzad Azad, Head of Business Development and
Alliances to the respondent asking the respondent to let the appellant know if they
were not interested in working with the appellant any more which reads as under :
"What is this all rubbish going on?? and on top it I have come to know of various
representation by your people at operators, maligning Spice name which is totally
unacceptable and not in the spirit of the partnership.
Let me know you if you are not interested in working with Spice anymore,
I am pretty sure both of us can survive independently."
13. It is submitted that the said letter could not read in isolation. In any
event, it was personal opinion of said Mr. Shaizad Azad who was Head of the
Business Development and Alliances and not on the instruction of the appellant
to put an end to the contract. The finding of the learned arbitrator that the
applicant would not suffer any irreparable loss or injury if the injunction is not
granted, is based only on isolated e-mail dated 11 th June, 2012 and not on the
basis of any records produced by the respondent before the learned arbitrator. The
appellant had already entered into agreements with various customers and in the
14 ARBPL1164.12.odt
event of such illegal termination during the lock-in period, serious prejudice
would be caused to the appellant.
(v) It is submitted that since ad interim order came to be passed by this court
before the expiry of 14 days notice issued by the respondent for curing the alleged
defects, termination did not come into effect and thus the finding given by the
learned arbitrator that the contract having been terminated, no injunction can be
granted in view of section 41 (e) of the Specific Relief Act read with section
41(1)(c) and section 9 of the Arbitration Act, 1996 is contrary to law and facts.
The learned counsel submitted that though the appellant has pleaded before the
arbitral tribunal that the contract was terminated, however, it is apparent from
the order passed by this court on 29 th June, 2012 that termination did not come
into effect and thus in the interest of justice, both the parties be directed to
perform their respective obligations under the agreement.
(vi) It is submitted that the provisions under the agreement provides that the
respondent shall not enter into any agreement with anybody-else during the lock-
in period and thus shows that the contract was of special value and thus grant of
specific performance is the only proper remedy available to the appellant and
compensation in terms of money is not adequate.
(vii) The learned counsel placed reliance on the judgment of Delhi High Court
in the case of Satyanarayan Sharma1, the judgment of Madhya Pradesh High
Court in Jabalpur Cable Network Pvt. Ltd. Vs. E.S.P.N. Software India Pvt.
1 CS (OS) No. 1339 of 2008 delivered on 6th April, 2009
15 ARBPL1164.12.odt
Ltd. and Ors.2 . Reliance is placed on the judgment in the case of Satya Narain
Sharma (supra) in support of the proposition that if the contract prohibits
termination within the lock-in period, contract could not be terminated before
expiry of the lock-in period. Reliance placed on the judgment in the case of
Jabalpur Cable (supra) is in support of the plea that the obligation to provide
content and its related services was in the nature of contract for supplying goods
which is not easily obtainable in the market and thus specific performance of this
contract is enforceable under section 10 of the Specific Relief Act.
14.
On the other hand, Mr. Sancheti, the learned senior counsel on behalf of
the respondent submits as under :
(i) the learned Arbitrator has considered in detail the provisions of the
agreement and has interpreted such provisions and has come to the conclusion
that the contract was determinable and considering section 14(1)(c) of the
Specific Relief Act, specific performance of such contract could not be granted. It
is submitted that if specific performance could not be granted in terms of section
41(e) of the Specific Relief Act, no injunction could be granted. It is submitted
that the clause 14.6(a) of the amended agreement read with clause 14.6 A of the
principal agreement provided that in case of breach of the exclusivity provisions
by the licensor, then the licensee shall have undisputed right to withhold the
payment of licence fee (as specified in annexure B of the Principal agreement), if
any due at the time of such breach along with right to approach the court of law
for appropriate remedies that the licensee may be entitled to in law. It is submitted
2 AIR 1999 Madhya Pradesh 271
16 ARBPL1164.12.odt
that there is no finding given by the learned arbitrator that in no circumstances,
the appellant would be entitled to claim damages even if ultimately the
termination is found contrary to the provisions of the agreement. The
apprehension of the appellant therefore, that it would be without any remedy is
not proper. The appellant having pleaded in its application under section 17
before the learned arbitrator that the agreement was terminated by the respondent,
can not be permitted to argue across the bar contrary to such pleadings. It is
submitted that even if there is no termination of the contract, once it is found that
the contract is determinable, then considering section 14(1)(c) of the Specific
Relief Act no specific performance can be granted and thus no interim
injunction can be granted in such situation. If the appellant succeeds, he would be
entitled to claim damages in accordance with provisions in the contract and law.
(ii) It is submitted that the agreement entered into between the parties as well
as correspondence exchanged clearly indicate that the agreement was for
providing services by the respondent to the appellant and the same was not for
supplying the goods. No plea that contract was for supply of goods was raised by
the appellant before the learned arbitrator or in this court in the earlier
proceedings. The appellant's own case is that in respect of one of the Gurudwara,
the appellant had entered into separate contract with third party. The learned
counsel distinguished the judgment in the case of Jabalpur (supra) relied upon
by the appellants on this issue.
17 ARBPL1164.12.odt
(iii) It is submitted that reliance placed by the appellant on the judgment in
the case of Satyanarayan (supra) is also totally misplaced. The learned senior
counsel placed reliance on the judgment of the Supreme Court in the case of
Indian Oil Corporation Limited Vs.Amritsar Gas Service3, , in the case of
Her Highness Maharani Shantidevi P. Gaikawad 4, Cox and Kings India
Limited Vs. Indian Railways Catering Tourism Corporation Limited and
another5 and in the case of Rajsthan Breweries Limited Vs. Stroh Brewery
Company6 .
(iv)
It is submitted that considering the nature of the contract entered into
between the parties, it is clear that it is determinable. The learned arbitrator has
given a prima facie finding holding that the contract is in the nature of
determinable. It is submitted that the contract cannot be specifically enforced if
the performance of which involves continuous duty and supervision of the court.
It is submitted that in addition to the minimum guarantee amount, the appellants
were also liable to pay to the respondent on the basis of the amount to be
calculated based on MIS reports. It is submitted that the court cannot supervise as
to whether the appellant has submitted all MIS report from time to time and if
so about the accuracy thereof. The court also cannot supervise whether the
payment on the basis of such MIS reports are made by the appellant to the
3(1991) 1 SCC 533
4 (2001) 5 SCC 101
5 (2012) 7 SCC 587
6 AIR 2000 Delhi 450
18 ARBPL1164.12.odt
respondent or not. At the same time the Court also cannot supervise whether the
respondent has complied with its part of obligation under the contract. It is
submitted that the learned arbitrator has given prima facie finding of fact and this
court shall not re-appreciate the finding of fact under section 37 of the Arbitration
Act, 1996.
(v) The learned counsel placed reliance upon various breaches alleged by the
respondent against the appellant as summarized by the learned arbitrator in Para
30 of the order and thereafter prima facie finding thereon recorded in para 32 and
36 of the order which are extracted as under :
"30. We may now consider the notice served by the Respondent on
the Applicant dated 18.06.2012. By that notice, the Respondent has
pleaded various breaches as on the date of the notice. We may
summarize briefly the said breaches as raised by the Respondent :
(a) That the Applicant was under a specific contractual obligation to
inform them through e-mail, written communication prior to any
Content been made available like any telecom operator as per clause
12.6 of the Principal Agreement. The Respondent has contended that
the Applicant failed to inform seemingly with the intention to conceal
relevant information from them to make wrongful gains and to cause
loss to the Respondent.
(b) The Applicant, it is set out by e-mail dated 5.12.2011, was called
upon to provide the status of 'live aartis" on operators, including MTS,
19 ARBPL1164.12.odt
Aircel, Uninor and Loop". The Respondent in their reply, admitted
being "live" with the operators in question and undertook to share
reports with the Respondent upon billing the operators. That the
Applicant had failed to inform as of the date of the notice about the
Content;
(c ) It is then contended that as "late as 8.12.2011 till date, the
Applicant had not shared the MIS reports of the Content provided to
the operators and as a result had dishonestly appropriated the revenue
and denied the due share to the Applicant.
(d) That the Applicant had illegally exploited the content in the
manner not warranted by the terms of the Agreement and had
committed material breach of the said Agreement. The Applicant was
called upon the send written authentication from the respective telecom
operators stating the dates on which the Content was made live by them
on their platforms within 14 days from the receipt of the letter. Further,
the Applicant was called upon to send the complete MIS reports for the
Respondent's Content for these additional telecom operators.
(e) That the Applicant had failed to pay the monthly minimum
guaranteed amount for the months of May 2012 and June 2012 and
also failed to make the payment of the minimum guaranteed amount
within the time frame stipulated in the Agreement. Also, the Applicant
without prior intimation and for no conceivable reason, ceased to
continue the "Manokamana Service" from December, 2011 onwards,
20 ARBPL1164.12.odt
even though the same was provided in the Principal Agreement.
(f) The Applicant had failed to provide the reconciled MIS reports
of revenue for the Contents within 45 days from the end of each quarter
and disburse the amount as determined after perusal of the reconciled
MIS report over and above the minimum guarantee amount within 10
days of such reconciliation. The applicant, it was set out had failed to
provide the aforesaid reconciled MIS report.
(g) That the Applicant had received the feed of "Shri Bangla Saheb
Gurudwara, New Delhi".
ig The Applicant had admitted and
acknowledged offering the feed of the Respondent on their platform
and that took 60 days to reply to Content that they were not using the
feed for Bangla Saheb. The Applicant was also called upon to disclose
the name of the third party, who was providing the feed to the
Applicant which they were contending they were using.
(h) That the Applicant had failed to grant inspection and necessary
access to the details of the MIS reports for cross verification in respect
of the Content of Manokamana Services. The Applicant had also failed
to furnish the said information.
(i) That the Applicant had failed to provide the reconciled MIS reports
within 45 days from the end of each quarter and had not received the
MIS reports from April, 2011 from some of the telecom operators and
for the all telecom operators for the months of January, 2012, February,
2012 and March, 2012 thereby committing material breaches.
21 ARBPL1164.12.odt
32. The question for consideration is whether the breaches as
alleged subsist having not been cured, can only be answered (on the
evidence being led) at this stage on the material based on pleadings,
affidavits and documents. There is some material from the replies and
the correspondence exchanged between the parties that some breaches
subsist. Some of these it has been contended by the Applicant were
dependent on the operators furnishing the information. The question is
whether in an agreement of the nature entered into between the parties,
can there be specific performance? A prima facie finding has been
recorded that the contract by its very nature is determinable. Waiver of
breaches committed can only be in terms of clause 14.7 and not
otherwise. Considering clause 12.1(b), the Applicant could have cured
the breaches within 14 days of receipt of the notice. The issue would
still remain whether the breaches as set out in the notice had been cured
within the period of 14 days. In my opinion, even prima facie, it is not
possible to hold that there are no subsisting breaches. Further,
considering the Agreement is prima facie determinable, specific
performance cannot be granted and as such, the question of granting
temporary injunction would not arise.
36. For all the aforesaid reasons, viz. That the contract by its very
nature is determinable, that prima facie there are breaches, which are
not cured, interim relief by way of injunction cannot be granted. Even
in the alternative, if it can be said that the specific performance can be
22 ARBPL1164.12.odt
granted, nonetheless this is not a case where the Applicant have been
able to establish that irreparable injury and loss will be caused to them
if the injunction is not granted and/or balance of convenience is in
their favour. Accordingly, the application u/s. 17 of the Act is
dismissed."
(vi) It is submitted that in view of such prima facie findings of facts on
breaches, the learned arbitrator was justified in refusing to grant any
interim relief to the appellants and thus this court shall not interfere ig with
such findings of fact given by the learned arbitrator. The validity of
termination of the contract and consequences thereof will be finally decided
by the learned arbitrator. If any interim injunction of termination is
granted, it would amount to re-writing the contract between the parties by
the Court, which is not permissible in law.
15. It is not in dispute that even during the lock in period, the respondent can
terminate the contract if there was material breach of contract. Whether the
contract was rightly terminated or not is the issue which is pending before the
arbitral tribunal and would be decided at the time hearing of the claims made by
the Appellant before the arbitral tribunal. The question that arises for
consideration of this court is that whether inteirm mesures can be grnted in a
contract which is determinable. Section 14(1)(a) to (d) of the Specific Relief Act,
1963 are extracted as under :
"Section 14 - Contracts not specifically enforceable
23 ARBPL1164.12.odt
(1) The following contracts cannot be specifically enforced, namely:--
(a) a contract for the non-performance of which compensation is an
adequate relief;
(b) a contract which runs into such minute or numerous details or which is so dependent on the personal qualifications or volition of the parties, or otherwise from its nature is such, that the court cannot enforce specific performance of its material terms;
(c ) a contract which is in its nature determinable;
(d) a contract the performance of which involves the performance of a continuous duty which the Court cannot supervise."
16. The arbitral tribunal in the impugned order after referring to clause 6.2 as
amended and clause 12.1 of the agreement has recorded prima facie finding that
the agreement by its very nature is determinable even during the lock in period. It
is held that in case other than for material breach, the licensor if it invokes
clause 12 and terminated the agreement, the the licensee is entitled to certain
rights which include withholding any license fees that may be due and payable
and also moving the competent court for whatever reliefs the Licensee would be
entitled. In Para 36 of the impugned order the arbitral tribunal has recorded a
finding that the contract by its nature is determinable and interim relief by way of
injunction cannot be granted. In Para 29 of the impugned order, it is held that if
the agreement by its very nature is determinable within the meaning of section
14(1)(c) of the Specific Relief Act, specific performance cannot be granted. If
specific relief cannot be granted, then in terms of section 41(e) of the Specific
Relief Act no injunction can be granted. It is held that if the licencee is not entitled
to final relief of permanent injunction, then in that event no interim relief by way
of injunction can be granted.
24 ARBPL1164.12.odt
17. In the case of Indian Oil Limited (supra), the Supreme Court was
considering the fact that if the contract by its nature is determinable, granting
relief of restoration of distributorship even on finding that the breach was
committed by Indian Oil Limited was contrary to the mandate in section 14(1)
of the Specific Relief Act and thus there was error of law apparent on the face
of the award which cannot be sustained. The relevant portion of the judgment of
the Supreme Court in the case of Indian Oil Limited (supra) reads thus :
"12. The arbitrator recorded finding on Issue No.1 that termination of
distributorship by the appellant-Corporation was not validly made under clause 27. Thereafter, he proceeded to record the finding on
Issue No. 2 relating to grant of relief and held that the plaintiff- respondent no. 1 was entitled to compensation flowing from the breach of contract till the breach was remedied by restoration of
distributorship. Restoration of distributorship was granted in view of
the peculiar facts of the case on the basis of which it was treated to be an exceptional case for the reasons given. The reasons given state that the Distributorship Agreement was for an indefinite period till
terminated in accordance with the terms of the agreement and, therefore, the plaintiff-respondent 1 was entitled to continuance of the distributorship till it was terminated in accordance with the agreed
terms. The award further says as under :
"This award will, however, not fetter the right of the defendant corporation to terminate the distributorship of the plaintiff in accordance with the terms of the agreement dated April 1, 1976, if and when an occasion arises."
This finding read along with the reasons given in the award clearly accepts that the distributorship could be terminated in
25 ARBPL1164.12.odt
accordance wit the terms of the agreement dated April 1, 1976, which contains the aforesaid clauses 27 and 28. Having said so in the award
itself, it is obvious that the arbitrator held the distributorship to be revokable in accordance with clauses 27 and 28 of the agreement it is
in this sense that the award describes th Distributorship Agreement as one for an indefinite period, that is, till terminated in accordance with clauses 27 and 28. The finding in the award being that the
Distributorship agreement was revokable and the same being admittedly for rendering personal service, the relevant provisions of the Specific Relief Act were automatically attracted. Sub section (1) of
Section 14 of the Specific Relief Act specifies the contracts which cannot be specifically ig enforced, one of which is in its nature determinable. In the present case, it is not necessary to refer to the
other clauses of sub section (1) of section 14, which also may be attracted in the present case since clause (c) clearly applies on the finding read with reasons given in the award itself that the contract by
its nature is determinable. This being so granting the relief of restoration of the distributorship even on the finding that the breach
was committed by the appellant-Corporation is contrary to the mandate in section 14(1) of the Specific Relief Act and there is an error of law apparent on the face of the award which is stated to be
made according to 'the law governing such cases'. The grant of this relief in the award cannot, therefore, be sustained."
18. In the case of Rajasthan Breweries Limited (supra), the Delhi High Court
after following the judgment of the Supreme Court in the case of Indian Oil
Limited (supra), held that if ultimately it is found that the termination was bad in
law or contrary to the terms of the agreement between the parties, the remedy of
the party would be to seek compensation for wrongful termination but not a claim
26 ARBPL1164.12.odt
for specific performance of the agreements. Para 20 of the said judgment reads
thus :
"20. Even in the absence of specific clause authorising and enabling
either party to terminate the agreement in the event of happening of the events specified therein, from the very nature of the agreement, which is private commercial transaction, the same could be terminated even
without assigning any reason by serving a reasonable notice. At the most, in case ultimately it is found that termination was bad in law or contrary to the terms of the agreement or of any understanding
between the parties or for any other reason, the remedy of the appellants would be to seek compensation for wrongful termination but
not a claim for specific performance of the agreements and for that view of the matter learned Single Judge was justified in coming to the
conclusion that the appellant had sought for an injunction seeking to specifically enforce the agreement. Such an injunction is statutorily prohibited with respect of a contract, which is determinable in nature.
The application being under the provisions of Section 9(ii)(e) of the
Arbitration and Conciliation Act, relief was not granted in view of Section 14(i)(c) read with Section 41 of the Specific Relief Act. It was rightly held that other clauses of Section 9 of the Act shall not apply to
the contract, which is otherwise determinable in respect of which the prayer is made specifically to enforce the same."
19. In the case of Cox and Kings India Limited (supra), the Supreme
Court was considering the case of restoration of the leased agreement which was terminated by the party by applying for interim measures under section 9 of the Arbitration Act, 1996. The Appellant in the said case had also pleaded that he had invested large sum of money in the project and thus was entitled to mandatory order of injunction once the lease agreement had been terminated. The Supreme Court has dealt with these arguments in Para 25 and 26 of the said judgment which read thus :
27 ARBPL1164.12.odt
"25. It is evident from the submissions made on behalf of the respective parties that the arrangement between the Respondent No.1, IRCTC,
was with the Appellant Company and, although, it was the intention of the parties by virtue of the Joint Venture Agreement that the luxury
train, belonging to the Respondent No.1, was to be operated by the Joint Venture Company, at least for a minimum period of 15 years, what ultimately transpired was the termination of the Agreement by the
Respondent No.1 in favour of the Joint Venture Company. As pointed out by the Division Bench of the High Court, the Appellant was not entitled to question such termination as by itself it had no existence as
far as the running of the train was concerned and it was not a party to
the proceedings. In fact, what the Appellant has attempted to do in these proceedings is to either restore the Lease Agreement, which had
been terminated, or to create a fresh Agreement to enable the Appellant to operate the luxury train indefinitely, till a decision was arrived at in Section 9 Application.
26. It is no doubt true that the Appellant has invested large sums of money in the project, but that cannot entitle it to pray for and obtain a mandatory
order of injunction to operate the train once the lease agreement/arrangement had been terminated. We are also unable to accept Mr. Rohatgi's submission that the Joint Venture Agreement was akin to a
partnership. Such submission had been rightly rejected by the Division Bench. As rightly pointed out by the Division Bench of the High Court, the Appellant's remedy, if any, would lie in an action for damages against IRCTC
for breach of any of the terms and conditions of the Joint Venture Agreement and the Memorandum of Understanding."
20. In my view, the arbitral tribunal was right in its prima facie view that
clause 6.2 read with clause 12. 1 shows that the contract is determinable during
the lock in period. Section 14(1)(c) provides that the contract which in its nature
28 ARBPL1164.12.odt
is determinable, cannot be specifically enforced. The Judgments of the Supreme
Court in the case of Indian Oil Limited (supra), Delhi High Court and also the
judgment of the Supreme Court in the case of Cox and Kings are clearly
applicable to the facts of this case. In my view, the arbitral tribunal has interpreted
the terms of the contract and has recored prima facie finding that the contract is
determinable and thus no specific performance of such contract can be enforced
in view of section 14(1)(c). This interpretation of the arbitral tribunal is a possible
interpretation and thus no interference is warranted at this stage.
21.
In my view, the injunction sought by the Appellant under section 17 of the
Arbitration Act, 1996 for the contract which is determinable or is terminated
even according to the appellant, such injunction is statutorily prohibited. In my
view, at the interim stage, the arbitral tribunal while deciding application under
section 17 and the court deciding application under section 9 of the Arbitration
Act, 1996 cannot continue operation of such determinable contract or the same
having been terminated otherwise it would amount to re-writing the contract. In
my view the arbitral tribunal was thus right in refusing to grant injunction under
section 17 of the Arbitration Act, 1996. Even otherwise, the arbitral tribunal has
given a finding of fact after considering the facts, provisions of the agreement and
the provisions of Specific Relief Act and thus no interference is warranted by
this court with such finding of fact recorded by the arbitral tribunal at this stage.
22. I am not inclined to accept the argument of the learned senior counsel
appearing for the appellant that the contract was not terminated by the respondent
as ad interim stay was granted by this court before expiry of fourteen days notice
29 ARBPL1164.12.odt
period. The learned counsel appearing for the respondent is right in his submission
that the Appellant itself had pleaded while making an application for interim
measures under section 17 before the arbitral tribunal that the contract was
terminated by the respondent and thus cannot be permitted to change its stand
across the bar in the present proceedings. The entire order passed by the arbitral
tribunal was on the premise that the agreement was terminated by the respondent.
I am, therefore, not inclined to permit the appellant to contend that the contract
was not terminated.
23.
The learned counsel for the respondent submitted that the court or the
arbitral tribunal cannot grant relief of specific performance of the contract,
performance of which involves performance of the continuous duty which the
court cannot supervise in view of section 14(1)(d) of the Specific Relief Act,
1963. The learned counsel submits that the respondent had agreed to provide feed
to the appellant. One of the obligation of the appellant to make payment to the
respondent was based on the MIS report required to be submitted by the appellant
from time to time to the respondent. The arbtiral tribunal has recorded a finding
that the appellant had not submitted MIS reports on time. The arbtiral tribunal has
also recorded a finding that the payment was made by the appellant in the case of
one of the site after fourteen days. It is submitted that the arbitral tribunal cannot
supervise compliance of the obligation on the part of either party and more
particularly whether MIS reports were submitted by the appellant on time or not
and vice versa the payments were released by the appellant to the respondent
30 ARBPL1164.12.odt
based on such MIS reports. The learned counsel submits that in this situation, the
arbtiral tribunal cannot grant specific performance to the appellant in such type
of agreements which involves performance of continuous duty which the tribunal
cannot supervise. The learned counsel appearing for the appellant on the other
hand submits that even if there was delay at any point of time in submission of
MIS reports or any payment followed by submission of such reports to the
respondent, or if there was any delay in supplying the feed by the respondent to
the appellant, the parties can always approach the arbitral tribunal for
appropriate relief for seeking compliance thereof. It is submitted that thus in this
agreement, no continuous duty or supervision was required by the arbitral tribunal
and thus the agreement can be specifically enforced and thus interim relief was
warranted in this case.
24. The learned senior counsel also placed reliance on the judgment of
Madhya Pradesh High Court in the case of Jabalpur Cable Network Pvt. Ltd. in
support of his plea that the agreement between the parties was for supply of
goods. It is submitted that the feed agreed to be provided by the respondent to the
appellant was of the special value of interest of the appellant and was not easily
obtainable in the market and thus specific performance of the agreement was
enforceable under section 10 of the Specific Relief Act. The learned senior
counsel appearing for the respondent distinguished the judgment of the Madhya
Pradesh High Court in the case of Jabalpur Cable Network on the ground that no
such plea that the feed agreed to be provided by the respondent was of special
value or was not easily obtainable in the market has been raised in the pleadings
31 ARBPL1164.12.odt
before the arbitral tribunal. The learned counsel invited my attention to Page 17,
19, 20, 21 to 25 of the application filed under section 17 of the Arbitration Act
by the appellant to show that it was all through out pleaded by the appellant that
under the agreement respondent had agreed to provide services to the appellant.
In para 19 of the impugned order, the arbitral tribunal has negatived this
contention of the appellant that they were governed by section 10 of the Specific
Relief Act on the ground that there was no pleadings by the appellant in their
application in that regard.
25.
In my view, the arbitral tribunal has rightly rejected the contention of the
appellant that the feed agreed to be provided by the respondent to the appellant
was of special nature and was not easily obtainable in the market on the ground
that no such plea was raised by the appellant in an application under section 17.
In my view, the learned counsel appearing for the respondent was right in his
submission that it was the appellant's own case that in case of Bangalasaheb
Gurudwara, New Delhi site, the appellant had already entered into a contract with
third party to provide services.
26. The next submission of the learned senior counsel appearing for the
appellant is that the arbitral tribunal has rejected the application for interim
measure based on isolated letter sent by an officer of the appellant which
was his personal opinion and who was not instructed to write any such letter
on behalf of the appellant. The learned counsel appearing on behalf of the
32 ARBPL1164.12.odt
respondent on the other hand submitted that there were series of such letters
addressed by same person on behalf of the appellant which were not
disputed by the appellant. There is no such plea raised by the appellant that
the said e-mail letter considered by arbitral tribunal was without any
authority. In my opinion the letters addressed by the parties at pages 246,
254, 258, 266 and 276 of the compilation indicates prima-facie that there
were series of letters in the same direction and thus I am not inclined to
accept the submission of the appellant that interim relief was refused based
on an isolated letter or that the officer of the appellant was not authorized to
address such letter. It is not in dispute that the appellant has not disputed the
other letters addressed and signed by the same person on behalf of the
appellant.
27. The next submission of the appellant through its senior counsel is that
a party cannot be be without a remedy of claiming specific performance
and/or damage. It is submitted that the prima-facie findings of the arbitral
tribunal is that in view of the contract being determinable, the appellant
would not be able to get relief of specific performance and at the same time
has also held that in case of termination on the ground of material breach of
contract, the appellant was also not entitled to claim any damages. The
learned senior counsel appearing on behalf of the respondent on the other
hand pointed out that the apprehension of the appellant that it would not be
33 ARBPL1164.12.odt
entitled to get any relief of compensation even if contract is found illegally
terminated is incorrect. The learned senior counsel placed reliance on
Clause 6.2 as amended read with clause 12.1 of the agreement which
provides that licencee is entitle to certain rights which includes withholding
any licence if that may be due and payable and also moving the competent
court for what the relief the licencee would be entitled to. The arbitral
tribunal has considered this issue and has rejected the submission of the
appellant that the contract does not provide for compensation on
interpretation of clause 6.2 read with clause 12.1 in paragraphs 14 and 17 of
the impugned order. In my view, this interpretation of the arbitral tribunal
is a possible interpretation and no interference is warranted by this court in
this appeal against such possible interpretation of the arbitral tribunal.
28. The next submission of the appellant through the learned senior
counsel is that the prima-facie finding of the arbitral tribunal that the
appellant had committed breach and that there would be no irreparable loss
if reliefs as prayed for were not granted and that the balance of convenience
was not in favour of the appellant are contrary to the facts on record and
such finding are mutually inconsistent and contradictory. The learned senior
counsel appearing for the respondent on the other hand submitted that after
considering the pleadings and documents filed by both the parties, the
arbitral tribunal after summarizing the breach alleged by the respondent in
34 ARBPL1164.12.odt
para 30 of the impugned order has recorded the findings on breaches, on the
part of the appellant, that no irreparable loss would be caused to the
appellant and that balance of convenience was not in favour of the appellant
in paragraphs 32 and 36 of the impugned order. It is submitted that this
court shall not interfere with such findings of fact recorded by the arbitral
tribunal in this appeal. In my view, the learned senior counsel appearing for
the respondent is right in his submission that this court shall not interfere
with these prima facie findings of fact recorded by the arbitral tribunal.
29.
In my view, there is no merit in the appeal filed by the appellant. It is,
however, made clear that the findings recorded by the arbitral tribunal are
prima facie and are recorded while deciding the interim application filed by
the appellant. It is made clear that the arbitral tribunal shall decide the
matter on merits without being influenced by the findings recorded by the
arbitral tribunal as well as the observations made by this court and shall
decide the matter in accordance with law.
30. Resultantly, the appeal is rejected.
There shall be no order as to costs.
(R.D. DHANUKA,J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!