Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

House vs 2 Mr. T. Sita Ramaiah
2012 Latest Caselaw 173 Bom

Citation : 2012 Latest Caselaw 173 Bom
Judgement Date : 11 October, 2012

Bombay High Court
House vs 2 Mr. T. Sita Ramaiah on 11 October, 2012
Bench: Anoop V.Mohta
     ssm                                1                              arbp1025.09

              IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                   ORDINARY ORIGINAL CIVIL JURISDICTION




                                                                          
                   ARBITRATION PETITION NO. 1025 OF 2009 




                                                  
     Hindustan Petroleum Corporation Ltd. 
     a Government of India Company, 
     registered under the Companies Act, 1956
     having its registered office at Petroleum




                                                 
     House, 17, J. Tata Road, Churchgate,
     Mumbai 400020                                         ..  Petitioner 

                 V/s.




                                     
     1  TEMA India Limited, a company
                        
         having its office at B-607, BSEL Tech
         Park, Sector 30A, Opp. Vashi Railway
         Station, Vashi, Navi Mumbai 400705
                       
     2  Mr. T. Sita Ramaiah, Sole Arbitrator
         having address at 201, Topaz,
         Bhakti Park, Wadala East,
      


         Mumbai-400 037.                                   ..  Respondents
   



     Mr. Minoo Siodia with Mr. Kaushik N. Singh i/by M/s. Rustomji 
     & Ginwala for the Petitioner.
     Dr.   Virendra   Tulzapurkar,   Senior   Advocate   with   Mr.   Sandip 





     Parikh i/by M/s. Vigil Juris for Respondent No.1. 


                                       CORAM   :  ANOOP V. MOHTA, J.
                        RESERVED ON         :  4 SEPTEMBER 2012.
                        PRONOUNCED ON  : 11 OCTOBER 2012.


     ORAL JUDGMENT :-


The Petitioner, original Respondent, has challenged the

ssm 2 arbp1025.09

Award under Section 34 of the Arbitration and Conciliation Act,

1996 (for short, "the Arbitration Act") dated 2 March 2009

passed by the sole Arbitrator. The operative part of the Award

is as under :-

"(a) I direct the Respondent to release and pay to the Claimant the amount of Rs. 2,66,48,000/- withheld by the Respondent out of the bills payable to the Claimant.

(b) Not many arguments were made for

payment of interest. However, the rate claimed is too high as per today's standards. I, therefore, direct the Respondent to pay to the Claimant

interest at the rate of 8% p.a from the date of the submission of the statement of claim i.e. 9th September, 2008 till payment of the awarded amount.

(c ) The arbitration proceedings were held

at the premises of the Respondent. I am not awarding cost to either party in the arbitration and I am directing both the parties to pay their own

costs.

(d) I am not inclined to pass any award or direction in respect of the Claimant for loss of profits as the same was neither pressed nor

substantiated or argued by either party. In any event, to compensate the Claimant, I have already awarded payment of interest. Hence, this claim is rejected."

     2     The basic events are as under :-





      ssm                                      3                               arbp1025.09

The Petitioner as a part of its Green Fuels Project for its

refinery at Mumbai, required 28 stainless steel heat exchangers.

Tender enquiry for supply of 28 NOS S S Duplex Heat

Exchangers for GFEC Project was floated by M/s. Engineers

India Ltd. (EIL), the Project Management Consultants (PMC).

Respondent No. 1 emerged as L1 bidder for supply of all 12

items at a total basic cost of Rs.33,86,00,000/-.

3 On 18 July 2005, Purchase Order No. 5000233 - OQ-

48009 for total basic value of Rs.33,86,00,000/- was issued to

Respondent No.1. The CIF value of import content indicated in

the P. O. was Rs.26,65,00,000/-. Initially, the quotations were

obtained on the basis of two conditions (I) project rate of

customs duty against issue of PAC (Project Authority Certificate)

and (ii) Merit rate of customs duty. The Petitioner had reserved

the right to place Purchase Order based on any of the

conditions. The Petitioner was not in a position to submit PAC

and therefore, the P. O. was issued on basis of merit rate of

customs duty.

      ssm                                   4                              arbp1025.09

     4     On 11 May 2007, after supply of the Heat Exchangers, by 




                                                                             

letter, the Petitioner asked Respondent No.1 to furnish

documentary evidence in support that they have actually

imported the materials. Respondent No.1 failed to do so, as

alleged. Hence, an amount of Rs.2,66,00,000/- was retained by

the Petitioner from the bills of Respondent No.1. The disputes

and differences arose between the parties and the same were

referred to Mr. T. Sita Ramaiah, as Sole Arbitration

(Respondent No.2 herein).

5 Respondent No.1 filed the claim Petition which was

replied by the Petitioner and also filed the counter claim.

Ultimately, the learned Arbitrator on 2 March 2009, by

considering the written submissions filed by the parties,

awarded the amount by observing as under :-

"20 Considering the aforesaid rival submissions,

I am not convinced with case of the Respondent and the argument put forth for the reasons set out above viz. That the prices were fixed and firm and not subject to any variation due to change in payment of customs duty as the said P.O. Was admittedly issued on basis of merits rate of customs duty. No PAC was issued to the Claimant and clauses 1(v)(b) to (i) are hence, not

ssm 5 arbp1025.09

applicable. The claimant has already submitted as evidence by way of copies of Bills of Entry and

hence, the ground of non-submission of document as a proof for the import of raw materials is also

not available to the Respondent. I am, therefore, passing an award in favour of the Claimant."

6 There is no dispute with regard to the existence of

Arbitration Clause, appointment of Arbitrator and the

jurisdiction to decide the dispute between the parties. There is

also no dispute with regard to the terms and conditions of the

purchase order. The amount so calculated and withheld and

details thereof, is also not in dispute. The Respondent supplied

the Heat Exchangers as per the contract. No objection of any

kind with regard to the delivery, quantity and quality of the

goods supplied.

7 Both the learned counsel appearing for the parties

referred and read the various clauses of the agreement

specifically clause 1 (v) (a) and clauses 1 (v) (b) to (i). It is

clear from the clauses that referred by the learned Arbitrator

that clause (a) speaks of merits rate of customs duty and sub-

clause (b) speaks of project rate of customs duty, the other sub-

ssm 6 arbp1025.09

clauses are extensions of sub-clause (b), which would be

applicable to the project rate of customs duty. The purchase

order was based on merits rate of customs duty. Therefore, the

prices and variation in customs duty cannot be read as

contended by the learned counsel appearing for the Petitioner

and as observed by the learned Arbitrator.

There is no dispute that PAC was not issued by the

Petitioner therefore, related clauses, just cannot be extended to

the merits rate of customs duty as provided in clause (a). The

CIF value of import was Rs.26,65,00,000/- (Rupees twenty six

crores sixty five lacs only) for the consideration of customs duty

in case the PAC is issued by the Respondents. The import

material components also provided in details. The Petitioner,

therefore, fully aware of the imported components and its

requirement while supplying the products in question. The

learned Arbitrator, therefore, taking overall view of the matter

decided the issues by interpreting the clauses by holding that

clauses 1(v)(b) to (i) are not applicable to the contract in

question. The learned Arbitrator has also rightly accepted the

ssm 7 arbp1025.09

case of the Respondent-Claimant, based upon the clauses and

the submission that the price was fixed for all the purposes.

Once it is held that the agreement was to provide product

and/or material based upon the fixed price, the change or

variation in customs duty, in my view, should not affect the rate

so fixed.

The Petitioner by letter dated 11 May 2007 requested the

Respondent-Claimant to provide the documentary evidence.

Prior to that the Respondent by letter dated 16 March 2007,

though not required, still submitted the copies of the Bills of

Entry under which the materials were imported by the

Respondent-Claimant. As recorded, these Bills of Entry show

that the materials were duly imported and also the date of

import. Importantly, even as per the Petitioner, the details of

the imported material components have already been

mentioned, based upon which the Respondent-Claimant

proceeded and accepted the contract. The learned Arbitrator

right in observing that having once not issued the PAC, the

provisions as referred and relied by the learned counsel

ssm 8 arbp1025.09

appearing for the Petitioner revolving around the same, are not

applicable. Therefore, the conclusion that the Petitioner has no

right to detain and/or retain the amount for want of documents,

apart from giving possible and proper interpretation to the

terms and conditions, in my view, just cannot be stated to be

perverse and/or illegal and/or contrary to the law.

I have already in Union of India Vs. M/s. Suraj

Infrastructures Pvt. Ltd., 1 maintaining similar types of award of

compensation on the ground of delay on the part of employer

observed as under:-

"26 The Apex Court in J.G. Engineers Private Limited Vs. Union of India & Anr. 2 , referring to Section 34 read with the provisions of Contract Act

observed as under:-

"Once it is held that the issues relating to who committed breach and who was responsible for delay were arbitrable, the findings of the

arbitrator that the contractor was not responsible for the delay and that the termination of contract is illegal are not open to challenge."

1 Arbitration Petition No. 324 of 2009, dated 17 September 2012 2 (2011) 5 SCC 758

ssm 9 arbp1025.09

In the result, the escalation price so awarded on the basis of delay and consequential termination of

contract by the employer upheld.

11 The Apex Court has also recently in Rashtriya Ispat

Nigam Limited Vs. Dewan Chand Ram Saran 3 reiterated that

the possible view and the interpretation given by the Arbitrator,

need not be interfered by the Court.

12 I have also, in similar situation, observed in Hindustan

Petroleum Corporation Ltd. Vs. M/s. ISGEC & Anr. 4 that-

"11 Apart from above, there is no terms and conditions referred and/or pointed out to show that

the Petitioner is entitled to withhold the amount in any of such conditions and basically for want of the

documents. The Petitioner, therefore, in absence of any contract clauses acted beyond the contract. The withholding action, therefore, rightly observed by the learned Arbitrator to be illegal. I am not inclined to

accept the case of the Petitioner that the contract price was not fixed but subject to variation. The submission is contrary to the plain reading of the terms itself. The learned Arbitrator, therefore, having

once held that the contract price was fixed / lump sum, which in the present facts and circumstances, cannot be stated to be illegal and contrary interpretation of the clauses. The reasoning in support of grant of award in favour of the Respondents, in my view, needs no interference."

     3      (2012) 5 SCC 306
     4      2012 (3) Bom. C,R. 243=2012(114) Bom. L.R. 1679





      ssm                                   10                              arbp1025.09




                                                                              
     13     In the present case, an additional factor is that there is no 




                                                      

clause and/or condition which permits the Petitioner-employer

to detain and/or retain the amount, in any such circumstances

and/or even otherwise. Therefore also, there was no question

of retaining such huge amount only for want of documents as

sought to be contended. The action was unauthorized and

illegal.

14 If there is no clause permits the Petitioner to retain and/or

withheld the amount, the burden lies upon them to justify their

action. Any retention of amount in such type of contract,

specifically when there was no dispute of whatsoever nature,

with regard to the quantity, quality and receipt of the goods,

itself is contrary to the terms and conditions and impermissible.

The Petitioner failed to discharge the basic burden in this

regard. It is not the case that the Respondent-claimant not

submitted their reply and details when asked for. The bills so

referred and submitted, if provides the basic details, including

quantity, material and the date of import, in my view, burden

ssm 11 arbp1025.09

lies upon the Petitioner to show and prove that the customs

duty rates were decreased and/or changed at the relevant time.

The documents and/or evidence must be placed before the

Arbitrator at the relevant time during the course of the trial and

not later on. Therefore, the documents so placed on record

after conclusion of the trial, just cannot be taken note of in such

fashion, basically when the learned Arbitrator has interpreted

the clauses and given findings against them. The scope and

power of Court under Section 34 of the Arbitration Act is quite

limited in this regard. One cannot overlook the fact that this is

a commercial transaction with clear terms and conditions.

Both the parties based upon the same acted upon and the goods

were supplied accordingly.

15 In this background, the submission of the learned counsel

appearing for the Petitioner that the release of this amount

and/or payment of this amount to the Respondent would be

"Unjust Enrichment" is also unacceptable. The doctrine of

"quantum meruit" is also referred and relied. It is necessary to

note that having once agreed and accordingly the Petitioner

ssm 12 arbp1025.09

supplied the goods on a foundation of the fixed price basis,

inclusive of customs duty, the variation, as sought to be

contended by the Petitioner is also untenable, considering the

terms and conditions of the contract. I am also of the view that

there is no question of unjust enrichment, as sought to be

contended by the learned counsel appearing for the Petitioner in

the present facts and circumstances of the case.

16 Therefore, taking note of rival contentions and the

submissions so made by the learned counsel appearing for the

parties and after reconsidering even the clauses so referred and

relied, I am inclined to observe that, in the present facts and

circumstances, the view taken by the learned Arbitrator based

upon the clauses, is a possible and plausible view. Therefore,

considering the commercial nature of transaction; and that

there is no dispute with regard to the quality, quantity and

supply of the goods; and that there is no provision in the

contract to retain/detain the amount in such fashion; and that

the Petitioner failed to discharge the burden to prove any

variation to the customs duty at the relevant time; and that the

ssm 13 arbp1025.09

findings with the agreement to supply goods based upon the

fixed rate, no case to interfere with the award. The reasons so

given by the learned Arbitrator is well within the purview of law

and the record. There is no perversity. The interest so awarded

from the date of statement of claim i.e. from 9 September 2008

till payment, is also reasonable and correct.

Resultantly, the Petition is dismissed. Award is maintained

in all respect. There shall be no order as to costs.

(ANOOP V. MOHTA, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter