Thursday, 30, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Shri Anand Umashankar Gupta vs Shri Jayant Maniklal Lunawat
2012 Latest Caselaw 166 Bom

Citation : 2012 Latest Caselaw 166 Bom
Judgement Date : 11 October, 2012

Bombay High Court
Shri Anand Umashankar Gupta vs Shri Jayant Maniklal Lunawat on 11 October, 2012
Bench: R.D. Dhanuka
kvm
                                              1/16
                                                                                       ARBP19.09


              IN THE HIGH COURT OF JUDICATURE AT BOMBAY




                                                                                     
                          CIVIL APPELLATE JURISDICTION




                                                             
                       ARBITRATION APPEAL NO. 19 OF 2009

      1. Shri Anand Umashankar Gupta          )
      Age/25 yrs. Occupation : Business       )




                                                            
      2. Shri Amit Umashankar Gupta           )
      Age/23 yrs. Occupation : Business       )




                                                 
      3. Smt. Uma Umashankar Gupta            )
      Age/40 yrs. Occupation : Business
                                 ig           )

      4. Shri Amrit Umashankar Gupta          )
      Age/20 yrs. Occupation :                )
                               
      All residing at 501, Lunawat Classic,   )
      Bhosle Nagar, ICS Colony, Pune          )
      411 007                                 )      ..... Appellants
            

            Versus
         



      Shri Jayant Maniklal Lunawat            )
      Age/51 years, occupation : Business     )
      Address : 1206/B/22, Shivajinagar,      )
      Pune - 411 004.                         )      ..... Respondent





      Shri P.S.Dani for the Appellants.

      Mr.S.U.Kamdar, Senior Counsel, Ms.Pooja Patil, Mr.Vivek Vashi, Mr.Darush





      Marfatia, Ms.Natasha B.Opaish, Ms.Alya Khan for Respondents.

                                          CORAM : R.D. DHANUKA, J.
                                          DATE       : 11th OCTOBER, 2012

      ORAL JUDGMENT :

By this appeal filed under Section 37 of the Arbitration and Conciliation

Act, 1996 (for short 'Arbitration Act, 1996'), the appellants have challenged

kvm

ARBP19.09

Order and Judgment dated 4th May, 2009 delivered by the learned District

Court, Pune in Civil Miscellaneous Application No. 809 of 2008 filed under

Section 34 of the Arbitration Act, 1996 thereby allowing the application filed

by the respondent and setting aside the arbitral award declared by the sole

arbitrator on 16th August, 2008 by which the arbitrator had allowed certain

claims made by the appellants.

2.

Some of the relevant facts for deciding the issue involved in this appeal

are as under :-

3. By an agreement and Power of Attorney dated 12th March, 2004,

M/s.Aman & Anand Associates, the partnership firm then consisting of the

appellant and Mr.Anand and Shreya Mehkari acquired development rights in

respect of the property bearing Survey No. 111, Hissa No. 11/1A admeasuring

21.5 R' 11/1B admeasuring 21.5 R and Survey No.112, Hissa No.1

admeasuring 13.56 R situate at Village Baner, Tal. Haveli, Dist. Pune.

Thereafter other partners viz. Anand and Shreya Mehkari retired from the firm

and the firm was renamed as M/s.Anand and Anand Associates. On 22nd

August, 2005, the respondent herein was admitted as a partner in the said

partnership firm. The firm was renamed as "Sri Sri Gurudeo Reality ". The

Memorandum of Understanding and Deed of Partnership was executed by and

between the parties on 22nd August, 2005. It was agreed that the net profits or

the gross sales of the firm were to be shared in the ratio of 30% to the appellant

kvm

ARBP19.09

and 70% to the respondent. The costs in advertisement, marketing and selling

were to be shared by the parties according to their respective ratio of profit and

loss. In the month of October, 2005, both the parties entered into a

Supplementary Deed of Partnership. It was agreed that the period for

completion of project was 30 months and in the event of any delay, the

respondent would pay interest at the rate of Rs.12% per annum for the delayed

period to the appellants on the market value of 30% of the total permissible

constructed area.

4. Clause (4) of the Memorandum of Understanding provides that 30% of

the constructed area would be exclusively sold by the appellants and 70% of

the constructed area would be exclusively sold by the respondent. The

respondent agreed to bring Rs.25 lacs as his capital contribution and that the

amount would be withdrawn by the appellants. It was further agreed that the

respondent would contribute additional sum of Rs. 25 lacs by the end of

September, 2005 and the same amount would be withdrawn by the appellants.

It was agreed that partnership deed executed by the parties was in respect of

the development of the property referred therein and it was "specific project

partnership" and shall be dissolved automatically on completion of the project

and on execution of conveyance and fulfillment of all legal and other

formalities in respect thereof. It was agreed that the duration of the

reconstituted partnership shall be particular partnership and shall be dissolved

kvm

ARBP19.09

automatically on the completion of the proposed construction and development

of project in all respect and conveyance in favour of all flats, tenaments,

offices and building on the property referred therein. Clause (20) of the

Partnership Deed provides for accounts to be taken of all the assets, credits,

debts and liabilities of the partnership etc. upon the determination of the

partnership and for sale of assets.

5. Clause (23) of the Partnership Deed provided that the respondent alone

was empowered to look after execution, implementation and supervision and

sales of constructed tenaments other than which were agreed to be sold by the

joint signatures of the parties of the appellants which is 30% of the total

permissible constructed area.

6. By a Supplementary Deed of Partnership entered into in the October,

2005, Clause 26A was inserted which reads thus :-

Clause No.26A :

The project undertaken by the firm regarding the development of property situated at Sr.No.111,

Hisssa No.11/1A, Hissa No.11/1B & Sr.No.112, Hissa No.1 totally admeasuring 56.56 Aars i.e. 5656 Sq.Mtrs. situated at Village : Baner, Tal.

Haveli, Dist. Pune is to be completed within 30 months from the date of execution of the partnership deed i.e. 22nd August, 2005. In any circumstances or for any reasons, the project is delayed, then, the party of fifth part will pay damages @ 12% p.a. for the delayed period to party of the first to fourth part on the market value of the 30% of total permissible constructed area,

kvm

ARBP19.09

i.e. the flats, shops, offices which are agreed to be sold by joint signature of the party of the first to

fourth part.

It is further agreed by and between the parties hereto that if they agree to develop the property referred above with the adjacent land then the period of 30 months as referred above may be

extended to 36 months matually.

7. According to the respondent, after execution of the Partnership Deed, he

introduced a sum of Rs.1,53,00,000/- in the Partnership Firm, out of which a

sum of Rs.1,03,00,000/- was withdrawn by the appellants even before

commencement of business of the firm. According to the respondent, the

appellants had represented that the land was capable of development forthwith

without any hindrance. However, at the time of demarcation of the land, it was

noticed that the area and the boundaries of the land in question as mentioned in

the Development Agreement were not tallying with the actual area and

boundaries. Some objection was also raised by original owners in response to

the public notice issued by the respondent before undertaking the work of

demarcation. The work could not commence on time. The respondent

submitted plan for sanction to Pune Municipal Corporation and had

commenced activity.

8. The appellants by their advocates' notice dated 6th January, 2007 alleged

that there was delay on the part of the respondent to commence the work of

construction and various breaches were committed by the respondent and

kvm

ARBP19.09

terminated the contract entered into between the parties. The respondent was

instructed to stop the construction activity on the site. The respondent was

informed that the appellants were at liberty to deal with and dispose of the

property as deem fit. The respondent replied to the said notice through his

advocate and pointed out that the large amount had been invested by the

respondent and various steps had been taken by him for the development of the

property. It was pointed out that 30 months time granted under the writing

entered into between the parties for completion of the project had not been

completed and thus the appellants could not terminate the contract.

9. In the year 2007, the respondent filed Misc. Application (383 of 2007) in

the District Court under Section 9 of the Act. It was agreed that both the

parties will maintain status quo with respect to land and activity till the matter

was referred to the arbitrator and arbitral award was passed. The matter was

thereafter referred to the sole arbitrator, Mr.Suhas P.Bora. The appellants made

a monetary claim of Rs.13,60,78,880/- against the respondent on account of

alleged breach of contract and in the alternate claimed Rs.12,49,70,400/-. The

appellants also claimed Rs.1 crore by way of additional damages. The

respondent also filed a counter claim before the learned arbitrator praying that

the partnership firm be dissolved and after taking into account balance be

distributed in the proportion of their respective shares and also made a

monetary claim of Rs.2,58,60,000/- with interest at the rate of 15% per annum

kvm

ARBP19.09

on the amount of Rs.53 lacs form the date of filing of the claim till realization.

The parties led oral as well as documentary evidence before the learned

arbitrator.

10. On 16th August, 2008, the learned arbitrator declared an award. The

learned arbitrator recorded the finding that the respondent had committed

default in not completing the project within 30 months. It is held that the

appellants were entitled for damages for the default as stipulated in clause 26A

of the Supplementary Deed of Partnership. The Learned arbitrator recorded a

finding that the respondent had proved that the Agreement dated 22nd August,

2005 was a Partnership Agreement and not a Development Agreement. The

arbitrator recorded that the claim of the appellants was computed at Rs.3,800/-

sq.ft. and the appellants was also eligible for the damages at the rate of 12%

per annum for the period of delay on the market value of 30% of total

permissible constructed area. It was further held that the market value of the

constructed area average out to be Rs.5,000/-, the interest at the rate of 12%

would work out at Rs.1,30,17,750/- . The arbitrator held that the appellants

were entitled to claim Rs.17,35,70,000/- and an amount of Rs.1,30,17,750/- by

way of damages pursuant to Clause 26A of the Supplementary Deed of

Partnership. It is held by the arbitrator that the respondent was entitled to sale

proceeds of 70% of the constructed area, the construction costs of which were

to be borne by the respondent. It is held that in the event the respondent did

kvm

ARBP19.09

not agree to the direction as given by the arbitrator, the only alternative

solution to the dispute would be that the appellants refund the amount of Rs.

93,00,000/- plus interest on the capital at the rate of 12% per annum plus

expenditure incurred by the respondent on the project till the date of award to

the respondent. It is further held that in such a situation, respondent would not

be entitled to any further claim by way of interest or damages and further that

he shall move out of the partnership without any right, title or interest in the

development rights.

11. Being aggrieved by the said Award, the respondent herein filed Civil

Misc. Application (809 of 2008) under Section 34 of the Arbitration and

Conciliation Act, 1996 before the District Court. By an order dated 4th May,

2009, the Learned District Judge allowed the said application and set aside the

impugned award dated 16th August, 2008.

12. The Learned Counsel appearing for the appellants submits as under :-

(a) that the agreement entered into between the

parties was not only an agreement for partnership

but was a development agreement. The nature of

the transaction arising between the parties shows

that it was development agreement. There is no

format prescribed under the provisions of the

Partnership Act for execution of a Partnership

kvm

ARBP19.09

Deed.

(b) There is no provision under the Indian

Partnership Act, 1932 prohibiting such clause in

the partnership deed. The partnership deed and

Memorandum of Understanding intermingled with

each other and was partnership cum development

agreement.

(c)

That though the finding was recorded by the

learned District Judge that deed of partnership,

Memorandum of Understanding and

Supplementary Deed of Partnership were

admittedly executed between the parties and all the

terms and conditions in those documents were also

specifically admitted, the learned Judge erred in

holding that the arbitral award passed by the

arbitrator was in consonance with the provisions of

law and was legal and binding.

(d) That Clause 26A inserted by consent of both

the parties in the Supplementary Partnership Deed

by which the respondent had agreed to pay

damages/interest to the appellants was not contrary

to any provision under the Indian Partnership Act.

kvm

ARBP19.09

Such agreement was voluntarily entered into

between the parties and was not contrary to law.

(e) That the award given by the learned

arbitrator was based on finding of facts which

could not be interfered with by the learned District

Judge.

(f) The claim for damages was maintainable

before the arbitrator. The learned District Judge

could not have substituted the factual finding of

the learned arbitrator and could not have arrived at

a different finding in view of limited scope of

Section 34 of the Act.

13. The learned senior counsel Mr.S.U.Kamdar appearing for the respondent

submits as under :-

(a) The learned arbitrator ought to have

dissolved the partnership firm and ought to have

settled the accounts between the parties under

Section 48 of the Partnership Act, 1932 which

reads thus :-

48. Mode of settlement of accounts between partners. - In settling the accounts of a firm after dissolution, the

kvm

ARBP19.09

following rules shall, subject to agreement by the partners, be observed:-

(a) losses, including deficiencies of

capital, shall be paid first out of profits, next out of capital, and, lastly, if necessary, by the partners individually in the proportions in which they were entitled to

share profits.

(b) the assets of the firm, including any sums contributed by the partners to make

up deficiencies of capital, shall be applied in the following manner and order:-

(i)

in paying the debts of the firm to third parties ;

(ii) in paying to each partner rateably what is due to him from the firm for advances as distinguished from capital;

(iii) in paying to each partner rateably what is due to him on account of capital;

and

(iv) the residue, if any, shall be divided among the partners in the proportions in which they were entitled to share profits.

(b) The learned arbitrator did not decide the

counter claim filed by the respondent seeking

dissolution of the firm and for settlement of the

accounts as per the provisions of Section 48 of the

Partnership Act. The award is vague and

incomplete. The learned arbitrator not having

decided the counter claim filed by the respondent

and not having settled the accounts as per Section

kvm

ARBP19.09

48 which is mandatory, the entire award was

vitiated being contrary to law and in conflict with

public policy. The learned District Judge was thus

right in setting aside the impugned award under

section 34(2) (a) (iv) and (v) and section 34(2) (b)

(ii) of the Arbitration and Conciliation Act, 1996.

(c) That though the appellants had made claim

for damages at the rate of Rs.3,800/- sq.ft., the

arbitrator has considered the claim at Rs.5,000/-.

The arbitrator had thus exceeded his jurisdiction

and had decided contrary to the submission made

by the parties for adjudication.

(d) That the alternate award given by the learned

arbitrator is totally perverse and contrary to law and

could not be implemented in any manner

whatsoever. The learned district judge was right in

setting aside such perverse award.

(e) That the learned arbitrator considered the

damages on the basis of the market value of the

constructed property. The construction of the

property admittedly was not complete. The

kvm

ARBP19.09

appellants had admittedly terminated the agreement

before expiry of 30 months. The District Judge had

thereafter by consent of both the parties had

granted status quo order. The appellants thus in no

circumstances could claim damages against the

respondent for not completing the construction

before expiry of the period of 30 months. The

appellants themselves were responsible for the

respondent's not completing the construction

within 30 months. The claim thus awarded by the

arbitrator was totally perverse and on the face of it

illegal.

14. The learned senior counsel for the respondent placed reliance on the

judgment of Supreme Court in the case of Addanki Narayanappa and another

vs. Bhaskara Krishnappa1 , judgment of this court in case of Sherbanubai

Jafferbhoy vs. Hooseinbhoy Abdoolabhoy and another2 and judgment of the

Supreme Court in case of Asandas Mitharam Narsinghani and others vs.

Tekchand Mitharam Sevakramani and others3 in support of his plea that the

arbitrator was bound to settle accounts between the parties in the mode and

manner prescribed under Section 48 of the Partnership Act, 1932 and not

1 AIR 1966 SC 1300 2 AIR (35) 1948 Bombay 292 3 (1999) 3 Supreme Court Cases 110

kvm

ARBP19.09

having done so, the award was totally contrary to law and thus in conflict with

public policy.

15. It is not in dispute that the respondent had made counter claim before the

learned arbitrator seeking dissolution of the firm and for settlement of the

account. On the perusal of the award, it is clear that the counter claim made by

the respondent had not been decided by the learned arbitrator. Though the

learned arbitrator was bound to decide the issue of dissolution of the firm and

to settle the accounts between the parties in the modes and manner prescribed

under Section 48, admittedly no such exercise has been done by the learned

arbitrator in the impugned award. The learned arbitrator granted relief of

retirement of a partner and not dissolution. In my view, the learned arbitrator

was bound to follow the mandatory procedure under Section 48 while

dissolving the firm and to settle the account of the firm in the manner setout

therein. In my view, the award made by the learned arbitrator was not in

compliance of mandatory procedure prescribed under Section 48 of the

Partnership Act and was thus in conflict with public policy. In my view the

learned District Judge was right in setting aside the said perverse and illegal

award and thus the said order passed by the learned District Judge cannot be

faulted with.

16. The learned arbitrator could not have ignored the counter claim made by

the respondent which was referred to him. The award was thus incomplete

kvm

ARBP19.09

and vague. The learned District Judge was thus in my view correct in setting

aside the impugned award given by the learned arbitrator.

17. The Clause 26(A) of the Supplementary Deed provides for payment of

interest at the rate of 12% per annum to the appellants by the respondent if the

respondent was not able to complete the construction of the plot in question

within a period of 30 months. The record indicates that before the expiry of 30

months, the appellants had terminated the agreement and thereafter the status-

quo order came to be passed by the learned District Judge against both the

parties by consent. The claim thus made for damages by the appellants on the

basis of clause 26(A) was on the face of it not maintainable. In view of such

premature termination, the appellants could not have made any claim for

damages under Clause 26(A). The learned arbitrator acted contrary to the

terms of the contract and thus the award was in conflict with public policy.

The arbitrator was bound to decide in accordance with the contract and in

accordance with Clause 26(A) of the Supplementary Deed and not having done

so, the award is in conflict with the public policy. The learned District Judge

was thus right in setting aside the same.

18. The record produced by the parties also indicates that though the claim

made by the appellants was for damage at the rate of Rs.3,800/- per sq.ft.

whereas the learned arbitrator has considered claim at the rate of Rs.5,000/-.

kvm

ARBP19.09

In my view, the learned arbitrator cannot award more than claim made by a

party. The arbitrator has thus exceeded his jurisdiction by awarding more than

what was claimed by the appellants. The award was on the face of it illegal

and in conflict with public policy. The appellants did not lead any evidence in

support of such claim for damages. The onus to prove such damages was on

the appellants which the appellants had failed to discharge. The learned

arbitrator could not have awarded claim for damages without any such

evidence produced and proved by the appellants. The award was totally

vitiated and was rightly set aside by the learned District Judge.

19. In my view, there is no merit in the submissions made by the learned

counsel appearing for the appellants. In my view, the learned District Judge

has rightly set aside the impugned award and does not require any interference

by this court under Section 37 of the Arbitration and Conciliation Act, 1996.

20. The appeal is dismissed.

21. There is no order as to costs.

22. It is made clear that the parties are free to adopt such proceeding as are

permissible in law.

(R.D. DHANUKA, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter