Citation : 2012 Latest Caselaw 166 Bom
Judgement Date : 11 October, 2012
kvm
1/16
ARBP19.09
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
ARBITRATION APPEAL NO. 19 OF 2009
1. Shri Anand Umashankar Gupta )
Age/25 yrs. Occupation : Business )
2. Shri Amit Umashankar Gupta )
Age/23 yrs. Occupation : Business )
3. Smt. Uma Umashankar Gupta )
Age/40 yrs. Occupation : Business
ig )
4. Shri Amrit Umashankar Gupta )
Age/20 yrs. Occupation : )
All residing at 501, Lunawat Classic, )
Bhosle Nagar, ICS Colony, Pune )
411 007 ) ..... Appellants
Versus
Shri Jayant Maniklal Lunawat )
Age/51 years, occupation : Business )
Address : 1206/B/22, Shivajinagar, )
Pune - 411 004. ) ..... Respondent
Shri P.S.Dani for the Appellants.
Mr.S.U.Kamdar, Senior Counsel, Ms.Pooja Patil, Mr.Vivek Vashi, Mr.Darush
Marfatia, Ms.Natasha B.Opaish, Ms.Alya Khan for Respondents.
CORAM : R.D. DHANUKA, J.
DATE : 11th OCTOBER, 2012
ORAL JUDGMENT :
By this appeal filed under Section 37 of the Arbitration and Conciliation
Act, 1996 (for short 'Arbitration Act, 1996'), the appellants have challenged
kvm
ARBP19.09
Order and Judgment dated 4th May, 2009 delivered by the learned District
Court, Pune in Civil Miscellaneous Application No. 809 of 2008 filed under
Section 34 of the Arbitration Act, 1996 thereby allowing the application filed
by the respondent and setting aside the arbitral award declared by the sole
arbitrator on 16th August, 2008 by which the arbitrator had allowed certain
claims made by the appellants.
2.
Some of the relevant facts for deciding the issue involved in this appeal
are as under :-
3. By an agreement and Power of Attorney dated 12th March, 2004,
M/s.Aman & Anand Associates, the partnership firm then consisting of the
appellant and Mr.Anand and Shreya Mehkari acquired development rights in
respect of the property bearing Survey No. 111, Hissa No. 11/1A admeasuring
21.5 R' 11/1B admeasuring 21.5 R and Survey No.112, Hissa No.1
admeasuring 13.56 R situate at Village Baner, Tal. Haveli, Dist. Pune.
Thereafter other partners viz. Anand and Shreya Mehkari retired from the firm
and the firm was renamed as M/s.Anand and Anand Associates. On 22nd
August, 2005, the respondent herein was admitted as a partner in the said
partnership firm. The firm was renamed as "Sri Sri Gurudeo Reality ". The
Memorandum of Understanding and Deed of Partnership was executed by and
between the parties on 22nd August, 2005. It was agreed that the net profits or
the gross sales of the firm were to be shared in the ratio of 30% to the appellant
kvm
ARBP19.09
and 70% to the respondent. The costs in advertisement, marketing and selling
were to be shared by the parties according to their respective ratio of profit and
loss. In the month of October, 2005, both the parties entered into a
Supplementary Deed of Partnership. It was agreed that the period for
completion of project was 30 months and in the event of any delay, the
respondent would pay interest at the rate of Rs.12% per annum for the delayed
period to the appellants on the market value of 30% of the total permissible
constructed area.
4. Clause (4) of the Memorandum of Understanding provides that 30% of
the constructed area would be exclusively sold by the appellants and 70% of
the constructed area would be exclusively sold by the respondent. The
respondent agreed to bring Rs.25 lacs as his capital contribution and that the
amount would be withdrawn by the appellants. It was further agreed that the
respondent would contribute additional sum of Rs. 25 lacs by the end of
September, 2005 and the same amount would be withdrawn by the appellants.
It was agreed that partnership deed executed by the parties was in respect of
the development of the property referred therein and it was "specific project
partnership" and shall be dissolved automatically on completion of the project
and on execution of conveyance and fulfillment of all legal and other
formalities in respect thereof. It was agreed that the duration of the
reconstituted partnership shall be particular partnership and shall be dissolved
kvm
ARBP19.09
automatically on the completion of the proposed construction and development
of project in all respect and conveyance in favour of all flats, tenaments,
offices and building on the property referred therein. Clause (20) of the
Partnership Deed provides for accounts to be taken of all the assets, credits,
debts and liabilities of the partnership etc. upon the determination of the
partnership and for sale of assets.
5. Clause (23) of the Partnership Deed provided that the respondent alone
was empowered to look after execution, implementation and supervision and
sales of constructed tenaments other than which were agreed to be sold by the
joint signatures of the parties of the appellants which is 30% of the total
permissible constructed area.
6. By a Supplementary Deed of Partnership entered into in the October,
2005, Clause 26A was inserted which reads thus :-
Clause No.26A :
The project undertaken by the firm regarding the development of property situated at Sr.No.111,
Hisssa No.11/1A, Hissa No.11/1B & Sr.No.112, Hissa No.1 totally admeasuring 56.56 Aars i.e. 5656 Sq.Mtrs. situated at Village : Baner, Tal.
Haveli, Dist. Pune is to be completed within 30 months from the date of execution of the partnership deed i.e. 22nd August, 2005. In any circumstances or for any reasons, the project is delayed, then, the party of fifth part will pay damages @ 12% p.a. for the delayed period to party of the first to fourth part on the market value of the 30% of total permissible constructed area,
kvm
ARBP19.09
i.e. the flats, shops, offices which are agreed to be sold by joint signature of the party of the first to
fourth part.
It is further agreed by and between the parties hereto that if they agree to develop the property referred above with the adjacent land then the period of 30 months as referred above may be
extended to 36 months matually.
7. According to the respondent, after execution of the Partnership Deed, he
introduced a sum of Rs.1,53,00,000/- in the Partnership Firm, out of which a
sum of Rs.1,03,00,000/- was withdrawn by the appellants even before
commencement of business of the firm. According to the respondent, the
appellants had represented that the land was capable of development forthwith
without any hindrance. However, at the time of demarcation of the land, it was
noticed that the area and the boundaries of the land in question as mentioned in
the Development Agreement were not tallying with the actual area and
boundaries. Some objection was also raised by original owners in response to
the public notice issued by the respondent before undertaking the work of
demarcation. The work could not commence on time. The respondent
submitted plan for sanction to Pune Municipal Corporation and had
commenced activity.
8. The appellants by their advocates' notice dated 6th January, 2007 alleged
that there was delay on the part of the respondent to commence the work of
construction and various breaches were committed by the respondent and
kvm
ARBP19.09
terminated the contract entered into between the parties. The respondent was
instructed to stop the construction activity on the site. The respondent was
informed that the appellants were at liberty to deal with and dispose of the
property as deem fit. The respondent replied to the said notice through his
advocate and pointed out that the large amount had been invested by the
respondent and various steps had been taken by him for the development of the
property. It was pointed out that 30 months time granted under the writing
entered into between the parties for completion of the project had not been
completed and thus the appellants could not terminate the contract.
9. In the year 2007, the respondent filed Misc. Application (383 of 2007) in
the District Court under Section 9 of the Act. It was agreed that both the
parties will maintain status quo with respect to land and activity till the matter
was referred to the arbitrator and arbitral award was passed. The matter was
thereafter referred to the sole arbitrator, Mr.Suhas P.Bora. The appellants made
a monetary claim of Rs.13,60,78,880/- against the respondent on account of
alleged breach of contract and in the alternate claimed Rs.12,49,70,400/-. The
appellants also claimed Rs.1 crore by way of additional damages. The
respondent also filed a counter claim before the learned arbitrator praying that
the partnership firm be dissolved and after taking into account balance be
distributed in the proportion of their respective shares and also made a
monetary claim of Rs.2,58,60,000/- with interest at the rate of 15% per annum
kvm
ARBP19.09
on the amount of Rs.53 lacs form the date of filing of the claim till realization.
The parties led oral as well as documentary evidence before the learned
arbitrator.
10. On 16th August, 2008, the learned arbitrator declared an award. The
learned arbitrator recorded the finding that the respondent had committed
default in not completing the project within 30 months. It is held that the
appellants were entitled for damages for the default as stipulated in clause 26A
of the Supplementary Deed of Partnership. The Learned arbitrator recorded a
finding that the respondent had proved that the Agreement dated 22nd August,
2005 was a Partnership Agreement and not a Development Agreement. The
arbitrator recorded that the claim of the appellants was computed at Rs.3,800/-
sq.ft. and the appellants was also eligible for the damages at the rate of 12%
per annum for the period of delay on the market value of 30% of total
permissible constructed area. It was further held that the market value of the
constructed area average out to be Rs.5,000/-, the interest at the rate of 12%
would work out at Rs.1,30,17,750/- . The arbitrator held that the appellants
were entitled to claim Rs.17,35,70,000/- and an amount of Rs.1,30,17,750/- by
way of damages pursuant to Clause 26A of the Supplementary Deed of
Partnership. It is held by the arbitrator that the respondent was entitled to sale
proceeds of 70% of the constructed area, the construction costs of which were
to be borne by the respondent. It is held that in the event the respondent did
kvm
ARBP19.09
not agree to the direction as given by the arbitrator, the only alternative
solution to the dispute would be that the appellants refund the amount of Rs.
93,00,000/- plus interest on the capital at the rate of 12% per annum plus
expenditure incurred by the respondent on the project till the date of award to
the respondent. It is further held that in such a situation, respondent would not
be entitled to any further claim by way of interest or damages and further that
he shall move out of the partnership without any right, title or interest in the
development rights.
11. Being aggrieved by the said Award, the respondent herein filed Civil
Misc. Application (809 of 2008) under Section 34 of the Arbitration and
Conciliation Act, 1996 before the District Court. By an order dated 4th May,
2009, the Learned District Judge allowed the said application and set aside the
impugned award dated 16th August, 2008.
12. The Learned Counsel appearing for the appellants submits as under :-
(a) that the agreement entered into between the
parties was not only an agreement for partnership
but was a development agreement. The nature of
the transaction arising between the parties shows
that it was development agreement. There is no
format prescribed under the provisions of the
Partnership Act for execution of a Partnership
kvm
ARBP19.09
Deed.
(b) There is no provision under the Indian
Partnership Act, 1932 prohibiting such clause in
the partnership deed. The partnership deed and
Memorandum of Understanding intermingled with
each other and was partnership cum development
agreement.
(c)
That though the finding was recorded by the
learned District Judge that deed of partnership,
Memorandum of Understanding and
Supplementary Deed of Partnership were
admittedly executed between the parties and all the
terms and conditions in those documents were also
specifically admitted, the learned Judge erred in
holding that the arbitral award passed by the
arbitrator was in consonance with the provisions of
law and was legal and binding.
(d) That Clause 26A inserted by consent of both
the parties in the Supplementary Partnership Deed
by which the respondent had agreed to pay
damages/interest to the appellants was not contrary
to any provision under the Indian Partnership Act.
kvm
ARBP19.09
Such agreement was voluntarily entered into
between the parties and was not contrary to law.
(e) That the award given by the learned
arbitrator was based on finding of facts which
could not be interfered with by the learned District
Judge.
(f) The claim for damages was maintainable
before the arbitrator. The learned District Judge
could not have substituted the factual finding of
the learned arbitrator and could not have arrived at
a different finding in view of limited scope of
Section 34 of the Act.
13. The learned senior counsel Mr.S.U.Kamdar appearing for the respondent
submits as under :-
(a) The learned arbitrator ought to have
dissolved the partnership firm and ought to have
settled the accounts between the parties under
Section 48 of the Partnership Act, 1932 which
reads thus :-
48. Mode of settlement of accounts between partners. - In settling the accounts of a firm after dissolution, the
kvm
ARBP19.09
following rules shall, subject to agreement by the partners, be observed:-
(a) losses, including deficiencies of
capital, shall be paid first out of profits, next out of capital, and, lastly, if necessary, by the partners individually in the proportions in which they were entitled to
share profits.
(b) the assets of the firm, including any sums contributed by the partners to make
up deficiencies of capital, shall be applied in the following manner and order:-
(i)
in paying the debts of the firm to third parties ;
(ii) in paying to each partner rateably what is due to him from the firm for advances as distinguished from capital;
(iii) in paying to each partner rateably what is due to him on account of capital;
and
(iv) the residue, if any, shall be divided among the partners in the proportions in which they were entitled to share profits.
(b) The learned arbitrator did not decide the
counter claim filed by the respondent seeking
dissolution of the firm and for settlement of the
accounts as per the provisions of Section 48 of the
Partnership Act. The award is vague and
incomplete. The learned arbitrator not having
decided the counter claim filed by the respondent
and not having settled the accounts as per Section
kvm
ARBP19.09
48 which is mandatory, the entire award was
vitiated being contrary to law and in conflict with
public policy. The learned District Judge was thus
right in setting aside the impugned award under
section 34(2) (a) (iv) and (v) and section 34(2) (b)
(ii) of the Arbitration and Conciliation Act, 1996.
(c) That though the appellants had made claim
for damages at the rate of Rs.3,800/- sq.ft., the
arbitrator has considered the claim at Rs.5,000/-.
The arbitrator had thus exceeded his jurisdiction
and had decided contrary to the submission made
by the parties for adjudication.
(d) That the alternate award given by the learned
arbitrator is totally perverse and contrary to law and
could not be implemented in any manner
whatsoever. The learned district judge was right in
setting aside such perverse award.
(e) That the learned arbitrator considered the
damages on the basis of the market value of the
constructed property. The construction of the
property admittedly was not complete. The
kvm
ARBP19.09
appellants had admittedly terminated the agreement
before expiry of 30 months. The District Judge had
thereafter by consent of both the parties had
granted status quo order. The appellants thus in no
circumstances could claim damages against the
respondent for not completing the construction
before expiry of the period of 30 months. The
appellants themselves were responsible for the
respondent's not completing the construction
within 30 months. The claim thus awarded by the
arbitrator was totally perverse and on the face of it
illegal.
14. The learned senior counsel for the respondent placed reliance on the
judgment of Supreme Court in the case of Addanki Narayanappa and another
vs. Bhaskara Krishnappa1 , judgment of this court in case of Sherbanubai
Jafferbhoy vs. Hooseinbhoy Abdoolabhoy and another2 and judgment of the
Supreme Court in case of Asandas Mitharam Narsinghani and others vs.
Tekchand Mitharam Sevakramani and others3 in support of his plea that the
arbitrator was bound to settle accounts between the parties in the mode and
manner prescribed under Section 48 of the Partnership Act, 1932 and not
1 AIR 1966 SC 1300 2 AIR (35) 1948 Bombay 292 3 (1999) 3 Supreme Court Cases 110
kvm
ARBP19.09
having done so, the award was totally contrary to law and thus in conflict with
public policy.
15. It is not in dispute that the respondent had made counter claim before the
learned arbitrator seeking dissolution of the firm and for settlement of the
account. On the perusal of the award, it is clear that the counter claim made by
the respondent had not been decided by the learned arbitrator. Though the
learned arbitrator was bound to decide the issue of dissolution of the firm and
to settle the accounts between the parties in the modes and manner prescribed
under Section 48, admittedly no such exercise has been done by the learned
arbitrator in the impugned award. The learned arbitrator granted relief of
retirement of a partner and not dissolution. In my view, the learned arbitrator
was bound to follow the mandatory procedure under Section 48 while
dissolving the firm and to settle the account of the firm in the manner setout
therein. In my view, the award made by the learned arbitrator was not in
compliance of mandatory procedure prescribed under Section 48 of the
Partnership Act and was thus in conflict with public policy. In my view the
learned District Judge was right in setting aside the said perverse and illegal
award and thus the said order passed by the learned District Judge cannot be
faulted with.
16. The learned arbitrator could not have ignored the counter claim made by
the respondent which was referred to him. The award was thus incomplete
kvm
ARBP19.09
and vague. The learned District Judge was thus in my view correct in setting
aside the impugned award given by the learned arbitrator.
17. The Clause 26(A) of the Supplementary Deed provides for payment of
interest at the rate of 12% per annum to the appellants by the respondent if the
respondent was not able to complete the construction of the plot in question
within a period of 30 months. The record indicates that before the expiry of 30
months, the appellants had terminated the agreement and thereafter the status-
quo order came to be passed by the learned District Judge against both the
parties by consent. The claim thus made for damages by the appellants on the
basis of clause 26(A) was on the face of it not maintainable. In view of such
premature termination, the appellants could not have made any claim for
damages under Clause 26(A). The learned arbitrator acted contrary to the
terms of the contract and thus the award was in conflict with public policy.
The arbitrator was bound to decide in accordance with the contract and in
accordance with Clause 26(A) of the Supplementary Deed and not having done
so, the award is in conflict with the public policy. The learned District Judge
was thus right in setting aside the same.
18. The record produced by the parties also indicates that though the claim
made by the appellants was for damage at the rate of Rs.3,800/- per sq.ft.
whereas the learned arbitrator has considered claim at the rate of Rs.5,000/-.
kvm
ARBP19.09
In my view, the learned arbitrator cannot award more than claim made by a
party. The arbitrator has thus exceeded his jurisdiction by awarding more than
what was claimed by the appellants. The award was on the face of it illegal
and in conflict with public policy. The appellants did not lead any evidence in
support of such claim for damages. The onus to prove such damages was on
the appellants which the appellants had failed to discharge. The learned
arbitrator could not have awarded claim for damages without any such
evidence produced and proved by the appellants. The award was totally
vitiated and was rightly set aside by the learned District Judge.
19. In my view, there is no merit in the submissions made by the learned
counsel appearing for the appellants. In my view, the learned District Judge
has rightly set aside the impugned award and does not require any interference
by this court under Section 37 of the Arbitration and Conciliation Act, 1996.
20. The appeal is dismissed.
21. There is no order as to costs.
22. It is made clear that the parties are free to adopt such proceeding as are
permissible in law.
(R.D. DHANUKA, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!