Citation : 2012 Latest Caselaw 148 Bom
Judgement Date : 9 October, 2012
1 212-arbp-366-09.sxw
dgm
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
ARBITRATION PETITION NO. 366 OF 2009
Union of India,
Represented by the Executive Engineer,
Mumbai Central Division-VI, Central
Public Works Department, Mumbai
ig .... Petitioner
vs
1 A. K. Construction Co.
(A sole proprietary concern)
having its office situated at
Anjanaya, Opp.Hiranandani
School, Orchid Avenue,Powai,
Mumbai 400 076.
2 Shri A. P. Joshi, Arbitrator .... Respondents
Mr. G. Hariharan i/by Mr. Pankaj Kapoor for the petitioner.
Mr. Ajit S. Karwande for respondent No.1.
CORAM: ANOOP V. MOHTA, J.
DATE : October 09, 2012
ORAL JUDGMENT.:
The Petitioner/Union of India has challenged the Award under
Section 34 of the Arbitration and Conciliation Act, 1996 (for short,
Arbitration Act) basically Claim Nos. 4, 69 only. There is no specific
challenge to the other claims. The Respondent/contractor has not
2 212-arbp-366-09.sxw
challenged the rest of the Award.
2 The basic submissions of the learned counsel for the Petitioner
revolve around Clause 12 of the Central Conditions of Contract for
Central P.W.D. Works, 2008 which permits in case of deviation of extra
items and substituted items, pricing part to be adjudicated by the
concerned Engineer. This itself means, there is no bar that in case of
deviation and/or substitution, the contractor, subject to the decision
by the concerned Authority is entitled to claim for extra items.
Admittedly, there was deviation in the work referring to design also.
The decision so given by the Engineer, so far as the work as liable and
the deviated and/or directed to be completed. There is no dispute
that the contractor completed the work as directed from time to time.
The time was extended for about 4 years. There was no restricted
terms and/or conditions for such extension.
3 The learned Arbitrator, therefore, considering the nature of
various civil and construction work and as there arose dispute
between the parties, granted the claims which are under challenge.
4 So far as Claim No.4 is concerned, which are towards the
3 212-arbp-366-09.sxw
balance of payment that substituted items and for extra items of work,
there is no serious dispute with regard to the material placed on
record in support of the claim. The learned Arbitrator, therefore, in
view of above by giving sufficient reason and also by recording the
fact that the work was done as per the direction, awarded the claim at
the rate of 980 per square meter as for similarly placed contractor, the
work in adjacent building, during the same period, the Department
accepted and made the payment accordingly.
5 So far as the claim No.6 is concerned, based upon the statement
of claim and the material placed on record and after considering the
rival contention of the Petitioner again by noting that there was no
denial to the extra work done by the contractor, granted the claim as
prayed. The reason so given in this regard also is well within the
frame work of law and the record and needs no interference.
6 So far as claim No.9 is concerned, the claim was made by the
Respondent/contractor for more than Rs. 38 lacs with losses suffered
into various defaults including prolongation of Respondent's overhead
tools and plants and direct labour. The learned Arbitrator, however,
in view of the admitted position on record that the contract was
4 212-arbp-366-09.sxw
extended without any restricted terms and conditions awarded only
Rs.3,36,029/- towards prolonging of overhead. The reason so given
in view of the admitted position and even considering the provisions
of the law and referring to the judgments of Bombay High Court as
well as Supreme Court cannot be stated to be perverse, contrary to the
record.
The Arbitrator, though interest was claimed at the rate of 21%
per annum, awarded only 8% per annum on the with effect from
20.11.2006 which is the date of demand for the substituted and extra
items of the work including the prolongation of overheads. I see there
is no case made out in this background to interfere with the impugned
award.
8 Resultantly, as the Award is well within the frame work of law
and there is no perversity, no case is made out to interfere with the
impugned Award. The Petition is accordingly dismissed. There shall
be no order as to costs.
(ANOOP V. MOHTA, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!