Citation : 2012 Latest Caselaw 132 Bom
Judgement Date : 8 October, 2012
kvm
1
ARBPL1255.12
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
ARBITRATION PETITION (L) NO. 1255 OF 2012
Prajapati Gunvant Keshavlal )
Having office at 14/21, Ground Floor,)
Mata Prasad Chawl, Galli No.1, )
Koldongari, Andheri (East), )
Mumbai 400 069. ) ..... Petitioner
Versus
1. Union of India through ig )
General Manager, Western Railway, )
Churchgate, Mumbai 400 020 )
2. The Chief Commercial Manager, )
Western Railway, Churchgate, )
Mumbai 400 020 ) ..... Respondents
Mr.Rohan Cama, a/w. Ms.Astha Tamhankar, i/b. Mr.Akash Singh for the
Petitioner.
Mr.Kevic Setalvad, Additional Solicitor General, a/w. Mr.Sumit Patni, i/b.
Mr.Suresh Kumar for the Respondents.
CORAM : R.D. DHANUKA, J.
DATE : 8st OCTOBER, 2012
JUDGMENT :
By consent of both the parties, arbitration petition was heard finally at
the admission stage and is being disposed of by this order. This petition was
heard at length by this Court on 8th October, 2012 and oral order was
kvm
ARBPL1255.12
pronounced in the court dismissing this arbitration petition and that reasons
would be dictated separately. Reasons are now recorded.
2. By this petition filed under Section 34 of the Arbitration and
Conciliation Act, 1996 (in short 'Arbitration Act, 1996'), the petitioner seeks to
challenge an award dated 17th September, 2012 declared by the learned
arbitrator rejecting a claim made by the petitioner.
Some of the relevant facts which are relevant for the purpose of deciding
this petition are as under :-
3. The petitioner is engaged in business of loading and unloading goods,
parcels, etc. from and to railway wagons.
4. On 11th June, 2009, the respondent issued Allotment-cum-Acceptance
letter in favour of the petitioner in respect of the loading of 23 tonnes parcel
space in the parcel van by the Train No. 12925 / 12926 from Bandra Terminus
to Amritsar and back on regular basis for a period of three years. The total
contract value was at Rs.20,10,42,972/-. It was agreed that the payment would
be at Rs.1,90,924/- per trip. The contract commenced w.e.f. 16th June, 2009
and was valid upto 15th June, 2012.
kvm
ARBPL1255.12
5. In the month of March, 2012, the petitioner entered into an agreement
with the respondent w.e.f. 16th June, 2009 pursuant to the said letter of
acceptance dated 16th June, 2009.
6. It is the case of the petitioner that as per the railway administration
letters dated 17th April, 2012, 18th May, 2012, 29th May, 2012 and 9th December,
2011, it was recorded that the performance of the petitioner was satisfactory.
7.
By a letter dated 2nd April, 2012, the petitioner informed the respondent
that the petitioner was successfully completing three years of lease without any
complaints and as per the lease policy dated 28th March, 2006, the petitioner
should be given an opportunity for the extension for two more years at increase
lease freight rate by 25% for the lease of VPH by Train No. 12925/26 Bandra
Terminus - Amritsar.
8. By letter dated 16th April, 2012, the petitioner sent reminder to the
respondent about extension of lease. By letter dated 15th June, 2012, the
respondent informed the petitioner that competent authority had accorded
sanction for temporary extension for a period of three months or till the
finalization of new tender whichever was earlier for VPH on round trip basis
by Train No. 12925/12926 Bandra Terminus - Amritsar at the rate of Rs.
2,38,655/- (current lease + 25%). The respondent requested the petitioner to
kvm
ARBPL1255.12
re-validate the bank guarantee submitted on 28th February, 2009 in favour of
Senior DCM till 27th August, 2012 and also to furnish security deposit for the
period of extended contract plus three months. The petitioner accepted the said
extension on the condition setout therein.
9. On 22nd June, 2012, the respondent invited fresh tenders from the
registered lease holders for leasing of parcel vans (VP) 23 tonnes capacity on
round trip basis on payment of lumpsum rate for loading and unloading of
parcels for a period of three years by various trains including Paschim Express
(Train No. 12925/12926). It is common ground that the petitioner did not
submit his bid in respect of the said tender invited by the respondent.
10. By letter dated 25th June, 2012 to the General Manager, after expiry of
10 days from the date of receipt of acceptance letter, the petitioner contended
that the said temporary extension was against the clause 18.1 of the contract
for VHP by the train Paschim Express and against Clause 13(E) of the lease
policy of the railway dated 28th March, 2006. It is contended that the petitioner
was entitled to further extension of two years. The petitioner requested for
setting aside the tenders invited by the respondent and requested for grant of
two years extension failing which appropriate civil proceedings would be filed
against the respondent.
kvm
ARBPL1255.12
11. By a letter dated 2nd July, 2012, the respondent invited attention of the
petitioner that temporary extension was granted by the respondent to the
petitioner by letter dated 15th June, 2012 for a period of three months or till
finalization of new tender whichever was earlier and the same was
accepted/acknowledged by the petitioner on the same day. The respondent
pointed out that clause 18.1of the agreement and para 'E' of CPLP (policy)
pertaining to the extension in the agreement is only an enabling clause to
extend contracts in cases of exigencies mutually agreed by both the parties. It
was not mandatory or right of the leaseholder to claim extension for two years.
It was stated that in the larger interest of the railway administration, tenders
were being called after three years so that administration could test the market
and explore maximum revenue earning through finalizing contracts by floating
open tenders. It was pointed out that the tenders were already invited and
would be open for the subject train on 17th July, 2012.
12. The petitioner filed Arbitration Petition (Lodging No.851 of 2012) in
this Court under Section 9 of the Arbitration Act, 1996. On 10th July, 2012, this
Court disposed of the said petition. By consent of parties, the General
Manager, Western Railway was directed to appoint an arbitrator within the
period of one week from the date of the said order to decide the disputes raised
by the petitioner as regards the contract dated 16th June, 2009 and directed that
said petition under Section 9 of the Arbitration Act, 1996 filed by the petitioner
kvm
ARBPL1255.12
shall be treated as petition under Section 17 of the Act and shall be disposed of
by the arbitrator within a period of two weeks from the date of his
appointment. This court directed parties to appear before the arbitrator on 20th
July, 2012 at 12 noon to enable the learned arbitrator to pass appropriate
directions in the matter. All rights and contentions of the parties were kept
open.
13. By letter dated 12th / 13th July, 2012, the Deputy General Manager (G),
Western Railway appointed Smt.Bela Meena, Deputy CCM (PM) as the sole
arbitrator pursuant to the order dated 10th July, 2012 passed by this court to
resolve the disputes between the petitioner and the respondent. It is mentioned
that the disputes to be resolved was of extension of lease of VPH by train No.
12925/12926 for two more years from the date 16th June, 2012 to 15th June,
2014.
14. On 27th July, 2012 the learned arbitrator made an interim order under
Section 17 of the Arbitration Act, 1996. After considering the submissions of
the petitioner that the issuance of advertisement for fresh tender by the
respondent was contrary to the clause 18.1 of the contract agreement, the
learned arbitrator passed the following order :-
" I have examined the issue and found that Respondents are at a liberty to call for fresh tenders at the end of the contractual term to avoid
kvm
ARBPL1255.12
the revenue loss. The fresh tender has been opened on 17.7.202 and offers higher than the
Reserve Price have been received, but the same are yet to be finalized by the Respondents. The
Respondents have also given a temporary extension for the running lease contract operated by the Claimant for a period of three months and as such there will be a committed earning to
Railways and no loss for the said extended period to the government exchequer.
As the Hon'ble High Court of Bombay has directed that the present Petition filed by the
Claimant under section 9 of the Arbitration and Concilliation Act, 1996 ("the Act") shall be treated
by the learned Arbitrator as a Petition under Section 17 of the Act and shall be disposed of by him within a period of two weeks from the date of
his appointment, to avoid casing prejudice to either parties, and having considered all aspects, I am of the opinion that the interest of justice would meet to both the parties by following directions :
The Respondents are free to invite fresh
tender and finalize the same, however allotment of which would be subject to final award in the present Arbitration. The
Operation of lease in VPH by train 12925/26 ex BDTS-ASR by the Petitioner permitted by Respondents vide their letter No.C128/12/VPH/Tender 17.10.08(2925/2926) Vol I dated
15.06.2012 will continue till disposal of Arbitration. "
15. The petitioner did not challenge the said interim order which granted
liberty to the respondent to invite fresh tenders and to finalise the same with a
rider that allotment of the contract would be subject to final award in the
present arbitration.
kvm
ARBPL1255.12
16. On 23rd August, 2012, the petitioner filed statement of claim before the
learned arbitrator making six claims including claim for extension of lease of
VPH by Train No. 12925-12926 for two years from the date of 16th June, 2012
to 15th June, 2014. The respondent filed written statement opposing the said
claims. The arbitration meeting was thereafter held on 23rd August, 2012. The
learned arbitrator recorded that it was mutually agreed by the parties that mode
of arbitration proceedings would not be oral and shall be conducted on the
basis of documents only. The next date of the hearing was fixed on 30th
August, 2012. The minutes of the said meeting was served upon both the
parties by the learned arbitrator and has been accepted by the parties by
acknowledging the same.
17. On 30th August, 2012 in the arbitration meeting, it has been recorded by
the learned arbitrator that as regards framing of issues, it has been decided by
the sole arbitrator that the only claim falling under the purview of sole
arbitrator was the extension of lease of VPH by Train No. 12925/26 for two
more years from the date 16th June, 2012 to 15th June, 2014 was the only issue
made admissible and the same had been advised to the parties. The learned
arbitrator fixed the next date of hearing of 5th September, 2012.
18. On 5th September, 2012, by consent of both the parties, it was decided
that evidence would be filed by the petitioner on 7th September, 2012 and the
kvm
ARBPL1255.12
respondent had agreed to cross examine the witness on the same day. The
next date of the meeting was fixed on 7th September, 2012.
19. On 7th September, 2012, the petitioner submitted that due to some
casualty in the family of his advocate, his advocate had to leave for Benaras
and the petitioner therefore was unable to file evidence on the date of hearing.
The petitioner, however, requested the learned arbitrator to permit the brother
of the petitioner Mr.Hasmukh Prajapati to depose in the further arbitration
proceedings. The respondent submitted their no objection to the said request
made by the petitioner. The learned arbitrator accepted the request of the
petitioner and adjourned the matter to 10th September, 2012. The learned
arbitrator recorded the statement of the respondent that new tender for the train
in question had been finalised and requested the learned arbitrator to expedite
the arbitration proceedings. The learned arbitrator directed the respondent to
submit the copy of the allotment letter and acceptance letter on record.
20. On 10th September, 2012, the arbitration meeting was attended by the
brother of the petitioner pursuant to the liberty asked for by the petitioner in
the meeting held on 7th September, 2012 and granted by the learned arbitrator,
alongwith the representative of the petitioner's advocate. The petitioner
submitted a request in writing for one week to file evidence on the same
ground. The learned arbitrator adjourned the meeting on 13th September, 2012.
kvm
ARBPL1255.12
21. On 13th September, 2012, the petitioner attended the meeting alongwith
his counsel. The learned counsel made submission that certain stages of
proceedings of arbitration as per Code of Civil Procedure were yet to be
complied with by the learned arbitrator. In the minutes of the said meeting, the
learned arbitrator recorded what transpired in some of the earlier meetings
about the procedure followed by both parties and recorded in the minutes of
the meeting duly endorsed by the petitioner as well the respondent. The
learned arbitrator recorded that though in the hearing held on 5th September,
2012 it had been clearly mentioned that by mutual consent, it has been decided
that the evidence will be filed on 7th September, 2012, the petitioner once again
by his application dated 10th September, 2012 requested for one week time to
file affidavit. The learned counsel appearing for the petitioner accepted the
fault of the petitioner that the petitioner was raising an issue of formal framing
of issues and admissibility of documents at a delayed stage wherein they had
earlier submitted a request for filing of evidence. The learned arbitrator
advised the claimant through his counsel to go through all the record sheets
with emphasis on the record sheet of 30th August, 2012 wherein framing and
admissibility of issues had already been discussed. The learned arbitrator once
again permitted the respondent to submit his say on the admissibility of
documents by 05.00 p.m. on 13th September, 2012 and directed the claimant to
submit draft issues at 05.00 p.m. on 14th September, 2012. The learned
arbitrator however conveyed categorically that the only issue was "Extension
kvm
ARBPL1255.12
of lease of VPH by Train No. 12925/12926 for two more years from 16th June,
2012 i.e. upto 15th June, 2014". The learned arbitrator rejected the application
of the petitioner for amendment of statement of claim on the ground that such
reference had already been discussed in the meeting held on 30th August, 2012.
22. On 13th September, 2012 at 05.00 p.m., the respondent admitted some of
the documents submitted by the petitioner and denied the remaining
documents. On 14th September, 2012, the learned arbitrator recorded that issue
was framed during the hearing on 30th August, 2012 and was conveyed to the
petitioner. It was recorded that the petitioner had agreed to file evidence on 7th
September, 2012 during the hearing held on 5th September, 2012 and since the
advocate of the petitioner was not able to appear for hearing on 7th September,
2012, time for filing evidence was granted till 10th September, 2012. On 10th
September, 2012, further time was granted on the request of the petitioner to
file evidence on 13th September, 2012. On 13th September, 2012, inspite of
filing evidence, the petitioner raised issue about admissibility of documents
and framing of issues. As regards framing of issues, the learned arbitrator
once again conveyed the issue to the parties. It was recorded that already three
opportunities were granted to the petitioner for filing evidence. The learned
arbitrator directed the petitioner to avoid any further delaying tactics and co-
operate with the arbitrator for conducting hearing. The learned arbitrator gave
last opportunity to file evidence in the meeting supposed to be held on 15th
kvm
ARBPL1255.12
September, 2012.
23. On 13th September, 2012, the petitioner mentioned Arbitration Petition
No. 785 of 2012 before this Court. After hearing the learned counsel appearing
for the parties, this Court modified the order dated 10th July, 2012 by consent.
The operative part of the said order reads as under :-
(a) The dispute as regards the extension of lease
for VPH by Train No.12925/26 for two more years i.e. from 16th June, 2012 to 15th June, 2014 shall be
treated as one independent reference and decided by the sole Arbitrator i.e. Ms.Bela Meena, Deputy Chief Commercial Engineer (PM). Needless to add
that the arbitration proceedings shall be conducted by following the provisions laid down under the Arbitration and Conciliation Act,1996.
(b) As regards the other disputes raised/proposed to be raised by the Petitioner regarding the Contract
dated 16-06-2009, the same shall be referred to another Arbitrator by the General Manager, Western Railways, within two weeks from today.
The said reference shall be an independent reference, which shall be decided by the Arbitrator so appointed by following the provisions laid down under the Arbitration and Conciliation Act, 1996. The Arbitrator shall endeavour to pass
his award within a period of six months from today.
24. On 14th September, 2012, the respondent conveyed the decision of the
Deputy CMM (PM) to the petitioner that leasing contract in question would be
continued till the disposal of the pending arbitration case. On 15th September,
2012, neither the petitioner nor his advocate was present and failed to
kvm
ARBPL1255.12
communicate any sufficient reasons for their failure to appear for hearing on
15th September, 2012. The learned arbitrator after going through the records,
the documents submitted by the parties was convinced that there was enough
evidence before the arbitrator to proceed with the arbitral award, concluded the
hearing and adjourned the proceeding to 17th September, 2012 for making
arbitral award.
25. On 17th September, 2012, the petitioner through his advocate to the
learned arbitrator contended that on 13th September, 2012, neither the issues
were farmed nor settled and therefore there was no question of leading
evidence on 15th September, 2012 . The petitioner contended that the learned
arbitrator was not following the principle of natural justice. The petitioner
requested the learned arbitrator to fix a date for framing of issues. On 17th
September, 2012 by another letter the petitioner made certain allegations
against the arbitrator and requested the respondent to change the learned
arbitrator and to refer the further claims referred therein and other claims to a
different arbitrator. The petitioner referred to the order passed by this court on
13th September, 2012.
26. On 17th September, 2012, the learned arbitrator declared an award
rejecting the claim for extension of lease made by the petitioner.
kvm
ARBPL1255.12
27. Being aggrieved by the said impugned award dated 17th September,
2012, the petitioner has filed this petition under Section 34 of the Arbitration
Act, 1996. The petitioner also filed petition under Section 9 of the Arbitration
Act, 1996 (Lodging No. 1254 of 2012) interalia praying for a direction to the
respondent to continue order dated 27th July, 2012 passed by the learned
arbitrator.
28. Clause 18.1 of the agreement reads thus :-
18.1 Extension of lease is permissible only in
case of long term lease of 3 years wherein the same can be extended only once, by 2 more years at a lease rate of 25% more than the lumpsum leased freight rate subject to satisfactory performance by
the leaseholder, without any penalty for overloading or violation of any provision of the
contract.
29. Clause (E) of the lease policy framed by the Government of India,
Ministry of Railway (Railway Board) lease policy No.12/06 which is
applicable to the facts of this case is extracted below :-
(E) Extension of Lease :
1. Extension of lease is permissible only in case of long term lease of 3 years.
2. In case of Long Term Lease, on expiry of the contract period, the same can be extended only once, by 2 more years at a lease rate of 25% more than the lumpsum leased freight rate.
kvm
ARBPL1255.12
3. Such extension will be subject to satisfactory performance by the lease holder, without any
penalty for overloading or violation of any provision of the contract.
4. In case of expiry of contract period and non- finalization of new contract due to administrative delays, temporary extension can be permitted by
the CCM only once, for a period of 3 months.
30. The learned counsel appearing for the petitioner made the following
submissions :-
(a)
The learned arbitrator has proceeded ex-
parte against the petitioner and has not given equal
opportunity to the petitioner to represent his case,
to file affidavit of evidence, an opportunity of
being heard, by not framing issues, by
discriminating and not treating both the parties
equally.
(b) The arbitrator was totally biased.
(c) The learned arbitrator who was Deputy
CCM (PM) was junior in rank to the Chief
Commissioner Manager, Western Railway whose
order refusing to grant extension of lease was being
subject mater of the arbitration and thus the learned
kvm
ARBPL1255.12
arbitrator in ordinary course would not have acted
impartially while deciding the claims made by the
petitioner.
(d) The learned arbitrator was making
unwarranted comments against the petitioner
during the course of the hearing.
(e) The learned arbitrator placed reliance of the
judgment of the Supreme Court in case of
Mallikarjun vs. Gulbarga University1 and in case
of Indian Oil Corporation Limited and others vs.
Raja Transport Private Ltd.2 in support of his plea
which are not applicable.
(f) The learned arbitrator did not consider Claim
Nos. 2 to 6 though referred to the learned arbitrator
and were made in the statement of claim and dealt
with by the respondent in written statement. The
learned arbitrator has thus not decided in
accordance with the disputes referred to her by the
parties.
1 (2004) 1 SCC 372 2 (2009) 8 SCC 520
kvm
ARBPL1255.12
(g) The learned arbitrator has not considered the
matter on merits and not followed the judgments of
Delhi High Court, Calcutta High Court and Patna
High Court in similar matters which were forming
part of the record before the arbitrator.
(h) It is submitted that the Bombay High Court
judgment in case of M/s.Airwide Express Cargo
vs. Union of India delivered on 3rd December,
2010 in Writ Petition (L) No. 2604 of 2010 was not
relied upon by the parties. The judgment of the
Bombay High Court in case of M/s.Airwide
Express Cargo was in the writ petition and not in
the arbitration matter. Power of this court under
Article 226 of the Constitution of India was
considered in the said judgment. The said
judgment was thus distinguishable in the facts of
this case.
(i) The learned counsel for the petitioner also
placed reliance on the judgment of Calcutta High
Court in case of M/s.S.G.Traders and another vs.
Union of India & Ors. in Writ Petition No.
kvm
ARBPL1255.12
23926(W) of 2007 and in support of his plea that
the Calcutta High Court after following the
judgment of Delhi High Court and Patna High
Court had directed the railway to extend the lease
agreement by a period of two years after
interpreting the similar clause which is the subject
matter of this proceedings.
(j)
The learned counsel also placed reliance on
the order passed by this Court in Writ Petition Nos.
1266 of 2010 and (L) No. 2810 of 2010.
31. The learned Additional Solicitor General appearing on behalf of the
respondent on the other hand made following submissions :-
(a) The petitioner had no vested right provided
under the contract nor under any law to get
extension of contract for any period. Under Clause
18.1 of the contract, the respondent has been given
a discretionary power to grant extension and the
same is enabling power. The said power does not
confer any right in the contractor to seek extension
of lease. Comprehensive partial lease policy of
2006 which is admittedly applicable to the contract
kvm
ARBPL1255.12
in question provides that in case of expiry of
contract period and non finalization of the new
contract due to administrative delay, temporary
extension can be permitted by the CCM only once
for a period of three months.
(b) It is submitted that the respondent have
already invited fresh tenders and have already
issued letter of acceptance. According to the
policy, till such period when finalization of new
contract is pending and is delayed due to any
administrative reasons, with a view to protect the
revenue of the respondent, such temporary
extensions are permitted at the discretion of the
respondent for a limited period of three months on
conditions. It is submitted that such provision is
thus not mandatory.
(c) The Learned Solicitor General placed
reliance on the judgment of this court delivered on
3rd December, 2010 in case of M/s.Airwide
Express Cargo vs. Union of India, through
kvm
ARBPL1255.12
General Manager, Western Railway & Anr in
Writ Petition (L) No.2604 of 2010, judgment of
Madras High Court in case of Green Express
Division of Green Carriers and Contractors
(Delhi) Pvt. Ltd. vs. The Chief Traffic Manager
decided on 12th November, 2010 in Writ Petition
No. 9734 and 12239 of 2010. Reliance is also
placed on the other judgments of this court
forming part of the record in which identical
provisions have been considered and in all such
cases contractors were allowed to continue for a
temporary period till tenders invited by the
respondents were finalised. It is submitted that all
these judgments delivered by the Bombay High
Court were binding on the learned arbitrator as
also parties.
(d) The learned Arbitrator has given sufficient
opportunity of producing documents, hearing and
adducing oral evidence to both the parties. Issues
were framed on 30th August, 2012 which fact was
recorded in the Minutes of Meeting conducted by
kvm
ARBPL1255.12
the learned Arbitrator. The minutes were served
upon both the parties at the same time and duly
acknowledged by both the parties.
(e) The petitioner, after obtaining extension of
contract under application made under Section 17
of the Arbitration Act 1996 was delaying the
arbitration proceeding on one or other frivolous
ground.
(f) In view of the order dated 13th September
2012 passed by this Court thereby modifying its
order dated 10th July 2012 and restricting the
reference of dispute as regards extension of lease
for two more years and referred to the learned
Arbitrator Mrs Bela Meena, the only issue
regarding extension of lease was the subject matter
of reference which was forming part of claim No.1
filed by the petitioner. The learned Arbitrator thus,
was not required to consider claim Nos.2 to 6 in
the same award. The petitioner was free to take
appropriate steps for appointment of another
kvm
ARBPL1255.12
Arbitrator for referring claim Nos.2 to 6 and all
other claims in respect of the disputes that had
arisen, if any, according to the petitioner. The
learned Arbitrator was thus, justified in deciding
only one claim in view of the order dated 13th
September 2012 passed by this Court. It is
submitted that the respondents have no objection if
claim Nos.2 to 6 are referred to another Arbitrator
as directed by this Court by order dated 13th
September 2012 in accordance with the provisions
of law and the contract entered into between the
parties.
(g) The petitioner has never raised any issue of
bias against the learned Arbitrator at any point of
time in any of the correspondence and/or
submissions made before the learned Arbitrator.
The petitioner also did not raise any issue about
competency of the learned Arbitrator to act as
Arbitrator, she being junior to the Chief
Commercial Manager, Western Railway and whose
order refusing the grant of extension of contract
kvm
ARBPL1255.12
was being the subject matter of the arbitral
proceeding. It is submitted that by an order dated
13th September 2012, this Court by consent of both
the parties had modified its earlier order dated 10th
July 2012 and had referred the dispute as regards
the extension of lease to Mrs Bela Meena, Deputy
Chief Commercial Manager. The petitioner,
therefore could not challenge the appointment of
the learned Arbitrator across the bar that she being
the junior in rank and could not have acted as an
Arbitrator when order passed by the Chief
Commercial Manager was in issue before her. It is
submitted that none of these grounds are even
raised in the present petition and therefore cannot
be allowed to be agitated across the bar for the first
time.
(h) By letter dated 15th June 2012, the
respondent had granted extension of lease period
for a period of 3 months or till finalization of lease
tender whichever was earlier on payment of
correct lease rent plus 25%. It is submitted that
kvm
ARBPL1255.12
petitioner accepted such extension for a period of 3
months and thus waived his right to challenge the
said extension. It is submitted that even interim
order passed by the learned Arbitrator on 27th July
2012 was also operative for a limited period till
disposal of the arbitral proceeding, granting
liberty to the respondents to invite fresh tenders
and finalize the same, with a rider that the
allotment being made subject to final award in the
arbitral proceedings. Even this interim award
permitting the respondent to invite fresh tenders
and to finalize the same has been accepted and not
challenged by the petitioner. It is submitted that
the petitioner did not bid for the same work,
knowing fully well that the price of the bid which
would be received by the respondents would be
obviously much higher amount than the price for
which contract was awarded to the petitioner.
(i) The petitioner deliberately failed to remain
present in the meeting held on 15th September,
2012. The learned Arbitrator was justified in
kvm
ARBPL1255.12
closing the hearing and in declaring an award on
17th September 2012 after considering the
pleadings, documents made available on record
and the judgment of this court. The petitioner thus
cannot make any grievance of non compliance of
principles of natural justice. The petitioner having
remained absent deliberately without any prior
intimation or without giving intimation and
without sufficient reasons cannot be permitted to
challenge the award on the ground that no
opportunity was given to make submissions or to
file affidavit by the learned Arbitrator. The
petitioner has waived his right to challenge the
jurisdiction of the learned Arbitrator.
32. I have heard the learned counsel and have given my anxious
consideration to the rival submissions made by the learned counsel.
33. Order dated 13th September, 2012 passed by this Court indicates that the
said order was passed by consent and order dated 10th July, 2012 was
modified. The learned Arbitrator was appointed to adjudicate upon the dispute
as regards the extension of lease for two more years. It was provided that it
kvm
ARBPL1255.12
shall be treated as independent reference and to be decided by Mrs Bela
Meena, Dy. Chief Commercial Manager. In my view, it is thus clear that only
one claim which was referred to the learned Arbitrator by consent has been
rightly decided by her in the impugned award. Claim Nos.2 to 6 made by the
petitioner thus were rightly not decided by the learned Arbitrator. The order
dated 13th September 2012 indicates that all other disputes raised/proposed to
be raised regarding the contract dated 16th June 2009 shall be referred to
another Arbitrator by the General Manager, Western Railway within two weeks
from the date of the said order and the said reference shall be independent
reference. The petitioner has not taken any steps to get another Arbitrator
appointed in respect of such dispute raised/proposed to be raised including
Clause Nos.2 to 6.
34. Perusal of the record as well as grounds raised in the petition indicate
that no allegation of bias and/or about her alleged incapacity to act as an
Arbitrator she being junior in rank to the Chief Commercial Manager has been
raised at any point of time in the correspondence with the respondent, with the
arbitrator or even in this petition.
35. The petitioner has also not filed any application under Section 12 and 13
of the Arbitration Act 1996 before the learned Arbitrator challenging her
appointment on any of these grounds or impugning bias against the learned
kvm
ARBPL1255.12
Arbitrator. On the contrary, appointment of the learned Arbitrator was by
consent of parties as is apparent from the order dated 13th September, 2012
passed by this Court. The petitioner not having raised any such pleading of
bias and/or jurisdiction of the learned Arbitrator before the learned Arbitrator
or even in the present proceeding, cannot be allowed to agitate such issues for
the first time across the bar.
36. The next question arise for consideration of this Court is whether the
learned Arbitrator was right in refusing to grant relief to the petitioner seeking
an extension of lease for further period of two years. Perusal of Clause 18.1
of the contract indicates that grant of extension of lease by the respondents is
not mandatory but is discretionary. Clause18.1 read with para (E) of the
Comprehensive Parcel Leasing Policy 2006 which is applicable to the facts of
this case clearly indicates that in case of expiry of contract period and non
finalization of lease contract due to administrative delays, temporary extension
can be permitted by the Chief Commercial Manager only once, for a period of
3 months. In my view from the perusal of the said policy, it is clear that
though the respondents in appropriate cases can grant temporary extension for
a period of 3 months if any administrative delay is occasioned in finalization of
lease contract so as to protect the revenue of respondents, in my under Cl.18.1
read with para (E) of the Comprehensive Parcel Leasing Policy 2006, no right
of any nature whatsoever is vested in favour of the contractor for seeking
kvm
ARBPL1255.12
extension of lease as a matter of right. The said provision is enabling
provision and gives discretion to the respondents to grant extension for a
period of 3 months and that also only once due to administrative delay in
finalization of lease contract. Whether such discretion to grant temporary
extension till the lease contract is finalized or not, shall be exercised or not
exclusively vests with the respondents. The findings of the learned Arbitrator
thus, in my view, cannot be faulted with and does not require any interference.
37.
This Court in number of writ petitions had occasion to consider the
identical clauses in the contract and the policy. The Division Bench of this
Court in case of M/s. Airwide Express Cargo (supra) after considering Clause
20.1 which is in para materia with Clause18.1, considering the policy of the
Ministry of Railways which was under consideration in this matter after
following the earlier orders passed by the Division Bench of this Court dated
13th April 2010 and 28th October 2010 has held in para 8 as under :
8. ... The rate which has been accepted by the Western Railway of Rs.2,32,560/- per round trip is
almost double the rate which was quoted by the Petitioner and accepted for the contract which was entered into in 2006. The Petitioner has had the benefit of not only the period of the original contract of 2006-09 but as a result of the interim order of status quo that was passed by the City Civil Court, the Petitioner continued thereafter, at the same rate until 25 November 2010. There is no vested right to extension or renewal of the contract. Having regard to all these circumstance, we do not consider that it would be either
kvm
ARBPL1255.12
appropriate or proper for this Court in the exercise of the writ jurisdiction to direct that the contract of
the Petitioner should be continued on the same terms and conditions. Whether the existing parcel
van which was allotted to the Petitioner should be continued or discontinued and if it is continued whether it should be at existing rates, is a matter which is not within the jurisdiction of this Court
under Article 226 of the Constitution.
38. The Madras High Court in case of Green Express Division of Green
Carriers and Contractors (Delhi) Pvt. Ltd. (supra) has distinguished the
judgment of the Delhi High Court and Patna High Court relied upon by the
petitioner. The Madras High Court has construed the expression "can" used in
Clause 18.1 and Clause E of Freight Marketing Circular No.12 of 2006 and in
para 45 has held thus :
45. In these writ petitions, as already stated above,
there is no public good or benefit of others are involved. It is purely a matter of contract and commercial transaction. Therefore, one should look into the actual words used in the
contract/agreement. Hence, there is no warrant for reading "can" as "shall" or "must". Thus the Petitioners are not entitled to automatic extension of lease period. Issue No.2 is answered accordingly.
39. In my view, the learned Arbitrator was bound to follow the law laid
down by this Court in various judgments and has declared the award in
accordance with the law and contract. In my view there is no infirmity in the
impugned award and thus no interference is warranted with the impugned
award.
kvm
ARBPL1255.12
40. The record produced by the parties also indicates that the learned
Arbitrator had given sufficient opportunity to both the parties to file evidence,
issues, to plea and argue their respective cases, by granting sufficient
adjournments. From the record it is clear that the conduct of the petitioner is
totally blameworthy. After obtaining interim order under section 17 of the
Arbitration Act, the petitioner was bent upon to delay the arbitral proceedings
on one or the other ground obviously for the reason that temporary extension
of contract granted by the learned Arbitrator would operate till the proceedings
disposed of at a lower rate. The petitioner did not even submit his bid in
respect of the tenders invited by the respondents for the same work. The
learned additional Solicitor General was right in his submission that these
delay tactics played by the petitioner were to continue the benefit of the lower
rate being paid to the respondents by the petitioner as against the bid for higher
amount that was received by the respondents for the same work. In my view,
the only issue required to be decided by the learned Arbitrator was as to
whether petitioner was entitled to be granted the extension of lease for a further
period of two years under Cl.18.1 read with para E of the 2006 policy which
did not require any oral evidence, framing of any additional issues though
issues was already framed by the learned Arbitrator in this case. The learned
Arbitrator thus, has rightly decided the said issue by interpreting the terms of
contract and the policy and after following the judgments delivered by this
Court. In my view, there was no violation of principles of justice committed
kvm
ARBPL1255.12
by the learned Arbitrator.
41. Perusal of minutes of meeting submitted by the petitioner himself
indicates that sufficient opportunity was given to the petitioner. In my view, no
prejudice was caused to the petitioner due to shorter adjournments granted by
the learned Arbitrator to submit issues, affidavit of evidence or for arguments.
In my view, the learned Arbitrator is justified in granting shorter adjournments
in view of the facts that respondents had already invited the tenders as far back
in July 2012 and letter of acceptance was being issued. Any further delay in
conclusion of the arbitral proceedings was causing a loss and prejudice to the
respondents and in favour of the petitioner. The entire issue was to be decided
on interpretation of the terms and conditions of contract and the policy. If by
granting shorter adjournments ultimately if the parties have not suffered any
injustice or if no prejudice is caused, in my view it cannot be considered as
violation of principles of natural justice. The petitioner has failed to
demonstrate any substantial prejudice caused to the petitioner by not
submitting affidavit of evidence or number of issues not having framed by the
learned Arbitrator as demanded by the petitioner. The issue required to be
decided by the learned Arbitrator was limited issue which could be decided
based on the interpretation of the documents submitted by the parties and in
line of principles laid down by this Court in various judgments. In my view
thus there is no substance in any of the grounds raised in the petition. The
kvm
ARBPL1255.12
learned Arbitrator has interpreted the terms of contract and has followed the
interpretation of this court in various judgments. The Judgments delivered by
this Court are binding not only on the parties but also on the learned Arbitrator.
The learned Arbitrator has acted in accordance with law and thus this Court
cannot interfere with the said award.
42. Resultantly, Arbitration Petition (L) No.1255 is rejected. There shall be
no order as to costs.
(R.D. DHANUKA, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!