Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Mahindra Lifespace Developers ... vs Biecrete Project Private Limited
2012 Latest Caselaw 399 Bom

Citation : 2012 Latest Caselaw 399 Bom
Judgement Date : 27 November, 2012

Bombay High Court
Mahindra Lifespace Developers ... vs Biecrete Project Private Limited on 27 November, 2012
Bench: Anoop V.Mohta
     ssm                                   1                                arbp406.09

               IN THE HIGH COURT OF JUDICATURE AT BOMBAY                                  
                 ORDINARY ORIGINAL CIVIL JURISDICTION




                                                                             
                 ARBITRATION PETITION NO. 406 OF 2009




                                                    
     Mahindra Lifespace Developers Limited,
     A Company incorporated under the 
     Provisions of the Companies Act, 1956,




                                                   
     Having its registered office at 
     5th Floor, Mahindra Towers, Worli,
     Mumbai-400 018.                                          .....Petitioners. 




                                       
                  Vs.
                        
     Biecrete Project Private Limited,
     A Company incorporated under the
     Provisions of the Companies Act, 1956,
                       
     Having its registered office at
     10, Gulam Hussain Mansion,
     Bhardawadi Lane, S.V. Road,
     Andheri (West), Mumbai-400 058.                       ....Respondents.
      


                                            ---
     Mr. Percy Modi, Senior Counsel a/w Mr. Nemil a/w Samindra 
   



     Surve   a/w   Mr.   Nirav   Shah   i/by   M/s.   Little   &   Co.   for   the 
     Petitioners.
     Mr.   Suresh   Gupte   a/w   Mr.   Devurat   Dhankar   Singh   i/by   Mr. 





     Sudheer S. Phadke for the Respondents.
                                            --- 
                                       
                                        CORAM    :  ANOOP V. MOHTA, J.

JUDGMENT RESERVED ON : 22 OCTOBER, 2012 JUDGMENT PRONOUNCED ON : 27 NOVEMBER,2012

ORAL JUDGMENT :-

1 The Petitioners original-Respondents have challenged award dated 20 February 2009, passed by the sole

ssm 2 arbp406.09

Arbitral Tribunal, under Section 34 of the Arbitration and

Conciliation Act, 1996 (for short, the Arbitration Act).

2 The conclusion of the final award is as under:-

"1 As a Sole Arbitral Tribunal I have jurisdiction to try, entertain and decide all the disputes

arising in this matter.

2 The Claims of the Claimants are not barred by limitation.

3 The Counter Claims of the Respondents are

barred by limitation.

4 The Claimants have proved their claim to the

extent of Rs.64,73,533/- for the work of Phase I and Phase II.

5 As the Claimants have restricted their claim

to the extent to the security deposit and retention money to the tune of Rs.44,75,590/- for Phase I work. I allow the claim to that extent only.

6 The Claimants are further entitled to receive

Rs.10,24,553/- for the work under Phase-II. 7 In the aforesaid discussion, I allow the claim of the Claimants partly by holding their entitlement to receive Rs.55,00,143/- from

the Respondents with interest @ 9% p.a. from the date of invocation of the arbitration i.e. 9.3.2005 till payment or realisation. I have dismissed the whole counter claim for the reasons recorded hereinabove.

Parties to bear their own costs."

3 The basic facts as per the Petitioners are as under:-

The Petitioners Company is in the business of development of immovable property and sale of flats/premises.

ssm 3 arbp406.09

The project in question was called "Mahindra Gardens" at

Goregaon. The Petitioners invited tenders for a construction of super structure and sub-structure of buildings. By Letter of

Intent (for short, LOI) dated 27 January 1999, the Respondents' tender was accepted. On 13 May 1999, the Agreement executed between the parties for Phase-I. Clause 2 expressly

incorporates the terms of tender, drawings, conditions of contract, specifications, BOQ and LOI.

4 The Respondents did the phase I construction work,

but delayed the same. The Respondents were awarded three

fresh contracts for "Phase-II" also :-

a) Work order dated 23 December 1999 for B3 - B4 Sub-structure.

b) Work order dated 13 April 2000 for A1 sub and

super structure.

c) Work order dated 10 May 2000 for B3 - B4 Super

structure.

5 The Respondents abandoned Phase II without

completing it. The Respondents only cast one slab of B4 and two slabs of B3 out of 8 slabs each as required under the work order. The Petitioners had to get the work completed through

other contractors.

6 The BMC issued occupation Certificates (for short, "OC"):-

a) On 14 September 2000, for A2 - A3 (Phase I)

b) On 29 June 2000, for B1-B2 (Phase I)

c) On 13 November 2001 for A1, B3 and B4 (Phase II).

ssm 4 arbp406.09

On 23 July 2001, Phase I had been completed in stipulated

time.

7 The Respondents allege that the last payment by the Petitioners was on 18 January 2002. All the work was completed in 2001 the payment should have been made by the

end of the 2001. On 9 March 2005, the Respondents invoked the Arbitration clause. On 20 January 2006, the Respondents

filed a Statement of claim for Rs.46.5 lakhs for phase I and Rs.22.5 lakhs for Phase II, as balance due. The last and final

Certificates of payment for phase I is dated 14 October 2000

and for Phase II the last Certificates of Payment is dated 25 February 2002.

8 The Petitioners filed an application to decide a point

of limitation as a preliminary issue. The Respondents filed its reply. The Petitioners filed rejoinder. The plea of limitation was rejected by order dated 17.7.2006, holding inter alia in

para 6 that the Respondents would confine its claim only to refund of security deposit and retention money, (since the right to claim the same would be after the defect liability period of

one year after the completion of the construction.)

9 On 28 September 2006, the Petitioners' Petition against the above order was disposed of by this Court by holding that the Petitioners would be at liberty to challenge the

ssm 5 arbp406.09

same along with the final award. On 17 October 2006, the

Petitioners filed their Written Statement and denied any liability to the Respondents and also counter claimed for the delay,

defective and abandonment of work (Rs.76.5 lakhs + Rs.41.6 lakhs + Rs. 50 lakhs). On 10 November 2006, the Respondents filed rejoinder and reply to counter claim. The evidence was

led by both the parties. The Written submissions were also filed. The award was on 20 February 2009 and corrected on 24

March, 2009.

Following three claims have been considered and

awarded by the Arbitral Tribunal-

(a) Claim for Phase I,

(b) Claim for Phase-II, and

(c) Interest.

11 The counter-claim of the Petitioners was rejected.

The main challenge and submissions made by the learned counsel appearing for the parties are on the following points.

i) Bar of Limitation

ii) Lack of jurisdiction.

iii) Challenge to claim for phase-I & II Work on merits.

iv) Challenge to rejection of counter-claim on merits.

BAR OF LIMITATION:-

12 The cause of action accrued for Phase-I on completion of work by Occupation Certificate issued by MCGM on 14 September 2000 for Building Nos. A-2 and A-3 and on 29

ssm 6 arbp406.09

June 2000 for Building Nos. B1 and B2 (Phase-1.) The cause of

action accrued for Phase-II on completion of work on 13 November 2001 (for Building Nos. A1, B3 and B4, Phase-II).

13 The Arbitration clause was invoked on 9 March 2005, admittedly, after more than 3 years. The learned

Arbitrator has held and considered 23 July 2001 as date of completion of Phase I work and 31 March 2002 as date of

completion of Phase II work. The amount of Rs.44,75,590/- so retained was payable on 23 July 2001, within one year of

completion of the work as per the agreement. The Arbitration

clause was invoked on 9 March 2005 and restricted the claims. Phase-II work was completed on 31 March 2002, subject to the defect liability period, expired on 31 March 2003. The Claim so

filed on 9 March 2005 was in time as per the Arbitrator.

14 Even as per Section 19 of the Limitation Act, 1963, (for short, "the Limitation Act"), the learned Arbitrator has

accepted the Respondents' case of part payments both in respect of Phase-I and Phase-II, within the period of limitation. The same were on 1 November 2002 and 6 December 2002.

15 There is no denial to the payment made by the Petitioners to the third parties on behalf of the Respondents' debt. From time to time, as recorded, such payments were made directly to the third person on behalf of the Respondents

ssm 7 arbp406.09

and the amount was debited and adjusted in the account of

Respondents, based upon the various certificates. The Respondents were also regularly issued such authorization

letters to the Petitioners to make such payment. The learned Arbitrator has accepted this evidence as it was permissible mode and practice between the parties to make the payment on

account of Respondents' debt. In my view, this is sufficient to cover the case of acknowledgment of payment in writing,

basically when the payment was made by the Petitioners directly and debited the same from the account of Respondents'

debts. The adopted practice and the receipt and the admission

of payment itself, falls within the ambit of "acknowledgement of payment in writing". The evidence so led by the parties through their respective witnesses (Mr. R.L. Gandhi, for the Petitioners)

supports the payment from time to time under the specific

vouchers.

16 This payment and acknowledgement, in my view,

falls within the ambit of Section 19 as elaborated by the

Supreme Court in Sant Lal Vs. Kamala Prasad 1 . Therefore, I am declined to accept the contention raised by the learned

counsel appearing for the Petitioners that, this payment was not on account of debt and not by the person liable to pay the debt and there was no acknowledgement of the payment in handwriting of or signed by the payer. The material so appreciated by the Arbitral Tribunal in this regard in no way can 1 AIR 1951 S.C. 477

ssm 8 arbp406.09

be stated to be contrary to the law and/or perverse. It is well

within the framework of law and the record. Therefore, taking overall view of the reasonings given, based upon the material

placed on record, there is no case made out to interfere with the award on this ground.

JURISDICTION

17 The terms and conditions including the Arbitration

clause for Phase-I work, in the facts and circumstances, in my view, also extended for phase-II work in view of the work order

dated 13 April 2000 itself, though there was no specific

incorporation of the entire contract terms. All terms and conditions in the tender form is part of LOI. Therefore, the corporation of the words "All other terms and conditions shall

remain the same as mentioned in LOI dated 27 January 1999"

itself make the position very clear and so also the understanding between the parties. This is a commercial agreement. The contention of the work, whichever the nature, but if based upon

the same terms and conditions, I am inclined to observe that there was Arbitration clause to resolve and settle the dispute between the parties. Admittedly, the Chief Justice of this Court

has appointed the Arbitrator and the matter proceeded before the sole Arbitrator pursuance to the order. By that time all the disputes referring to all these phases and related aspects had been arose between the parties. (M.R.Engineers and Contractors Private Limited Vs. Som Datt Builders Limited) 2 2 (2009) 7 SCC 696

ssm 9 arbp406.09

18 The learned Arbitrator, therefore, based upon the material, as well as the position of law, right in observing that

the intention of the parties was to incorporate the general conditions of the contract including the Arbitration clause. Merely because the LOI was not part of the record that itself

cannot be the reason to overlook the intention and the agreement between the parties, specifically when there is no

denial from the Petitioners' side that there is no Arbitration clause in the LOI. I am not inclined to accept the submission

of the learned counsel appearing for the Petitioners that

Agreement dated 13 May 1999 was for four specific buildings and not for remaining different buildings and therefore, there is no question of extension of same terms and conditions. The

admitted position on record including the correspondences so

referred and relied by the parties itself sufficient to disregard the submission of the Petitioners on this count also. The Petitioners ought to have proved the contrary and in support of

their submission that there was no such terms and conditions and/or Arbitration clause in the first agreement itself. They failed to produce the LOI of the year 1999 and therefore, cannot

be permitted to say that as the LOI was not on record, therefore, there was no question of extending the Arbitration Clause in such fashion to resolve the dispute about the remaining and subsequent works. In such composite matter, this submission itself is contradictory and demolishes the case of the Petitioners,

ssm 10 arbp406.09

when there is no denial to the existence of Arbitration

Agreement/clause in the LOI. I am inclined to observe, in the present facts and circumstances and in view of the findings

given by the learned Arbitrator and even otherwise that the Petitioners have accepted the stipulation that all other terms and conditions shall remain the same as mentioned in the LOI.

This includes and covers apart from the general conditions of contract and Arbitration clause 4.7.2 also. It is difficult to

dissect, now, at the instance of the Petitioners.

The Respondents were not party to the contract.

The Agreement dated 13 May 1999 was between the Petitioners and one M/s. Biecrete Projects Private Limited of partnership firm. The contract was assigned to the Respondents. As

alleged, it is without the Petitioners' prior consent. The

Arbitrator has dealt with this aspect and found that the subsequent conduct shows that the Petitioners consented to the assignment and in fact acted accordingly from time to time

without objection. The progress of the work were never stopped and/or halted on this ground of assignment. Therefore, the submission now so raised is without any substance and rightly

rejected. From time to time admittedly the Petitioners made payments to the Respondents based upon the material available on record and the part payments were also made to the third person/party. There was no question of making these payments, if there was no agreement between the parties and/

ssm 11 arbp406.09

or the Petitioners and for want of consent, notice and/or

intimation. No objection at any point of time on any of the issues was raised in this regard in the arbitration proceedings.

The learned Arbitrator, therefore, rightly rejected this issue while passing the final Award/Order.

THE CHALLENGE TO CLAIM OF PHASE-I ON MERIT.

BURDEN OF PROOF/ THE ARBITRTOR WAS AKSED TO

CONSIDER ALL MATERIAL ON RECORD :

The learned Arbitrator in this regard observed as under :

"There is no doubt that the whole burden of proof would lie on the Plaintiffs or the Claimants to prove their case. The Defendants and Respondents may not enter into witness box. It is always open for the

Defendants or the Respondents not to adduce any

evidence. In the present proceedings both the sides have adduced documentary and oral evidence. The Respondents have produced voluminous documentary evidence. Having done so it is not

open for them to say that the Claimants cannot rely on that documentary evidence to prove the case of the Claimants. The Claimants can very well rely on the facts in the documents of the Respondents to prove the case of the Claims. The Claimants are not

estopped from relying on the documents of the adversary. The Respondents have maintained methodically the entire documentary record during the course of the regular business with the Claimants. I will have to look into and consider the whole evidence, oral and documentary to finally decide the dispute or differences between the parties. No piece of evidence can be shut out from

ssm 12 arbp406.09

each other or totally ignored while deciding a lis between the parties. The doctrine of burden of

proof has been succinctly explained by the Supreme Court in the case of Lakshan Sao Vs. Dharmo

Chaudhari reported in (1991) 3 SCC 331. The Supreme Court observed as under :

"6. It is always open to the Defendant not to

lead any evidence where the onus is open (upon) the Plaintiff but after having gone into evidence, he cannot ask the Court not to look at and act on day. The question of burden of proof

at the end of case when both parties have tendered evidence is not of any great

importance and the Court has to come to a decision on a consideration of all materials."

The learned Arbitrator, therefore, based upon the material as well as documents placed on record by the parties, has passed

the Award by taking note of the whole evidence, oral and

documentary and decided the issues with regard to the claim as is contemplated.

THE DECISION ON MERIT :

21 As per the award : "Claim No. 1 : Phase I :

According to the Claimants the entire construction work under the contract was completed and that they are entitled to get the entire contract value of Rs. 7,42,02,320/-. According to the Respondents however the Claimants have carried out the work of Rs.7,37,28,552/-only. According to the Respondents the

ssm 13 arbp406.09

Claimants had not carried out the work of Renova Paint in

exteriors and therefore, they have deducted an amount of Rs. 5,98,768/-. I have to iron out this small difference in the

original contract value itself. The difference is on account of work of Renova Paint in exteriors. According to the Claimants they have applied three coats of Revona Paints and that after

completion of the work in September 2000 till the defence statement filed here, there was no complaint on this aspect at

any time that the Claimants had not carried out the work of the Renova Paint. As against the positive evidence of the

Claimants that they have carried out the Renova Paint work,

the Respondents' witness has admitted that the work of Renova Paint did not form part of the original contract. Coupled with this reply of the Respondents' witness it is

significant to note that there was no whisper of grievance

made by the Respondents at any time after September 2000 that the Claimants had failed to complete the work of Renova Paint. It is to be, therefore, inferred that the Claimants had

completed the Renova Paint work and, therefore, there was no complaint or grievance made by the Respondents. I will therefore proceed on the basis of the contract value of Rs.

7,42,02,320/-."

22 The work was completed as claimed. The Petitioners accepted the case that they carried out the work to the extent of Rs. 7,37,28,552/- only. The Arbitrator ultimately by recording the reasons proceeded with the said

ssm 14 arbp406.09

contract value, referring to the renewal and all other connected items.

EXTRA ITEMS :

23 Both the parties relied and referred including the

learned Arbitrator in this regard on two documents Exh. C-61 colly. and Exh. C-45. There is no serious disputes that after due discussion, though the claim was of Rs.

49,11,000/-, the settlement figure of Rs. 26,05,683/- was

fixed. But as it was not duly signed by the parties, there was dispute with regard to the same. The learned Arbitrator,

therefore, has considered the admitted bills/documents Exh. C-61 (colly.) and C-65 (colly.) to arrive at the conclusion by giving detailed reasons. The learned Arbitrator even

recorded that there is no dispute in the calculation of the

payment and receipts, except the findings so recorded above. There is ample material on record to show and as recorded by the learned Arbitrator that the Petitioners made

payment to the tune of Rs. 1,05,85,168/- to third person/party based upon the specific authorization given by the Respondents, the original Claimants. The Respondents,

however, disputed the amount of Rs. 11,03,315/-. The Petitioners failed to produce original receipts and/or any document except the disputed photocopy of the authorization letter. No acknowledgment of a third party was placed on record by the Petitioners. The Claimant have not admitted the amount of Rs. 9,95,917/-. The learned

ssm 15 arbp406.09

Arbitrator, therefore, based upon oral as well as the documentary evidence on record and by details of

arithmetics calculation/account, observed as under :

"I, therefore, hold that the Claimants are entitled to receive from the Respondents the net balance of Rs. 15,62,355/-. I have no doubt in my mind

about the fact that the Claimants are entitled to the aforesaid amount as far as their work in respect of Phase I is concerned. As far as the payments made to the third parties for which

the Respondents have not produced any kind of authorization given by the Claimants nor have

they produced any acknowledgment given by the concerned third parties, it is not possible for me to allow the aforesaid deduction and to

disallow the claim of the Claimants to the tune of Rs. 9,95,917/-."

24 The learned counsel appearing for the Petitioners, however, pointed out and made submissions

that the learned Arbitrator ought not to have relied upon the documents in part. The Respondents though admittedly

after the due discussion reduced the amount to Rs. 26,05,683/- it ought to have been overlooked by the Arbitrator. The important facet in this controversy is that the parties failed to accept these documents as final and

binding. The Respondents also failed to prove that the agreement/decision was final and binds the parties. Though initially it was agreed and recorded as Exh. C-45, but as there was a dispute there was contra material on record i.e. bunch of invoices produced by the Claimants (C- 61 colly.). This unsigned and/or invalid invoice/ document,

ssm 16 arbp406.09

in view of the objection so raised and the contra material available on record, just cannot be the foundation to award

the amount as set out therein. I am also of the opinion that

the learned Arbitrator has rightly considered the original documents in the form of invoices Exh. C-61 (colly.) specifically when there is no dispute raised with regard to

these documents even by the Petitioners. These documents were submitted by the Respondents and never disputed by the other side. The learned Arbitrator, therefore, rightly

observed as under :

"I am faced with a strange scenario here. The Claim of the Claimants for the extra items based

on a disputed statement Exh. C-45 is Rs.26,05,683/-. The Respondents have vehemently disputed this unsigned statement though it is in their favour as against the not

disputed bunch of invoices at Exh. C-61 colly.

             In   my   opinion,     I   will   be   legally     on   a   sound 
   



             footing     to   accept    the   claim     of   the   Claimants 
             based     on   admitted     and   not   disputed 

documents, Exh. C-61 colly. rather than the claim based on a disputed document Exh. C-45.

I am therefore inclined to allow the claim of the Claimants for Rs. 49,11,000/- for the work of extra items proved to have been done by the Claimants."

There is no denial to the fact of extra work. The learned Arbitrator has considered the oral evidence led by the parties in this regard. Therefore, the finding that the extra work done by the claimants is covered by the main contract which also implies that such extra work required to be done

ssm 17 arbp406.09

as and when necessity arises being items in the statement. It is just, proper and reasonable to award for this extra

work that was done by the Claimants.

25 In so far as the amounts of security deposit and retention money under the contract, the learned Arbitrator

after taking note of the evidence as well as the evidence of claimants witnesses, accepted that the claim of the claimants is restricted to the recovery of the accumulated

amounts under the head security deposit and retention

money as per the contract. This was so by referring to the admitted document Exh. C-44. The learned Arbitrator,

therefore, right in observing in para 41 as under :

"I am, therefore, of the considered opinion that

the claim of the Claimants is surely restricted to the pronounced two items i.e. the Retention

Money and the Security Deposit under the Contract and also their entitlement for extra items work under the Contract and the COP (Ex.C-44)

The learned Arbitrator in the said para further observed as under :

"I, therefore, conclude that the Claimants are entitled to receive from the Respondents the balance of Rs. 15,62,355/- out of the contractual value of the work and Rs. 49,11,000/- for the extra items which are also contemplated and implied in the contract. The Respondents have not denied or disputed that there was no extra work done by the Claimants.

      ssm                                 18                                arbp406.09

             It   would   be     unjust     enrichment     to   deny   this 
             legitimate          claim of  the  Claimants   for  their 




                                                                            
             extra   items   work.     The   total   entitlement, 

therefore, comes to Rs.64,73,355/-. Admittedly, however, the claim is restricted to the total of

security deposit and retention money i.e. Rs. 44,75,590/- only."

PHASE II WORKS:

26 There is no dispute that the Respondents/

Claimants received part payment from the contract value of

Rs.2,15,65,940/-. The balance was Rs. 10,24,553/-. The learned Arbitrator after considering material placed on

record as also referring to the work done, extra item, deductions, direct payment, TDS, WCT and others items observes that the net balance remains to Rs. 10,24,554/-.

27 The learned Arbitrator rejected certain claims of

the claimants and not awarded the full amount so claimed by the Respondents/ Claimants. There is no counter

challenge in this regard by the Respondents/ original Claimants. The Arbitrator, therefore, taking overall view of the matter rightly granted Award.

INTEREST

28 There is no specific agreement and/ or clause in the contract with regard to the interest. Section 31(7) of the Arbitration and Conciliation Act empowers the Arbitrator to exercise discretion to award interest even at the rate of 18%

ssm 19 arbp406.09

per annum. But one cannot overlook the aspect of the exercising discretion even in such commercial contract

matters that the claim of interest and/or grant should be

just and reasonable. The learned Arbitrator having once given finding so recorded above and observed that the Respondents have withheld the legitimate dues and claims of

the Claimants without any justification but ultimately awarded interest at the rate of Rs. 12% per annum from 09.03.2005 on the amount of Rs. 55,00,143/-. In this

regard as admittedly the dispute was with reference to the

construction work based upon the tender so invited and the work awarded from time to time and as admittedly

substantial payments were made during the progress of the work also and further to some extent the parties are interested in certain amounts that ultimately could not be

finalized. However, as the Arbitrator has granted the amount

for the first time after considering the material as well as evidence on record, I am inclined to restrict the rate of interest to 9% per annum instead of interest 12% per annum

as awarded by the learned Arbitrator. Based on the Supreme Court Judgment, I am restricting the rate of interest to 9% in such contractive matters.

COUNTER CLAIM :

29 The Petitioners (Respondents) though raised three counter claims but restricted only two claims; i.e. for the delay in completion of work and the defective work. The

ssm 20 arbp406.09

claim of Rs. 50,000/- to the abandonment of work was given up. Both these counter claims requires supporting oral as

well as documentary evidence. Admittedly, the claims so

raised were for the first time in the arbitration proceedings though a reference was made, that they reserved their right to claim liquidated damages; but there was no such steps

initiated by them at the earliest point of time. In reply to the claim so raised, they invoked the Clause referring to the liquidated damages and also claimed towards the defective

work. The learned Arbitrator based upon the material

available on record, recorded the finding that the balance amount due and payable was wrongly retained by the

Petitioner (original Respondent) and based on the available material, awarded the claim. Therefore, in view of this reasoning itself and as there is no counter material on

record to support the counter claim, I am not inclined to

interfere with the reasons so given by the learned Arbitrator, rejecting the counter claim of the Petitioners. The aspect of basic burden to prove the counter claim, just cannot be

overlooked. There is no material placed on record or even brought on record by the Petitioners in support of the counter claim to show that the delay, if any, caused only and

exclusively by the Respondents/Claimants. Admittedly, the work was in progress from time to time and even regular payments were made to the 3rd party with the interest by the Respondents. The record shows that the substantial work was done and in fact based upon the original contract of the year 1999, the work orders were issued for other

ssm 21 arbp406.09

portion of the project. The due certificate invoices/ documents are part of the record. Therefore, the party one

who wants to recover his claim of liquidated damages, needs

to prove the delay caused and the actual losses, he suffered as pleaded. Both these elements are missing in the present case for want of evidence as well as material on record, apart

from the timely action. Assuming for the moment that there is some delay in completion of the project but still fact remains and as recorded by the learned Arbitrator that there

was no issue and proper invoices and/or the demand raised

by the Petitioners/original Respondents from time to time. It is always necessary to give notice and opportunity to the

others parties to remove the defects and/ or repair the defective work so that proper action, act or steps can be taken by the persons who is under an obligation to repair and/or

maintain structure for the particular period, as claimed. It

is relevant to note that the Petitioners have got the balance work done through the third agency. There is nothing to show that the Petitioners have complied with the conditions

and/or terms of the contract/ clauses so raised and relied by the parties before filing such a counter- claim at such a delayed stage. The learned Arbitrator, therefore, according to

the terms of contract and/or clause and the evidence and material placed on record rightly rejected the counter claim also. Even other wise considering the totality of the material and the reasons so given read with the material and the evidence so led and referred by the learned counsel appearing for the parties, I see there is no case made out by the

ssm 22 arbp406.09

Petitioners to interfere with the Award in any of the grounds so raised. I am inclined to observe that the Award is well

within the frame work of law and the record.

     30    Resultantly,  the following order :




                                                      
           i)     The Award dated 29th February, 2009 is modified 
           only   to   the   extent     of   rate   of   interest   to   be   9%   per  

annum instead of 12% per annum from 9.3.2005.

ii)

The rest of the Award is maintained.

iii) There shall be no order as to costs.

(ANOOP V. MOHTA, J.)

.....

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter