Tuesday, 21, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Abg Ports Limited vs M/S.Psa International Pte ...
2012 Latest Caselaw 378 Bom

Citation : 2012 Latest Caselaw 378 Bom
Judgement Date : 21 November, 2012

Bombay High Court
M/S.Abg Ports Limited vs M/S.Psa International Pte ... on 21 November, 2012
Bench: D.D. Sinha, V.K. Tahilramani
    krs                                                                AppealL727.12




                                                                            
            IN THE HIGH COURT OF JUDICATURE AT BOMBAY

               ORDINARY ORIGINAL CIVIL JURISDICTION




                                                    
                    APPEAL (L) NO.727 OF 2012
                               In
               NOTICE OF MOTION (L) NO.2890 OF 2012




                                                   
                               In
                    SUIT (L) NO.2544 OF 2012

    M/s.ABG Ports Limited, a company incorporated )




                                        
    under the provisions of the Companies Act, 1956, )
    having its registered office at 5th floor, Bhupati
                           ig                          )
    Chambers, 13, Mathew Road, Mumbai--400 004. ) : Appellant

                V/s.
                         
    1. M/s.PSA International Pte Limited, a company )
       incorporated under the laws of Singapore,    )
                              th
       having its office at 38 floor, PSA Building, )
      

       460, Alexandra Road, Singapore 119 963.      )
   



    2. M/s.PSA Mumbai Investments Pte Limied, a        )
       company incorporated under the provisions of    )
       the Companies Act, 1956, having its office at   )
       38th floor, PSA Building, 460 Alexandra Road,   )





       Singapore 119 963.                              )

    3. Bank of Baroda, a body corporate constituted )
       under the Banking Companies (Acquisition     )
       and Transfer of Undertakings) Act, 1970,     )





       having its Head Office at Mandavi, Baroda    )
       and a branch office at 3, Walchand Hirachand )
       Marg, 1st Floor,Ballard Pier,Mumbai--400 001.)

    4. The Board of Trustees of the Jawaharlal Nehru )
       Port Trust, a body corporate constituted under )
       the provisions of the Major Port Trusts Act,1963)
       and having its office at the Port Planning and )

                                                                               1/40



                                                    ::: Downloaded on - 09/06/2013 19:24:43 :::
     krs                                                                  AppealL727.12



       Development Department, Administrative )




                                                                              
       Building, Sheva, Navi Mumbai--400 707, )
       and an office at Raheja Centre, No.1107, )
       214, Nariman Point, Mumbai--400 021.      ) : Respondents




                                                      
                                    ....

    Mr.T.N.Subramaniam, Senior Advocate, with Mr.Simil Purohit,
    Mr.Indranil Deshmukh and Ms Ankita Godbole i/b. Amarchand




                                                     
    Mangaldas & S.A.Shroff & Co., for the appellant.

    Mr.D.J.Khambata, Senior Advocate, with Mr.Nikhil Sakhardande,
    Mr.Adhip Iyer and Ms Suruchi Rungta i/b. AZB Partners for respondent




                                          
    nos.1 & 2.
                           
    Mr.N. Shah with Ms Saloni Shah i/b. Fox Mandal Partner for resp.no.3.

    Mr.Himanshu Kode with Ms Amrita Joshi i/b. The Law Point for
                          
    respondent no.4.
                            ....

                                CORAM : D.D. SINHA AND
      

                                        SMT.V.K.TAHILRAMANI, JJ.
   



                               Date of Reserving     )
                               the Judgement.        ) : 18.10.2012.

                               Date of Pronouncing ) : 21.11.2012.





                               the Judgement.      )

    JUDGEMENT (Per D.D.Sinha,J.)

The appellant has filed the suit, inter alia, seeking a declaration

that the Joint Bid Agreement (JBA), the Counter Guarantee, and its

invocation by the respondent no.1 vide its letter dated 21.9.2012 is illegal,

wrongful and vitiated by fraud and is, therefore, null and void, non-est

krs AppealL727.12

and of no effect whatsoever. The appellant has taken out a Notice of

Motion for an order that pending the hearing and final disposal of the suit,

direct and restrain by way of a temporary injunction the respondent no.3

from acting by themselves or through their servants, agents,

representatives and/or all other persons claiming by, through or under

them paying to the respondent no.1 or to anyone else any amount

purportedly under the Counter Guarantee. Similar temporary injunction

is sought against the respondent no.1 from receiving from the respondent

no.3 any amount purportedly under the Counter Guarantee. The appellant

has also claimed a temporary injunction restraining the respondent nos.1

& 3 from invoking and/or encashing the Counter Guarantee. The learned

single Judge vide judgement dated 5.10.2012 dismissed the Notice of

Motion. Being aggrieved by the said judgement of the learned single

Judge, the appellant has filed the present appeal challenging the impugned

judgement.

2. The learned counsel for the appellant has submitted that the brief

facts of the case are as follows:-

(a) The appellant is a company incorporated in India. The respondent

no.1 is a company incorporated in Singapore, wholly owned and

krs AppealL727.12

controlled by Tamsek Holdings, an investment company of the

Government of Singapore. The respondent no.2 is a subsidiary of the

respondent no.1.

(b) The present appeal impugns the judgement dated 5.10.2012

whereby the learned single Judge has dismissed the Notice of Motion

filed by the appellant seeking an injunction against the encashment of the

Bank Guarantee.

( c)

It is the stand of the appellant that in view of the law declared by

the Apex Court in a catena of decisions with respect to Bank Guarantee

and the approach of Courts in granting injunctions restraining the

invocation of Bank Guarantee, it is evident that the Court can and ought

to grant an injunction for invocation of Bank Guarantee if a prima facie

case of (i) fraud; (ii) irretrievable injustice; (iii) invocation of a Bank

Guarantee not being in terms thereof; and (iv) special equities is made

out. It is submitted that once the appellant prima facie satisfies the Court

regarding the existence of any of the conditions enunciated above, the

appellant is entitled to interim relief.

3. The learned counsel for the appellant has submitted that the Bank

Guarantee dated 13.10.2010 issued by the respondent no.3 in the sum of

krs AppealL727.12

Rs.17,42,00,000/- being the Bank Guarantee No.29101GPER018310

(Counter Guarantee) in favour of the respondent no.1 is not the kind of

guarantee which is usually given in the course of ordinary commercial

transactions. The appellant has entered into a Joint Bid Agreement dated

21.8.2009 with the respondent no.2. The respondent no.2 on behalf of the

consortium submitted a Bid Bond (issued by Standard Chartered Bank) in

the sum of Rs.67,00,00,000/- to the respondent no.4. The respondent no.1

issued an indemnity to Standard Chartered Bank for the Bid Bond

submitted by the Respondent no.2. The appellant in turn submitted the

Counter Guarantee to the respondent no.1. Thus, the transaction was not

a regular commercial transaction and the Counter Guarantee is not a kind

of Bank Guarantee usually issued in the course of commercial

transactions. Therefore, the constraints and limitations normally

associated with restraining payment under regular Bank Guarantee are not

attracted in the present case.

3. The learned counsel for the petitioner further submitted that the

suit guarantee is a conditional one and the same can be invoked only in

terms of the guarantee. Clause 4 of the suit guarantee reads as under:-

krs AppealL727.12

"4. In consideration of PSA International Pte

Ltd. Counter indemnifying Standard Chartered

Bank for issue of the Bid Bond of

Rs.67,00,00,000/- (Rupees Sixty Seven Crore

Only) on behalf of the consortium of PSA

Mumbai Investments Pte Ltd and ABG Ports Pvt.

          Ltd.   ("Consortium"),       we      Bank       of    Baroda
                    
          ("Guarantor"),        hereby         irrevocably          and

          unconditionally   undertake          to    pay       to   PSA
                   

International Pte Ltd. "(Beneficiary"), on its first

demand, an amount up to Rs.17,42,00,000/-

(Rupees Seventeen Crores and Forty Two Lakhs

Only), as payment obligation to the Beneficiary

pursuant to the Bid Bond, without any demur,

reservation, recourse, contest or protest, without

notice or reference to ABG Ports Pvt. Ltd.,

irrespective of whether the Beneficiary's demand

is disputed by ABG Ports Pvt. Ltd. or any other

person or not, within 3 business days of a written

request from the Beneficiary for payment within

krs AppealL727.12

the Effective Period (as defined hereinafter),

supported by the following documents:

(emphasis supplied)

It is submitted that from the above, it is clear that the purpose of the

Counter Guarantee was to indemnity the respondent no.1. The words "as

payment obligation to the Beneficiary pursuant to the Bid Bond" which

find place in paragraph 4 of the Counter Guarantee are of great

significance and cannot be ignored.

4. It is submitted that the obligation of the respondent no.3 to pay to

the respondent no.1., viz., the beneficiary under the Counter Guarantee is

conditional on the respondent no.1's entitlement to receive payment. This

means that unless there is an obligation to make payment on the part of

the appellant to the respondent no.1, the Counter Guarantee cannot be

invoked and the respondent no.3 is not obliged to make payment. It is

submitted that in other words, unless the obligation fastens, the Counter

Guarantee cannot be invoked and no liability fastens on the appellant.

The Bid Bond was submitted by the respondent no.2 to the respondent

no.4 (JNPT) for and on behalf of the consortium. The appellant was

under no obligation qua the respondent no.1 under the Bid Bond. The

krs AppealL727.12

learned single Judge completely overlooked the above factual position.

The Counter Guarantee was issued to the respondent no.1 as the

respondent no.1 was indemnifying the claim of the Bid Bond issuing

Bank, viz., Standard Chartered Bank. It would, therefore, follow that the

respondent no.1 would be entitled to make a claim under the Counter

Guarantee only if it establishes that the loss caused under the indemnity is

attributable to the action/inaction of the appellant. The Counter

Guarantee is, therefore, more in the nature of a Guarantee indemnifying

the respondent no.1 for the loss caused to the respondent no.1, if any, due

to the conduct of the appellant. The Bid Bond was submitted to JNPT.

JNPT in turn invoked the Bid Bond as the respondent no.2 failed to

execute the concession agreement for the said project within the

stipulated time. Admittedly, the appellant is not responsible in any

manner whatsoever for the invocation of the Bid Bond by JNPT, and

consequently, the respondent no.1 is not entitled to make any claim under

the Counter Guarantee. The learned counsel for the appellant has further

contended that despite the aforesaid facts having been pointed out to the

learned single Judge, the learned single Judge erroneously held that as the

appellant was a member of the consortium, it was liable for proportionate

loss under the JBA for non-fulfilment of obligations by the respondent

krs AppealL727.12

no.2. The finding of the learned single Judge is patently erroneous and

proceeds on an erroneous premise that the Counter Guarantee was given

to the respondent no.2 towards the Bid Bond. The learned single Judge

failed to appreciate that the liability of the appellant, as aforesaid, if any,

was towards the respondent no.2 and not the respondent no.1. The parties

had carefully worded the terms of the Bank Guarantee to include the term

"payment obligation" in the guarantee. The impugned judgement

completely ignores the specific term used by the parties. In order to

enable the respondent no.1 to invoke the Counter Guarantee, it was

imperative that the respondent no.1 ought to have suffered a loss on

account of the conduct of the appellant. It is, therefore, contended that

under the JBA, all obligations were to be performed by the respondent

no.2 which in turn is a subsidiary of the respondent no.1. The respondent

no.2 having failed to comply with the same, cannot ask and seek

contribution to indemnify any loss of the respondent no.1 arising out of its

own inaction.

5. It is contended that if the encashment of the Counter Guarantee

is not injuncted, the same would tantamount to a party profiteering from

its own wrongs/inaction. It is submitted that there is no declaration in the

krs AppealL727.12

respondent no.1's letter dated 21.9.2012 that the payment obligation has

fastened on the appellant pursuant to the Bid Bond which was mandated

by the terms of the Counter Guarantee. The impugned order loses sight of

the fact that there has to be a loss caused to the respondent no.1 which

must be the result of direct actions/inactions on the part of the appellant.

The invocation of the counter guarantee thus not being in terms of the

guarantee is bad in law, non est and an injunction to restrain the

encashment thereof ought to have been granted by the learned single

Judge.

6. The learned counsel for the petitioner has submitted that the action

of the respondent nos.1 & 2 (collectively "PSA") of leading the appellant

to believe that it was interested in participating in and implementing the

development of the 4th Container Terminal project at Jawaharlal Nehru

Port, on Design, Build, Finance, Operate and Transfer (DBFOT) basis

(the "said Project"), despite being very well aware that it had no such

intention to implement the said project, is clearly an act of fraud as

defined under section 17 of the Contract Act. Such an act of egregious

fraud vitiates the JBA and all contractual agreements entered into between

the parties and steps taken pursuant thereto, including the Counter

krs AppealL727.12

Guarantee. It is contended that the fraudulent conduct of the PSA is

further substantiated from a perusal of exh.`K' wherein the Board Member

of JNPT has opined that PSA never intended to commence setting up of

terminal at JNPT.

7. The learned counsel for the petitioner has submitted that the PSA

never intended the project to take off so that all container traffic can be

diverted from the Middle East to Singapore port which is run and

controlled by the Holding Company of PSA/it's associates/affiliates. This

is evident from the unprecedented, unrealistic and commercially unviable

bid (which, at its time of making was the highest revenue share quoted for

all similar projects in the country) submitted by PSA for the said project.

The said intent is also clearly plausible in view of the fact that the parent

company of the respondent no.1 being Tamsek holding is an investment

arm of the Government of Singapore. Thus, the appellant had clearly

made out a strong prima facie case of the egregious fraud perpetuated by

PSA. It is contended that despite these facts, the learned single Judge has

erroneously held as under:-

"In my view, in the present case, the Plaintiff

krs AppealL727.12

has failed to make out any case of fraud. On a

reading of the averments made in paragraph 8

of the Suit it is clear that the said averments by

no stretch of imagination can be said to have

made out a case of fraud. The allegations of

fraud made by the Plaintiff are merely bald

assertions and do not establish a case of fraud

much less a fraud of a egregious nature.

.............."

8. The counsel for the appellant has further contended that the learned

single Judge has also negatived the appellant's contentions on fraud on the

ground that the appellant had till date not rescinded the JBA, which

according to the learned single Judge "speaks volumes about the

seriousness of the allegation of fraud made by them against Defendant

Nos.1 and 2." The conclusion of the learned single Judge is clearly

erroneous. The appellant specifically pleaded discharge of the contract

which fact has been completely ignored by the learned single Judge.

9. It is further submitted that the learned single Judge completely

krs AppealL727.12

overlooked the fact that the respondent no.2 has allowed the invocation of

the Bid Bond by JNPT without any protest. The learned Judge has held

that there are serious disputes between the respondent no.2 and JNPT,

however, the learned Judge overlooked that:-

(a) The respondent no.2 has till date not protested against/challenged

the invocation and/or encashment of the Bid Bond by JNPT;

(b) The respondent no.2 had also not initiated any proceedings to

prevent the invocation and/or encashment of the Bid Bond by

JNPT;

( c) The respondent no.2 has not initiated any proceedings against JNPT

for the recovery of the Bid Bond amount of Rs.67 crores.

(d) No steps were taken by the respondent no.2 to ensure that the Letter

of Award for the said project is not terminated/withdrawn, despite it

being the respondent no.2's case that it was not in default.

10. The learned counsel for the appellant has submitted that the

appellant in paragraph 3 as well as in paragraph 12 of the plaint has

categorically stated that the respondent no.2 is a shell company and has no

assets either in India or in Singapore and the said factual position is not

controverted. The obligation of the appellant was joint and several with

krs AppealL727.12

the respondent no.2 qua JNPT. The impugned order erroneously records

and refuses an injunction on the erroneous ground that the appellant was a

"joint promisor" and had jointly promised performance of its obligation

being a member of the consortium. It is contended that the impugned

judgement fails to consider that the joint promise, if any, was by the

appellant with the respondent no.2 qua JNPT. There was no joint promise

between the appellant and the respondent no.1. JNPT having invoked the

Bid Bond, the right to claim moneys from the appellant, if any, would

devolve only on the respondent no.2. In the absence of any joint promise

with the respondent no.1, the respondent no.1 could not invoke the

Counter Guarantee.

11. It is contended that if the Counter Guarantee is allowed to be

invoked/encashed, the eventual decree, if any, which would be passed in

favour of the appellant, in proceedings the appellant would initiate for

recovery of the amounts paid pursuant to the Counter Guarantee, would

be a mere paper decree against the respondent no.2 which is only a shell

company, with no assets either in India or in Singapore. The learned

single Judge has proceeded to reject the appellant's contentions on the

ground that the respondent no.1 is backed by the Government of

krs AppealL727.12

Singapore. It is contended that in view of the joint obligation under the

JBA, being between the appellant and the respondent no.2, the financial

soundness of the respondent no.1 cannot be a ground to deny injunctive

reliefs to the appellant.

12. The learned counsel for the appellant has specifically pleaded

that the facts and circumstances of the case clearly give rise to special

equities being invoked by the appellant to protect the rights of the

appellant. The sole ground taken by JNPT for invoking the Bid Bond is

the failure on the part of the respondent no.2 to sign the concession

agreement for the said project. This has clearly been on account of PSA

and the appellant has had no role to play in this. The default, if any, is

therefore of PSA alone. If the default and the consequent invocation of

the Bid Bond is solely due to PSA's failure to execute the concession

agreement, the respondent no.1 is not entitled to pass that burden or any

part thereof upon the appellant and claim benefit under the Counter

Guarantee. Allowing the respondent no.1 to do so would tantamount to

rewarding the respondent no.1 for its own inaction and fraudulent

conduct. The fraud is of the beneficiary (as it controls the respondent

no.2 absolutely) who cannot be allowed to take any benefit therefrom.

krs AppealL727.12

However, the learned single Judge failed to consider the same. The

impugned judgement, therefore, fails to render findings on the issues

specifically raised by the appellant. It is, therefore, respectfully submitted

by the appellant that this is a fit case for this Court to restrain the

invocation/encashment of the counter guarantee.

13. Mr.Khambata, the learned counsel for the respondent nos.1 & 2,

on the other hand, supported the impugned judgement passed by the

learned single Judge. It is contended that the law in regard to special

equities/irretrievable injury for injuncting the encashment of a Bank

Guarantee has been laid down by the Apex Court in Dwarikesh Sugar

Industries Ltd. v. Prem Heavy Engineering Works (P) Ltd. & Anr.

(1997) 6 SCC 450 in the following terms:-

"22. The second exception to the rule of

granting injunction, i.e., the resulting of

irretrievable injury, has to be such a circumstance

which would make it impossible for the guarantor

to reimburse himself, if he ultimately succeeds.

This will have to be decisively established and it

krs AppealL727.12

must be proved to the satisfaction of the court that

there would be no possibility whatsoever of the

recovery of the amount from the beneficiary, by

way of restitution."

It is contended that in the present case, the beneficiary of the Bank

Guarantee is the respondent no.1/defendant no.1. Hence, on an

application of the test laid down by the Apex Court in the case of

Dwarikesh Sugar Industries Ltd. (supra), it is necessary for the appellant

to plead and establish that recovery of the amount from the respondent

no.1 (beneficiary) is impossible. It is submitted that the test in the case of

Dwarikesh Sugar Industries Ltd. has not been satisfied as is evident from

the pleading of the appellant/plaintiff in the plaint which reads thus:-

"2. Defendant no.1 is a limited liability company

incorporated under the laws of Singapore and has its

office at the address stated in the cause title above.

Defendant No.1 is ultimately owned by the

Government of Singapore and is engaged in the

business of construction, development, maintenance

krs AppealL727.12

and operation of various container terminals at

various ports in around twenty nine countries.

Defendant no.1 is one of the largest container

terminal operators in the world."

It is contended that a reading of the above pleading in the plaint shows

that the respondent no.1 is one of the largest container terminal operators

in the world and, therefore, irretrievable injury/special equities for

injuncting the encashment of Bank Guarantee has not been established as

required in law by the appellant.

14. The learned counsel has further contended that the plaintiff has

pleaded special equities in paragraph 12 of the plaint which reads thus:-

"12. The Plaintiff states and submits that

irretrievable injustice will be caused to it in case

appropriate orders are not passed restraining

encashment of the Counter Guarantee. It is

submitted that Defendant No.2 is a shell

company and has no assets in either India or

krs AppealL727.12

Singapore and thereby any order that the

Plaintiff may obtain against Defendant No.1

will be a mere paper decree."

It is submitted that this pleading is irrelevant as the respondent no.2 is not

the beneficiary under the Bank Guarantee and as such, pleading in regard

to the respondent no.2 being a shell company for establishing irretrievable

injury is immaterial and ought to be discarded on the test laid down by the

Apex Court in the case of Dwarikesh Sugar Industries Ltd. (supra). It is,

therefore, contended that no irretrievable injury has been established and,

as such, the said recognised exception to the rule that a Bank Guarantee

ought not to be injuncted has not been satisfied in the present case.

15. The learned counsel for the respondent nos.1 & 2 further

contended that the appellant's reliance on a newspaper article dated

12.9.2012 to make out a case of fraud is entirely misplaced. The said

newspaper article has not even been pleaded in support of the case of

fraud in paragraph 8 of the plaint which is the only basis on which fraud

has been alleged in the plaint. It is further submitted that the respondent

no.1 took all necessary steps in regard to withdrawal of the appellant from

krs AppealL727.12

the consortium which steps were taken pursuant to the appellant's own

request in this regard, as evident from the appellant's letter dated

31.3.2012. Based on this request, the respondent no.2 by its letter dated

2.4.2012 wrote to the respondent no.4 seeking its consent for the

appellant's withdrawal from the consortium. The said request was

rejected by the respondent no.4 for which the respondent nos.1 & 2

cannot in any manner be held responsible. Thus, it cannot be contended

that there is a fraud practised upon the appellant.

16. The learned counsel for the respondent nos.1 & 2 has submitted

that insofar as the allegation of fraud in the context of non-signing of the

Concession Agreement is concerned, it is submitted that a show cause

notice in that regard had been issued and a detailed reply has been

submitted by the respondent no.2 explaining the reasons for not signing

the Concession Agreement. It has been clearly stated that the respondent

no.2 had been ready and willing to execute the Concession Agreement,

but the same could not be executed only because of stamp duty issues and

because of which it was mutually agreed to postpone the signing of

agreement. It is submitted that it could never have been the intention of

the respondent no.1 to defraud the plaintiff of Rs.17.42 crores covered by

krs AppealL727.12

the Counter Guarantee and in the process suffer a loss of Rs.50 crores (in

view of the encashment of Bid Bond of Rs.67 crores) and also further lose

the valuable right to enter into a Concession Agreement which was for a

period of 30 years. It is, therefore, submitted by the counsel for the

respondent nos.1 & 2 that the contention of the appellant regarding

fraudulent intention on the part of the respondent no.1, in the facts and

circumstances of the present case, is absurd.

17. It is further contended that the appellant who has alleged fraud

has not terminated the Joint Bid Agreement (JBA). It is important to note

that the appellant has not avoided the transaction nor has it avoided the

same in the plaint. The appellant, therefore, is estopped from raising the

plea of fraud.

18. The learned counsel for the respondent nos.1 & 2 has contended

that the Supreme Court in the case of Svenska Handelsbanken v.

M/s.Indian Charge Chrome & Ors. (1994) 1 SCC 502) has held in

paragraph 71 thus:-

"71. Shetty, J. speaking for the Bench noticed the

krs AppealL727.12

earlier observations of Mukharji, J. in the case of

U.P. Cooperative Federation Ltd. and stated that the

nature of the fraud that the courts talk about is fraud

of an "egregious nature as to vitiate the entire

underlying transaction". It is fraud of the

beneficiary, not the fraud of somebody else."

19.

The learned counsel for the respondent nos.1 & 2 has placed

reliance on the observations made by the Apex Court in paragraph 28 of

the judgement in the case of Dwarikesh Sugar Industries Ltd. (supra). It

is, therefore, contended that for a Court to restrain encashment of a Bank

Guarantee, the fraud has to be absolute and egregious, vitiating the very

foundation of the Bank Guarantee. The averments on fraud are to be

found in paragraphs 8 to 10 of the plaint. On a reading of the same, it is

clear that the averments by no stretch of imagination can be said to have

made out a case of such fraud apart from the fact that the allegations are

incredible and does not establish that the respondent nos.1 & 2 practised

any fraud whatsoever.

20. The learned counsel for the respondent nos.1 & 2 further

krs AppealL727.12

contended that the appellant and the respondent no.2 are part of the

consortium. A consortium is in the nature of a partnership and consortium

members must, in law, bear the liabilities of the consortium to the extent

of their share in the consortium. It is further submitted that section 43 of

the Indian Contract Act provides as under:-

"43. Any one of joint promisors may be

compelled to perform.--When two or more

persons make a joint promise, the promisee

may, in the absence of express agreement to the

contrary, compel any one or more of such joint

promisors to perform the whole of the promise.

Each promisor may compel contribution -

Each of two or more joint promisors may

compel every other joint promisor to contribute

equally with himself to the performance of the

promise, unless a contrary intention appears

from the contract.

Sharing of loss by default in contribution.-

If any one of two or more joint promisors

krs AppealL727.12

makes default in such contribution, the

remaining joint promisors must bear the loss

arising from such default in equal shares.

Explanation.-- Nothing in this section shall

prevent a surety from recovering, from his

principal, payments made by the surety on

behalf of the principal, or entitle the principal

to recover anything from the surety on account

of payment made by the principal."

21. The learned counsel for the respondent nos.1 & 2 further

contended that there is no contract to the contrary in the JBA. Indeed, the

JBA reaffirms the liability by providing as follows:-

"5. Joint and Several Liability

The Parties do hereby undertake to be jointly

and severally responsible for all Obligations

and liabilities relating to the Project and in

accordance with the terms of the RFQ, RFP and

the Concession Agreement, till such time as the

Financial Close for the Project is achieved

krs AppealL727.12

under and in accordance with the Concession

Agreement."

It is submitted that the appellant has itself admitted its joint and several

liability under Clause 5 of the JBA for any/all obligations and liabilities

relating to the project. This is evident from the appellant's letter to the

respondent no.1 dated 31.3.2012.

22. The counsel for the respondent nos.1 & 2 further submitted that

under the Request for Proposal issued by the respondent no.4 (RFP), a

Bid Bond of Rs.67 crores was required to be furnished by the consortium

of which the appellant is a 26% member/partner. The sum of Rs.17.42

crores (Counter Guarantee) thus represents the appellant's share (26%) of

the total amount of Rs.67 crores covered by the Bid Bond. It is submitted

that the respondent nos.1 & 2 could have submitted their share of 74% of

the Bid Bond amount the appellant would have required to submit its

share of the Bid Bond directly to the respondent no.4 and the effect would

have been that the respondent no.4 would have invoked two Bank

Guarantees aggregating to Rs.67 crores. However, the respondent no.4

wanted a single Bank Guarantee and, therefore, the Counter Guarantee

krs AppealL727.12

was obtained.

23. It is contended that the Counter Guarantee is unconditional and

irrevocable guarantee and contains an unequivocal promise to pay a sum

of Rs.17.42 crores without any demur or protest and the same could be

encashed. The Counter Guarantee is an independent contract and whether

an injunction ought to be granted or not has to be considered without any

reference to the underlying contract. Even the ground of unjust

enrichment has been rejected by the Apex Court in the case of Dwarikesh

Sugar Industries Ltd. (supra) by observing thus in paragraph 29 of the

judgement:-

"29. .................... We also do not find any

justification for the High Court in invoking the

alleged principle of unjust enrichment to the

facts of the present case and then deny the

appellant the right to encash the bank guarantee.

If the High Court had taken the trouble to see

the law on the point it would have been clear

that in encashment of bank guarantee the

krs AppealL727.12

applicability of the principle of undue

enrichment has no application."

It is submitted that the appellant's argument that the Counter Guarantee is

a conditional one is erroneous: (i) the expression `payment obligation' is

merely descriptive of what the Counter Guarantee has been furnished for.

Once the Bid Bond for a sum of Rs.67 crores is encashed, the respondent

no.1 is entitled to be reimbursed to the extent of Rs.17.42 crores which is

the appellant's share of the amount covered by the Bid Bond encashed by

the respondent no.4. The Counter Guarantee provides that the

encashment of the Bid Bond is to be established by providing a copy of

the respondent no.4's invocation letter to the respondent no.3 Bank. In the

present case, this has been done.

24. The appellant's contention that the respondent no.1 would be

entitled to make a claim under the Counter Guarantee only in case it

establishes that the appellant is obligated to make payment to the

respondent no.1 due to the loss it has suffered under the counter

indemnity, is erroneous in law. The present case is one of an

unconditional Bank Guarantee and not an indemnity. Therefore, it is clear

krs AppealL727.12

that the respondent no.1 is entitled to call upon the respondent no.3 to pay

under the Counter Guarantee dated 13.10.2010 once there is a letter of

invocation of the Bid Bond by the respondent no.4. That letter of

invocation by the respondent no.4, therefore, establishes the right to

invoke the Counter Guarantee. The counsel for the respondent nos.1 & 2

further submitted that even otherwise, the Counter Guarantee was given

as consideration of the respondent no.1 indemnifying Standard Chartered

Bank for issuing the Bid Bond in favour of the respondent no.4 and was

not an indemnity given by the appellant to the respondent no.1. Thus, the

reliance placed by the appellant on section 124 of the Indian Contract Act,

1872 is entirely misplaced as the said section does not apply. It is,

therefore, contended that the order of the learned single Judge is a well-

reasoned order and does not warrant any interference. The appeal,

therefore, deserves to be dismissed with costs.

25. We have given anxious thought to the various contentions

canvassed by the respective learned counsel for the appellant as well as

the respondents, considered the decisions cited as well as the impugned

judgment passed by the learned single Judge. We feel it appropriate to

express the well-settled legal position relating to encashment of Bank

krs AppealL727.12

Guarantee in view of the decision of the Apex Court. A Bank Guarantee

is one which is payable by the guarantor on demand if the Bank

Guarantee is the unconditional Bank Guarantee. Similarly, in the course

of commercial dealings, unconditional guarantees have been given or

accepted, the beneficiary is entitled to realise such a Bank Guarantee in

terms thereof irrespective of any pending disputes. The Bank giving such

a guarantee is bound to honour it as per its terms irrespective of any

dispute raised by a customer. The law on this subject settled by the

decision of the Apex Court clearly demonstrates that the Court should be

slow in granting an injunction to restrain the realisation of such a Bank

Guarantee and there are two exceptions to the general rule. A fraud in

connection with such a Bank Guarantee would vitiate the very foundation

of such a Bank Guarantee and, therefore, such beneficiary can be

injuncted from encashing the Bank Guarantee. The second exception

relates to cases where allowing the encashment of an unconditional Bank

Guarantee would result in irretrievable harm or injustice to one of the

parties concerned. Since in most cases payment of money under such a

Bank Guarantee would adversely affect the bank and its customer at

whose instance the guarantee is given, the harm or injustice contemplated

under this head must be of such an exceptional and irretrievable nature as

krs AppealL727.12

would over-ride the terms of the guarantee.

26. On the back-drop of the above referred well-settled position in

law on the subject, it will be appropriate to consider whether the

appellant was able to establish a prima facie case in respect of these two

exceptions along with other circumstances for injuncting the respondent

no.1 from encashing the Counter Guarantee and whether the finding

recorded by the learned single Judge in this regard are consistent with the

law declared by the Apex Court on the subject.

27. Insofar as the contentions canvassed by the learned counsel for

the appellant, in order to demonstrate that fraud has been practised by the

respondent nos.1 & 2 is concerned, we have already recorded the

contentions canvassed by the learned counsel for the appellant as well as

the respondent nos.1 & 2 in this regard as mentioned hereinabove and it

is, therefore, not necessary for us to reiterate the same. We have perused

paragraphs 8 to 10 of the suit filed by the appellant. The learned single

Judge, after taking into consideration all these aspects in paragraph 27 of

the impugned judgement has observed thus:-

krs AppealL727.12

"27. It is trite law that a Court can restrain

encashment of Bank Guarantee in cases of

established fraud in issuance of the Bank

Guarantee. The fraud has to be absolute and

egregious vitiating the very foundation of the

Bank Guarantee. In my view, in the present case,

the Plaintiff has failed to make out any case of

fraud. On a reading of the averments made in

paragraph 8 of the Suit it is clear that the said

averments by no stretch of imagination can be said

to have made out a case of fraud. The allegations

of fraud made by the Plaintiff are merely bald

assertions and do not establish a case of fraud

much less a fraud of a egregious nature. In view

thereof, the decisions cited by the Learned Senior

Counsel for the Plaintiff in the cases of U.P.

Cooperative Federation Ltd. vs. Singh Consultants

and Engineers (P) Ltd. (supra) and Yog Systems

India Ltd. Vs. SU-KAM Power Systems Ltd.

(supra) are of no assistance to the Plaintiff. As

krs AppealL727.12

held hereinafter, the said Counter Guarantee is an

unconditional and irrevocable Guarantee. It is

settled law that encashment of an unconditional

and irrevocable Bank Guarantee ought not to be

injuncted by the Courts unless the case falls within

the recognized exceptions laid down by the

Hon'ble Supreme Court in a catena of decisions in

which

case an injunction restraining the

encashment of a Bank Guarantee can be granted.

An unconditional and irrevocable Bank Guarantee

is an independent contract and whether

encashment of the same ought to be permitted or

not has to be considered without any reference to

the underlying or main contract or to the

disputes/claims thereunder. It is also pertinent to

note that though the Plaintiff has alleged fraud on

the part of Defendant Nos. 1 and 2, the Plaintiff

has till date not rescinded the JBA which speaks

volumes about the seriousness of the allegation of

fraud made by them against Defendant Nos. 1 and

krs AppealL727.12

2. The allegation therefore made by the Plaintiff

that the invocation of the Bank Guarantee is

vitiated by fraud cannot be accepted and the said

contention is rejected."

28. In paragraph 8 of the plaint, the appellant in sub-paragraphs (f)

and (h) made allegation of fraud being practised by the respondent nos.1

& 2 which read thus:-

"(f) The Plaintiff has acted on the false and

fraudulent representation made by PSA and

altered its position to its detriment."

"(h) Further, PSA continued to act fraudulently

and deceitfully even after Defendant No.4

had terminated the contract and invoked the

Bid Bond, when PSA assured the Plaintiff

that they are pursuing the matter with

Defendant No.4 and the situation will be

salvaged."

Sub-paragraphs (a) to (e), (g), (i) and (j) of paragraph 8 are bald

krs AppealL727.12

assertions which do not establish absolute and egregious fraud practised

by the respondent nos.1 & 2 to vitiate the foundation of Bank Guarantee

at this stage. On the other hand, they pertain to the implementation of the

project if selected and obligations under the RFQ and RFP documents as

well as Joint Bid Agreement, responsibility of lead member of the

consortium requiring it to sign concessional agreement with the

respondent no.4, etc. We agree with the observations made by the learned

single Judge that unconditional and irretrievable Bank Guarantee is an

independent contract and whether encashment of the same ought to be

permitted or not has to be considered without reference to the underlying

or main contract or to the disputes/claim thereunder. Even a perusal of

the allegations made in paragraphs 9 and 10 are also not specific to

establish absolute fraud as required in law and, therefore, mere

allegation/bald assertions of fraud made by the appellant, in our view,

does not prima facie establish that fraud has been practised by the

respondent nos.1 & 2 to vitiate the very foundation of Bank Guarantee in

order to injunct the respondent no.1 from invoking the Counter

Guarantee.

29. As regards the contention canvassed by the learned counsel for

krs AppealL727.12

the appellant that irretrievable injustice would be caused if the Counter

Guarantees permitted to be encashed by the respondent no.1 is concerned,

the law is well-settled on this subject and when applied to the facts of the

present case, it must show that if the respondent no.1 is permitted to

encash the Counter Guarantee, it would be impossible for the guarantor to

reimburse himself if he ultimately succeeds. In the instant case, it is not

disputed that the consortium is in the nature of partnership and the

consortium member in law bears liabilities of consortium to the extent of

their share in consortium. Clause 5 of the Joint Bid Agreement (JBA)

affirms that the nature of liability is joint and several and there is no

contract to the contrary in the JBA. In the plaint, it is stated by the

appellant that the respondent no.1 is owned by the Government of

Singapore and is one of the largest container terminal operators in the

world. The learned single Judge in paragraph 30 of the judgement

considered these facts and decision of the Apex Court in the case of U.P.

State Sugar Corporation v. Sumac International Ltd. (1997) 1 SCC 568)

and, in our view, has rightly held that the appellant has not made out a

case of irretrievable injustice as required in law. Similarly, the learned

single Judge has also justified in holding that the appellant has failed to

decisively establish and prove to the satisfaction of the Court that there

krs AppealL727.12

would be no possibility of recovery of the amount from the beneficiary by

way of restitution in view of the law laid down by the Apex Court in the

case of Dwarikesh Sugar Industries Ltd.

30. In the instant case, whether the Bank Guarantee is a conditional

one or not, it is necessary to consider paragraphs 4, 5 and 6 of the

Guarantee (which are already reproduced in the impugned judgement). A

perusal of these clauses of the guarantee would show that the Counter

Guarantee is an unconditional irrevocable guarantee and contains

equivocal promise to pay a sum of Rs.17.42 crores without any demur or

protest. Once the Bid Bond for the sum of Rs.67 crores is encashed, the

respondent no.1 is entitled to be reimbursed to the extent of Rs.17.42

crores which is the appellant's share of the amount covered by the Bid

Bond which in the present case has been encashed by the respondent

no.4. It is in these circumstances of the case that the finding recorded by

the learned single Judge in paragraph 29 of the impugned judgement, in

our view, is just and proper and sustainable in law since Counter

Guarantee is unconditional and irrevocable, the relevant portion of which

reads thus:-

krs AppealL727.12

"29. As set out hereinabove, it is clear that

Defendant No.2 initially furnished a Bid Bond of

Rs. 67 crores through the Standard Chartered Bank

to Defendant No.4 on behalf of the Consortium

which included the Plaintiff's contribution. Since

the Plaintiff was required to make its contribution

to the extent of 26 per cent of the said Bid Bond

i.e. to the extent of 17.42 crores and since the

Defendant No.1 counter indemnified the said Bid

Bond of Rs. 67 crores, the Plaintiff furnished a

Counter Guarantee dated 13th October 2010 issued

by Defendant No.3 in favour of Defendant No.1

for a sum of Rs. 17.42 crores. The terms of the

Counter Guarantee make it clear that the Counter

Guarantee is for issue of Bid Bond of Rs. 67 crores

by PSA on behalf of the Consortium. The payment

under the Counter Guarantee is described as the

payment obligation of the Plaintiff to the

beneficiary pursuant to the Bid Bond. The

payment under the Counter Guarantee is without

krs AppealL727.12

demur, reservation, recourse, contest or protest.

The only condition for such payment is that the

demand or the payment must be supported by the

documents listed in Clause 4 and must be in

accordance with Clauses 5 and 6. Admittedly the

demand complies with this requirement. Upon

such demand being made, the Defendant No.3

Bank, within 3 days upon receipt of a written

request from Defendant No.1, is bound to pay an

amount upto Rs. 17.42 crores as payment

obligation to Defendant No.1 pursuant to the Bid

Bond, without any demur, reservation, recourse,

contest or protest, without notice or reference to

the Plaintiff, irrespective of whether the Defendant

No.1's demand is disputed or not by the Plaintiff

or any other person. Mr. Khambata is therefore

correct in his submission that the expression

"payment obligation" is merely descriptive of what

the Counter Guarantee has been furnished for, and

it cannot be contended that the same is a

krs AppealL727.12

conditional guarantee. He is further correct in his

contention that once the Bid Bond for a sum of

Rs.67 crores is encashed, Defendant No. 1 is

entitled to be reimbursed to the extent of Rs. 17.42

crores, which is the Plaintiff's share of the amount

covered by the Bid Bond and which has been

encashed by Defendant No.4."

31. The contention canvassed by the learned counsel for the appellant

that the respondent no.1 would be entitled to make a claim under the

Counter Guarantee only if it establishes that the loss caused under the

indemnity is attributable to the action/inaction of the appellant is difficult

for us to agree, in the facts and circumstances of the present case. As we

have already observed hereinabove, the Counter Guarantee is

unconditional irrevocable guarantee, its legal complexion does not change

merely because it is given in the context of an obligation to indemnify.

32. Similarly, the contention canvassed by the learned counsel for the

appellant in respect of special equities, in the circumstance of the present

case, cannot be accepted, for the reasons stated hereinabove.

krs AppealL727.12

33. In our view, no case is made out for showing indulgence in the

present appeal which suffers from lack of merits and is, therefore,

dismissed with costs.




                                                      
                                                    (D. D. SINHA, J.)




                                            
                               ig               (SMT.V.K.TAHILRAMANI,J.)
                             
       
    






    Suundaresan







 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter