Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Angerlehner Structural & ... vs Municipal Corporation Of Brihan
2012 Latest Caselaw 311 Bom

Citation : 2012 Latest Caselaw 311 Bom
Judgement Date : 1 November, 2012

Bombay High Court
M/S. Angerlehner Structural & ... vs Municipal Corporation Of Brihan on 1 November, 2012
Bench: Anoop V.Mohta
     ssm                               1                               arbp164.09

              IN THE HIGH COURT OF JUDICATURE AT BOMBAY                              




                                                                        
               ORDINARY ORIGINAL CIVIL JURISDICTION




                                               
                ARBITRATION PETITION NO. 164 OF 2009

     M/s. Angerlehner Structural & Civil
     Engineering Co., a company incorporated




                                              
     in Austria Having its registered
     Office at A-1055, Pucking, Obere
     Landstrasse 19 and having its project
     office at 2078 "B" Wing,




                                    
     Oberoi Gardens, 
     Chandivali Studio Compound,
                       
     Saki Vihar Road, Sakinaka, Andheri (East),
     Mumbai 400 072                                      .....Petitioner. 
                      
                 Vs.

     Municipal Corporation of Brihan
     Mumbai, 3rd Floor, Annexe Building,
      


     Municipal Head Office,
     Municipal Corporation of Brihan Mumbai,
   



     Mahapalika Marg, 
     Fort, Mumbai-400 001.                               ....Respondent.





     Mr.  Zal  Andhyarujina with Ms. Dohita Lewis, Mr. Javed Gaya 
     Ms.   Vidya   Choudhari,   Ms.   Mona   Malvade   i/by   Chamber   of 
     Javed Gaya for the Petitioner.
     Mr. Kevic Setalwad, Senior Counsel with Ms. Daisy Dubash and 
     Mr. Harshad Pimple i/by S.H. Ujjainwala for the Respondent.





                                      
                                   CORAM     :  ANOOP V. MOHTA, J.
         JUDGMENT RESERVED ON        :  8 OCTOBER 2012.
         JUDGMENT PRONOUNCED ON  : 1 NOVEMBER 2012

     JUDGMENT :-





      ssm                                  2                               arbp164.09

The Petitioner, a contracting company governed by the

laws of Austria and carries out engineering works including

trenchless rehabilitation of underground pipes, sewers and

water construction and also sewer rehabilitation, all over the

world. The Respondent is a statutory body and is in-charge and

responsible for the disposal and maintenance of sewers in the

city of Mumbai.

2 The Petitioner has challenged award dated 11 July 2007

passed by the majority learned Arbitrators. The minority learned

Arbitrator's award is in favour of the Petitioner.

3 The majority Arbitrators have dismissed the claim for

payment of dewatering in the additional stretch and thereby

rejected all other claims. The background of facts as per the

Petitioner revolving around the alleged claim is relevant.

4 In the month of August 1999, bids were invited by the

Mumbai Municipal Corporation (for short, MMC). On 21

September 2000, the MMC addressed a letter to the Petitioner,

ssm 3 arbp164.09

awarding them the Contract that included dewatering (Item

No.3 of BOQ). On 18 February 2000, the Petitioner's

representatives attended a meeting in Mumbai to give a

comprehensive and exhaustive demonstration of the MCS

System to the representatives of the MMC. On 2 March 2001,

the contract bearing reference No. SO-CA-02 ("contract") was

executed and entered into by and between the parties. The

contract was initially for a period of 24 months, but was

extended on justifiable grounds to nearly 29 months with the

date of commencement as 11 January 2001 and the extended

date of completion as 31 May 2003. Under the contract, the

Petitioner was to undertake the rehabilitation of sewers at, inter

alia, package No.9 being rehabilitation of (760 x 1140 mm)

ovoid brick-masonry sewer running along Keshavrao Khade

Marg, which includes sewer line portion from MH No. 1 to 8

and 14 to 21 of the Keshavrao Khade Marg (package No.9). For

unknown reasons the sewer at package No.9 intermitted

sections, i.e. the portion crossing the Western Railways tracks

from manhole no.8 to no.14 near Mahalaxmi Station were left

out in the BOQ/ contract. Therefore, MMC proposed to the

ssm 4 arbp164.09

Petitioner to take up the portion of sewer below the railway

lines (177.5 mm.) in package no.9 (Additional stretch)

5 On 14 March 2001, letter from the Engineer (MMC) to the

Petitioner, informing them that M/s. TTI consultants have been

appointed as the "Consultants" under the contract. On 13

December 2001, the Petitioner offered the consultant to

undertake a feasibility study of Additional Stretch at package

No.9. On 21 December 2001, the Petitioner's letter to the

Consultant informing them that due to the existing silt and high

level of water inside the sewer line, a feasibility study was not

possible unless and until there is a confirmation for desilting.

On 3 January 2002, the consultant's letter to the Petitioner

informing that as a result of the site visits in package no.9 the

chief engineer had approved to continue the desilting works

with applicable BOQ rates in the intermediate section at the

railway crossing with a total additional length of 335.4 m.

6 From 12 February 2002 to 27 March 2002, the Petitioner

commenced the desilting works, which could only be carried out

ssm 5 arbp164.09

under dewatered condition. The Petitioner requested the MMC

for approval of further works for Additional Stretch at package

no.9 prior to commencement of works. Consultant completed

his study of variation in quantities and confirmed that works "as

per master plan" to be taken up by all contractors.

7 On 9 September 2002, in accordance with the minutes of

meetings the Petitioner was to proceed with GRP lining works at

the intermitted section (package No. 9) On 8 February 2003,

consultant's letter to the Petitioner.

8 From September 2001 to 8 February 2003, time taken by

the Consultant to conduct the scrutiny of additional works. On

17 February 2003, since the extended completion date of the

contract was 31 May 2003. The Petitioner informed the

Engineer that completion within the contract period was not

possible.

9 On 10 May 2004, the Consultant's letter addressed to the

Petitioner that payment for providing dewatering at package

ssm 6 arbp164.09

no.9 is not to be conceded. On 15 May 2004, the Petitioner's

letter to the Engineer informing him that they did not agree

with the opinion of the Consultant that no payments are due for

dewatering. The Petitioner gave the notification of dispute to

the MMC to call the Dispute Review Expert (DRE). On 31 May

2004, the Petitioner's letter addressed to the MMC informing

them that they will forward the dispute regarding providing

dewatering for additional works under the "master plan" at

package no.9. On 27 July 2004, MMC's reply to the issue

presented by the Petitioner before the DRE. On 6 August 2004,

the Petitioner's response to the reply of MMC.

10 On 23 September 2004, the recommendations of the DRE

recommending the MMC to make payment for dewatering for

the railway crossing portion at 80 USD per meter for the actual

length involved = price adjustment payable under clause 70

corresponding to the relevant period of execution= interest at

the rate provided in the contract for delayed payment from a

date 42 days after date of claim of the Petitioner i.e. 25

November 2003.

      ssm                                   7                                arbp164.09




                                                                             
     11     On   5   October   2004,   notice   of   Arbitration   given   by   the 




                                                     

Petitioner to the MMC nominated Dr. Harold Wagner as its

Arbitrator. On 19 October 2004, the MMC's letter proposing Mr.

Sharad Upasni to be their Arbitrator in relation to this dispute.

On 15 December 2004, reference made to President of institute

of Engineers (India) to appoint a third and presiding arbitrator.

On 26 April 2005, the president of Institute of Engineers (India)

appointing Mr. S.L. Garg to be the third and presiding arbitrator.

On 7th July 2005, the president of Institute of Engineers (india)

reappointing Mr. S.L. Garg to be the third and presiding

arbitrator. On 27 June 2007, the Arbitral Award of Dr. Harold

Wagner in favour of the Petitioner. On 11 July 2007, the

majority Arbitral Award of Mr. S.P. Upasani and Mr. S.L. Garg

rejecting the Petitioner's claim entirely.

12 The learned Arbitrator, after hearing both the parties and

considering the nature/concluded contract, terms and

conditions and the material placed on record rightly rejected the

claims. Both the learned counsel read and referred the

ssm 8 arbp164.09

documents and material placed on record including the reasons

given by the Arbitrators, the majority, as well as, the minority.

The relevant factors in the present matter as considered by the

majority Arbitrators are in the following words.

"22 We have carefully considered the facts on record,

information filed as per the direction of the Arbitral Tribunal,

legal arguments advanced by both the sides and clarifications/

explanations given by both the parties on points mentioned

during the hearing and all written as well as oral submissions of

both the parties. Following are the admitted facts in this

dispute.

a) The length between MH no.8 to MH 14 of the sewer along

the Keshavrao Khade Marg was not part of the contract No. SO-

CA-02 or package 9.

b) By letter dated 13-12-2001 the Claimant proposed to

undertake the work in the length not covered earlier subject to

feasibility study and arranging permit from the Railway

authority by the Respondent.

      ssm                                   9                                arbp164.09

     c)    In the remarks on retransmitted letter of 13-12-2001 the 




                                                                             

Respondent informed the Claimant that under the

circumstances explained, you are requested to undertake the

preliminary surveys so as to add the said Railway Crossing in

between the Contract Lengths and give feasibility report (survey

at your cost).

d) By letter dated 21st December 2001 in reply the Claimant

informed that the feasibility study can only be carried out

subject to condition of confirmation for desilting.

e) By letter dated 3-1-2002 the Engineer approved desilting

with applicable BOQ rates in the intermittent section.

f) By the letter dated 15th April 2002 the Claimant submitted

feasibility report without asking any payment for dewatering.

g) By letter dated 9th September 2002, completion of package

9 was declared without claiming for dewatering.

h) Till handing over the work of package- 9, on 24-6-2003,

the Claimant did not issue any notice of claim for dewatering.

i) Payment for desilting was claimed in IPC of June 2002.

j) Claim for dewatering is made on 25-11-2003.

      ssm                                  10                                arbp164.09

     23    The   Arbitral   Tribunal   has   also   noted   that   there   is   no 




                                                                             

variation order given for work in the Additional Stretch under

the Contract SO-CA-02 in respect of feasibility report. However

there are certain letters exchanged between the parties which

constitute proposal, acceptance and agreement for conduct of

feasibility study. The Arbitral tribunal has also carefully

considered the Clauses 2.2 and 2.3 of the Contract between the

parties under which the Engineer and Consultant have powers

to delegate work to the Contractor. The Tribunal has taken into

consideration the provisions relating to "Interpretation clause"

given in the sections 2(a) on "proposal", 2(b) "acceptance of

proposal", and 2(e) "agreement" in the India Contract Act, 1872

and provisions of section 7 which provides "in order to convert a

proposal into a promise, the acceptance must be absolute and

unqualified".

24 Based on the documents and facts placed before the

Arbitral tribunal and the provisions of the Indian Contract Act

the Tribunal had no hesitation to come to conclusion that

taking into consideration the proposal made by the Claimant on

13-12-2201 to the Consultant for conducting feasibility study,

ssm 11 arbp164.09

the acceptance remarks of the Consultant on the retransmitted

letter of 13-12-2001 that the survey to be conducted at the cost

of the Claimant and subsequent letter dated 21st December 2001

by claimant to the Consultant regarding desilting and reply

dated 3-1-2002 from consultant informing the approval of the

Chief Engineer (SO) for desilting with applicable BOQ rats in

the intermittent section all prove that the Claimant had agreed

to conduct feasibility study on payment for desilting. It is also

on record that by letter dated 15th April 2002 the Claimant

submitted feasibility report without asking any payment for

dewatering. Even in the letter dated 9th September 2002 from

the Claimant declaring completion of the work of Package 9, the

Claimant had not raised the question of payment for

dewatering. No notice of any claim was issued till the work of

package 9 was handed over on 24-6-2003. Thus both on the

basis of documents before us and subsequent conduct of the

party the Arbitral Tribunal has no hesitation to conclude that

the Claimant has failed to establish his claim for payment for

dewatering in the Additional Stretch and hence it is rejected.

Therefore the question in looking into claim on account of

ssm 12 arbp164.09

adjustment clause and interest also does not arise."

13 The reasonings so given above, and also the reasons given

by the learned Dissenter, I am inclined to observe that there is

no case made out by the Petitioner to interfere with the majority

award. It is well within the framework of law and the record.

There is no perversity. The view so expressed is plausible and

possible based upon the nature and the terms and conditions of

the contract. The Petitioner in no way entitled for payment of

dewatering at the additional Stretch, as there was no contract

whatsoever. The Petitioner failed to prove the contract,

specifically for the claim so raised. The learned Arbitrators

rightly considered the nature of contract and the work so

permitted to be carried out by the Petitioner. The scope and

purpose of Section 34 of the Arbitration Act is quite restrictive.

The admitted facts, as recorded above based upon the material,

destroys even the case and the claims so raised. These admitted

documents have been rightly considered by the learned

Arbitrators. The Petitioner failed to destroy the Respondent's

case and/or unable to bring on record further contra material,

ssm 13 arbp164.09

in their support. Admittedly the feasibility report was

submitted. No such demand was raised at the appropriate time.

The party who raises the demand, must prove the same by

leading and supporting the documents including the validity

and the supporting binding contract. In the present case, as

recorded rightly by the learned Arbitrators, that there exists

none. The rejection of other connected claims, therefore, also

need no interference, except the costs so awarded.

14 Resultantly, the Petition is dismissed. No order as to costs.

(ANOOP V. MOHTA, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter