Citation : 2009 Latest Caselaw 111 Bom
Judgement Date : 16 December, 2009
1
IN THE HIGH COURT OF JUDICATURE AT
BOMBAY
BENCH AT AURANGABAD.
ARBITRATION APPEAL NO.16 OF 2009.
M/s S.D.Shinde and Company
Contractor "Shri Parvati"
Savedi Road, Ahmednagar,
Tq. and Dist.Ahmednagar
ig ... Appellant.
Versus
The State of Maharashtra
through the Executive Engineer,
Uppar Penganga Project,
Division No.8, Nanded,
Tq. & Dist. Nanded. ... Respondent.
...
Mr.R.N.Dhorde, advocate for the appellant.
Mrs.Geeta Deshpande, advocate for the Respondent.
...
CORAM : V.R.KINGAONKAR,J.
Date : 15/16.12.2009.
ORAL JUDGMENT
1. This Arbitration Appeal arises out of
order rendered by learned Joint Civil Judge
(S.D.), Nanded, in proceedings seeking indulgence
of the Court to make award of Arbitrator as
rule of the Court.
2. The appellant filed application before
Civil Court alleging that after following due
procedure the Arbitrator, duly appointed, had
rendered award which may be made rule of the
Court. The appellant's application came to be
dismissed.
3.
The appellant is a company duly
incorporated and deals in contractual Civil
works. The Respondent called for tenders
regarding the work for construction of earth
work lining and structures of Isapur Right Bank
Canal. The appellant filled the tender which was
lowest one and, therefore, the contractual work
was assigned to the appellant vide LCB Contract
No.11/87/88. The work order was issued on
9.12.1987. The appellant was directed to
complete the work on or before 9.6.1990. There
is no dispute about the fact that completion of
the work was delayed. The appellant was granted
third extension to complete the work on or before
30th September 1992. It appears that there was
no further extension issued but the appellant
continued to work notwithstanding the expiration
of outer limit of third extension period. The
Respondent terminated the works contract by
virtue of a notice dated 30th October 1992. The
notice, however, indicated that the authority to
work was terminated with retrospective effect
from 1.10.1992.
4. ig The appellant approached the Chief
Engineer in order to ventilate his grievances.
He contended that certain work was carried out by
him and he was not at fault. No action was taken
in pursuance to his representation. He had filed
suit (RCS No.143/1993) challenging the order
pertaining to withdrawal of the work and for
allowing encashment of the bank guarantee. That
suit was dismissed in default. The appellant,
therefore, communicated to the Respondent to
appoint Arbitrator as per the Arbitration clause
in the contract. No reply was, however, given by
the Chief Engineer or other authorities. The
appellant gave notice to the Chief Engineer on
3.12.1994. The appellant lastly communicated
that on his part retired Superintending Engineer
Shri S.M.Dandawate, was appointed as Arbitrator.
5. The Arbitrator commenced the
Arbitration proceedings. The Respondent was
informed by the Arbitrator regarding the
procedure to be followed by him. The Respondent
inter alia challenged authority of Shri
S.M.Dandawate
ig to act as an Arbitrator. The
Respondent submitted that the appellant had
failed to execute the work within the given time
frame and thereby committed breach of the
contract. The Respondent further submitted that
they were required to engage another agency for
completion of the work and, therefore, loss was
incurred due to such irresponsible conduct of the
appellant. It was further submitted that the
Respondents had filed suit against the appellant
for recovery of the damages and compensation to
the tune of Rs.53,83,375/- (Rupees fifty three
lacs eighty three thousand three hundred seventy
five). The Respondent, therefore, sought
dismissal of the Arbitration proceedings.
6. Upon hearing both the sides and on
consideration of the material placed before him,
the Arbitrator rendered the award. He held that
there was no breach of agreement on part of the
appellant. He further held that the Respondent
was liable to pay the difference of amount
regarding the work executed by the appellant. It
is pertinent to notice that the Respondent had
challenged ig appointment of the Arbitrator by
filing a suit which came to be dismissed. The
Respondent preferred CRA No.543/1996 which came
to be dismissed by this Court on 30.4.1996.
7. It appears that the suit (Spl.C.S.No.
238/1995) is pending and has been stayed vide
order dated 10.12.2003, rendered by this Court in
W.P.No.5171/2003.
8. While dismissing the CRA No.543/96,
this Court observed that legality of the
Arbitrator's appointment and his authority to
render the award can be challenged in the
Arbitration proceedings by the Respondent.
Taking cue from such liberty, the Respondent
questioned appointment of the Arbitrator and his
jurisdiction in the proceedings before the
Arbitrator. The contention of the Respondent was
that as per the contract, retired person could
not be appointed as sole Arbitrator. It was also
contended that unilaterally the appellant could
not have appointed Shri Dandawate. It was
further contended that the Arbitrator committed
misconduct while rendering the award by allowing
certain items which were impermissible. It was
further contended that the award was rendered
without any sufficient material and, therefore,
was improper and illegal. On these premises, the
Respondent sought dismissal of the application
seeking leave of the Court to make the award as
rule of the Court.
9. The objections raised by the Respondent
were accepted by the learned Civil Judge (S.D.),
Nanded and the award was set aside. Feeling
aggrieved, the appellant has come up in appeal.
10. Heard learned counsel.
11. The record shows that the Arbitrator
informed the parties by letter dated 14.11.1995
about the Arbitration proceedings. He called a
preliminary meeting at Pune on 28.1.1996. It
also appears that in the said meeting
representatives of the appellant were present.
Thereafter, several meetings were called wherein
representatives of both the sides were present.
The two final meetings were held on 30th and 31st
January, 1998. The counter claim filed by the
respondent was also considered. Ultimately, the
Arbitrator came to the conclusion that the
Respondents were liable to pay Rs.60,62,080/-
(Rupees sixty lacs sixty two thousand and eighty
only) to the appellant.
12. The important question involved in this
appeal is :
"Whether in the facts and
circumstances of the present matter,
the Arbitrator was ineligible and
disqualified to act as such because he
is a retired Superintending Engineer
of Irrigation Department.?"
13. The learned Civil Judge held that the
appointment of Shri Dandawate, was invalid for
the reason that the Arbitration clause envisaged
that Officer of the rank of Superintending
Engineer or higher rank only was eligible for
appointment as sole Arbitrator.
14. The Arbitration clause is as follows :
"Within 30 days of receipt of notice
from the contractor of his intention
to refer the dispute to arbitration
the Chief Engineer, Irrigation
Department, Aurangabad shall send to
the contractor a list of three
Officers of the rank of
Su0perintending Engineer or higher who
have not been connected with the work
under this contract. The contractor
shall within (15) days of receipt of
this list select and communicate to
the Chief Engineer the name of one
officer from the list who shall then
be appointed as the sole arbitrator.
In case contractor, fails to
communicate his selection of name
within the stipulated period, the
Chief Engineer shall without delay
select one officer from the list and
appoint him as the sole arbitrator.
If the Chief Engineer fails to send
such ig a list within (30) days as
stipulated, the contractor shall send
a similar list to the Chief Engineer
within (15) days. The Chief Engineer
shall then select one officer from the
list and appoint him as the Sole
Arbitrator, within (15) days. If the
Chief Engineer fails to do so, the
contractor shall communicate to the
Chief Engineer the name of one officer
from the list who shall then be the
sole arbitrator."
The appellant took necessary steps for calling
upon the Chief Engineer to appoint an Arbitrator.
It was for the Chief Engineer who was required
to send names of three (3) officers of the rank
of Superintending Engineer or higher rank, who
were not connected with the work under the
contract. This was not complied with by the
Chief Engineer. The expression "the officers of
the rank of Superintending Engineer or higher
rank is qualified by further explanation that
they shall not have any connection with the work
under the igcontract. This condition is more
important. It would imply that such appointee
must be completely disassociated with the work of
said contract. It is but natural that a
Superintending Engineer in service may be someway
or the other connected with the work regarding
the contract. In any case, the Arbitration
clause No.52 does not specifically disqualify "a
retired Superintending Engineer". The retired
Superintending Engineer is not specifically
barred to work as sole arbitrator.
15. At this juncture, it is important to
notice that the Respondent did not challenge the
qualification of the Arbitrator by filing
separate proceedings under the Arbitration Act,
1996. A suit was filed by the respondent in
order to challenge the appointment of arbitrator
but the same was dismissed. The CRA also came to
be dismissed. Why a retired Superintending
Engineer could not be appointed as the sole
Arbitrator is rather difficult to comprehend.
The Chief Engineer did not take initiative in
appointment of any Arbitrator. Moreover, the
representatives of the respondent participated in
the proceedings before the Arbitrator. A counter
claim was also filed before the same Arbitrator.
Considering the conduct of the Respondent's
officers, I am of the opinion that principle of
estoppel is applicable and the appointment of
sole Arbitrator could not have been challenged.
The challenge on this score ought to have been
rejected by the learned Civil Judge.
Dt.16.12.2009.
16. The interpretation of the Arbitration
clause could be made from another stand point of
the view. It is of common knowledge that the
Officer in service is employee of the Government
and can not do any other work unless there is
specific permission of the Government to
undertake such work. The Arbitrator is entitled
to receive remuneration. An Officer in service is
not entitled to receive any remuneration because
he is the paid employee and such payment can not
be accepted without prior permission of the
Government. The officer in service can not do
the arbitration work within the working hours.
If Rule 16 of the Maharashtra Civil Services
(Conduct) Rules, 1979 is perused then it will be
clear that such an Officer can not undertake
private trade or employment. The Government
servant is always considered to be on duty for
all the time. He can not do extra private work
unless is statutorily appointed or officially
nominated to do such work besides the office
work. In other words, ordinarily, an officer who
is in service can not be appointed as arbitrator
unless, of-course, there is some special
permission granted by the Government or statute
provides for such appointment. Considering such
legal embargo envisaged under the Maharashtra
Civil Services Rules, it does not stand to reason
that the Arbitration clause provided for
appointment of only officiating Superintending
Engineer or anyone above such rank. In this view
of the matter, the award could not be set aside
on the ground that it was rendered by the retired
Superintending Engineer, namely, Shri
M.S.Dandawate.
17. Now,
ig it may be gathered that the
learned Civil Judge was pleased to set aside the
award on the ground that detailed reasons were
not recorded in support of award of
compensation. The learned Civil Judge held that
as per the agreement, the rate of extra items of
the work to be carried out under directions of
the Executive Engineer was Rs.61/- per cubic,
whereas the arbitrator awarded Rs.147.50 per
cubic. This was treated as major deficiency in
the award and also misconduct of the arbitrator.
The learned Civil Judge also observed that the
arbitrator did not give detailed reasons as to
why the counter claim of the respondent was
disallowed. Obviously, it is required to be seen
whether the award could be set aside only because
detailed reasons were not recorded by the
arbitrator.
18. In "Raipur Development Authority etc.
Vs.M/s Chokhamal Contractors etc. etc." (AIR 1990
Supreme Court 1426), the Apex Court observed that
Arbitration Award is not liable to be remitted or
set aside merely on the ground that no reasons
have been ig given in support of the same. The
relevant observations are quoted in para 38 as
reproduced below :
"In the result we hold that an award
passed under the Arbitration Act is
not liable to be remitted or set aside
merely on the ground that no reasons
have been given in its support except
where the arbitration agreement or the
deed of submission or an order made by
the Court such as the one under
Section 20 or Section 21 or Section 34
of the Act or the statute governing
the arbitration requires that the
arbitrator or the umpire should give
reasons for the award."
In this view of the matter, when there was no
specific agreement between the parties that the
arbitrator shall give detail reasons in support
of the award, the learned Civil Judge should not
have interfered with the award on the ground that
there was no reasoning recorded in respect of
certain items of the claim.
19. It may be mentioned that Smt.Geeta
Deshpande, learned counsel for the Respondent
strenuously argued that the award is unfair and
that the same has been properly set aside by the
learned Civil Judge because the findings recorded
by the arbitrator are contrary to the record.
She seeks to rely on "Union of India Vs. M/s
Arora Associates and another" 2003 (4) ALL MR 901
in this context. A Single Bench of this Court
held that where the finding of arbitrator was
contrary to the material available on record,the
award could not be allowed to stand and was
required to be set aside. In the fact situation
of the present case only because certain rate is
shown in the agreement and enhanced rate is
considered while passing of the award, it can not
be said that the findings are contrary to the
record. The contradiction was not brought on
surface. It is important to notice that the
parties had agreed for escalation of the prices.
20. The learned counsel would also rely on
"Union of India and another Vs. M/s Sohan Lal
Puglia" 2004 (5) ALL MR (S.C.) 147. In the given
case, appointment of a retired District Judge was
challenged and was set aside. It was noticed,
however, that the employer had not refused to
appoint the arbitrator and, therefore, the
petition was not maintainable U/s 20 of the Act.
Reliance is also placed on "M/s Graphic Interiors
Vs. The Commander Works Engineer (Naval Works)
Mumbai" AIR 2000 Bombay 303. The arbitration
award was set aside on account of misconduct of
the arbitrator for omission to record reasons in
the context of claims which were allowed.
However, in the given case there was a specific
agreement which provided and made it obligatory
on the part of the arbitrator to indicate his
finding along with the sums awarded separately on
each individual item of dispute. Obviously, it
was obligatory on the arbitrator to assign the
reasons and record the findings as per the
agreement. This authority can be distinguished on
the fact situation of the present case.
Mrs.Geeta Deshpande, also invited my attention to
"J.C.Budhraja Vs. Chairman, Orissa Mining
Corporation Ltd. and another" (2008) 2 Supreme
Court Cases 444. The Apex Court held that
granting of rate of interest in excess of what
was claimed, could be regarded as a legal
misconduct, vitiating the award to that extent.
I do not find any parallel between facts of the
given case and the facts of the present case.
22. It is well settled that normally the
arbitration award can not be lightly brushed
aside. It can not be set aside unless there are
tangible reasons to infer misconduct or
misfeasance by the arbitrator and for the reasons
which are legally permissible under the
provisions contained in Section 30 of the
Arbitration Act, 1940.
23. Considering the foregoing reasons, I
find it difficult to maintain the impugned order.
Hence, the appeal is allowed. The impugned
judgment and order rendered by the learned Civil
Judge (S.D.), Nanded is set aside. The learned
Civil Judge shall make the award a Rule of the
Court by allowing the application of the
Respondent. No costs.
(V.R.KINGAONKAR,J.)
asp/office/Arbappeal1609
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!